CN104616101B CN201510025991.3A CN201510025991A CN104616101B CN 104616101 B CN104616101 B CN 104616101B CN 201510025991 A CN201510025991 A CN 201510025991A CN 104616101 B CN104616101 B CN 104616101B
Authority
CN
China
Prior art keywords
equipment
plant
system resource
power system
integrated power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510025991.3A
Other languages
Chinese (zh)
Other versions
CN104616101A (en
Inventor
佘运波
闫训超
李莉
曹齐
吴淑玮
张德金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
NARI Group Corp
State Grid Shanghai Electric Power Co Ltd
Nari Information and Communication Technology Co
Original Assignee
State Grid Corp of China SGCC
State Grid Shanghai Electric Power Co Ltd
Nari Information and Communication Technology Co
Nanjing NARI Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Shanghai Electric Power Co Ltd, Nari Information and Communication Technology Co, Nanjing NARI Group Corp filed Critical State Grid Corp of China SGCC
Priority to CN201510025991.3A priority Critical patent/CN104616101B/en
Publication of CN104616101A publication Critical patent/CN104616101A/en
Application granted granted Critical
Publication of CN104616101B publication Critical patent/CN104616101B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Quality & Reliability (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of integrated power system resource model and foundation and maintaining method, for generating electricity, transmission of electricity, power transformation, distribution is until the electric power networks of user side, foundation can cover different resource species, merge each professional range, support the integrated power system resource model and standardization maintenance process of different time span, realize master, the seamless connection of distribution and figure, the integrated management of machine account, integrated power system resource model is by equipment electricity system nameplate, Unit account of plant and equipment graphical information three parts composition, the association of Unit account of plant and equipment graphical information is realized by equipment electricity system nameplate.The present invention meets electric power enterprise using power network resources model as the Various types of data of core is longitudinally through and laterally merges main trend, solve the common problem that electric power enterprise accumulates precipitation on global information is shared, eliminate the bottleneck for hindering the further strong intelligent grid of development.

