CN104594369B - Karst region high-pressure group hole replacement grouting method and structure thereof - Google Patents

Karst region high-pressure group hole replacement grouting method and structure thereof Download PDF

Info

Publication number
CN104594369B
CN104594369B CN201410694710.9A CN201410694710A CN104594369B CN 104594369 B CN104594369 B CN 104594369B CN 201410694710 A CN201410694710 A CN 201410694710A CN 104594369 B CN104594369 B CN 104594369B
Authority
CN
China
Prior art keywords
drilling
displacement
grouting
solution cavity
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410694710.9A
Other languages
Chinese (zh)
Other versions
CN104594369A (en
Inventor
屈昌华
郭维祥
余波
朱代强
昝廷东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201410694710.9A priority Critical patent/CN104594369B/en
Publication of CN104594369A publication Critical patent/CN104594369A/en
Application granted granted Critical
Publication of CN104594369B publication Critical patent/CN104594369B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a karst region high-pressure group hole replacement grouting method and a structure thereof, wherein a grouting gallery or a flat cave (2) is arranged above a karst cave region (1), a drilling hole (3) is distributed in the grouting gallery or the flat cave (2) to the karst cave region (1), the lower end of the drilling hole (3) is positioned in the karst cave region (1), and the range of the drilling hole (3) is divided into a replacement inlet region (4) and a replacement outlet region (5); and (3) injecting sand-doped cement slurry with the mass ratio of 0.5:1 into the drill hole (3) of the replacement inlet area (4) at high pressure, filling all or most of karst caves, extruding out from the drill hole (3) of the replacement outlet area (5), and pouring by adopting a conventional cement grouting method after setting for 24-36 h. The grouting method can solve the grouting problem of geological defect sections such as small and medium filling type karst caves and the like in the karst region, and has the advantages of simple method, capability of greatly prolonging the construction period, low cost, remarkable effect, capability of ensuring grouting quality and the like.

