CN104601372B - A kind of intelligent substation void circuit visualization comparison method based on three layer patterns - Google Patents

A kind of intelligent substation void circuit visualization comparison method based on three layer patterns Download PDF

Info

Publication number
CN104601372B
CN104601372B CN201410813240.3A CN201410813240A CN104601372B CN 104601372 B CN104601372 B CN 104601372B CN 201410813240 A CN201410813240 A CN 201410813240A CN 104601372 B CN104601372 B CN 104601372B
Authority
CN
China
Prior art keywords
link
intelligent substation
information
circuit
void
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410813240.3A
Other languages
Chinese (zh)
Other versions
CN104601372A (en
Inventor
娄悦
曹卫国
秦健
巫怀军
马敏杰
王展
黄河
赵娜
宗柳
高笑青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING WUCAIZHIDIAN ELECTRIC POWER TECHNOLOGY Co Ltd
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
China Energy Engineering Group Jiangsu Power Design Institute Co Ltd
Original Assignee
NANJING WUCAIZHIDIAN ELECTRIC POWER TECHNOLOGY Co Ltd
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
China Energy Engineering Group Jiangsu Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING WUCAIZHIDIAN ELECTRIC POWER TECHNOLOGY Co Ltd, State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, China Energy Engineering Group Jiangsu Power Design Institute Co Ltd filed Critical NANJING WUCAIZHIDIAN ELECTRIC POWER TECHNOLOGY Co Ltd
Priority to CN201410813240.3A priority Critical patent/CN104601372B/en
Publication of CN104601372A publication Critical patent/CN104601372A/en
Application granted granted Critical
Publication of CN104601372B publication Critical patent/CN104601372B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing And Monitoring For Control Systems (AREA)
  • Design And Manufacture Of Integrated Circuits (AREA)

Abstract

The invention discloses a kind of intelligent substation void circuits based on three layer patterns to visualize comparison method, and this method is from three device, link and link channel levels, with the top-down comparison that empty circuit is done step-by-step of patterned way.The advantageous effect that the present invention is reached:By the way that the comparative pattern in intelligent substation void circuit is visualized, monitor the variation of empty loop configuration information in SCD file caused by including reorganization and expansion process in real time, ensure security, integrality, the uniformity of empty loop configuration information to greatest extent, change the poorly efficient and fragile present situation for ensureing empty loop configuration correctness by manpower, so as to ensure and be promoted intelligent substation safety operation level, shortening system puts into operation the time, mitigation system puts into operation pressure, reduces the maintenance cost in intelligent substation life cycle management.

