CN104481167A - High-formwork construction method for miscellaneous fill ground - Google Patents

High-formwork construction method for miscellaneous fill ground Download PDF

Info

Publication number
CN104481167A
CN104481167A CN201410541134.4A CN201410541134A CN104481167A CN 104481167 A CN104481167 A CN 104481167A CN 201410541134 A CN201410541134 A CN 201410541134A CN 104481167 A CN104481167 A CN 104481167A
Authority
CN
China
Prior art keywords
steel
support
joist
main joist
channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410541134.4A
Other languages
Chinese (zh)
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410541134.4A priority Critical patent/CN104481167A/en
Publication of CN104481167A publication Critical patent/CN104481167A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a high-formwork construction method for miscellaneous fill ground. The method is characterized in that an independent steel support serves as a vertical stress component, and a square steel main keel serves as a horizontal stress component; and the elevation of the independent steel support is detected by a level monitor in a concrete pouring process, when the independent steel support is more than 5mm, the concrete pouring immediately stops, and fine-adjusting nuts of the independent steel support are adjusted, so that a floor formwork can be in a level condition. The construction method comprises the steps of: (1) establishing the steel independent support; (2) strengthening the integrality of the independent steel support by using a horizontal crossbar; (3) building up a beam bottom die; (4) binding beam reinforcing steel bars and beam side die; (5) adjusting the jacking elevation, and placing the square steel main keel; (6) placing a steel channel secondary keel; (7) laying the floor template; (8) binding the reinforcing steel bars of the floor template; (9) detecting and pouring concrete; and (10) disassembling the support system.