Description

Karst high pressure group hole replacement grouting method and its structure
Technical field
The present invention relates to karst geological disposal method, and in particular to a kind of karst high pressure group hole displacement fills Paste-making method and its structure.
Background technology
Karst topography refer to have the water of corrosion power solublerock is carried out the formed earth's surface of the effect such as corrosion and The general name of underground form.Water includes erosion, the shallow erosion of flowing water, and the mechanical erosion process such as collapse based on corrosion.
Hydraulic and Hydro-Power Engineering is built in karst, its reservoir Karst Filter Zone is one of major project problem, is selected Can suitable and effective anti-seepage scheme is related to reservoir normal water storage.Karst impervious grouting handles engineering with water at present Based on mud grouting.During grouting construction, big and small filling clay, the solution cavity of dauk are frequently encountered, is used Conventional grouting method does not reach design requirement.Current specifications(DL/T5148-2012)There is specially filling-type Karst cave grouting in although Door requires, you can using engineering measures such as high-pressure grouting, high pressure phase equilibria, low pressure, underflow, current limliting, limitation, intervals, but During practice of construction these methods often exist the construction time it is long, costly, anti-seepage effect is poor the shortcomings of.
When grout hole runs into the solution cavity of the fillings such as clay, dauk, often there is collapse hole, bit freezing, burying, the leakage of string hole The problems such as slurry, in addition to midge amount is very big, construction speed and construction quality are also had a strong impact on, although using conventional grouting measure Processing has certain effect, but after constructing again to the solution cavity section, its construction water often again deteriorates its character, again must not Do not repeat to be in the milk, and so on repeatedly, cause the significant wastage of grouting material, and do not reach preferably processing effect also Fruit.
Therefore, for the processing of such Geological Defects, in the prior art still without preferable technical scheme.
The content of the invention
It is an object of the invention to solve in the prior art to the project seepage controlling grouting treatment of casta region A kind of problem, there is provided karst high pressure group hole replacement grouting method.
It is the technical scheme is that such:
It employs such a grouting structure:Irrigation gallery or adit are set in the top in solution cavity area, in irrigation gallery Or adit is laid to solution cavity area and drilled, the lower end of drilling is located in solution cavity area, and drilling location is divided into displacement entrance region With displacement outlet area;Orifice sealing device is installed at the aperture of the drilling in region.The pitch-row of drilling is 2~2.5m.Grouting When, it is 0.5 in the drilling mesohigh implantation quality ratio of displacement entrance region:1 mixes sand cement slurry, by solution-cavity filling is whole or big portion Divide from the drilling of displacement outlet area and extrude, take traditional cements grouting method to be irrigated again after solidifying 24h~36h.
Specifically, this group of hole replacement grouting methods comprise the following steps:
1)Utilize grout hole, pilot hole(Generally be in the milk pilot hole or I sequence grout hole)Or physical prospecting means find out solution cavity area The development scale of middle solution cavity, the property of charges, roof and floor hole depth elevation;
2)All grout holes in solution cavity area are constructed to more than Upper Plate of Karst Cave 1~2m by the grouting order of design requirement, 1~2m of complete basement rock below solution cavity bottom plate is pierced again;
3)It is determined that displacement entrance region and displacement outlet area, and determination can be as the drilling of displacement entrance region and displacement outlet area Grout hole, the then mounting hole sealer at the aperture of all drillings, wherein the aperture in the drilling of displacement outlet area is close Valve on envelope device is in open mode;
Drilling namely using existing grout hole as replacement grouting, and can not have to carry out secondary drilling.But not All existing grout holes can act as the drilling of the replacement grouting of the present invention, it is determined that displacement entrance region and displacement outlet area The principle of drilling is:
When solution cavity development is horizontal or near horizontal direction, the grout hole in solution cavity area can be used as displacement entrance region and put Swap out the drilling of mouth region;
When solution cavity development is incline direction, drilling of the grout hole of low elevation as displacement entrance region in solution cavity area.
4)High-pressure rubber pipe on high pressure mortar pump is connected with replacing the orifice sealing device of entrance region, and pressurizes and is noted into hole Enter the ratio of mud for 0.5:1 cement mortar, grouting pressure are controlled in 4~6MPa;
5)When solution-cavity filling thing occurs in the drilling orifice for replacing outlet area, replace infusion in the drilling of entrance region and adjust To mix sand cement slurry, sand ratio is mixed(Cement weight ratio)For 10%, 20%, 30% three-level, and by from as low as being mixed step by step into cement mortar greatly Enter;
6)When cement mortar occurs in the drilling orifice for replacing outlet area, suspend replacement operator;The drilling of outlet area will be replaced On orifice sealing device valve close after be further continued for perfusion mix sand cement slurry, until import drilling injection rate be no more than 5L/min It can terminate to replace, and 36h~48h to be coagulated;
7)Reach after the solidifying time, to routinely grouting method carries out strengthening grouting in order in solution cavity area, until passing through The solution cavity fills section.
When being in the milk using the present invention in the solution cavity location that karst clay and dauk fill, rationally utilize Grout hole(Do not increase quantities)Solution-cavity filling thing is replaced, can fast and effeciently reach design requirement, while also can significantly carry High construction efficiency and reduction grouting material waste.The high pressure replacement grouting method of the present invention is to be less than 5m packed type for height A kind of quick, economic, efficient grouting treatment technology of solution cavity, have method simple(Use live grouting equipment and operation people Member, it is not necessary to increase special construction equipment and special operation workers), can increase substantially low construction time, expense, significant effect, The advantages that can guarantee that grouting quality.
The present invention solves the middle-size and small-size filling of karst with a kind of brand-new thinking in a manner of simple, efficient The grouting problem in the Geological Defects such as type solution cavity location.
Brief description of the drawings
Fig. 1 is the group hole replacement grouting planar structure schematic diagram of the present invention;
Fig. 2 is the A-A diagrammatic cross-sections in Fig. 1.
Description of reference numerals:1- solution cavities area, 2- irrigation galleries or adit, 3- drillings, 4- displacement entrance regions, 5- displacements outlet Area.
Embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.
Fig. 1 and Fig. 2 are seen, wherein Fig. 1 illustrates the floor map of this grouting structure of the present invention, and Fig. 2 is illustrated A-A diagrammatic cross-sections in Fig. 1, from fig. 2 it can be seen that the development direction in the solution cavity area 1 is similar to horizontal direction, slightly to the right Inclined downward, the present invention are to set irrigation gallery or adit 2 in the top in solution cavity area 1, in irrigation gallery or adit 2 to solution cavity area 1 lays drilling 3, and using the I sequences grout hole that has been drilled in previous process as drilling 3,3 lower end of drilling is located at solution cavity area In 1;After drilling 3 is determined, 3 locations of drilling are divided into displacement entrance region 4 and displacement outlet area 5.
Left-hand component is displacement outlet area 5 in Fig. 2, and right-hand component is displacement entrance region 4, and from fig. 2 it can be seen that right The solution cavity elevation of the displacement entrance region 4 on side is lower than the left side, therefore using the right as displacement entrance region 4, is so compared with the right side Side priming charge mud extrudes the charges in left-hand component solution cavity completely from the drilling 3 of left-hand component;In addition, drilling Orifice sealing device is installed at 3 aperture, will so replace the orifice closing of the drilling 3 of entrance region 4, and in displacement outlet area 5 Aperture open wide, such cement mortar high pressure effect under, in solution cavity can only from displacement entrance region 4 to displacement outlet area 5 side To flowing, most the charges in solution cavity are extruded from the aperture of the drilling 3 of displacement outlet area 5 at last.
It will be noted from fig. 1 that drilling 3 is evenly arranged in the range of the development in solution cavity area 1, according to the development in solution cavity area 1 Scope selects quincuncial arrangement or two row's interlaced arrangements as shown in Figure 1, it is preferred that 3 pitch-row of drilling is 2~2.5m.
Embodiment 1:
The filling-type Karst cave in adit curtain grouting area, charges are mainly clay under some hydropower station, are easily occurred porous Communicate(String water, grout leaking)Phenomenon, it is porous to be unable to reach design requirement by repeatedly multiple fill, at the method using the present invention Reason, design requirement can be met through inspection hole inspection of being in the milk after processing completion.
Certainly, the above is the concrete application example of the present invention, and the present invention also has other embodiments, all using equivalent The technical scheme that replacement or equivalent transformation are formed, all falls within protection domain of the presently claimed invention.