Description

A kind of intelligent substation void circuit visualization comparison method based on three layer patterns
Technical field
The present invention relates to a kind of intelligent substation void circuits based on three layer patterns to visualize comparison method, belongs to intelligent change The figure presentation technology field in power station.
Background technology
Increasingly perfect with intelligent substation correlation technique, intelligent substation steps into the extensive practical stage. In intelligent substation, process-level network connection primary equipment and bay device, between completion bay device and primary equipment, Real time information between bay device exchanges, and uses digital transmission technology(Fiber optic Ethernet)Instead of edge in conventional substation With secondary cable for many years, the interoperability to realize data sharing and equipment provides necessary technical foundation, this is great Change will be to the form of secondary device in future substation, equipment debugging flow, each side such as station and operations specification Face will all generate deep effect.
Traditional substation is compared, Secondary Design a big chunk drawing of intelligent substation becomes to be described by system configuration (SCD)The virtual terminator connection of File Mapping, this document configuration correctness is most important to the safe operation of intelligent substation, especially Expressed virtual terminator and reflect the empty circuit of virtual terminator connection relation in SCD file, influence intelligent substation breaker tripping and closing, The secondary circuits connection relations such as sampling, it is extremely important to the safe operation of intelligent substation.But SCD file is described by SCL language, Empty loop configuration information can not be intuitively embodied, considerably increases exam of design core, debugging, O&M, maintenance and reorganization and expansion overall process Grasp the difficulty of whole station configuration.
The content of the invention
To solve the deficiencies in the prior art, it is an object of the invention to provide a kind of intelligent substation void circuits to visualize ratio To method, the variation of empty loop configuration information in SCD file caused by including reorganization and expansion process is monitored in real time, to greatest extent The empty loop configuration information of guarantee security, integrality, uniformity, change by manpower to ensure empty loop configuration correctness Poorly efficient and fragile present situation, so as to ensure and be promoted intelligent substation safety operation level, shortening system puts into operation the time, mitigate System puts into operation pressure, reduces the maintenance cost in intelligent substation life cycle management.
In order to realize above-mentioned target, the present invention adopts the following technical scheme that:
A kind of intelligent substation void circuit visualization comparison method based on three layer patterns, it is characterized in that, including walking as follows Suddenly:
1)First layer based on device void circuit cyclic redundancy check compares:It is all related to device void circuit by extracting Information, and be the unique empty circuit cyclic redundancy check of each device generation according to the information;To the empty circuit cyclic redundancy check It is compared, whether the empty loop configuration information for comparing each device changes, and determines changed device;
2)The second layer based on device link information compares:By to step 1)In changed device into line link believe Breath comparison, from the situation of change of device interaction angle-determining link;
3)Third layer based on link channel information compares:By to step 2)In change the link of information into row of channels Information compares, the situation of change from virtual terminator interaction angle-determining void circuit.
A kind of foregoing intelligent substation void circuit visualization comparison method based on three layer patterns, it is characterized in that, it is described Step 1)The generation of middle void circuit cyclic redundancy check includes the following steps;
1)It is extracted in units of IED devices and the relevant empty loop configuration information of IED devices this described;The void circuit Configuration information mainly includes GOOSE and sends information, GOOSE receive informations, SV transmission information and SV receive informations;
2)In the step 1)Afterwards using the CRC algorithm generation cyclic redundancy check of 32 as empty loop configuration information Identifier.
A kind of foregoing intelligent substation void circuit visualization comparison method based on three layer patterns, it is characterized in that, it is described Step 1)The comparison of middle void circuit cyclic redundancy check is using IED device names as matching keyword, by graphical list mode, and with Color marks the IED devices of different cyclic redundancy checks, quickly compares the empty changed dress of loop configuration information on the whole It puts.
A kind of foregoing intelligent substation void circuit visualization comparison method based on three layer patterns, it is characterized in that, it is described Step 2)The comparison of link information includes following aspect:Newly-increased link reduces link and link data variation;By with single IED devices are visual angle, with the link relation of patterned way displaying IED devices and outer device, and pass through patterned symbol mark The change information of the link of two version apparatus of note, the patterned way are specific as follows:
1)Using the "+" symbol logo link as newly-increased link on respective links figure;
2)Using the "-" symbol logo link as reduction link on respective links figure;
3)On respective links figure with "!" the symbol logo link is there are link data variations.
A kind of foregoing intelligent substation void circuit visualization comparison method based on three layer patterns, it is characterized in that, it is described Step 3)The comparison of link passage includes following aspect:Newly-increased passage reduces passage, channel data variation;By with single chain Road is visual angle, and the variation of the link channel is shown with graphical forms mode, and marks two versions by patterned symbol This link channel change information, specific patterned way are as follows:
(1)Using the "+" symbol logo passage as newly-increased passage on respective channel figure;
(2)Using the "-" symbol logo passage as reduction passage on respective channel figure;
(3)On respective channel figure with "!" the symbol logo passage is there are channel data variations.
The advantageous effect that the present invention is reached:By the way that the comparative pattern in intelligent substation void circuit is visualized, supervise in real time The variation of empty loop configuration information in SCD file caused by including reorganization and expansion process is controlled, ensures empty circuit to greatest extent Security, integrality, the uniformity of configuration information change by manpower to ensure the poorly efficient and fragile of empty loop configuration correctness Present situation, so as to ensure and be promoted intelligent substation safety operation level, put into operation time, mitigation system of shortening system puts into operation pressure Power reduces the maintenance cost in intelligent substation life cycle management.