Description

Miscellaneous fill ground high-formwork construction method
Technical field
The present invention relates to a kind of construction method of high-supported formwork, particularly a kind of miscellaneous fill ground high-formwork construction method.
Background technology
At house building course, when ground is shelved on miscellaneous fill ground, because miscellaneous fill ground is difficult to compacting, in high-supported formwork situation, easily there is local subsidence.Land subsidence can cause vertical rod discontinuity to occur unstability on the one hand, one deck floor can be made to occur funnel shaped mass defect on the other hand.For this two problems: the stability that will ensure supporting rod on the one hand as far as possible, vertical rod to be made on the other hand to carry out regulating according to local, ground situation of sinking thus to ensure that construction quality can meet the demands.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of miscellaneous fill ground high-formwork construction method, solves the problem of traditional miscellaneous fill ground high-formwork construction difficult quality guarantee.
The present invention adopts steel independently to support as vertical applied force component, adopts square steel main joist and channel-section steel secondary joist as horizontal force component.Floor Slab Deformation is caused in order to prevent from sinking due to the not firm generation template in ground in concreting process, the present invention adopts information-aided construction, by the absolute altitude situation that level gauge monitoring steel independently supports in concreting process, steel independently supports absolute altitude change once be greater than 5mm, stop concreting immediately, the fine-tuning nut that adjustment steel independently supports, makes slab form keep level.
In the present invention steel independently support structure adopt as follows: A-frame leg is collapsible, A-frame leg cross section is steel square tube, rubber pad is had bottom A-frame leg, A-frame is connected with steel fastener by pin, outer tube is welded on steel fastener, outer tube cross sectional shape is the round steel pipe of hollow, outer tube external diameter is 60mm, outer tube wall thickness is 5 ~ 7mm, outer tube top arranges screw thread, it is 100 ~ 120mm that screw thread arranges length, fine-tuning nut is had outside threaded portion round steel pipe, fine-tuning nut length is 150mm, dish-shaped rubber washer is set above fine-tuning nut, regulate owing to adopting internal thread, screw thread does not expose, can effectively prevent screw thread by clashing and breaking and pollution.Interior pipe is had above outer tube, interior tube section shape is the round steel pipe of hollow, inner tube length is 500 ~ 700mm, and interior pipe external diameter is 48mm, and inner tubal wall is thick is 4 ~ 6mm, interior pipe has a back-shaped pin pin-and-hole every 100mm, back-shaped pin pin-and-hole diameter is 8 ~ 12mm, and during operation, back-shaped pin is inserted reversion pin pin-and-hole, back-shaped pin is shelved on above fine-tuning nut, pipe in supporting member inserts, supporting member is fixedly connected with by steel pin with interior pipe.Supporting member is welded with 4 little angle steel, headroom is 80 ~ 90mm, arranges according to square steel main joist width.
Construction sequence comprises:
(1) install steel independently to support
Independently support according to the position of supporting plane arrangement diagram and pitch arrangement steel, steel independently supports and highly regulates as required, interts back-shaped pin.Ensure that steel independently supports layout and embarks on journey in column, and perpendicular to floor face.The obvious concrete gravity of different slab thicknesses has very big difference, and working load can increase, and steel independence tie distance wants corresponding adjustment.According to a large amount of engineering experience, be the engineering of 100mm for slab thickness, steel independence tie distance spacing is 2.7 ~ 2.9m; Be the engineering of 120mm for slab thickness, steel independence tie distance spacing is 2.4 ~ 2.6m; Be the engineering of 130mm for slab thickness, steel independence tie distance spacing is 2.1 ~ 2.3m; Slab thickness is greater than to the engineering of 130mm, steel independence tie distance spacing is 1.6 ~ 2.0m.
Square steel main joist two ends will arrange steel apart from wall 500mm place and two square steel main joist lap-joints and independently support.
(2) steel independence support integral is strengthened with horizontal cross bar
Adopt twice horizontal cross bars, horizontal cross bar adopts diameter to be the steel pipe of 48mm, and first horizontal cross bar overhead distance is 2 ~ 2.2m, and second horizontal cross bar setting position is in first cross bar and steel independently support bottom supporting member.
Traditional support will arrange multiple tracks horizontal cross bar, needs the steel pipe of at substantial on the one hand, and when constructing, personnel are current in addition, materials handling is inconvenient.In addition, in traditional support system, usually bar of sweeping the floor will be adopted, and invention need not adopt, in this, save material.
(3) beam bottom board is set up
1, the length direction of template arrangement is vertical with channel-section steel secondary joist, parallel with square steel main joist.
2, formwork edge joint position is arranged on channel-section steel secondary joist center line.
3, prioritization standard form, arrangement remainder is assigned to narrow shape template, the spacing of narrow shape template and maintenance support interval, and to remove when concrete reaches 50% design strength when seeking template, then maintenance support interval should be less than or equal to 2m.
(4) colligation beam steel and beam side
(5) square steel main joist is placed after adjusting jacking absolute altitude
Square steel pipe main joist is placed according to the direction in main joist layout plan and spacing, and by adjustable jack adjustment girder elevation of top.
After placing square steel main joist, steel independently supports fine-tuning nut and finely tunes, and makes square steel main joist at same level height.
(6) channel-section steel secondary joist is put
To note dodging the position needing the later stage to punch when secondary joist is arranged, comprise measure hole, pump line hole, electromechanics punches.
At narrow space, as passageway, balcony etc., when channel-section steel secondary joist is difficult to arrange, can only arrange square steel main joist, channel-section steel secondary joist 100mm × 100mm flitch replaces.
(7) slab form is laid
(8) floor bar colligation
(9) concreting is checked and accepted
(10) support system is removed
1, unclamp fine-tuning nut, square steel main joist and channel-section steel secondary joist decline, and are lain on one's side by channel-section steel secondary joist.
2, stripping, takes off template from channel-section steel secondary joist neutral gear.
3, channel-section steel secondary joist is removed.
4, square steel main joist is removed.
5, extract back-shaped pin, shrink support bar, removal supporting member, remove support bar.
The present invention has following characteristics:
1, adjust steel in time according to condition of construction independently to support, the mass defect occurred because support system occurs depression can be avoided.
2, when concrete reaches strength of mould stripping, except reservation maintenance support and a small amount of narrow shape template, all the other are all dismountable, not only ensure superstructure sequential production but also can accelerate template turnover use.
3, support on-the-spot cross bar relatively few, thus personnel are current, materials handling is unimpeded, on-the-spot civilization.
Accompanying drawing explanation
Fig. 1 is that steel independently supports schematic diagram.
Reference numeral: 1, rubber pad, 2, A-frame, 3, steel fastener, 4, outer tube, 5, fine-tuning nut, 6, rubber washer, 7, interior pipe, 8, supporting member, 9, back-shaped pin.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present embodiment is described in detail.
The present embodiment is by the absolute altitude situation that level gauge monitoring steel independently supports in concreting process, and steel independently supports absolute altitude change once be greater than 5mm, stops concreting immediately, the fine-tuning nut that adjustment steel independently supports, and makes slab form keep level.
In the present embodiment steel independently support structure adopt as follows: A-frame 2 leg is collapsible, A-frame 2 leg cross section is steel square tube, rubber pad 1 is had bottom A-frame leg, A-frame 2 is connected with steel fastener 3 by pin, outer tube is welded on steel fastener 3, outer tube 4 cross sectional shape is the round steel pipe of hollow, outer tube 4 external diameter is 60mm, outer tube 4 wall thickness is 5 ~ 7mm, outer tube 4 top arranges screw thread, it is 110mm that screw thread arranges length, fine-tuning nut 5 is had outside threaded portion round steel pipe, fine-tuning nut 5 length is 150mm, fine-tuning nut 5 arranges dish-shaped rubber washer 6 above.Outer tube 4 has interior pipe 7 above, interior pipe 7 cross sectional shape is the round steel pipe of hollow, interior pipe 7 length is 500 ~ 700mm, and interior pipe 7 external diameter is 48mm, and interior pipe 7 wall thickness is 4 ~ 6mm, interior pipe 7 has back-shaped pin 9 pin-and-hole every 100mm, back-shaped pin 9 pin-and-hole diameter is 8 ~ 12mm, and during operation, back-shaped pin 9 is inserted reversion pin 9 pin-and-hole, back-shaped pin 9 is shelved on above fine-tuning nut 5, supporting member 8 inserts interior pipe 7, and supporting member 8 is fixedly connected with by steel pin with interior pipe 7.Supporting member 8 is welded with 4 little angle steel, headroom is 80 ~ 90mm, arranges according to square steel main joist width.
Construction sequence comprises:
(1) install steel independently to support
Independently support according to the position of supporting plane arrangement diagram and pitch arrangement steel, steel independently supports and highly regulates as required, interts back-shaped pin.Ensure that steel independently supports layout and embarks on journey in column, and perpendicular to floor face.The obvious concrete gravity of different slab thicknesses has very big difference, and working load can increase, and steel independence tie distance wants corresponding adjustment.The present embodiment slab thickness is the engineering of 120mm, and steel independence tie distance spacing is 2.5m.
Square steel main joist two ends will arrange steel apart from wall 500mm place and two square steel main joist lap-joints and independently support.
(2) steel independence support integral is strengthened with horizontal cross bar
Adopt twice horizontal cross bar, horizontal cross bar adopts diameter to be the steel pipe of 48mm, and first horizontal cross bar overhead distance is 2.1m, and second horizontal cross bar overhead distance is 4.3m.
(3) beam bottom board is set up
1, the length direction of template arrangement is vertical with channel-section steel secondary joist, parallel with square steel main joist.
2, formwork edge joint position is arranged on channel-section steel secondary joist center line.
3, prioritization standard form, arrangement remainder is assigned to narrow shape template.
(4) colligation beam steel and beam side
(5) square steel main joist is placed after adjusting jacking absolute altitude
Square steel pipe main joist is placed according to the direction in main joist layout plan and spacing, and by adjustable jack adjustment girder elevation of top.
After placing square steel main joist, steel independently supports fine-tuning nut and finely tunes, and makes square steel main joist at same level height.
(6) channel-section steel secondary joist is put
To note dodging the position needing the later stage to punch when secondary joist is arranged, comprise measure hole, pump line hole, electromechanics punches.
(7) slab form is laid
(8) floor bar colligation
(9) concreting is checked and accepted
(10) support system is removed
1, unclamp fine-tuning nut, square steel main joist and channel-section steel secondary joist decline, and are lain on one's side by channel-section steel secondary joist.
2, stripping, takes off template from channel-section steel secondary joist neutral gear.
3, channel-section steel secondary joist is removed.
4, square steel main joist is removed.
5, extract back-shaped pin, shrink support bar, removal supporting member, remove support bar.

Claims (7)

1. a miscellaneous fill ground high-formwork construction method, is characterized in that adopting steel independently to support as vertical applied force component, adopts square steel main joist and channel-section steel secondary joist as horizontal force component; By the absolute altitude situation that level gauge monitoring steel independently supports in concreting process, steel independently supports absolute altitude change once be greater than 5mm, stops concreting immediately, the fine-tuning nut that adjustment steel independently supports, and makes slab form keep level;
Construction sequence comprises:
(1) install steel independently to support
Independently support according to the position of supporting plane arrangement diagram and pitch arrangement steel, steel independently supports and highly regulates as required, interts back-shaped pin;
(2) steel independence support integral is strengthened with horizontal cross bar
Adopt twice horizontal cross bar, horizontal cross bar adopts diameter to be the steel pipe of 48mm;
(3) beam bottom board is set up
1, the length direction of template arrangement is vertical with channel-section steel secondary joist, parallel with square steel main joist;
2, formwork edge joint position is arranged on channel-section steel secondary joist center line;
3, prioritization standard form, arrangement remainder is assigned to narrow shape template, the spacing of narrow shape template and maintenance support interval, and to remove when concrete reaches 50% design strength when seeking template, then maintenance support interval should be less than or equal to 2m;
(4) colligation beam steel and beam side
(5) square steel main joist is placed after adjusting jacking absolute altitude
Square steel pipe main joist is placed according to the direction in main joist layout plan and spacing, and by adjustable jack adjustment girder elevation of top;
After placing square steel main joist, steel independently supports fine-tuning nut and finely tunes, and makes square steel main joist at same level height;
(6) channel-section steel secondary joist is put
To note dodging the position needing the later stage to punch when secondary joist is arranged, comprise measure hole, pump line hole, electromechanics punches;
(7) slab form is laid
(8) floor bar colligation
(9) concreting is checked and accepted
(10) support system is removed
1, unclamp fine-tuning nut, square steel main joist and channel-section steel secondary joist decline, and are lain on one's side by channel-section steel secondary joist;
2, stripping, takes off template from channel-section steel secondary joist neutral gear;
3, channel-section steel secondary joist is removed;
4, square steel main joist is removed;
5, extract back-shaped pin, shrink support bar, removal supporting member, remove support bar.
2. the miscellaneous fill ground high-formwork construction method according to claim, it is characterized in that steel independently supports structure and adopts as follows: A-frame leg is collapsible, A-frame leg cross section is steel square tube, rubber pad is had bottom A-frame leg, A-frame is connected with steel fastener by pin, outer tube is welded on steel fastener, outer tube cross sectional shape is the round steel pipe of hollow, outer tube external diameter is 60mm, outer tube wall thickness is 5 ~ 7mm, outer tube top arranges screw thread, it is 100 ~ 120mm that screw thread arranges length, fine-tuning nut is had outside threaded portion round steel pipe, fine-tuning nut length is 150mm, dish-shaped rubber washer is set above fine-tuning nut, interior pipe is had above outer tube, interior tube section shape is the round steel pipe of hollow, inner tube length is 500 ~ 700mm, and interior pipe external diameter is 48mm, and inner tubal wall is thick is 4 ~ 6mm, interior pipe has a back-shaped pin pin-and-hole every 100mm, back-shaped pin pin-and-hole diameter is 8 ~ 12mm, and during operation, back-shaped pin is inserted reversion pin pin-and-hole, back-shaped pin is shelved on above fine-tuning nut, pipe in supporting member inserts, supporting member is fixedly connected with by steel pin with interior pipe, supporting member is welded with 4 little angle steel, headroom is 80 ~ 90mm, arranges according to square steel main joist width.
3. the miscellaneous fill ground high-formwork construction method according to claim, it is characterized in that for slab thickness be the engineering of 100mm, steel independence tie distance spacing is 2.7 ~ 2.9m; Be the engineering of 120mm for slab thickness, steel independence tie distance spacing is 2.4 ~ 2.6m; Be the engineering of 130mm for slab thickness, steel independence tie distance spacing is 2.1 ~ 2.3m; Slab thickness is greater than to the engineering of 130mm, steel independence tie distance spacing is 1.6 ~ 2.0m.
4. the miscellaneous fill ground high-formwork construction method according to claim, is characterized in that installing steel and independently supports in step and will ensure that steel independently supports layout and embarks on journey in column, and perpendicular to floor face.
5. the miscellaneous fill ground high-formwork construction method according to claim, is characterized in that installing steel and independently supports square steel main joist two ends in step and will arrange steel apart from wall 500mm place and two square steel main joist lap-joints and independently support.
6. the miscellaneous fill ground high-formwork construction method according to claim, it is characterized in that first horizontal cross bar overhead distance be 2 ~ 2.2m, second horizontal cross bar setting position is in first cross bar and steel independently support bottom supporting member.
7. the miscellaneous fill ground high-formwork construction method according to claim, is characterized in that at narrow space, and when channel-section steel secondary joist is difficult to arrange, only arrange square steel main joist, channel-section steel secondary joist 100mm × 100mm flitch replaces.
CN201410541134.4A 2014-09-27 2014-09-27 High-formwork construction method for miscellaneous fill ground Pending CN104481167A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410541134.4A CN104481167A (en) 2014-09-27 2014-09-27 High-formwork construction method for miscellaneous fill ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410541134.4A CN104481167A (en) 2014-09-27 2014-09-27 High-formwork construction method for miscellaneous fill ground