Claims (2)

  1. A kind of 1. karst high pressure group hole replacement grouting method, it is characterised in that:In solution cavity area(1)Top set grouting Gallery or adit(2), in irrigation gallery or adit(2)To solution cavity area(1)Lay drilling(3), drilling(3)Lower end be located at solution cavity Area(1)In, it will drill(3)Location is divided into displacement entrance region(4)With displacement outlet area(5);In displacement entrance region(4)'s Drilling(3)Mesohigh implantation quality ratio is 0.5:1 sand cement of mixing is starched, by solution-cavity filling wholly or largely from displacement outlet area (5)Drilling(3)Middle extrusion, traditional cements grouting method is taken to be irrigated again after solidifying 24h~36h;
    This method comprises the following steps:
    1)Solution cavity area is found out using grout hole, pilot hole or physical prospecting means(1)The development scale of middle solution cavity, the property of charges, Roof and floor hole depth elevation;
    2)By solution cavity area(1)Interior all grout holes are constructed to more than Upper Plate of Karst Cave 1~2m by the grouting order of design requirement, then Pierce 1~2m of complete basement rock below solution cavity bottom plate;
    3)It is determined that displacement entrance region(4)With displacement outlet area(5), and determine that displacement entrance region can be used as(4)With displacement outlet area (5)Drilling(3)Grout hole, then in all drillings(3)Aperture at mounting hole sealer, wherein replacing outlet area (5)Drilling(3)On orifice sealing device on valve be in open mode;
    4)By the high-pressure rubber pipe on high pressure mortar pump and displacement entrance region(4)Orifice sealing device be connected, and pressurize and noted into hole Enter the ratio of mud for 0.5:1 cement mortar;
    5)When displacement outlet area(5)Drilling(3)When solution-cavity filling thing occurs in aperture, entrance region is replaced(4)Drilling(3)Interior note Enter thing and be adjusted to mix sand cement slurry, it is 10%, 20%, 30% three-level to mix sand ratio, and by from as low as being mixed step by step into cement mortar greatly;
    6)When displacement outlet area(5)Drilling(3)When cement mortar occurs in aperture, suspend replacement operator;Outlet area will be replaced(5)'s Drilling(3)On orifice sealing device valve close after be further continued for perfusion mix sand cement slurry, until import drilling injection rate be not more than 5L/min can terminate to replace, and 36h~48h to be coagulated;
    7)Reach after the solidifying time, to solution cavity area(1)Inside routinely grouting method carries out strengthening grouting in order.
  2. 2. karst high pressure group hole according to claim 1 replacement grouting method, it is characterised in that:Step 3)It is determined that Replace entrance region(4)With displacement outlet area(5)Drilling(3)Principle be:When solution cavity development is horizontal or near horizontal direction, Solution cavity area(1)Interior grout hole can be used as displacement entrance region(4)With displacement outlet area(5)Drilling(3);
    When solution cavity development is incline direction, solution cavity area(1)The grout hole of interior low elevation is as displacement entrance region(4)Drilling (3).
CN201410694710.9A 2014-11-27 2014-11-27 Karst region high-pressure group hole replacement grouting method and structure thereof Active CN104594369B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410694710.9A CN104594369B (en) 2014-11-27 2014-11-27 Karst region high-pressure group hole replacement grouting method and structure thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410694710.9A CN104594369B (en) 2014-11-27 2014-11-27 Karst region high-pressure group hole replacement grouting method and structure thereof

Publications (2)

Publication Number Publication Date
CN104594369A CN104594369A (en) 2015-05-06
CN104594369B true CN104594369B (en) 2017-12-05

Family

ID=53120396

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410694710.9A Active CN104594369B (en) 2014-11-27 2014-11-27 Karst region high-pressure group hole replacement grouting method and structure thereof

Country Status (1)

Country Link
CN (1) CN104594369B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106437692B (en) * 2016-08-23 2023-03-21 中国电建集团贵阳勘测设计研究院有限公司 Deep karst leakage channel detection structure and method based on water level of inner pipe of drill rod
CN106837411B (en) * 2017-02-04 2020-04-03 长江勘测规划设计研究有限责任公司 Arrangement structure and method for filling and grouting of deep-buried shield tunnel
CN111733794A (en) * 2020-06-11 2020-10-02 中铁一局集团第二工程有限公司 Method for determining safe thickness of side wall of karst area of foundation pit and grouting device

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6834720B1 (en) * 2001-12-03 2004-12-28 Sandia Corporation Method and apparatus for injecting particulate media into the ground
JP2005048518A (en) * 2003-07-31 2005-02-24 World Engineering Kk Controlled type revetment
CN202227325U (en) * 2011-08-18 2012-05-23 水利部交通运输部国家能源局南京水利科学研究院 Structure for reducing and preventing sound and vibration of service gate of water-filling gallery by means of natural ventilation
CN104179159B (en) * 2014-09-11 2016-05-25 武汉大学 Power station bright flowing full tail water system
CN204266222U (en) * 2014-11-27 2015-04-15 中国电建集团贵阳勘测设计研究院有限公司 Group hole replacement grouting structure suitable for karst region
CN104790404B (en) * 2015-05-05 2016-08-24 中国电建集团中南勘测设计研究院有限公司 A kind of dam foundation high-pressure grouting structure and grouting method

Also Published As

Publication number Publication date
CN104594369A (en) 2015-05-06

Similar Documents

Publication Publication Date Title
CN103967507B (en) A kind of curtain-grouting technique being suitable for rich water mine down-hole exploitation water blockoff
CN109208637A (en) Increase the construction method of open-cut station newly on the basis of existing tunnel
CN101525881B (en) Structure of karst strata pile holes protecting wall and method for constructing pile holes
CN106320354B (en) The Seepage method on solution cavity development stratum under coating
CN103866780B (en) A kind of construction method of carrying out quick seepage preventing curtain grouting in karst blowby area
CN105201001B (en) Composite seepage-proofing structure of large karst cave in karst region and construction method thereof
CN104963334A (en) Construction method for utilizing grouting freezing pipe to reinforce and freeze contact passage to restrain frost heaving and thaw collapsing
CN105926624B (en) Inverse-stopping type set hole grouting device and its construction method
CN102787602A (en) Curtain grouting technique
CN105041264B (en) A kind of mash gas pumping drilling whirl spraying solidify can multiple sealing of hole method
CN103912003B (en) The method of water and hole is moved on a kind of simple and efficient shutoff stratum
CN104612130A (en) Method for processing grouting position of hidden cave at bottom of tunnel
CN105887886A (en) Strong karst development stratum curtain grouting construction method
CN109322699A (en) Pollution isolation blocking technology under a kind of mine
CN103696416B (en) A kind of method for processing foundation
CN109538295A (en) Seal groundwater in mining area library system
CN104594369B (en) Karst region high-pressure group hole replacement grouting method and structure thereof
CN107178077B (en) karst area karst cave overburden grouting reinforcement structure and design method thereof
CN105731978B (en) A kind of grouting serous fluid and grouting method for fine sand layer jacking culvert solidifying of the working face
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN103556646A (en) Method for forming water shutoff walls in sand and gravel layer
CN205062827U (en) Composite seepage-proofing structure of large karst cave in karst area
CN103883291B (en) Throw gravel in Hydrology well casing and become well equipment and construction method
CN103967506B (en) A kind of ore body roof Karst Fissures is grown and the curtain-grouting method in strong Fu Shui mineral deposit
CN204266222U (en) Group hole replacement grouting structure suitable for karst region

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant