CN104534167B - The drag reduction method of thixotropic slurry - Google Patents

The drag reduction method of thixotropic slurry Download PDF

Info

Publication number
CN104534167B
CN104534167B CN201410741416.9A CN201410741416A CN104534167B CN 104534167 B CN104534167 B CN 104534167B CN 201410741416 A CN201410741416 A CN 201410741416A CN 104534167 B CN104534167 B CN 104534167B
Authority
CN
China
Prior art keywords
grouting
slurry
thixotropic slurry
drag reduction
injected hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410741416.9A
Other languages
Chinese (zh)
Other versions
CN104534167A (en
Inventor
黄忠
周如明
黄超
肖来兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201410741416.9A priority Critical patent/CN104534167B/en
Publication of CN104534167A publication Critical patent/CN104534167A/en
Application granted granted Critical
Publication of CN104534167B publication Critical patent/CN104534167B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B30/00Compositions for artificial stone, not containing binders

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Materials Engineering (AREA)
  • Structural Engineering (AREA)
  • Organic Chemistry (AREA)
  • Mechanical Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The present invention discloses the drag reduction method of a kind of thixotropic slurry, belongs to technical field of civil engineering.First the method prepares the thixotropic slurry of drag reduction, and this thixotropic slurry is made up of sodium bentonite, carboxymethyl cellulose, sodium carbonate, clean water and appropriate admixture;The thixotropic slurry being stirred is put in slurry can, arranges injected hole and connect grouting pipe, then carrying out grouting pressure calculating, selecting grouting pump, finally carry out slip casting.The inventive method reduces the frictional resistance of tubing and soil by grouting process, use grouting process lubrication, apex distance can be made after drag reduction to improve 40% 70%, the resistance in push pipe work can be effectively reduced, the push pipe that can make heavy caliber distance constantly extends, the inventive method has low cost, technology is easily implemented, and drag reduction efficiency is high.