Publications (1)

Publication Number Publication Date
CN104481167A true CN104481167A (en) 2015-04-01

Family

ID=52755761

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410541134.4A Pending CN104481167A (en) 2014-09-27 2014-09-27 High-formwork construction method for miscellaneous fill ground

Country Status (1)

Country Link
CN (1) CN104481167A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105525752A (en) * 2016-01-20 2016-04-27 江西师范大学 Formwork support rod
CN107687268A (en) * 2017-09-29 2018-02-13 江苏省苏中建设集团股份有限公司 A kind of building construction frame
CN107905543A (en) * 2017-11-28 2018-04-13 上海建工五建集团有限公司 Laminated floor slab supporting structure and its application construction method
CN110439269A (en) * 2018-05-02 2019-11-12 深圳市前海胜德建筑科技有限公司 Independent support system and its installation method based on high-supported formwork
CN111305596A (en) * 2019-11-28 2020-06-19 上海泾东建筑发展有限公司 Rapid dismounting and mounting reinforcing structure for beamless floor slab of basement and construction method thereof
CN113323216A (en) * 2021-07-06 2021-08-31 中建八局天津建设工程有限公司 Support-free laminated slab and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201620615U (en) * 2010-01-30 2010-11-03 盛明春 Supporting adjustable upright column of construction engineering formwork
KR101019411B1 (en) * 2010-12-15 2011-03-07 노윤근 Slab construction technique
CN102277959A (en) * 2011-05-13 2011-12-14 中国新兴保信建设总公司 Standard steel frame formwork system for concrete floor slabs and construction method thereof
JP2013129961A (en) * 2011-12-20 2013-07-04 Toda Constr Co Ltd Temporary fixation method for steel staircase and pipe support for supporting steel staircase

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201620615U (en) * 2010-01-30 2010-11-03 盛明春 Supporting adjustable upright column of construction engineering formwork
KR101019411B1 (en) * 2010-12-15 2011-03-07 노윤근 Slab construction technique
CN102277959A (en) * 2011-05-13 2011-12-14 中国新兴保信建设总公司 Standard steel frame formwork system for concrete floor slabs and construction method thereof
JP2013129961A (en) * 2011-12-20 2013-07-04 Toda Constr Co Ltd Temporary fixation method for steel staircase and pipe support for supporting steel staircase

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
姜超: "独立钢支撑式水平模板早拆体系在住宅工程施工中的应用研究", 《住宅产业》 *
张良杰: "早拆模板施工技术及新型水平模板支撑***应用", 《施工技术》 *
李晓琼等: "独立钢支撑工具化水平模板支撑体系施工技术", 《施工技术》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105525752A (en) * 2016-01-20 2016-04-27 江西师范大学 Formwork support rod
CN107687268A (en) * 2017-09-29 2018-02-13 江苏省苏中建设集团股份有限公司 A kind of building construction frame
CN107905543A (en) * 2017-11-28 2018-04-13 上海建工五建集团有限公司 Laminated floor slab supporting structure and its application construction method
CN110439269A (en) * 2018-05-02 2019-11-12 深圳市前海胜德建筑科技有限公司 Independent support system and its installation method based on high-supported formwork
CN111305596A (en) * 2019-11-28 2020-06-19 上海泾东建筑发展有限公司 Rapid dismounting and mounting reinforcing structure for beamless floor slab of basement and construction method thereof
CN113323216A (en) * 2021-07-06 2021-08-31 中建八局天津建设工程有限公司 Support-free laminated slab and construction method thereof

Similar Documents

Publication Publication Date Title
CN104481167A (en) High-formwork construction method for miscellaneous fill ground
CN104141383B (en) A kind of Bailey beam pendent form support system and construction thereof
CN106150055B (en) The installation method of the flat hanging installment work rack of concrete embedded part essence and built-in fitting
CN103422667B (en) Double-plate prefabricated superposed wall supporting system
US20140175259A1 (en) Modular Panel Concrete Form For Self-Lifting Concrete Form System
CN103669655A (en) Construction technology for pouring concrete of walls on two sides of deformation joint
CN103334527A (en) Steel structure cast-in-site floor arching construction method
CN105863253A (en) Integral formwork-supporting type asynchronous casting stairwell wall column formwork supporting system and construction method
CN102239302A (en) A means of stripping concrete formwork from a concrete surface
CN104196231A (en) Concrete floor aluminum alloy template and construction method thereof
CN104032969A (en) Precise positioning and process regulation and control device for vibration isolation support embedded plate
CN103883052A (en) Upturned beam and cast-in-place slab overall pouring construction method
CN112627034A (en) Synchronous construction method for turning over mold of high pier of bridge
CN204059940U (en) A kind of concrete floor aluminum alloy mould plate
CN106567538A (en) Positioning mold for bathroom concrete flanges
CN102409850A (en) Construction method for template for building
CN107724672A (en) A kind of steel construction skyscraper cast-in-situ floor formwork support structure
CN209907886U (en) Adjustable assembled stair construction platform
CN203603490U (en) Supporting structure used for erecting formwork truss on prefabricated beam
CN205935706U (en) A elevation controlling means for terrace construction
CN203701588U (en) Shaping steel formwork for one-time-formed plastering-free cast-in-situ stair
CN103526698B (en) Cast-in-cantilever construction 0# block concrete supporting system and construction method
CN110348142A (en) Based on the BIM method of gang form bracket technique molding curve bridge
CN204212449U (en) Steel independently supports
CN106049283A (en) Bridge rectangular pier hanging die construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150401