Description of the drawings
Fig. 1 is that the first layer based on device void circuit cyclic redundancy check compares schematic diagram in the present invention;
Fig. 2 is that the second layer based on device link information compares schematic diagram in the present invention;
Fig. 3 is that the third layer based on link channel information compares schematic diagram in the present invention.
Specific embodiment
The invention will be further described below in conjunction with the accompanying drawings.Following embodiment is only used for clearly illustrating the present invention Technical solution, and be not intended to limit the protection scope of the present invention and limit the scope of the invention.
It is of the present invention it is a kind of based on three layer patterns intelligent substation void circuit visualization comparison method, this method from Three device, link and link channel levels, with the top-down comparison that empty circuit is done step-by-step of patterned way.Including as follows Three steps:
1)First layer based on device void circuit cyclic redundancy check compares:
Such as Fig. 1, the calculating of empty circuit cyclic redundancy check is mainly to the SCD file of input, for all dresses in this document It puts, is unique empty time of each device generation by extracting all and relevant information in device void circuit, and according to the information Road cyclic redundancy check;Empty circuit cyclic redundancy check is compared, can quickly compare the empty loop configuration letter of each device Whether breath changes, and determines changed device.
In this step specifically empty circuit is relatively related generally in the first layer based on device void circuit cyclic redundancy check The generation of cyclic redundancy check and two steps of comparison of empty circuit cyclic redundancy check.
Wherein, the generation of empty circuit cyclic redundancy check includes following two steps;
Step(1):It is extracted in units of IED devices and the relevant empty loop configuration information of the IED devices.IED devices Between the reaction of empty circuit be GOOSE in communication network and SV transmission control information transmission/reception correspondence.And SCD The product that file is integrated as system configuration contains all system configuration informations of whole station, and GOOSE/ is sent including IED devices The messaging parameter of SV control information, the acceptable GOOSE/SV message contents for coming from other devices of IED devices etc..It is specific next Say that can be extracted from SCD file mainly includes GOOSE transmission letters to describe single IED devices void loop configuration information Breath, GOOSE receive informations, SV send information and SV receive informations.
Step(2):In step(1)Afterwards using the CRC algorithm generation cyclic redundancy check of 32 as empty loop configuration information Identifier.First, the IED device void loop configuration information extracted can be expressed in the form of binary stream, binary system Stream can be the binary data file on one section of internal storage data or disk in computer program, and concrete form can be by computer Program voluntarily selects.Secondly, 32 CRC generator polynomials that generator polynomial may be selected to be widely used and have been standardized, for example, X32+x26+x23+...+x2+x+1 or x32+x28+x27+...+x8+x6+1.It is of course also possible to do not provide that CRC generations are more Item formula, as long as safeguarding that the computer program of check code uses same generator polynomial.Finally, CRC algorithm right and wrong Often ripe checking algorithm is applied to the 32 of binary data and agreement for CRC generator polynomials in algorithm, you can must be right The cyclic redundancy check answered, and IED void loop configuration information is identified with this.
The comparison of empty circuit cyclic redundancy check passes through each IED devices generation mark in the SCD file for two different editions The cyclic redundancy check of its empty loop configuration information, using IED device names as matching keyword, by graphical list mode, and with face Colour code notes the IED devices of different cyclic redundancy checks, quickly compares the empty changed device of loop configuration information on the whole.
2)The second layer based on device link information compares:
Such as Fig. 2, device link information reflects the information exchanged between device by GOOSE and SV, by step 1)In Changed device is compared into downlink message, from the situation of change of device interaction angle-determining link.
Link information comparison includes following aspect:Newly-increased link reduces link and link data variation.By with single IED devices are visual angle, with the link relation of patterned way displaying IED devices and outer device, and pass through patterned symbol mark The change information of the link of two version apparatus of note.
Here patterned way specifically uses following scheme:
(1)Using the "+" symbol logo link as newly-increased link on respective links figure;
(2)Using the "-" symbol logo link as reduction link on respective links figure;
(3)On respective links figure with "!" the symbol logo link is there are link data variations.
3)Third layer based on link channel information compares:
Such as Fig. 3, the channel data of actual transmissions, is embodied in hair in the link between link channel message reflection device A pair of of virtual terminator of the side of sending and recipient connect, by step 2)In have data variation link carry out channel information comparison, Situation of change from virtual terminator interaction angle-determining void circuit.
Link channel comparison includes following aspect:Newly-increased passage reduces passage, channel data variation.By with single chain Road is visual angle, and the variation of the link channel is shown with graphical forms mode, and marks two versions by patterned symbol This link channel change information.
Here specific patterned way is as follows:
(1)Using the "+" symbol logo passage as newly-increased passage on respective channel figure;
(2)Using the "-" symbol logo passage as reduction passage on respective channel figure;
(3)On respective channel figure with "!" the symbol logo passage is there are channel data variations.
By the way that the comparative pattern in intelligent substation void circuit is visualized, real time monitoring includes changing the method that the present invention uses The variation of empty loop configuration information in SCD file caused by including enlarging process, ensures empty loop configuration information to greatest extent Security, integrality, uniformity, change by manpower to ensure the poorly efficient and fragile present situation of empty loop configuration correctness, So as to ensure and be promoted intelligent substation safety operation level, put into operation time, mitigation system of shortening system puts into operation pressure, reduces intelligence Maintenance cost in energy substation life cycle management.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the technical principles of the invention, several improvement and deformation can also be made, these are improved and deformation Also it should be regarded as protection scope of the present invention.

Claims (5)

1. a kind of intelligent substation void circuit visualization comparison method based on three layer patterns, it is characterized in that, include the following steps:
1)First layer based on device void circuit cyclic redundancy check compares:By extracting all and relevant letter in device void circuit Breath, and be the unique empty circuit cyclic redundancy check of each device generation according to the information;The empty circuit cyclic redundancy check is carried out Whether comparison, the empty loop configuration information for comparing each device change, and determine changed device;
2)The second layer based on device link information compares:By to step 1)In changed device into downlink message pair Than from the situation of change of device interaction angle-determining link;
3)Third layer based on link channel information compares:By to step 2)In change information link carry out channel information Comparison, the situation of change from virtual terminator interaction angle-determining void circuit.
2. a kind of intelligent substation void circuit visualization comparison method based on three layer patterns according to claim 1, It is characterized in, the step 1)The generation of middle void circuit cyclic redundancy check includes the following steps;
1)It is extracted in units of IED devices and the relevant empty loop configuration information of IED devices this described;The void loop configuration Information mainly includes GOOSE and sends information, GOOSE receive informations, SV transmission information and SV receive informations;
2)In the step 1)Afterwards using mark of the CRC algorithm generation cyclic redundancy check of 32 as empty loop configuration information Symbol.
3. a kind of intelligent substation void circuit visualization comparison method based on three layer patterns according to claim 1, It is characterized in, the step 1)The comparison of middle void circuit cyclic redundancy check is arranged using IED device names as matching keyword by figure Table mode, and with the IED devices of the different cyclic redundancy checks of color mark, empty loop configuration information hair is quickly compared on the whole The device for changing.
4. a kind of intelligent substation void circuit visualization comparison method based on three layer patterns according to claim 1, It is characterized in, the step 2)The comparison of link information includes following aspect:Newly-increased link reduces link and link data variation; By using single IED devices as visual angle, with the link relation of patterned way displaying IED devices and outer device, and passing through figure The symbol of change marks the change information of the link of two version apparatus, and the patterned way is specific as follows:
1)Using the "+" symbol logo link as newly-increased link on respective links figure;
2)Using the "-" symbol logo link as reduction link on respective links figure;
3)On respective links figure with "!" the symbol logo link is there are link data variations.
5. a kind of intelligent substation void circuit visualization comparison method based on three layer patterns according to claim 1, It is characterized in, the step 3)The comparison of link passage includes following aspect:Newly-increased passage reduces passage, channel data variation;It is logical It crosses using single link as visual angle, the variation of the link channel is shown with graphical forms mode, and pass through patterned symbol Two version link channel change informations are marked, specific patterned way is as follows:
(1)Using the "+" symbol logo passage as newly-increased passage on respective channel figure;
(2)Using the "-" symbol logo passage as reduction passage on respective channel figure;
(3)On respective channel figure with "!" the symbol logo passage is there are channel data variations.
CN201410813240.3A 2014-12-24 2014-12-24 A kind of intelligent substation void circuit visualization comparison method based on three layer patterns Active CN104601372B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410813240.3A CN104601372B (en) 2014-12-24 2014-12-24 A kind of intelligent substation void circuit visualization comparison method based on three layer patterns

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410813240.3A CN104601372B (en) 2014-12-24 2014-12-24 A kind of intelligent substation void circuit visualization comparison method based on three layer patterns

Publications (2)

Publication Number Publication Date
CN104601372A CN104601372A (en) 2015-05-06
CN104601372B true CN104601372B (en) 2018-06-05

Family

ID=53126897

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410813240.3A Active CN104601372B (en) 2014-12-24 2014-12-24 A kind of intelligent substation void circuit visualization comparison method based on three layer patterns

Country Status (1)

Country Link
CN (1) CN104601372B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105577428A (en) * 2015-12-14 2016-05-11 南京国电南自电网自动化有限公司 Intelligent substation virtual loop comprehensive monitoring system based on multidimensional information acquisition
CN109582719B (en) * 2018-10-19 2021-08-24 国电南瑞科技股份有限公司 Method and system for automatically linking SCD file of intelligent substation to virtual terminal
CN110865849B (en) * 2019-11-04 2022-03-11 国网四川省电力公司电力科学研究院 Intelligent substation configuration file management and control method for improving debugging and operation and inspection efficiency
CN111009966A (en) * 2019-11-22 2020-04-14 贵州电网有限责任公司 Data interaction system, method and device of transformer substation equipment and storage medium

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6988025B2 (en) * 2000-11-28 2006-01-17 Power Measurement Ltd. System and method for implementing XML on an energy management device
EP1850109A1 (en) * 2006-04-24 2007-10-31 ABB Research Ltd Intelligent electronic device configuration verification
CN102611199B (en) * 2012-03-07 2014-04-02 长园深瑞继保自动化有限公司 Design and configuration integrated system for intelligent substation
CN103077093B (en) * 2013-01-14 2015-04-01 山东电力集团公司 Substation configuration description (SCD) calibration method based on model objectification semantics
CN103106623A (en) * 2013-02-02 2013-05-15 北京智网创能科技有限公司 Graphical display method of substation configuration description (SCD) file of intelligent substation
CN103218398B (en) * 2013-03-13 2015-02-25 江苏省电力公司电力科学研究院 Intelligent substation SCL (substation configuration description language) file difference comparison method
US20140282021A1 (en) * 2013-03-15 2014-09-18 Schweitzer Engineering Laboratories, Inc. Visualization of Communication Between Devices in an Electric Power System
CN103578048A (en) * 2013-11-13 2014-02-12 国家电网公司 Method for checking and comparing configuration related information of intelligent substation SCL documents
CN103593742A (en) * 2013-11-29 2014-02-19 国家电网公司 Secondary circuit configuration controlling method and system for intelligent substation
CN103927332A (en) * 2014-03-24 2014-07-16 河海大学 IEC (international electrotechnical commission) 61850-based visual graphics configuration method and IEC61850-based visual graphics configuration system
CN103942734B (en) * 2014-04-25 2017-09-26 国网四川省电力公司电力科学研究院 Various dimensions graphic software platform method based on virtual connections between each devices of intelligent substation SCD

Also Published As

Publication number Publication date
CN104601372A (en) 2015-05-06

Similar Documents

Publication Publication Date Title
CN104601372B (en) A kind of intelligent substation void circuit visualization comparison method based on three layer patterns
CN104750477B (en) A kind of SCD version comparison methods based on standard pilot process file
CN104486075B (en) A kind of verification method of intelligent substation ICD model file digital signature
CN104702466B (en) A kind of process layer safety test system and method based on IEC62351
CN105429803B (en) Quadratic Imaginary loop fault localization method based on fault zone Difference formula reasoning
CN105302121A (en) Sequential control operation order automatic anti-error check method based on simulation IED device
Anwar et al. Anomaly detection in electric network database of smart grid: Graph matching approach
CN105093017B (en) Intelligent substation GOOSE integrated testabilities device and its method of testing
CN106200615B (en) A kind of intelligent track-traffic early warning implementation method based on incidence relation
CN107453354B (en) A kind of weak link recognition methods of power distribution network
CN209545248U (en) A kind of intelligent Substation System of visualized O&M
CN104599060A (en) Secondary circuit file comparison based intelligent substation debugging scheme generation method
CN106383958A (en) Intelligent check and acceptance system of substation anti-misoperation locking logic
CN104091289A (en) Large-scale power distribution network N-1 rapid verification method based on wiring mode rules
CN104766246A (en) Power system fault diagnosis method based on timing order fuzzy Petri net
CN108090674A (en) The risk assessment of the area power grid method of operation and aid decision-making method and system
CN106655292A (en) Ultra-high-voltage AC/DC hybrid grid stability analysis method
CN105978147A (en) File interaction based remote constant value amending system for automatic safety devices
CN104639328B (en) A kind of GOOSE message authentication method and system
Tan et al. Power grid fault diagnosis method using intuitionistic fuzzy petri nets based on time series matching
CN106292499A (en) The safe related function method and device of secondary equipment of intelligent converting station O&M operation object
CN107995050A (en) Secondary system of intelligent substation process layer communication failure diagnostic system and method
CN104299172A (en) Power grid weak link comprehensive recognition method
CN104376440A (en) Automatic power grid dispatching electronic token confirming method based on network token issuing
CN107563608A (en) A kind of power distribution communication net safety evaluation method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB02 Change of applicant information

Address after: 210009 Gulou District, Jiangsu, Nanjing new model road, No. 5

Applicant after: Chinese energy construction group Jiangsu Prov. Power Design Inst Co., Ltd

Applicant after: NANJING WUCAIZHIDIAN ELECTRIC POWER TECHNOLOGY CO., LTD.

Applicant after: State Grid Corporation of China

Applicant after: Jiangsu Electric Power Company

Address before: 210009 Gulou District, Jiangsu, Nanjing new model road, No. 5

Applicant before: Jiangsu Electric Power Designing Institute

Applicant before: NANJING WUCAIZHIDIAN ELECTRIC POWER TECHNOLOGY CO., LTD.

Applicant before: State Grid Corporation of China

Applicant before: Jiangsu Electric Power Company

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: JIANGSU ELECTRIC POWER DESIGNING INST. TO: CHINA ENERGY ENGINEERING GROUP JIANGSU ELECTRIC POWER DESIGN INSTITUTE CO., LTD.

GR01 Patent grant
GR01 Patent grant