Description

The drag reduction method of thixotropic slurry
Technical field:
The invention belongs to technical field of civil engineering, be specifically related to the drag reduction method of a kind of thixotropic slurry, the method be applied to push pipe, In the construction of the trenchless engineering such as open caisson, boring, realize Gu Bi, lubrication, to reduce the soil body by injecting thixotropic slurry Frictional resistance, improves work efficiency.
Background technology:
Along with the continuous propelling of China's Urbanization Construction process, no-excavation construction method is applied to city integrated the most more and more widely In the middle of the construction projects such as pipe network push pipe, open caisson, boring, owing to the frictional resistance by the soil body is affected, constrain to a certain extent Speed of application, even causes construction to cannot be carried out down.How to reduce the frictional resistance of the soil body, improve trenchless engineering construction work Effect, becomes for the important technical barrier of this technical field.
Affecting work efficiency problem because of the frictional resistance of the soil body for solving trenchless engineering, vast engineers and technicians pass through year in year out Technical research and practice of innovation, slip casing by pressure technology creates, and many thixotropic slurry material mixture ratios are also born, thixotropic slurry Drag reduction method is thus arisen at the historic moment.
In the trenchless engineering constructions such as push pipe, open caisson, boring, the drag reduction method mechanism of thixotropic slurry primarily serves the purpose of: one is Playing the effect of the supporting & stablizing soil body, two has been the effect of lubrication drag reduction.The trenchless engineering construction got up as a kind of new development is auxiliary Helping technology, its outstanding support is approved by vast unit in charge of construction the most more and more with drag-reduction effect and promotes the use of, and has wide Development prospect.
Summary of the invention:
The present invention is directed to the technical problem that thixotropic slurry resistance present in existing jacking construction is bigger, it is provided that a kind of thixotropic slurry Drag reduction method, the method specifically comprises the following steps that
(1) preparation drag reduction thixotropic slurry:
Thixotropic slurry is made up of sodium bentonite, carboxymethyl cellulose, sodium carbonate, clean water and appropriate admixture, described tactile Become the mud mass percent that respectively forms into sodium bentonite 10~20%, carboxymethyl cellulose 0.3~0.5%, sodium carbonate 0.2~ 0.4%, clean water and appropriate admixture 80~90%;Dispensing is carried out, so according to the composition mass percent of described thixotropic slurry The described thixotropic slurry being stirred is put into standing 12h~24h in slurry can by rear employing blender after being stirred;Prepared Drag reduction thixotropic slurry main performance be: density 1.1~1.17g/cm3, viscosity 30~80s, gel strength 80~120Pa, loses Water yield < 25cm3/ 30min, pH value < 10.
(2) arrange injected hole and connect grouting pipe:
Push-bench afterbody, by the concrete tube coupling of jacking on reserved 3~5 injected holes, described injected hole is distributed evenly in Pipeline, described injected hole has degassing function, and each injected hole is respectively provided with faucet control valves door, prevents serosity reflux, Each injected hole is provided with check valve;Grouting pipe is made up of with supervisor arm, described arm and the faucet control valves of each injected hole After door connects, then receiving on supervisor, described supervisor connects on grouting pump, and one end of described grouting pump is connected on slurry can.
(3) grouting pressure calculates:
Grouting pressure P can be by formula PA≤P≤PA+ 30kPa calculates, in formula:
When power arch is unloaded in existence:
PAThe water pressure at mud sleeve top and active earth pressure (kPa);
Density (the kN/m of γ soil3);
γWForce density (the kN/m of water3);
The external diameter (m) of D pipeline;
The thickness (m) of the above overlying soil in H pipeline top;
The internal friction angle of soil layer residing for pipeline;
h0Unload the height (m) of power arch;
H1Soil face or power of unloading encircle above water-column (m);
The cohesiveness (kPa) of C soil.
(4) grouting pump is selected: grouting pump selects the screw pump that pulsation is little, and flow matches with move speed.
(5) slip casting:
A: when tube coupling jacking, open grouting pump, implement synchronous grouting, it is ensured that when push-bench forward time, shape after push-bench The space become is immediately by described thixotropic slurry filling, thus forms complete mud sleeve.
B: in jack-in process, answers certain interval of time to be tracked mending slurry, and supplementary part is lost to the serosity in soil layer.
C: grouting amount should control 2 times for pipeline outer wall theory voidage, grouting pressure outline launching stress above Ground, control System is between 0.02MPa~0.15MPa, and along with push pipe distance increase, pressure also must increase therewith, the Stress control of grouting pump 20~50kPa.
D: after jacking terminates, uses cement mortar to mix proper amount of pulverized fuel ash slurry and replaces the serosity of mud sleeve, wait to press Slurry removes grouting pipeline after condensing, and changes boring cover by injected hole closure.
