The content of the invention
The technical problem to be solved in the present invention is to provide a kind of Seawater Desalination Project total scale and grouping module scale to calculate
Method and device, by adjusting desalinization water scale, realize that seawater desalination system load can be with the change of wind-power electricity generation
Change and change immediately and be allowed to power consumption adaptation wind power generation capacity.
To achieve the above object, embodiments of the invention provide a kind of Seawater Desalination Project total scale and grouping module scale
Computational methods, applied to wind-powered electricity generation-desalinization coupled system, comprise the following steps:
Obtain wind power and cumulative frequency distribution and wind power generation cumulative frequency distribution curve occurs;
Cumulative frequency distribution curve is occurred according to the wind power, determines Seawater Desalination Project total scale;
Cumulative frequency distribution curve and the Seawater Desalination Project total scale are occurred according to the wind power, by desalinization
Engineering carries out modularization packet;
The grouping module scale carried out to Seawater Desalination Project after modularization packet optimizes.
Wherein, the step of cumulative frequency distribution and wind power generation cumulative frequency distribution curve occur for wind power is obtained to wrap
Include:
The wind data of acquisition or wind power data are calculated and are converted into wind power occurrence frequency;
The wind power occurrence frequency is calculated and is converted into wind power generation cumulative frequency distribution, and wind power is occurred tired
Product probability carries out S types curve matching and obtains wind power generation cumulative frequency distribution curve.
Wherein, the step of cumulative frequency distribution curve determines Seawater Desalination Project total scale occurs according to the wind power to wrap
Include:
Cumulative frequency distribution curve is occurred according to the wind power, determines that cumulative frequency is corresponding in first threshold scope
Wind-power electricity generation power;
Using the wind-power electricity generation power as the available electrical power of Seawater Desalination Project, divided by desalination process
Specific yield institute subfam. Spiraeoideae, obtain the first Seawater Desalination Project total scale;
Estimated according to engineering experience formula, obtain the second Seawater Desalination Project total scale;
Compare the first Seawater Desalination Project total scale and the second Seawater Desalination Project total scale, take smaller value to make
For Seawater Desalination Project total scale.
Wherein, the engineering experience formula is exponential formula, and index parameters span is 0.8~1.2.
Wherein, the index parameters span is 1.0~1.05.
Wherein, the index parameters value is 1.016.
Wherein, the first threshold scope is 10%~30%.
Wherein, cumulative frequency distribution curve and the Seawater Desalination Project total scale are occurred according to the wind power, by sea
The step of water desalting engineering progress modularization packet, includes:
Cumulative frequency distribution curve is occurred according to the wind power, determines that cumulative frequency is more than the wind corresponding to Second Threshold
Power generated output, divided by the specific yield institute subfam. Spiraeoideae in desalination process, the smallest size of module is obtained, carry out module
Change packet;Or
Cumulative frequency distribution curve is occurred according to the wind power, determines wind-force of the cumulative frequency corresponding to the 3rd threshold value
Generated output, divided by the specific yield institute subfam. Spiraeoideae in desalination process, the module scale of acquisition as each module scale,
Carry out modularization packet.
Wherein, the grouping module scale summation after the modularization packet is not more than Seawater Desalination Project total scale.
Wherein, the Second Threshold is 80%, and the 3rd threshold value is 50%.
Wherein, the step of grouping module scale carried out to Seawater Desalination Project after modularization packet optimizes includes:
Required by linear function, that is, produce water scale=fmax, f (xi)=Σxi≤xT, financial cost=gmin, g (xi)=ΣBi+
Σh(xi), obtain the design of Seawater Desalination Project grouping module and build;
Wherein, xiScale, B are grouped for moduleiFor the equipment cost corresponding to each module scale, h (xi) it is each module scale
Required energy storage device cost.
The embodiment of the present invention provides a kind of Seawater Desalination Project total scale and grouping module scale computing device, applied to wind
Electricity-desalinization coupled system, including:
First obtains module, and for obtaining, cumulative frequency distribution occurs for wind power and the generation cumulative frequency distribution of wind power is bent
Line;
Total scale determining module, for cumulative frequency distribution curve to occur according to the wind power, determine desalinization work
Journey total scale;
Grouping module, for cumulative frequency distribution and the Seawater Desalination Project total scale to occur according to the wind power,
Seawater Desalination Project is subjected to modularization packet;
Optimization module, optimized for carrying out the grouping module scale after modularization packet to Seawater Desalination Project.