Description

A kind of integrated power system resource model and foundation and maintaining method
Technical field
The present invention relates to a kind of integrated power system resource model and foundation and maintaining method, belong to technical field of power systems.
Background technology
The maintenance of power network resources model at present and application is main or different majors towards power industry, fortune inspection, scheduling, Each specialties such as marketing safeguard the power network resources model that oneself needs respectively, it is each it is professional between then model disunity, it is difficult to realize business Fusion and data sharing, Data duplication maintenance condition happen occasionally.First, non-unified power network resources model causes device code It is lack of consistency with device parameter specification.For example to same grid equipment, the different majors inside electric power enterprise are using different Numbering, name and form modeling.This disunity, the repetition of nonstandardized technique model artificially has manufactured wall to the exchange of information Build, it is necessary to largely work to carry out the exchange and mapping between data model.Secondly, the business scope of different majors often relates to And different types of grid equipment resource so that the species of non-unified power network resources model covering is not complete, modelling it is wide General property and autgmentability deficiency.
In terms of power network resources model, IEC (International Electrotechnical Commission) has formulated 61970/61968 serial CIM standards Various equipment in electric power networks are described.Both establish complete standard to power transmission and transforming equipment model and electricity distribution network model respectively Description.But because CIM standards are a kind of general data models, its Parameter specifications can not all meet the production fortune of domestic enterprise Battalion's demand.In addition, CIM standards do not consider the service application of grid equipment multi-time Scales, it is difficult to when the angle of slave unit assets meets Between span management requirement.
At present, electric power enterprise lack one can cover multiple types, the power network resources of multi-specialized, more time span unify mould Type.Non- unified model, cause the standards and norms of Various types of data inconsistent, Data duplication typing be present, fortune inspection, adjust Machine account, graphical information between the business such as degree, marketing are difficult to share, and the difficulty for collaboration of being commenced business between each specialty is big.
The content of the invention
The invention provides a kind of integrated power system resource model and foundation and maintaining method, realizes that power network resources model is providing The expansion and extension of source category, professional range and time span three dimensionality, realize all kinds of numbers using power network resources information as core According to the longitudinally through and horizontal needs for merging, meeting informatization, for planning, capital construction, production, operation and the battalion of electric power enterprise The orderly development and management innovation of the business such as pin provide support.
To reach above-mentioned purpose, the technical solution adopted by the present invention is as follows:
A kind of integrated power system resource model, it is made up of equipment electricity system nameplate, Unit account of plant and equipment graphical information, by setting Standby electricity system nameplate realizes the association of Unit account of plant and equipment graphical information.
The integrated power system resource apparatus of foregoing integrated power system resource model includes primary equipment in station, stands and once sets outside It is standby, low-voltage equipment, secondary device and public utility, not by it is defeated, become, divided with specialty;Primary equipment is included in station in the station Exchange primary equipment, stand in change of current primary equipment and valve cooling system;Primary equipment includes overhead transmission line equipment, electricity outside the station Cable pipeline equipment;The secondary device includes control and protection device/system, power of alterating and direct current and station power use system, online prison Survey device, automation equipment;The public utility includes production auxiliary equipment.
Foregoing integrated power system resource model record integrated power system resource apparatus is in planning and designing, buying is built, operation is examined Repair, the temporal information of four big Service Periods of retired disposal.
Foregoing integrated power system resource model has formulated unified standard criterion, including device code specification and device parameter Specification, the device code specification use linear classification method, by three sections of totally seven digit numeric code component devices Sort Codes, to power transmission and transformation And production auxiliary equipment, distribution and low-voltage equipment, secondary device, the specific Parameter specifications of direct current primary equipment formulation, including thing Manage parameter, operational factor, assets parameter and regulation and control operational factor.
Device id, job number parameter are designed in foregoing integrated power system resource model, in planning and designing and builds rank Section, by job number tracking equipment information, in equipment operation, turn money, retired turn of recycling stage, set by device id tracking Standby and assets information.
To it is foregoing it is defeated, become, carry out integrated design with each professional electric network model, it is contemplated that equipment difference and manage it is poor It is different, the equipment of 10kV and above is subjected to integrated design, not divided by defeated, change, with specialty, each sets Facility information table and figure table corresponding to standby type foundation, pass through the range of management of voltage class control device parameter;To low pressure Equipment individually models, to adapt to the management mode that low-voltage equipment is different from high-tension apparatus.
A kind of creation method of integrated power system resource model, comprises the following steps:
1) equipment electricity system nameplate is first created, is then that the nameplate given an written reply in nameplate Runtime Library creates equipment figure according to electricity And Unit account of plant;
2) for planless equipment, synchronously create equipment electricity system's nameplate when creating equipment account and identify the nameplate with Figure is unrelated.
A kind of maintaining method of integrated power system resource model, including the newly-increased maintenance of equipment, equipment figure and equipment account are repaiied Change maintenance,
The equipment increases maintenance newly and comprised the following steps:
(1-1) equipment changing application:After engineering terminates, equipment changing request slip is created, task distribution is carried out after reporting, and Version task is initiated, forms version repository;
(1-2) equipment figure is safeguarded:If having obtained figure, four small device information are supplemented on figure;If do not obtain Figure, then graphing, and associate electricity system nameplate;
(1-3) Unit account of plant is safeguarded:Unit account of plant is created based on equipment figure and asset handover inventory, and fills in equipment pass Bond parameter;
(1-4) equipment figure and Unit account of plant examination & verification:The integrality of equipment figure and parameter, accuracy, normalization are entered Row examination & verification;
(1-5) equipment figure and Unit account of plant issue:Equipment figure and Unit account of plant are issued;
(1-6) device parameter supplement is perfect:Version task is initiated, and device parameter supplement perfect;
(1-7) equipment supplementary parameter is issued:Issued to supplementing the device parameter after improving, terminate version task;
The equipment figure and equipment account modification maintenance comprise the following steps:
(2-1) equipment changing application:Equipment changing request slip is created, task distribution is carried out after reporting, and initiates version and appoints Business, form version repository;
(2-2) equipment figure is changed:If being related to the modification of equipment figure, equipment figure is modified, otherwise directly jumped Unit account of plant modification is carried out to the 3rd step;
(2-3) Unit account of plant is changed:Unit account of plant information is modified;
(2-4) equipment figure and Unit account of plant examination & verification:The integrality of equipment figure and parameter, accuracy, normalization are entered Row examination & verification;
(2-5) equipment figure and equipment account issue:Fortune inspection class monitor and group leader issues to equipment figure and Unit account of plant.
The present invention is by the object model between unified each system, model specification, graphical specification between unified each system, system The granularity of resource model and grid graph between one each system so that " source full maintenance, globally shared " becomes a reality, It is horizontal with integrated services to improve data sharing, the maintenance quality of data is greatly improved, reduces the maintenance difficulties and cost of data In addition, integrated power system resource model promotes the related types of applications standardization of power network resources model, standardization, it is information system Develop and integrate and provide unified standard, saved the cost of investment of project, also cause business personnel for based on unified electricity The training and grasp of the types of applications system of net resource model become more simple, reduce project implementation expense, promote letter Breath system preferably provides service support for power business.
Brief description of the drawings
Fig. 1 is the device class code structure schematic diagram of the integrated power system resource apparatus of the present invention;
Fig. 2 is power network resources illustraton of model number integration schematic diagram in embodiments of the invention;
Fig. 3 is integrated power system resource model figure in embodiments of the invention.
Embodiment
The present invention is described in further detail in conjunction with the drawings and specific embodiments.
The standard criterion of integrated power system resource model has been formulated before the establishment integrated power system resource model of the present invention first, It is as follows:
The present invention has formulated the standard criterion of integrated power system resource model, establishes device code specification and device parameter rule Model.
Integrated power system resource apparatus covers multiple types, specifically includes primary equipment in station, outer primary equipment of standing, and low pressure is set It is standby, secondary device and public utility, do not divided by defeated, change, with specialty.Wherein, primary equipment includes exchanging once in station in standing Equipment, stand in change of current primary equipment and valve cooling system;Outer primary equipment of standing includes overhead transmission line equipment, cable plant; Secondary device includes control and protection device (system), power of alterating and direct current and station power use system, on-Line Monitor Device, automation are set It is standby;Public utility includes production auxiliary equipment.Linear classification method is used to integrated power system resource apparatus, by three sections of totally seven digit numeric codes Component devices Sort Code, as shown in Figure 1.
The device class code and professional classification of specific each power network resources equipment are as shown in table 1 to table 10.
In addition, power transmission and transformation and production auxiliary equipment, distribution and low-voltage equipment, secondary device, direct current primary equipment are formulated Specific Parameter specifications, cover physical parameter, operational factor, assets parameter and regulation and control operational factor, meet different majors field Business demand.
Device class code and Parameter specifications specify that the equipment hierarchical relationship and data content of power network resources model, be base Provided the foundation support in the service application of asset of equipments.
The overhead transmission line equipment of table 1
The cable plant of table 2
Primary equipment is exchanged in the station of table 3
Change of current primary equipment and valve cooling system in the station of table 4
Table 5 controls and protection device (system)
The power of alterating and direct current of table 6 and station power use system
The on-Line Monitor Device of table 7
The automation equipment of table 8
Table 9 produces auxiliary equipment
The low-voltage equipment of table 10
1~2 The device class first order 3~4 The device class second level 5~7 The device class third level Remarks
31 Low-voltage circuit equipment
01 Primary cable
02 Low pressure shaft tower
03 Low pressure on-pole switch
06 Fuse in lower pressure column
07 Low-tension fuse
08 Capacitor in lower pressure column
10 Low-voltage reactive compensator
11 Arrester in lower pressure column
12 Low-voltage meter box
1~2 The device class first order 3~4 The device class second level 5~7 The device class third level Remarks
13 Low-tension fuse case
14 Wall bracket
17 Low-tension distribution box
18 Low pressure residual current operated protective device
32 Low-voltage cable equipment
01 Low-voltage cable section
02 Low-voltage cable terminal
03 Low-voltage cable joint
04 Low-voltage cable distribution box
05 Low-voltage cable termination rack
33 Primary equipment in low pressure station
01 Low tension switch
03 Low-voltage bus bar
04 Low-tension distribution board
05 Low-tension switch cabinet
06 Low-voltage power electronic equipment Utilize the low-voltage equipment of Power Electronic Technique
07 Low pressure energy storage device Energy storage device for low pressure
08 Anti-islanding device
09 Low-voltage current mutual inductor
10 Low-tension fuse
11 Secondary capacitor
12 Low voltage surge arrester
Integrated power system Resource Design scheme
1) unified numbering, name and format specification are formulated, such as:Pass through operation numbering, the device name of unit equipment And voltage class, to carry out the numbering of asset of equipments and name.Device resource after unified format specification, is easy to implement multi-disciplinary Service application.
2) to realize power network horizontal and vertical " one throws the net ", seamless connection major network and distribution on electric network composition, to it is defeated, Become, carry out integrated design with each professional electric network model.In view of equipment difference and management difference, by 10kV and above voltage etc. The equipment of level carries out integrated design, is not divided by defeated, change, with specialty, equipment corresponding to the foundation of each device type Information table and figure table, by the range of management of voltage class control device parameter, adapt to the regulatory requirement of differentiation;To low pressure Equipment (380V) individually models, to adapt to the management mode that low-voltage equipment is different from high-tension apparatus.
3) power network resources are recorded in integrated power system resource model and (contain equipment in planning and designing, buying construction, operating maintenance Change), the temporal information of the four big Service Periods such as retired disposal, realize " equipment a record ", meet power grid asset from Planning and designing are to the retired time span management requirement scrapped.
4) device id, job number parameter are designed in integrated power system resource model, in planning and designing and construction period, is led to Cross job number tracking equipment information, equipment operation, turn money, retired turn recycling etc. the stage, pass through device id tracking equipment And assets information, more time spans are covered, support the lifecycle management of grid equipment.
The resource integrated modeling of integrated power system
Integrated power system resource model is made up of equipment electricity system nameplate, Unit account of plant and equipment graphical information three parts.To have Effect ensures the uniformity and data maintenance efficient of machine account, figure and topology information, structure Unit account of plant, equipment figure, topology Integrated Model, the association of equipment figure and Unit account of plant is realized by equipment electricity system nameplate.
The foundation step of integrated power system resource model is:Equipment electricity system nameplate is created by dispatching professional, then basis The nameplate given an written reply in electricity system nameplate Runtime Library creates equipment figure and Unit account of plant, and to electricity system nameplate fortune after completion is created Row storehouse is spaced ID, device id, affiliated station circuit ID belonging to filling in.It is same when creating Unit account of plant for planless equipment Step creates equipment electricity system's nameplate and to identify the nameplate unrelated with figure.
By taking main transformer as an example, its data model is as follows:
Equipment electricity system name plate information:Including controlling equipment name, affiliated transformer station, voltage class, device type information.
Unit account of plant information:Including physical attribute, Asset Attributes and operation information.Physical attribute includes manufacturer, Model, factory number, rated capacity etc.;Asset Attributes include asset number, asset units etc.;Operation information includes implementor name Claim, run unit, equipment owner, date of putting into operation etc.;Contained in equipment operation information with electricity be nameplate relation;
Equipment graphical information:Including equipment operation information, locus, topological connection relation in power network, operation letter It is the relation of nameplate that breath, which is included with electricity, and corresponding Unit account of plant ID.
The class data message of the above three realizes figure number board service by the electricity system nameplate of equipment, by taking main transformer as an example, Incidence relation between three data models as shown in Fig. 2 it can be seen that in Unit account of plant table, graphical information table There are " electricity system nameplate Runtime Library ID " fields, so as to establish association between three data models.Fig. 3 shows the main transformer Integrated power system resource model figure.
The maintenance of integrated power system resource model is divided into newly-increased equipment, equipment figure and Unit account of plant modification, and wherein engineering is new The equipment of increasing increases flow newly by equipment and safeguarded;Physical device change does not occur, but needs to carry out equipment figure and machine account (such as data initialization, account error message are changed) is safeguarded by equipment figure, Unit account of plant modification process during modification.
1st, equipment increases flow newly:
(1) equipment changing application:After engineering terminates, equipment changing request slip is created, task distribution is carried out after reporting, concurrently Version task is played, forms version repository.
(2) equipment figure is safeguarded:If having obtained figure, the information such as four small devices are supplemented on figure;If do not obtain Figure, then graphing, and associate electricity system nameplate.
(3) Unit account of plant is safeguarded:Unit account of plant is created based on equipment figure and asset handover inventory, and fills in equipment key Parameter.
(4) equipment figure and Unit account of plant examination & verification:To the integrality of equipment figure and parameter, accuracy, normative progress Examination & verification.
(5) equipment figure and Unit account of plant issue:Equipment figure and Unit account of plant are issued.
(6) device parameter supplement is perfect:Version task is initiated, and device parameter supplement perfect.
(7) equipment supplementary parameter is issued:Issued to supplementing the device parameter after improving, terminate version task.
2nd, equipment figure and Unit account of plant modification process:
(1) equipment changing application:Equipment changing request slip is created, task distribution is carried out after reporting, and initiates version task, Form version repository.
(2) equipment figure is changed:If being related to figure modification, equipment figure is modified, otherwise leaps to the 3rd Step carries out Unit account of plant modification.
(3) Unit account of plant is changed:Unit account of plant information is modified.
(4) equipment figure and Unit account of plant examination & verification:To the integrality of equipment figure and parameter, accuracy, normative progress Examination & verification.
(5) equipment figure and Unit account of plant issue:Fortune inspection class monitor and group leader issues to equipment figure and Unit account of plant.

Claims (5)

1. establishment and the maintaining method of a kind of integrated power system resource model, it is characterised in that the integrated power system resource model Integrated power system resource apparatus is including primary equipment in station, stand outer primary equipment, low-voltage equipment, secondary device and public utility, no Divided by defeated, change, with specialty;Primary equipment includes change of current primary equipment and valve in primary equipment is exchanged in station, is stood in the station Cooling system;Primary equipment includes overhead transmission line equipment, cable plant outside the station;The secondary device include control and Protection device/system, power of alterating and direct current and station power use system, on-Line Monitor Device, automation equipment;The public utility includes Produce auxiliary equipment;
The creation method comprises the following steps:
1) equipment electricity system nameplate is first created, is then that the nameplate given an written reply in nameplate Runtime Library creates equipment figure and set according to electricity Standby machine account;
2) for planless equipment, synchronously create equipment electricity system's nameplate when creating equipment account and identify the nameplate and figure It is unrelated;
3) association of Unit account of plant and equipment graphical information is realized by equipment electricity system nameplate;
The maintaining method includes the newly-increased maintenance of equipment, and equipment figure and equipment account modification are safeguarded,
The equipment increases maintenance newly and comprised the following steps:
(1-1) equipment changing application:After engineering terminates, equipment changing request slip is created, task distribution is carried out after reporting, and initiate Version task, form version repository;
(1-2) equipment figure is safeguarded:If having obtained figure, four small device information are supplemented on figure;If not obtaining figure, Then graphing, and associate electricity system nameplate;
(1-3) Unit account of plant is safeguarded:Unit account of plant is created based on equipment figure and asset handover inventory, and fills in the crucial ginseng of equipment Number;
(1-4) equipment figure and Unit account of plant examination & verification:The integrality of equipment figure and parameter, accuracy, normalization are examined Core;
(1-5) equipment figure and Unit account of plant issue:Equipment figure and Unit account of plant are issued;
(1-6) device parameter supplement is perfect:Version task is initiated, and device parameter supplement perfect;
(1-7) equipment supplementary parameter is issued:Issued to supplementing the device parameter after improving, terminate version task;
The equipment figure and equipment account modification maintenance comprise the following steps:
(2-1) equipment changing application:Equipment changing request slip is created, task distribution is carried out after reporting, and initiate version task, shape Into version repository;
(2-2) equipment figure is changed:If being related to the modification of equipment figure, equipment figure is modified, otherwise leaps to the Three steps carry out Unit account of plant modification;
(2-3) Unit account of plant is changed:Unit account of plant information is modified;
(2-4) equipment figure and Unit account of plant examination & verification:The integrality of equipment figure and parameter, accuracy, normalization are examined Core;
(2-5) equipment figure and equipment account issue:Fortune inspection class monitor and group leader issues to equipment figure and Unit account of plant.
2. establishment and the maintaining method of a kind of integrated power system resource model according to claim 1, it is characterised in that described It is big in planning and designing, buying construction, operating maintenance, retired disposal four that integrated power system resource model records integrated power system resource apparatus The temporal information of Service Period.
3. establishment and the maintaining method of a kind of integrated power system resource model according to claim 1, it is characterised in that described Integrated power system resource model has formulated unified standard criterion, including device code specification and device parameter specification, the equipment Code specification uses linear classification method, and by three sections of totally seven digit numeric code component devices Sort Codes, power transmission and transformation and production auxiliary are set Standby, distribution and low-voltage equipment, secondary device, direct current primary equipment formulate specific Parameter specifications, including physical parameter, operation ginseng Number, assets parameter and regulation and control operational factor.
4. establishment and the maintaining method of a kind of integrated power system resource model according to claim 1, it is characterised in that in institute State and device id, job number parameter are designed in integrated power system resource model, in planning and designing and construction period, pass through job number Tracking equipment information, in equipment operation, turn money, retired turn of recycling stage, pass through device id tracking equipment and assets information.
5. establishment and the maintaining method of a kind of integrated power system resource model according to claim 1, it is characterised in that to institute State it is defeated, become, carry out integrated design with each professional electric network model, it is contemplated that equipment difference and management difference, by 10kV and more than The equipment of voltage class carries out integrated design, is not divided by defeated, change, with specialty, each device type is established corresponding Facility information table and figure table, pass through the range of management of voltage class control device parameter;To the independent modeling of low-voltage equipment, with Adapt to the management mode that low-voltage equipment is different from high-tension apparatus.
CN201510025991.3A 2015-01-19 2015-01-19 A kind of integrated power system resource model and foundation and maintaining method Active CN104616101B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510025991.3A CN104616101B (en) 2015-01-19 2015-01-19 A kind of integrated power system resource model and foundation and maintaining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510025991.3A CN104616101B (en) 2015-01-19 2015-01-19 A kind of integrated power system resource model and foundation and maintaining method

Publications (2)

Publication Number Publication Date
CN104616101A CN104616101A (en) 2015-05-13
CN104616101B true CN104616101B (en) 2017-11-21

Family

ID=53150537

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510025991.3A Active CN104616101B (en) 2015-01-19 2015-01-19 A kind of integrated power system resource model and foundation and maintaining method

Country Status (1)

Country Link
CN (1) CN104616101B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105046427A (en) * 2015-07-10 2015-11-11 国家电网公司 Marketing associated equipment neuron-based three-level power grid asset group classification method
CN105447771A (en) * 2015-12-10 2016-03-30 国网四川省电力公司成都供电公司 Processing control method for low-voltage data in distribution network
CN106022961A (en) * 2016-05-20 2016-10-12 南京南瑞继保电气有限公司 Power grid multi-system comprehensive model building method
CN107045666A (en) * 2016-12-30 2017-08-15 国电南瑞科技股份有限公司 A kind of electric network model management method based on multisystem under the ground integrated environment of province
CN107016108A (en) * 2017-04-13 2017-08-04 广东电网有限责任公司电力科学研究院 The method for building up and device of transformer multiple physical field coupling model parameter database
CN107230162A (en) * 2017-05-19 2017-10-03 国家电网公司 Equipment alteration treating method and apparatus based on production management system
CN108090714A (en) * 2017-11-09 2018-05-29 国网山东省电力公司济宁供电公司 Distribution goods and materials secondary use scheme generation method and platform based on cities and counties' one
CN107958337A (en) * 2017-12-07 2018-04-24 国网江西省电力有限公司信息通信分公司 A kind of information resources visualize mobile management system
CN108717415B (en) * 2018-03-30 2020-04-14 广州供电局有限公司 Production equipment life cycle state data modeling method and system
CN110032552B (en) * 2019-03-27 2023-02-28 国网山东省电力公司青岛供电公司 Standardization system and method based on equipment transaction information and scheduling online update
CN111367939B (en) * 2020-03-04 2023-08-22 昆明海巍科技有限公司 Highway engineering project account compiling and managing system, method and computer
CN116579116B (en) * 2023-07-12 2023-10-10 南京南瑞信息通信科技有限公司 Method and system for integrated maintenance of distribution line diagram module

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103440546A (en) * 2013-08-02 2013-12-11 广东电网公司电力科学研究院 Method for automatically maintaining topological relation of power grid
KR20140028626A (en) * 2012-08-29 2014-03-10 주식회사 삼천리 Integrated system for co-generation system
CN103995932A (en) * 2014-05-22 2014-08-20 中国南方电网有限责任公司电网技术研究中心 Unified modeling method adopting generalized measurement transverse association mode
CN104036373A (en) * 2014-07-04 2014-09-10 云南电力调度控制中心 Power dispatching equipment main data management method based on data center
CN104143127A (en) * 2014-07-18 2014-11-12 国家电网公司 CIM-based three-diagram linkage processing method for distribution network

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20140028626A (en) * 2012-08-29 2014-03-10 주식회사 삼천리 Integrated system for co-generation system
CN103440546A (en) * 2013-08-02 2013-12-11 广东电网公司电力科学研究院 Method for automatically maintaining topological relation of power grid
CN103995932A (en) * 2014-05-22 2014-08-20 中国南方电网有限责任公司电网技术研究中心 Unified modeling method adopting generalized measurement transverse association mode
CN104036373A (en) * 2014-07-04 2014-09-10 云南电力调度控制中心 Power dispatching equipment main data management method based on data center
CN104143127A (en) * 2014-07-18 2014-11-12 国家电网公司 CIM-based three-diagram linkage processing method for distribution network

Also Published As

Publication number Publication date
CN104616101A (en) 2015-05-13

Similar Documents

Publication Publication Date Title
CN104616101B (en) A kind of integrated power system resource model and foundation and maintaining method
CN104133953B (en) Intelligent substation secondary design system
CN104123271B (en) Intelligent substation secondary design system based on Excel
CN103066698B (en) Implement method for automatic generation of visible power grid trend chart in dispatching system
CN101436790B (en) On-line splicing and coalition method for electric network model containing complex T connection line
CN103970887B (en) A kind of information flow display system and method based on GIS power distribution network figures
CN102957205B (en) A kind of method and system setting up electricity distribution network model
CN104135069B (en) Method for configuring operating parameters of secondary equipment of intelligent substation
CN106056481A (en) Distribution power multi-source data system and multi-source data processing method
CN108345739B (en) Method for identifying CIME and SVG model file information to realize protection fixed value on-line check function and obtain model
CN105095600A (en) Intelligent substation and regulation and control center coordinative modeling method
CN102929911A (en) All-in-one modeling method for transformer substation and dispatching master station
CN102521343B (en) Transformation method of input data of simulation software of power system
CN103065217A (en) Digital model splicing method of electric power setting calculating system
CN102708196B (en) Method for coordinating and sharing transformer substation end and dispatching end model based on E language
CN103246958B (en) Production concentrating operation system of provincial power metering center
CN104504485A (en) Integrative power system relay protection setting calculation method
CN102567603A (en) Method for automatically generating BPA calculation file based on actual measurement topology and measured data
CN105447175A (en) Power grid model sharing method applicable to distributed computation of power system
CN104915794A (en) Multi-time-state full-service unified modeling method based on model center
CN105976262A (en) Power plant granularity based power grid model version sharing method
CN114372594A (en) Distributed power supply comprehensive analysis and safety management and control system
WO2022150015A1 (en) A system for generating a mechanical and electrical service system design for a structure and a method thereof
CN113762724A (en) Method for collaborative design and management of power transmission and transformation project based on BIM technology
CN113793111A (en) Power equipment asset management method, system, device and storage medium

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20161220

Address after: 100031 West Chang'an Avenue, Beijing, No. 86

Applicant after: State Power Networks Co

Applicant after: State Grid Shanghai Municipal Electric Power Company

Applicant after: Nanjing Nari Group Corporation

Applicant after: NANJING NARI INFORMATION COMMUNICATION SCIENCE & TECHNOLOGY CO., LTD.

Address before: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant before: State Power Networks Co

Applicant before: Nanjing Nari Group Corporation

Applicant before: NANJING NARI INFORMATION COMMUNICATION SCIENCE & TECHNOLOGY CO., LTD.

GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100031 No. 86 West Chang'an Avenue, Beijing

Co-patentee after: STATE GRID SHANGHAI MUNICIPAL ELECTRIC POWER Co.

Patentee after: State Grid Corporation of China

Co-patentee after: NARI Group Corp.

Co-patentee after: NARI INFORMATION AND COMMUNICATION TECHNOLOGY Co.

Address before: 100031 No. 86 West Chang'an Avenue, Beijing

Co-patentee before: STATE GRID SHANGHAI MUNICIPAL ELECTRIC POWER Co.

Patentee before: State Grid Corporation of China

Co-patentee before: NARI Group CORPORATION STATE GRID ELECTRIC POWER INSTITUTE

Co-patentee before: NARI INFORMATION AND COMMUNICATION TECHNOLOGY Co.