The thixotropic slurry main material of drag reduction is bentonite and water.After bentonite mixes with water, owing to water is mixed in people's bentonite, Bentonite swollen weight in water can reach 600% the 700% of bentonite origin weight.Agitated storage is solidifying shape, outside having In flow regime under power effect, this material note is clipped between pipe shell and soil, can be substantially reduced the frictional resistance that tube coupling advances. Time static, mud has good stability.For making swelling serosity have good performance, pulping process to add some auxiliary in right amount Raw material: such as soda, cellulose CMC, retarder etc..Bentonite is divided into again calcium-base bentonite and sodium bentonite, absorbs calcium Ion many for calcio, absorb sodium ion many for sodium bentonite, select different formula according to different soil properties.By executing Work is summed up and is found: in sand soil, sodium bentonite drag-reduction effect is more apparent.
The inventive method reduces the frictional resistance of tubing and soil by grouting process.Can after using grouting process lubrication, drag reduction So that apex distance improves 40% one 70%.The resistance in push pipe work can be effectively reduced, the push pipe of heavy caliber distance can be made not Breaking and extend, and low cost, technology are easily implemented, drag reduction efficiency is high.
Detailed description of the invention:
The present invention provides the drag reduction method of a kind of thixotropic slurry, and it is as follows that the method is embodied as step:
(1) thixotropic slurry of preparation drag reduction:
Thixotropic slurry is by sodium bentonite, carboxymethyl cellulose (CMC), sodium carbonate (Na2CO3), clean water and mixing in right amount Mixture form, the mass percent that described thixotropic slurry respectively forms is: sodium bentonite 10~20%, carboxymethyl cellulose 0.3~ 0.5%, sodium carbonate 0.2~0.4%, clean water and appropriate admixture 80~90%;Composition quality hundred according to described thixotropic slurry Proportion by subtraction carries out dispensing, is put in slurry can by the described thixotropic slurry being stirred and stand after then using blender to be stirred 12h~24h, makes bentonite clay particle fully absorb water, expand into colloid;The drag reduction thixotropic slurry main performance prepared is: Density 1.1~1.17g/cm3, viscosity 30~80s (measuring with funnel viscometer), gel strength 80~120Pa, fluid loss < 25cm3/ 30min, pH value < 10.
(2) arrange injected hole and connect grouting pipe:
Push-bench afterbody, by the concrete tube coupling of jacking on reserved 3~5 injected holes, described injected hole is distributed evenly in Pipeline, described injected hole has degassing function, and each injected hole is respectively provided with faucet control valves door, prevents serosity reflux, Each injected hole is provided with check valve, makes the mud outside pipe can not pour in down a chimney and block injected hole, thus affect slip casting effect;Slip casting Pipeline is made up of with supervisor arm, and arm diameter selects the rubber tube of 25~30mm, supervisor's selection a diameter of 40~the steel of 50mm Pipe, after described arm is connected with the faucet control valves door of each injected hole, then receives on supervisor, and described supervisor connects on grouting pump, One end of described grouting pump is connected on slurry can.
(3) grouting pressure calculates
Grouting pressure P can be by formula PA≤P≤PA+ 30kPa calculates, in formula:
When power arch is unloaded in existence:
PAThe water pressure at mud sleeve top and active earth pressure (kPa);
Density (the kN/m of γ soil3);
γWForce density (the kN/m of water3);
The external diameter (m) of D pipeline;
The thickness (m) of the above overlying soil in H pipeline top;
The internal friction angle of soil layer residing for pipeline;
h0Unload the height (m) of power arch;
H1Soil face or power of unloading encircle above water-column (m);
The cohesiveness (kPa) of C soil.
(4) grouting pump is selected: grouting pump selects the screw pump that pulsation is little, and flow matches with move speed.
(5) slip casting:
The thixotropic slurry stirred should can start perfusion after static certain time (12~24h);Before slip casting, reply note Equipment, pipeline etc. check, confirm that device systems can start perfusion after working properly;Grouting mode based on synchronous grouting, It is auxiliary for mending slurry, in jack-in process, needs to check the serosity formational situation of each propelling section.
A: when tube coupling jacking, open grouting pump, implement synchronous grouting, it is ensured that when push-bench forward time, shape after push-bench The space become is immediately by described thixotropic slurry filling, thus forms complete mud sleeve;
B: in jack-in process, answers certain interval of time to be tracked mending slurry, and supplementary part is lost to the serosity in soil layer;
C: grouting amount should control 2 times for pipeline outer wall theory voidage, grouting pressure outline launching stress above Ground, control System is between 0.02MPa~0.15MPa, and along with push pipe distance increase, pressure also must increase therewith, the Stress control of grouting pump 20~50kPa;
D: after jacking terminates, uses cement mortar to mix proper amount of pulverized fuel ash slurry and replaces the serosity of mud sleeve, wait to press After slurry condenses, (typically more than 24 hours) can remove grouting pipeline, and changes boring cover by injected hole closure.

Claims (1)

1. the drag reduction method of thixotropic slurry, it is characterised in that the method specifically comprises the following steps that
(1) preparation drag reduction thixotropic slurry:
Thixotropic slurry is made up of sodium bentonite, carboxymethyl cellulose, sodium carbonate, clean water and appropriate admixture, described tactile Become the mud mass percent that respectively forms into sodium bentonite 10~20%, carboxymethyl cellulose 0.3~0.5%, sodium carbonate 0.2~ 0.4%, clean water and appropriate admixture 80~90%;Dispensing is carried out, then according to the composition mass percent of described thixotropic slurry After using blender to be stirred, the described thixotropic slurry being stirred is put into standing 12h~24h in slurry can;Prepared Drag reduction thixotropic slurry main performance is: density 1.1~1.17g/cm3, viscosity 30~80s, gel strength 80~120Pa, dehydration Amount < 25cm3/ 30min, pH value < 10;
(2) arrange injected hole and connect grouting pipe:
Push-bench afterbody, by the concrete tube coupling of jacking on reserved 3~5 injected holes, described injected hole is distributed evenly in pipe Around road, described injected hole has degassing function, and each injected hole is respectively provided with faucet control valves door, prevents serosity reflux, often Individual injected hole is provided with check valve;Grouting pipe is made up of with supervisor arm, described arm and the faucet control valves door of each injected hole After connection, then receiving on supervisor, described supervisor connects on grouting pump, and one end of described grouting pump is connected on slurry can;
(3) grouting pressure calculates:
Grouting pressure P can be by formula PA≤P≤PA+ 30kPa calculates, in formula:
When power arch is unloaded in existence: PAWH1h0
PAThe water pressure at mud sleeve top and active earth pressure (kPa);
Density (the kN/m of γ soil3);
γWForce density (the kN/m of water3);
The external diameter (m) of D pipeline;
The thickness (m) of the above overlying soil in H pipeline top;
The internal friction angle of soil layer residing for pipeline;
h0Unload the height (m) of power arch;
H1Soil face or power of unloading encircle above water-column (m);
The cohesiveness (kPa) of C soil;
(4) grouting pump is selected: grouting pump selects the screw pump that pulsation is little, and flow matches with move speed;
(5) slip casting:
A: when tube coupling jacking, open grouting pump, implement synchronous grouting, it is ensured that when push-bench forward time, after push-bench formed Space immediately by described thixotropic slurry filling, thus form complete mud sleeve;
B: in jack-in process, answers certain interval of time to be tracked mending slurry, and supplementary part is lost to the serosity in soil layer;
C: grouting amount should control 2 times for pipeline outer wall theory voidage, grouting pressure outline launching stress above Ground, controls Between 0.02MPa~0.15MPa, along with push pipe distance increase, pressure also must increase therewith, and the Stress control of grouting pump exists 20~50kPa;
D: after jacking terminates, uses cement mortar to mix proper amount of pulverized fuel ash slurry and replaces the serosity of mud sleeve, treat mud jacking Body removes grouting pipeline after condensing, and changes boring cover by injected hole closure.
CN201410741416.9A 2014-12-08 2014-12-08 The drag reduction method of thixotropic slurry Active CN104534167B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410741416.9A CN104534167B (en) 2014-12-08 2014-12-08 The drag reduction method of thixotropic slurry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410741416.9A CN104534167B (en) 2014-12-08 2014-12-08 The drag reduction method of thixotropic slurry

Publications (2)

Publication Number Publication Date
CN104534167A CN104534167A (en) 2015-04-22
CN104534167B true CN104534167B (en) 2016-08-24

Family

ID=52849753

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410741416.9A Active CN104534167B (en) 2014-12-08 2014-12-08 The drag reduction method of thixotropic slurry

Country Status (1)

Country Link
CN (1) CN104534167B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108843328A (en) * 2018-06-25 2018-11-20 佳琳 A kind of Metro Connection Passage excavation construction support construction method

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104844129B (en) * 2015-04-28 2016-01-13 广东华恒建设工程有限公司 A kind of modification thixotropic slurry and compound method thereof
CN105154205A (en) * 2015-08-31 2015-12-16 江苏锐成机械有限公司 Lubricating material for pipe jacking construction
CN105782564B (en) * 2016-05-05 2018-06-05 江西建工第三建筑有限责任公司 Push pipe mud physics touch-control drag reduction method
CN106007637A (en) * 2016-05-13 2016-10-12 中煤第三建设(集团)有限责任公司广州分公司 Plasticizer injected to rear portion of pipe joint wall of jacking pipe
CN105781589A (en) * 2016-05-14 2016-07-20 中铁四局集团有限公司 Novel grouting process applicable to pipe jacking construction of desert region
US11095101B2 (en) 2016-09-06 2021-08-17 Quanta Associates, L.P. Repurposing pipeline for electrical cable
CN108395172B (en) * 2018-03-14 2020-10-02 中南大学 Complete wall protection slurry for super-long-distance large-diameter steel roof pipe penetrating through lake bottom goaf
CN108487097A (en) * 2018-04-09 2018-09-04 大连久鼎祥瑞特种工程技术研究院有限公司 Horizontal seepage well or pipeline push pipe rapid constructing method
CN108531151A (en) * 2018-04-26 2018-09-14 中铁隧道集团二处有限公司 Push-bench anti-drag mud and preparation method thereof in one planting sand soil property
CN108547308A (en) * 2018-05-04 2018-09-18 中国建筑第四工程局有限公司 A kind of mud sleeve auxiliary Double-Wall Steel Boxed Cofferdam sinking construction method
CN110185844B (en) * 2019-06-05 2021-05-11 中交一公局第三工程有限公司 Shallow-earthing large-diameter pipe jacking construction method
CN110864162B (en) * 2019-11-05 2021-11-02 国网浙江省电力有限公司宁波市镇海区供电公司 Construction process of argillaceous sandstone geological pipe jacking
CN111302710A (en) * 2020-03-03 2020-06-19 中国五冶集团有限公司 Large-diameter overlong punching slurry in dense pebble bed area
CN113531207B (en) * 2020-04-17 2023-09-22 中建三局安装工程有限公司 Drag-reducing and stone chip-blocking grouting method suitable for long-distance rock jacking engineering
CN111691889B (en) * 2020-05-15 2022-04-12 中电建十一局工程有限公司 Pipe jacking engineering construction method
CN112901178B (en) * 2021-01-18 2023-03-24 中铁上海工程局集团第五工程有限公司 Thixotropic slurry anti-drag grouting system and grouting method for medium-long distance oversized-diameter jacking pipe
CN112960942B (en) * 2021-02-02 2023-04-07 中铁四局集团第三建设有限公司 Thixotropic slurry for earth pressure balance jacking pipe in anhydrous sand layer, preparation method thereof, grouting method and slurry replacement method
CN113389563B (en) * 2021-08-04 2023-04-11 郑州亚欧交通职业学院 Drilling equipment in tunnel push pipe thixotropic mud slip casting hole