Wherein, the first acquisition module includes:
First obtains submodule, and wind power generation frequency is converted into for the wind data of acquisition or wind power data to be calculated
Rate;
Second obtains submodule, and wind power generation cumulative frequency point is converted into for the wind power occurrence frequency to be calculated
Cloth, and cumulative probability occurs to wind power and carries out S types curve matching acquisition wind power generation cumulative frequency distribution curve.
Wherein, the total scale determining module includes:
Wind-power electricity generation power confirms module, for cumulative frequency distribution curve to occur according to the wind power, it is determined that accumulation
Frequency corresponding wind-power electricity generation power in first threshold scope;
3rd obtains submodule, for using the wind-power electricity generation power as the available electrical power of Seawater Desalination Project,
Divided by the specific yield institute subfam. Spiraeoideae in desalination process, obtain the first Seawater Desalination Project total scale;
4th obtains submodule, for being estimated according to engineering experience formula, obtains the second Seawater Desalination Project total scale;
Comparison module, always advised for the first Seawater Desalination Project total scale and second Seawater Desalination Project
Mould, smaller value is taken as Seawater Desalination Project total scale.
Wherein, the engineering experience formula is exponential formula, and index parameters span is 0.8~1.2.
Wherein, the index parameters span is 1.0~1.05.
Wherein, the index parameters value is 1.016.
Wherein, the first threshold scope is 10%~30%.
Wherein, the grouping module includes:
First packet submodule, for cumulative frequency distribution curve to occur according to the wind power, determines that cumulative frequency is big
In the wind-power electricity generation power corresponding to Second Threshold, divided by the specific yield institute subfam. Spiraeoideae in desalination process, obtain mould
The smallest size of block, carry out modularization packet;Or
Second packet submodule, for cumulative frequency distribution curve to occur according to the wind power, determine that cumulative frequency is
Wind-power electricity generation power corresponding to 3rd threshold value, divided by the specific yield institute subfam. Spiraeoideae in desalination process, the mould of acquisition
Block size carries out modularization packet as each module scale.
Wherein, the grouping module scale summation after the modularization packet is not more than Seawater Desalination Project total scale.
Wherein, the Second Threshold is 80%, and the 3rd threshold value is 50%.
Wherein, the optimization module includes:
Optimize submodule, for being required by linear function, that is, produce water scale=fmax, f (xi)=Σxi≤xT, financial cost
=gmin, g (xi)=ΣBi+Σh(xi), obtain the design of Seawater Desalination Project grouping module and build;
Wherein, xiScale, B are grouped for moduleiFor the equipment cost corresponding to each module scale, h (xi) it is each module scale
Required energy storage device cost.
The above-mentioned technical proposal of the present invention has the beneficial effect that:
The embodiment of the present invention, Seawater Desalination Project total scale and grouping module scale computational methods, pass through step first
1, obtain wind power and cumulative frequency distribution and wind power generation cumulative frequency distribution curve occurs;Then by step 2, according to described
Cumulative frequency distribution curve occurs for wind power, determines Seawater Desalination Project total scale;Step 3, occurred according to the wind power tired
Curve of frequency distribution and the Seawater Desalination Project total scale are counted, Seawater Desalination Project is subjected to modularization packet;Finally, step
4, the grouping module scale carried out to Seawater Desalination Project after modularization packet optimizes.Wind-powered electricity generation-desalinization coupled system
Rational Seawater Desalination Project grouping module design in wind-powered electricity generation-desalinization coupled system may finally be obtained and built, full
On the premise of sufficient wind-powered electricity generation-desalinization coupled system total yield water scale is tried one's best greatly, overall desalinization work after packet is rationally reduced
Skill equipment cost and wind-powered electricity generation energy storage device cost, realize system loading can change immediately with the change of wind-power electricity generation and
It is allowed to power consumption and adapts to wind power generation capacity.
Embodiment
To make the technical problem to be solved in the present invention, technical scheme and advantage clearer, below in conjunction with accompanying drawing and tool
Body embodiment is described in detail.
The present invention can not realize that seawater desalination system load can be with for existing wind-powered electricity generation-desalinization coupled system
The change of wind-power electricity generation and change immediately and be allowed to the problem of power consumption adapts to wind power generation capacity, there is provided a kind of desalinization
Engineering total scale and grouping module scale computational methods.
As shown in figure 1, the Seawater Desalination Project total scale and grouping module scale computational methods of embodiments of the invention, should
For wind-powered electricity generation-desalinization coupled system, comprise the following steps:
1, obtain wind power and cumulative frequency distribution and wind power generation cumulative frequency distribution curve occurs;
2, cumulative frequency distribution curve is occurred according to the wind power, determines Seawater Desalination Project total scale;
3, cumulative frequency distribution curve and the Seawater Desalination Project total scale are occurred according to the wind power, seawater is light
Chemical industry journey carries out modularization packet;
4, the grouping module scale carried out to Seawater Desalination Project after modularization packet optimizes.
By step 1,2,3,4, wind-powered electricity generation-desalinization coupled system may finally obtain wind-powered electricity generation-desalinization coupling
The rational design of Seawater Desalination Project grouping module and construction, are meeting wind-powered electricity generation-desalinization coupled system total yield water in system
On the premise of scale is tried one's best greatly, overall desalination process equipment cost and wind-powered electricity generation energy storage device cost after packet are rationally reduced,
Realize that system loading can change and be allowed to the change of wind-power electricity generation power consumption immediately and adapt to wind power generation capacity.
The Seawater Desalination Project total scale and grouping module scale computational methods of another embodiment of the present invention, it is above-mentioned be real
On the basis of applying example, step 1, obtain wind power and cumulative frequency distribution and wind power generation cumulative frequency distribution curve, bag occurs
Include:
11, the wind data of acquisition or wind power data are calculated and are converted into wind power occurrence frequency;
12, the wind power occurrence frequency is calculated and is converted into wind power generation cumulative frequency distribution, and wind power is sent out
Raw cumulative probability carries out S types curve matching and obtains wind power generation cumulative frequency distribution curve.
By step 11 and step 12, the wind data of acquisition or wind power data are calculated and are converted into wind power generation frequency
Rate, and then calculate and be converted into wind power generation cumulative frequency distribution, and cumulative probability is occurred to wind power and carries out S type curve matchings
Obtain wind power and cumulative frequency distribution curve occurs.The wind power finally obtained occurs cumulative frequency distribution curve and is used in seawater
In the acquisition of desalting engineering total scale and Seawater Desalination Project grouping module scale.
The Seawater Desalination Project total scale and grouping module scale computational methods of another embodiment of the present invention, it is above-mentioned be real
On the basis of applying example, step 2, the wind power occurs cumulative frequency distribution curve and determines Seawater Desalination Project total scale, including:
21, cumulative frequency distribution curve is occurred according to the wind power, determines cumulative frequency in first threshold scope pair
The wind-power electricity generation power answered;
22, using the wind-power electricity generation power as the available electrical power of Seawater Desalination Project, divided by desalinization work
Specific yield institute subfam. Spiraeoideae in skill, obtain the first Seawater Desalination Project total scale;
23, estimated according to engineering experience formula, obtain the second Seawater Desalination Project total scale;
24, the first Seawater Desalination Project total scale and the second Seawater Desalination Project total scale take smaller
Value is used as Seawater Desalination Project total scale.
Wherein, the engineering experience formula is exponential formula, and index parameters span is 0.8~1.2.
Wherein, the index parameters span is 1.0~1.05.
Wherein, the index parameters value is 1.016.
Wherein, the first threshold scope is 10%~30%.
In coupled system, by the estimation of engineering experience formula and wind power cumulative frequency point occurs for Seawater Desalination Project total scale
Cloth curve determines jointly.Due to the Seawater Desalination Project total scale and grouping module scale computational methods of the embodiment of the present invention, sea
Water desalinating process uses reverse osmosis process, so engineering experience formula is as follows:
Aquifer yield(m3/d)=blower fan rated power(KW)k, it is exponential formula, obtains the second Seawater Desalination Project total scale.
Wherein k is parameter, and scope is 0.8~1.2.Accurately, the index parameters span is 1.0~1.05.It is excellent by experiment
It is 1.016 to select the index parameters value.
And cumulative frequency distribution curve is occurred by wind power, determine cumulative frequency corresponding wind in first threshold scope
Power generated output, using this wind-power electricity generation power as the available electrical power of Seawater Desalination Project, divided by desalination process
Middle specific yield institute subfam. Spiraeoideae, obtain the first Seawater Desalination Project total scale.Determined by experiment, the first threshold scope
For 10%~30%.
By the second Seawater Desalination Project total scale compared with the first Seawater Desalination Project total scale, smaller value is taken as wind
The reverse osmosis seawater desalting engineering total scale of electricity-desalinization coupled system.
It is necessary to carrying out modularization packet after Seawater Desalination Project total scale is obtained.The seawater of this bright another embodiment is light
Chemical industry journey total scale and grouping module scale computational methods, it is above-mentioned be embodiment on the basis of, step 3, according to the wind work(
Cumulative frequency distribution curve and the Seawater Desalination Project total scale occur for rate, and Seawater Desalination Project is carried out into modularization packet,
Including:
Cumulative frequency distribution curve is occurred according to the wind power, determines that cumulative frequency is more than the wind corresponding to Second Threshold
Power generated output, divided by the specific yield institute subfam. Spiraeoideae in desalination process, the smallest size of module is obtained, carry out module
Change packet;Or
Cumulative frequency distribution curve is occurred according to the wind power, determines wind-force of the cumulative frequency corresponding to the 3rd threshold value
Generated output, divided by the specific yield institute subfam. Spiraeoideae in desalination process, the module scale of acquisition as each module scale,
Carry out modularization packet.
Module packet as can be seen here has two ways.Mode one, as shown in Fig. 2 smallest size passes through wind power accumulation frequency
Rate distribution curve determines, that is, determines that cumulative frequency is more than the wind-power electricity generation power corresponding to Second Threshold, divided by desalinization
Specific yield institute subfam. Spiraeoideae in technique, the smallest size of module is obtained, carry out modularization packet.Mode two, as shown in figure 3,
Cumulative frequency distribution curve is occurred according to the wind power, determines wind-power electricity generation work(of the cumulative frequency corresponding to the 3rd threshold value
Rate, divided by the specific yield institute subfam. Spiraeoideae in desalination process, the module scale of acquisition is as each module scale.In Fig. 2,
P1, P2, P3 in Fig. 3, all it is infiltration production water.C1, C2, C3, all it is concentration production water.
Wherein, the grouping module scale summation after the modularization packet is not more than Seawater Desalination Project total scale.
Wherein, by experiment, preferably described Second Threshold is 80%, and the 3rd threshold value is 50%.
Finally, grouping module scale is optimized.The Seawater Desalination Project total scale of another embodiment of the present invention and point
Group module scale computational methods, on the basis of above-described embodiment, step 4, after carrying out modularization packet to Seawater Desalination Project
Grouping module scale optimize, including:
Required by linear function, that is, produce water scale=fmax, f (xi)=Σxi≤xT, financial cost=gmin, g (xi)=ΣBi+
Σh(xi), obtain the design of Seawater Desalination Project grouping module and build;
Wherein, xiScale, B are grouped for moduleiFor the equipment cost corresponding to each module scale, h (xi) it is each module scale
Required energy storage device cost.
In wind-powered electricity generation-desalinization coupled system, wind power can not be entirely used for desalination process, need as much as possible
Using wind power, on the premise of meeting wind-powered electricity generation-desalinization coupled system total yield water scale as far as possible greatly, rationally reduce and divide
Overall desalination process equipment cost and wind-powered electricity generation energy storage device cost after group.Required by linear function, that is, produce water scale=
fmax, f (xi)=Σxi≤xT, financial cost=gmin, g (xi)=ΣBi+Σh(xi), obtain the design of Seawater Desalination Project grouping module
And construction;Wherein, xiScale, B are grouped for moduleiFor the equipment cost corresponding to each module scale, h (xi) it is each module scale
Required energy storage device cost.By grouping module scale optimization, rational seawater in wind-powered electricity generation-desalinization coupled system is obtained
Desalting engineering grouping module is designed and built.
The embodiment of the present invention also provides a kind of Seawater Desalination Project total scale and grouping module scale computing device, such as Fig. 4
It is shown, applied to wind-powered electricity generation-desalinization coupled system, including:
First obtains module, and for obtaining, cumulative frequency distribution occurs for wind power and the generation cumulative frequency distribution of wind power is bent
Line;
Total scale determining module, for cumulative frequency distribution curve to occur according to the wind power, determine desalinization work
Journey total scale;
Grouping module, for cumulative frequency distribution and the Seawater Desalination Project total scale to occur according to the wind power,
Seawater Desalination Project is subjected to modularization packet;
Optimization module, optimized for carrying out the grouping module scale after modularization packet to Seawater Desalination Project.
Wherein, the first acquisition module includes:
First obtains submodule, and wind power generation frequency is converted into for the wind data of acquisition or wind power data to be calculated
Rate;
Second obtains submodule, and wind power generation cumulative frequency point is converted into for the wind power occurrence frequency to be calculated
Cloth, and cumulative probability occurs to wind power and carries out S types curve matching acquisition wind power generation cumulative frequency distribution curve.
Wherein, the total scale determining module includes:
Wind-power electricity generation power confirms module, for cumulative frequency distribution curve to occur according to the wind power, it is determined that accumulation
Frequency corresponding wind-power electricity generation power in first threshold scope;
3rd obtains submodule, for using the wind-power electricity generation power as the available electrical power of Seawater Desalination Project,
Divided by the specific yield institute subfam. Spiraeoideae in desalination process, obtain the first Seawater Desalination Project total scale;
4th obtains submodule, for being estimated according to engineering experience formula, obtains the second Seawater Desalination Project total scale;
Comparison module, always advised for the first Seawater Desalination Project total scale and second Seawater Desalination Project
Mould, smaller value is taken as Seawater Desalination Project total scale.
Wherein, the engineering experience formula is exponential formula, and index parameters span is 0.8~1.2.
Wherein, the index parameters span is 1.0~1.05.
Wherein, the index parameters value is 1.016.
Wherein, the first threshold scope is 10%~30%.
Wherein, the grouping module includes:
First packet submodule, for cumulative frequency distribution curve to occur according to the wind power, determines that cumulative frequency is big
In the wind-power electricity generation power corresponding to Second Threshold, divided by the specific yield institute subfam. Spiraeoideae in desalination process, obtain mould
The smallest size of block, carry out modularization packet;Or
Second packet submodule, for cumulative frequency distribution curve to occur according to the wind power, determine that cumulative frequency is
Wind-power electricity generation power corresponding to 3rd threshold value, divided by the specific yield institute subfam. Spiraeoideae in desalination process, the mould of acquisition
Block size carries out modularization packet as each module scale.
Wherein, the grouping module scale summation after the modularization packet is not more than Seawater Desalination Project total scale.
Wherein, the Second Threshold is 80%, and the 3rd threshold value is 50%.
Wherein, the optimization module includes:
Optimize submodule, for being required by linear function, that is, produce water scale=fmax, f (xi)=Σxi≤xT, financial cost
=gmin, g (xi)=ΣBi+Σh(xi), obtain the design of Seawater Desalination Project grouping module and build;
Wherein, xiScale, B are grouped for moduleiFor the equipment cost corresponding to each module scale, h (xi) it is each module scale
Required energy storage device cost.
It should be noted that the device is to apply above-mentioned Seawater Desalination Project total scale and grouping module scale calculating side
The device of method, the implementation of above-mentioned Seawater Desalination Project total scale and grouping module scale computational methods are applied to the device
In, it can also reach identical technique effect.
Described above is the preferred embodiment of the present invention, it is noted that for those skilled in the art
For, on the premise of principle of the present invention is not departed from, some improvements and modifications can also be made, these improvements and modifications
It should be regarded as protection scope of the present invention.