CN104612294B - Stainless steel outer packed pipe drag-line and preparation method thereof - Google Patents

Stainless steel outer packed pipe drag-line and preparation method thereof Download PDF

Info

Publication number
CN104612294B
CN104612294B CN201410766522.2A CN201410766522A CN104612294B CN 104612294 B CN104612294 B CN 104612294B CN 201410766522 A CN201410766522 A CN 201410766522A CN 104612294 B CN104612294 B CN 104612294B
Authority
CN
China
Prior art keywords
steel strand
steel
coupling assembly
strand wires
thermoplastic tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410766522.2A
Other languages
Chinese (zh)
Other versions
CN104612294A (en
Inventor
徐瑞龙
吕品
张翠翠
王泽强
刘占省
尤德清
陈新礼
袁应战
张东
马锦姝
张晓迪
胡洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Building Construction Research Institute Co Ltd
Original Assignee
Beijing Building Construction Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Building Construction Research Institute Co Ltd filed Critical Beijing Building Construction Research Institute Co Ltd
Priority to CN201410766522.2A priority Critical patent/CN104612294B/en
Publication of CN104612294A publication Critical patent/CN104612294A/en
Application granted granted Critical
Publication of CN104612294B publication Critical patent/CN104612294B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ropes Or Cables (AREA)
  • Building Environments (AREA)

Abstract

The invention belongs to building engineering field, in particular it relates to a kind of stainless steel outer packed pipe drag-line.Stainless steel outer packed steel pipe drag-line includes the first steel strand wires coupling assembly, the second steel strand wires coupling assembly, single steel strand, polyethylene coating, the first thermoplastic tube, the second thermoplastic tube, stainless-steel pipe;First steel strand wires coupling assembly, the second steel strand wires coupling assembly are connected with the two ends of single steel strand respectively;Polyethylene coating is removed in single steel strand outsourcing polyethylene coating, single steel strand and the first steel strand wires coupling assembly, the second steel strand wires coupling assembly junction;First thermoplastic tube, the second thermoplastic tube are outer respectively to be wrapped in single steel strand and the first steel strand wires, the second steel strand wires coupling assembly junction;Stainless-steel pipe is enclosed within outside the single steel strand of outsourcing polyethylene coating.Present inventive concept is ingenious, simple structure meets the requirement of structure, and processes simple, greatly improves curtain wall construction efficiency, shortens the duration, is adapted to the large-scale promotion in rope net curtain wall.

Description

Stainless steel outer packed pipe drag-line and preparation method thereof
Technical field
The invention belongs to building engineering field, in particular it relates to a kind of stainless steel outer packed pipe drag-line and preparation method thereof.
Background technology
Rope net curtain wall is widely used in various utilities buildings as a kind of new curtain wall construction form, such as saloon The engineerings such as shop, high-grade office building, office building.At present, rope net curtain wall construction is by the rope net system reality for possessing standing wire power distribution It is existing, stainless steel cable is mostly used in engineering, price is high, and engineering cost is big.
Prestress wire is cheap, using technology and technique all highly developed today, complete advantageous substitution The steel cable often applied now, as the main bearing member of structure, engineering cost is reduced with this, improves profit, reduces valency Lattice.But steel strand wires outward appearance is unsightly a direct problem, current guy of twisted steel cable outward appearance is generally zinc-plated and two kinds of outsourcing PE, plating The original intention of the relatively costly and reduces cost of zinc steel strand wires is disagreed, and outsourcing PE guy of twisted steel cable can not solve the problems, such as fireproof, And the color of outsourcing PE differs too big with the tone of total.
In current construction market, urgent need wants that stainless steel cable can be replaced in a kind of intensity, and in appearance can be with it The relatively low guy of twisted steel cable of the engineering cost that compares favourably.Therefore, in building structure, high intensity (1670MPa-1860MPa) Guy of twisted steel cable is developed into rope net curtain wall and is very important using rope, but there is no this kind of complete sets of products at present.
The content of the invention
It is the defect for overcoming prior art to exist, the present invention provides a kind of stainless steel outer packed pipe drag-line and preparation method thereof, To solve the problems, such as that conventional guy of twisted steel cable is not suitable for being used in rope net curtain wall, while solving stainless steel outer packed pipe drag-line and showing The problem of some curtain wall pawl adaptors.
To achieve the above object, the present invention uses following proposal:
Stainless steel outer packed steel pipe drag-line, including:First steel strand wires coupling assembly, the second steel strand wires coupling assembly, single steel Twisted wire, polyethylene coating, the first thermoplastic tube, the second thermoplastic tube, stainless-steel pipe;Wherein:
First steel strand wires coupling assembly, the second steel strand wires coupling assembly are connected with the two ends of single steel strand respectively;
Single steel strand outsourcing polyethylene coating, single steel strand and the first steel strand wires coupling assembly, the second steel strand wires connect Remove polyethylene coating in connected components junction;
Single steel strand and the first steel strand wires coupling assembly junction are wrapped in outside first thermoplastic tube;It is wrapped in outside second thermoplastic tube The junction of single steel strand and the second steel strand wires coupling assembly;
Stainless-steel pipe is enclosed within outside the single steel strand of outsourcing polyethylene coating.
Relative to prior art, beneficial effects of the present invention are as follows:
1st, the new connected mode between the invention flexible steel twisted wire drag-line and rigid stainless steel tube, by there is bullet The structure weather-resistant glue of property makes to be integrally formed and can solve stress problem between the two.
2nd, the present invention can be used for load no more than 600KN tension members, and stainless steel outer packed pipe drag-line is in ripe steel strand wires It is derived on the basis of drag-line technique, the drag-line solves the inaesthetic problem of steel strand wires outward appearance, low cost, production efficiency It is high.
3rd, the present invention uses rubber seal at adaptor, stainless-steel pipe is solved well and between adaptor Connection.
4th, the requirement that present inventive concept is ingenious, simple structure meets structure, and process simple, greatly improve curtain wall construction Efficiency, shortens the duration, is adapted to the large-scale promotion in rope net curtain wall.
Brief description of the drawings
Fig. 1 is stainless steel outer packed steel pipe drag-line schematic front view;
Fig. 2 is stainless steel outer packed steel pipe drag-line schematic cross-sectional view;
Fig. 3 is the close-up schematic view of stainless steel outer packed steel pipe drag-line;
Fig. 4 is A-A generalized sections in Fig. 1;
Fig. 5 is B-B generalized sections in Fig. 1;
Fig. 6 is that stainless steel outer packed steel pipe drag-line installs adaptor axle side schematic diagram;
Fig. 7 is that stainless steel outer packed steel pipe drag-line installs adaptor floor map.
Specific embodiment
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 6, stainless steel outer packed steel pipe drag-line, including:First steel strand wires coupling assembly 11, Two steel strand wires coupling assemblies 12, single steel strand 2, polyethylene coating 3, the first thermoplastic tube 41, the second thermoplastic tube 42, stainless steel steel Pipe 6;Wherein:First steel strand wires coupling assembly 11, the second steel strand wires coupling assembly 12 connect with the two ends of single steel strand 2 respectively Connect, connected mode can use clip type or squash type;The one end of first steel strand wires coupling assembly 11 is set for fork ear anchor head, one end Cylinder, fork ear anchor head is connected with the component on steel construction, and sleeve is connected with guy of twisted steel cable, and fork ear anchor head uses single hinging-ear or double hinges Ear;Second steel strand wires coupling assembly 12 is adjustable fork ear anchor head, and one end is fork ear anchor head, one end is sleeve, centre is adjustable Section component, sleeve is connected with guy of twisted steel cable, and fork ear anchor head uses single hinging-ear or double hinge ears.
The outsourcing polyethylene coating 3 of single steel strand 2, the steel strand wires coupling assembly 11 of single steel strand 2 and first, the second steel are twisted Polyethylene coating 3 is removed in the junction of line coupling assembly 12, and removing length is 5cm.
The junction of 2 and first steel strand wires coupling assembly of single steel strand 11 is wrapped in outside first thermoplastic tube 41;Second thermoplastic tube The junction of the steel strand wires coupling assembly 12 of single steel strand 2 and second is wrapped in outside 42;
The length of the first thermoplastic tube 41 and the second thermoplastic tube 42 is controlled in 6cm, the first thermoplastic tube 41 and the second thermoplastic tube 42 color and the solid colour of polyethylene coating 3;First thermoplastic tube 41 and the second thermoplastic tube 42 are inserted in into the first steel respectively to twist Behind the junction of line coupling assembly 11, the second steel strand wires coupling assembly 12 and single steel strand 2, using heat gun to the first thermoplastic Pipe 41, the second thermoplastic tube 42 are heated, and make the heat-shrink tube after contraction interface tightly sleeve.
First thermoplastic tube 41 and the second thermoplastic tube 42 apply outward structure weather-resistant glue 5 with the part of the joint of single steel strand 2, Smear length 3cm;
Stainless-steel pipe 6 is enclosed within outside the single steel strand 2 of outsourcing polyethylene coating 3;
Stainless-steel pipe 6, is disconnected using whole steel pipe or point more piece;
For the stainless-steel pipe 6 that point more piece disconnects, according to size cutting is actually needed during disconnection, in adjacent two for disconnecting Two rubber blankets 8, length 2cm, encapsulant when rubber blanket 8 is to install are inserted between section stainless-steel pipe 6;During in-site installation Adaptor 9, adaptor 9 is needed to be connected by screw bolts using unidirectional, two-way and multidirectional form, adaptor 9 is fastened on and is surrounded by poly- second Above the single steel strand 2 of ene coatings 3, middle gap is sealed using rubber blanket 8.
The specific implementation preparation method (whole stainless-steel pipe) of above-mentioned stainless steel outer packed pipe drag-line, comprises the following steps:
Step 1:Selection single steel strand 2, by its outsourcing polyethylene coating 3;
Step 2:The single steel strand 2 of single outsourcing polyethylene coating 3 is selected, by design size blanking, and by single steel Twisted wire 2 is disposed with the first steel strand wires coupling assembly 11, the junction polyethylene coating 3 of the second steel strand wires coupling assembly 12, is removed Length is 5cm;
Step 3:The first thermoplastic tube 41 is inserted in one end of single steel strand 2 of outsourcing polyethylene coating 3 first, then by it The first steel strand wires connector 11 is stretched into, after the installation of 2 and first steel strand wires connector of single steel strand 11 terminates, with heat gun heat The first thermoplastic tube 41 is closed, sealing tightly sleeve is got up;
Step 4:Whole stainless-steel pipe 6 is inserted in from the other end of the single steel strand 2 of outsourcing polyethylene coating 3;
Step 5:Structure weather-resistant glue 5 is applied at thermoplastic tube 41 to full, the length of structure weather-resistant glue 5 is in 3 cms;Will End stainless-steel pipe 6 is firmly bonded with structure weather-resistant glue 5;
Step 6:The other end of the single steel strand 2 of outsourcing polyethylene coating 3 is inserted in the second heat-shrink tube 42, Ran Houshen first To the second steel strand wires coupling assembly 12, the single steel strand 2 of the second steel strand wires coupling assembly 12 and outsourcing polyethylene coating 5 is treated After installing, with the second thermoplastic tube of heat gun heat seal 42;
Step 7:Structure weather-resistant glue 5 is applied at the second thermoplastic tube 42 to full, the length of structure weather-resistant glue 5 is on 3 centimetres of left sides The right side, stainless-steel pipe 6 is firmly bonded with structure weather-resistant glue 5, is made single stainless steel outer packed steel pipe drag-line.
The specific implementation preparation method (disconnection stainless steel tube) of above-mentioned stainless steel outer packed pipe drag-line, comprises the following steps:
Step 1:Selection single steel strand 2, by its outsourcing polyethylene coating 3;
Step 2:The single steel strand 2 of single outsourcing polyethylene coating 3 is selected, by design size blanking, and by single steel Twisted wire 2 is disposed with the first steel strand wires coupling assembly 11, the junction polyethylene coating 3 of the second steel strand wires coupling assembly 12, is removed Length is 5cm;
Step 3:The first thermoplastic tube 41 is inserted in one end of single steel strand 2 of outsourcing polyethylene coating 3 first, then by it The first steel strand wires connector 11 is stretched into, after the installation of 2 and first steel strand wires connector of single steel strand 11 terminates, with heat gun heat The first thermoplastic tube 41 is closed, sealing tightly sleeve is got up;
Step 4:The stainless of disconnection is inserted in successively in order from the other end of the single steel strand 2 of outsourcing polyethylene coating 3 Steel steel pipe 6 and rubber blanket 8, two rubber blankets 8 are inserted between the every two sections of stainless steel tubes 6 for disconnecting.
Step 5:Structure weather-resistant glue 5 is applied at thermoplastic tube 41 to full, the length of structure weather-resistant glue 5 is in 3 cms;Will End stainless-steel pipe 6 is firmly bonded with structure weather-resistant glue 5;
Step 6:The other end of the single steel strand 2 of outsourcing polyethylene coating 3 is inserted in the second heat-shrink tube 42, Ran Houshen first To the second steel strand wires coupling assembly 12, the single steel strand 2 of the second steel strand wires coupling assembly 12 and outsourcing polyethylene coating 3 is treated After installing, with the second thermoplastic tube of heat gun heat seal 42;
Step 7:Structure weather-resistant glue 5 is applied at the second thermoplastic tube 42 to full, the length of structure weather-resistant glue 5 is on 3 centimetres of left sides The right side, stainless-steel pipe 6 is firmly bonded with structure weather-resistant glue 5, is made single stainless steel outer packed steel pipe drag-line.
Step 8:For the stainless-steel pipe 3 that point more piece disconnects, adaptor 9, adaptor 9 is needed to be during in-site installation Unidirectionally, two-way and multidirectional form, is connected by screw bolts, and adaptor 9 fastens the outside of single steel strand 2 of outsourcing polyethylene coating 3, Middle gap is sealed using rubber blanket 8.

Claims (5)

1. a kind of stainless steel outer packed steel pipe drag-line, including:It is first steel strand wires coupling assembly, the second steel strand wires coupling assembly, single Steel strand wires, polyethylene coating, the first thermoplastic tube, the second thermoplastic tube, stainless-steel pipe;It is characterized in that:Single steel strand outsourcing Polyethylene coating, the first steel strand wires coupling assembly, the second steel strand wires coupling assembly are connected with the two ends of single steel strand respectively, single Polyethylene coating is removed in root steel strand wires and the first steel strand wires coupling assembly, the second steel strand wires coupling assembly junction;First thermoplastic Pipe is outer to be wrapped in single steel strand and the first steel strand wires coupling assembly junction;Single steel strand and second are wrapped in outside second thermoplastic tube The junction of steel strand wires coupling assembly;Stainless-steel pipe is enclosed within outside the single steel strand of outsourcing polyethylene coating;
First thermoplastic tube and the second thermoplastic tube apply outward structure weather-resistant glue with the part of single steel strand joint, smear length 3cm;
Stainless-steel pipe, is disconnected using whole steel pipe or point more piece;
First steel strand wires coupling assembly, the second steel strand wires coupling assembly use folder with the two ends connected mode of single steel strand respectively Chip or squash type;First steel strand wires coupling assembly one end is sleeve for fork ear anchor head, one end, on fork ear anchor head and steel construction Component is connected, and sleeve is connected with guy of twisted steel cable, and fork ear anchor head uses single hinging-ear or double hinge ears;Second steel strand wires coupling assembly is Adjustable fork ear anchor head, one end is fork ear anchor head, one end is sleeve, centre is adjustable members, and sleeve connects with guy of twisted steel cable Connect, fork ear anchor head uses single hinging-ear or double hinge ears;
First thermoplastic tube and the second thermoplastic tube are inserted in the first steel strand wires coupling assembly, the second steel strand wires coupling assembly and list respectively Behind the junction of root steel strand wires, the first thermoplastic tube, the second thermoplastic tube are heated using heat gun, connect the handle of the heat-shrink tube after contraction Tight-lipped tight sleeve is got up;
For the stainless-steel pipe that point more piece disconnects, according to size cutting is actually needed during disconnection, in adjacent two sections for disconnecting not Two rubber blankets, length 2cm are inserted between rust steel steel pipe, rubber blanket is encapsulant when installing;Need to turn during in-site installation Fitting, adaptor is connected by screw bolts using unidirectional, two-way and multidirectional form, and adaptor is fastened on and is surrounded by polyethylene coating Above single steel strand, middle gap is sealed using rubber blanket.
2. stainless steel outer packed steel pipe drag-line according to claim 1, it is characterised in that:Removing length is 5cm.
3. stainless steel outer packed steel pipe drag-line according to claim 2, it is characterised in that:First thermoplastic tube and the second thermoplastic tube Length control in 6cm, the color of the first thermoplastic tube and the second thermoplastic tube and the solid colour of polyethylene coating.
4. the preparation method of the stainless steel outer packed pipe drag-line described in claim 1, it is characterised in that comprise the following steps:
Step 1:Selection single steel strand, by its outsourcing polyethylene coating;
Step 2:Select the single steel strand of single outsourcing polyethylene coating, by design size blanking, and by single steel strand with First steel strand wires coupling assembly, the second steel strand wires coupling assembly junction polyethylene coating are disposed, and removing length is 5cm;
Step 3:The first thermoplastic tube is inserted in single steel strand one end of outsourcing polyethylene coating first, first is then stretched into Steel strand wires connector, after single steel strand and the first steel strand wires connector are installed and terminated, with the thermoplastic tube of heat gun heat seal first, Sealing tightly sleeve is got up;
Step 4:Whole stainless-steel pipe is inserted in from the other end of the single steel strand of outsourcing polyethylene coating;
Step 5:Structure weather-resistant glue is applied at thermoplastic tube to full, the length of structure weather-resistant glue is at 3 centimetres;By end stainless steel steel Pipe is firmly bonded with structure weather-resistant glue;
Step 6:The other end of the single steel strand of outsourcing polyethylene coating is inserted in the second heat-shrink tube first, then extends the second steel In twisted wire coupling assembly, after the single steel strand of the second steel strand wires coupling assembly and outsourcing polyethylene coating is installed, use The thermoplastic tube of heat gun heat seal second;
Step 7:Structure weather-resistant glue is applied at the second thermoplastic tube to full, the length of structure weather-resistant glue at 3 centimetres, by stainless steel steel Pipe is firmly bonded with structure weather-resistant glue, is made single stainless steel outer packed steel pipe drag-line.
5. the specific implementation preparation method of the stainless steel outer packed pipe drag-line described in claim 1, it is characterised in that including following step Suddenly:
Step 1:Selection single steel strand, by its outsourcing polyethylene coating;
Step 2:Select the single steel strand of single outsourcing polyethylene coating, by design size blanking, and by single steel strand with First steel strand wires coupling assembly, the second steel strand wires coupling assembly junction polyethylene coating are disposed, and removing length is 5cm;
Step 3:The first thermoplastic tube is inserted in single steel strand one end of outsourcing polyethylene coating first, first is then stretched into Steel strand wires connector, after single steel strand and the first steel strand wires connector are installed and terminated, with the thermoplastic tube of heat gun heat seal first, Sealing tightly sleeve is got up;
Step 4:It is inserted in the stainless-steel pipe of disconnection successively in order from the other end of the single steel strand of outsourcing polyethylene coating And rubber blanket, it is inserted in two rubber blankets between the every two sections of stainless steel tubes for disconnecting;
Step 5:Structure weather-resistant glue is applied at thermoplastic tube to full, the length of structure weather-resistant glue is at 3 centimetres;By end stainless steel steel Pipe is firmly bonded with structure weather-resistant glue;
Step 6:The other end of the single steel strand of outsourcing polyethylene coating is inserted in the second heat-shrink tube first, then extends the second steel In twisted wire coupling assembly, after the single steel strand of the second steel strand wires coupling assembly and outsourcing polyethylene coating is installed, use The thermoplastic tube of heat gun heat seal second;
Step 7:Structure weather-resistant glue is applied at the second thermoplastic tube to full, the length of structure weather-resistant glue at 3 centimetres, by stainless steel steel Pipe is firmly bonded with structure weather-resistant glue, is made single stainless steel outer packed steel pipe drag-line;
Step 8:For the stainless-steel pipe that point more piece disconnects, need adaptor during in-site installation, adaptor for unidirectional, two-way or Multidirectional form, is connected by screw bolts, and adaptor fastens the single steel strand outside of outsourcing polyethylene coating, and middle gap uses Rubber blanket is sealed.
CN201410766522.2A 2014-08-20 2014-12-11 Stainless steel outer packed pipe drag-line and preparation method thereof Expired - Fee Related CN104612294B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410766522.2A CN104612294B (en) 2014-08-20 2014-12-11 Stainless steel outer packed pipe drag-line and preparation method thereof

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN2014104108068 2014-08-20
CN201410410806 2014-08-20
CN201410766522.2A CN104612294B (en) 2014-08-20 2014-12-11 Stainless steel outer packed pipe drag-line and preparation method thereof

Publications (2)

Publication Number Publication Date
CN104612294A CN104612294A (en) 2015-05-13
CN104612294B true CN104612294B (en) 2017-06-06

Family

ID=53146922

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410766522.2A Expired - Fee Related CN104612294B (en) 2014-08-20 2014-12-11 Stainless steel outer packed pipe drag-line and preparation method thereof

Country Status (1)

Country Link
CN (1) CN104612294B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109372007B (en) * 2018-11-28 2023-11-07 长江三峡集团福建能源投资有限公司 Sealing anchor bolt for installing anchor bolt cage of offshore wind turbine and construction method of sealing anchor bolt

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2692918B1 (en) * 1992-06-25 1994-09-23 Freyssinet Int & Co Improvements to the devices for holding the multiple strands constituting a stay cable juxtaposed laterally.
US20040159058A1 (en) * 2003-02-19 2004-08-19 Jacques Gulbenkian Unbonded post-tensioning system
CN200992685Y (en) * 2006-12-31 2007-12-19 巨力集团有限公司 Sleeve-regulating hot-cast anchor cable
CN101581070A (en) * 2008-05-14 2009-11-18 柳州欧维姆机械股份有限公司 Metallic corrugated pipe guard cable
CN102587572A (en) * 2012-04-01 2012-07-18 北京市建筑工程研究院有限责任公司 Steel strand stay rope and manufacturing method thereof
CN202969273U (en) * 2012-12-21 2013-06-05 安徽省交通投资集团有限责任公司 Cable-stayed bridge stay cable with saddle anchoring sections with composite sheaths

Also Published As

Publication number Publication date
CN104612294A (en) 2015-05-13

Similar Documents

Publication Publication Date Title
CN104896261B (en) Pipeline heat insulation pipe sleeve
CN204065499U (en) Anti-unfirmly closing ADSS optical cable
CN104612294B (en) Stainless steel outer packed pipe drag-line and preparation method thereof
CN201947480U (en) Joint of carbon fiber heat tracing belt
CN105914662A (en) Cable traction assembly and method of preventing cable stretching
CN106400685B (en) A kind of cord clip of suspension bridge and its construction method of installation with sealing structure
CN101201438A (en) Optical communication transmission network
CN201321597Y (en) Component used for corrosion protection, sealing and thermal shrinkage for steel cables and linking base of stay cable bridge
CN104164836A (en) Protection method for stainless steel combined casing pipe for bridge cable
CN202979330U (en) Floor heating cable with crimping joint
CN205582592U (en) Rubber sleeve cable head device that blocks water
CN104113035A (en) Cable intermediate joint and connecting method thereof
CN204717236U (en) Pipeline heat insulation pipe box
CN204030541U (en) A kind of cable built-in optical fiber transition joint
CN203983938U (en) A kind of cable intermediate joint
CN203930125U (en) Jumping fiber is strengthened in shaping protection
CN201956489U (en) Coaxial cable connector
CN105161228B (en) Insulation sleeve assembly for overhead wire and application method of insulation sleeve assembly
CN205429651U (en) Strain clamp
CN201708019U (en) 10kV wind power variable high voltage outlet structure
CN204858508U (en) A bi -pass sleeve pipe for power cable
CN204614491U (en) Dry type high water resistant telecommunication cable
CN203746529U (en) Photoelectric composite cable preventing a wall from cracking
CN109378775A (en) A kind of sealing of cable cold shrink type joint, which blocks water, optimizes production method
CN210318929U (en) Connecting and sealing structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Xu Ruilong

Inventor after: Ma Jinshu

Inventor after: Zhang Xiaodi

Inventor after: Hu Yang

Inventor after: Lv Pin

Inventor after: Zhang Cuicui

Inventor after: Wang Zeqiang

Inventor after: Liu Zhansheng

Inventor after: You Deqing

Inventor after: Chen Xinli

Inventor after: Yuan Yingzhan

Inventor after: Zhang Dong

Inventor before: Xu Ruilong

Inventor before: Lv Pin

Inventor before: Zhang Cuicui

Inventor before: Wang Zeqiang

Inventor before: Liu Zhansheng

Inventor before: You Deqing

Inventor before: Chen Xinli

Inventor before: Yuan Yingzhan

Inventor before: Zhang Dong

GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170606