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103232196B (en) * 2013-04-24 2014-12-24 中交第一公路工程局有限公司 Thixotropic slurry anti-drag material for pipe jacking and preparation method thereof
CN203685205U (en) * 2013-12-26 2014-07-02 中铁工程装备集团有限公司 Thixotropic mud injection device with replaceable one-way valve
CN104150822B (en) * 2014-07-22 2016-01-20 中铁隧道集团有限公司 Thixotropic slurry and preparation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108843328A (en) * 2018-06-25 2018-11-20 佳琳 A kind of Metro Connection Passage excavation construction support construction method

Also Published As

Publication number Publication date
CN104534167A (en) 2015-04-22

Similar Documents

Publication Publication Date Title
CN104534167B (en) The drag reduction method of thixotropic slurry
CN102250597B (en) Grouting slurry for unconsolidated strata
CN110374606A (en) Slurry shield seabed broken formation pre-grouting pressure maintaining construction method
CN103485345A (en) Construction method for covering layer closed porthole high-pressure curtain grouting
CN103626454A (en) Manufacturing method of fast-setting early-strength two-fluid injecting paste material
CN104594914A (en) Coal mine tunnel broken surrounding rock layering grouting technology and method
CN105174886B (en) A kind of limestone aquifer slip casting transformation material that is applicable to extra long distance pumping
CN108716410B (en) Mechanical method connecting channel high-strength elastic wall post-grouting slurry and grouting method
CN105712738A (en) High water filling material for filling of waste pipeline
CN202560319U (en) Tunnel drainage and pressure reduction structure
CN101525881A (en) Structure of karst strata pile holes protecting wall and method for constructing pile holes
CN109437771A (en) A kind of mining flexible hole-sealing grouting material
CN102977869A (en) Underground high-pressure hydraulic fracturing hole sealing material for coal mine and hole sealing technology
CN100453497C (en) Backfill to buried pipe heat exchanger through hole
CN107244869A (en) The thixotropic slurry and its preparation method of function are filled up with drag reduction
CN206874296U (en) A kind of tunnel hollow bolt grouting device
CN207145003U (en) Disposably and permanently stop grouting plug for goaf grouting filling
CN112960942B (en) Thixotropic slurry for earth pressure balance jacking pipe in anhydrous sand layer, preparation method thereof, grouting method and slurry replacement method
CN203702070U (en) Coal mine low pumping lane borehole slag-returning sealing apparatus
CN108395172A (en) One kind passing through the complete slurry wall of lakebed goaf extra long distance Large-diameter Steel push pipe
CN103922659B (en) Anti-under water dispersion mortar for large area cavity grouting and preparation method thereof
CN101870575A (en) Hydropower station pressure pipeline grouting construction method and gel material
CN103742098A (en) Device and method for sealing hole by using returned slag of layer-through drill hole of low drainage roadway of coal mine
CN105672203B (en) A kind of plugging construction method of dykes and dams RCCP
CN106869853A (en) A kind of " two steps " grouting water blocking method of application ultrahigh water material and cement

Legal Events

Date Code Title Description
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant