CN104453248A - Complex irregular-shaped multi-layer net rack construction method based on layered modular assembling technology - Google Patents

Complex irregular-shaped multi-layer net rack construction method based on layered modular assembling technology Download PDF

Info

Publication number
CN104453248A
CN104453248A CN201310436434.1A CN201310436434A CN104453248A CN 104453248 A CN104453248 A CN 104453248A CN 201310436434 A CN201310436434 A CN 201310436434A CN 104453248 A CN104453248 A CN 104453248A
Authority
CN
China
Prior art keywords
module
assembled
construction method
modules
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310436434.1A
Other languages
Chinese (zh)
Other versions
CN104453248B (en
Inventor
孙飞
李鸿骏
朱卫军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201310436434.1A priority Critical patent/CN104453248B/en
Publication of CN104453248A publication Critical patent/CN104453248A/en
Application granted granted Critical
Publication of CN104453248B publication Critical patent/CN104453248B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to multi-layer net rack construction methods, in particular to a complex irregular-shaped multi-layer net rack construction method based on a layered modular assembling technology. The construction method comprises the following steps that (1) firstly, small plane units are assembled on the ground; points where welded balls are placed are positioned through a total station, wherein the center lines of the balls and the center lines of pipes are located on the same horizontal plane, pipe fittings and the balls are in middle connection, gaskets are arranged in ball and pipe butt joint ports, and gaps are reserved in the ball and pipe butt joint ports; (2) after small assembly units are assembled, module assembling is performed; (3) modules are welded, wherein after assembling is completed, the modules are welded according to the sequence of welding from main chord members and web members in the middle to the two sides and from inside to outside; (4) the modules are hoisted, wherein each module is provided with five hoisting points, one hoisting point of the five hoisting points of each module is a main rope hoisting point which passes through the gravity center of the corresponding module, and the remaining four hoisting points adjust relative postures of the modules through chain blocks; (5) the modules are hoisted, wherein the modules are hoisted in place through a crawler crane. The construction method can simplify complex irregular-shaped multi-layer net rack construction and improve construction efficiency.

Description

The Complex Different Shape Multilayered net frame construction method of delamination modularization assembling process
Technical field
The present invention relates to Multilayered net frame construction method, particularly relate to a kind of Complex Different Shape Multilayered net frame construction method.
Background technology
Since the 2008 main competition fields of the Chinese Olympic Games " Bird's Nest ", the large stadium of the steel work of China gets more and more.These newly-built steel buildings are in order to pursue the visual effect of building, and its structure becomes increasingly complex, and shape is more and more peculiar.
For these buildings, the construction of its steel structure net rack mainly contains following method whole hanging method, Integral Lifting, aerial sliding methed, Assembly in pieces at height, and piecemeal Method for Installation etc. are several.
overall (piecemeal) lift-on/lift-off system:according to structural condition, by overall for space truss structure hoisting, utilize existing bearing during Steel Structure Installation or the auxiliary installation of supplemental support moulding bed is set.Scheme advantage: rack piecemeal installation on ground, construction quality is high, and work plane is many, short construction period, big machinery hoisting technology maturation, and efficiency of construction is high, safe and reliable, overall construction economy high efficiency.Scheme shortcoming: it is many that ground takies assembled place, and add main equipment input.
integral Lifting:first according to the projected area position of rack, undertaken levelling according to the lower edge face of rack by scaffold building platform, space truss structure (piecemeal) entirety assembly on platform, the Z value reduction of nearly vertical direction in grid node design three-dimensional coordinate in assembled process, horizontal direction X and Y value constant.Lifting process adopts hoist engine or hydraulic synchronization Robotics, does measure for improvement, to rack (piecemeal) Integral in-position after assembled welding at steel column top.Scheme advantage: platform for lining height is effectively reduced, saves full hall frame measure amount, make use of ground or flooring, improve working security.Lifting operation technique is advanced, high in technological content, adopts after promoting, decreases the input of big machinery.Consolidation service face is large, short construction period.Scheme shortcoming: on the basis utilizing existing ground or flooring platform, still want a large amount of full hall scaffolds, construction cost is high; Measure amount is large, full hall scaffold set up and the dismounting cycle long, be unfavorable for the entirety duration; Consolidation service or the scaffolding platform occupied ground time long, other specialty cannot be constructed completely.
aerial sliding methed:first set up bracing members, at bracing members top erection slippage beam, first from one end, start construction and set up mobile platform for lining, rack on a mobile platform assembled complete a unit after, unloading, mobile platform for lining, assembled next unit, completes Construction of The Grids successively.Scheme advantage: the mode favourable minimizing measure amount that rack accumulation slippage is in place, maximum benefit reduces amount of high-altitude operation, and construction technology is advanced, and high in technological content, working security is higher.Scheme shortcoming: support jig and slippage beam measure amount drop into higher, and construction cost is high; Operation side is little, only at one end works, and is unfavorable for the overall duration; Refer to that corridor roof system is longer, skidding distance is comparatively large, and accumulated error is large.
assembly in pieces at height:full hall support scaffolding platform set up by ground immediately below space truss structure or flooring, then utilizes support platform roof system rack original position assembly, welding.After top roof structure and berm execution complete, roof system rack is unloaded, then remove full hall scaffold support platform.Scheme advantage: the precision adjustment that the favourable high-altitude of mode that full hall scaffold sets up support platform is installed, mounting platform area is large, is conducive to the safety of constructor, is convenient to ensure welding quality.Scheme shortcoming: scaffolding platform set up the needs longer time, the time taking inner space is long, space large, is unfavorable for inner civil engineering and dynamo-electricly installs, and this engineering so short duration cannot complete; Although scaffold can have enough to meet the need, machinery can be strengthened and drop into and elongate the duration; According to the scaffolding platform of so large volume, large density, construction cost is too high, and economy is unreasonable.
This engineering rack is different from traditional rack type, and the solder sphere of upper lower edge all on the same axis, in two (many) layers and be limit surface modeling on facade, traditionally cannot construct by construction method.In view of design feature and company technique advantage, break the normal procedure and invented the complicated abnormal shape Multilayered net frame construction method of modularization, unitized multi-layered modular.
Summary of the invention
The present invention is intended to the problems referred to above solving prior art, provides a kind of Complex Different Shape Multilayered net frame construction method of delamination modularization assembling process.The present invention can simplify different for complexity Multilayered net frame construction, improves efficiency of construction.
For solving the problem, a kind of Complex Different Shape Multilayered net frame construction method of delamination modularization assembling process, it comprises: adopt earth module assembled, high-altitude module hoisting, adopts high altitude bulk between module and module, and Specific construction step is as follows:
Step one, on ground, advanced parallel planes junior unit is assembled; Requirement ground is welded, ball accurate positioning, and what adopt total powerstation to carry out solder sphere puts point location, and ball, tube hub line are at a horizontal plane, and pipe fitting is connected between two parties with ball, establish packing ring to stay gap in bulb docking port;
Step 2, smallest assembled rigid unit is assembled complete after carry out module spliced dress;
Step 3, module weld: assembled complete after welding sequence weld to both sides according to from middle main chord, web member, from inside to outside weld, same pipe fitting avoids two ends to weld simultaneously;
Step 4, module hoisting, each module establishes five suspension centres, and one is main rope suspension centre, and main rope suspension centre is by module center of gravity, and other 4 suspension centres carry out the adjustment of relative pose to module by Chain block;
Step 5, module hoisting, module adopts crawler crane to lift, and is slowly off the hook when module drops on directly over moulding bed, and module differs 2mm during with the moulding bed strong point, off the hook stops, and uses total powerstation three-dimensional localization, and module locates errorless rear off the hook, and lifting puts in place.
The Complex Different Shape Multilayered net frame construction method of described delamination modularization assembling process, described step one also comprises the division of unit:
First, formal approximation between the junior unit that division is formed, processing length is similar to
Secondly, divide the gradual change that the junior unit formed utilizes net shell curved surface, accomplish structure unification substantially, assembled complexity is close, is convenient to the difficulty reducing field technician and constructor's manipulation, improves quality.
Finally, the consumption at utmost reducing auxiliary moulding bed to be considered when junior unit divides.
The Complex Different Shape Multilayered net frame construction method of described delamination modularization assembling process, in the middle of described step 3, module relative pose is not by regulating at the relative relief of three centre ofs sphere of the same face on module lower edge.
The Complex Different Shape Multilayered net frame construction method of described delamination modularization assembling process, described step 4 is when assembled, first mark assembled unit ground line-transect, then platform for lining is set up, the chord member girder unit made is gone up tire successively according to the position of unit combination, finally with time beam element, girder is connected.
The Complex Different Shape Multilayered net frame construction method of described delamination modularization assembling process, in described step 5, when junior unit divides, has formulated unique erection sequence, has numbered in order and install one by one during installation.
The modular dividing elements rack region of the present invention, when lifting elements assembled, first assembled plane smallest assembled rigid unit, the assembled each layer smallest assembled rigid unit of recombinant forms the mode of lifting module, complete the shaping of final modularization lifting elements, modularization assemble, lifting, solve the installation of Complex Different Shape rack, and integral construction efficiency significantly promotes.The present invention adequately achieves Modern Large tool construction operation; Effectively complete the construction of two (many) layers rack of Complex Different Shape; Engineering practice proves that the method has for the lifting of two (many) layers space truss structure of Complex Different Shape and simplifies, the obvious effect of raising the efficiency.
Detailed description of the invention
Below in conjunction with detailed description of the invention, the present invention is further illustrated:
The Complex Different Shape Multilayered net frame construction method of a kind of delamination modularization assembling process of the present invention, comprise two (many) layers Construction of The Grids of abnormity and adopt earth module assembled, high-altitude module hoisting, adopts high altitude bulk between module and module, and Specific construction step is as follows:
The division of junior unit:
First, formal approximation between the junior unit that division is formed, processing length is similar to;
Secondly, divide the gradual change that the junior unit formed utilizes net shell curved surface, accomplish structure unification substantially, assembled complexity is close, is convenient to the difficulty reducing field technician and constructor's manipulation, improves quality.
Finally, the consumption at utmost reducing auxiliary moulding bed to be considered when junior unit divides.
On ground, advanced parallel planes junior unit is assembled; Technical essential is: ground solder sphere accurate positioning, what adopt total powerstation to carry out solder sphere puts point location, bulb center line is at a horizontal plane, pipe fitting is connected between two parties with ball, establish packing ring to stay gap in bulb docking port: when assembled, first mark assembled unit ground line-transect, then set up platform for lining, the chord member girder unit made is gone up tire successively according to the position of unit combination, finally with time beam element, girder is connected.
Smallest assembled rigid unit is assembled complete after carry out module spliced dress, technical essential is: moulding bed three-dimensional coordinate is accurate; Solder technology require be: assembled complete after welding sequence weld to both sides according to from middle main chord, web member, from inside to outside weld, same pipe fitting avoids two ends to weld simultaneously;
Module hoisting, each module establishes 5 suspension centres, and one is main rope suspension centre, and main rope suspension centre is by module center of gravity, and other 4 suspension centres carry out the adjustment of relative pose to module by Chain block; Technical essential: module relative pose not regulating at three centre of sphere relative reliefs of the same face by module lower edge;
When junior unit divides, formulate unique erection sequence, numbered in order during installation and install one by one.
Module adopts 350 tons of crawler cranes to lift, and is slowly off the hook when module drops on directly over moulding bed, and module differs 2mm during with the moulding bed strong point, off the hook stops, and carries out total powerstation three-dimensional localization, and the module errorless rear off the hook in location, lifting puts in place.

Claims (5)

1. a Complex Different Shape Multilayered net frame construction method for delamination modularization assembling process, it comprises: adopt earth module assembled, high-altitude module hoisting, adopts high altitude bulk between module and module, it is characterized in that, Specific construction step is as follows:
Step one, on ground, advanced parallel planes junior unit is assembled; Requirement ground is welded, ball accurate positioning, and what adopt total powerstation to carry out solder sphere puts point location, and ball, tube hub line are at a horizontal plane, and pipe fitting is connected between two parties with ball, establish packing ring to stay gap in bulb docking port;
Step 2, smallest assembled rigid unit is assembled complete after carry out module spliced dress;
Step 3, module weld: assembled complete after welding sequence weld to both sides according to from middle main chord, web member, from inside to outside weld, same pipe fitting avoids two ends to weld simultaneously;
Step 4, module hoisting, each module establishes five suspension centres, and one is main rope suspension centre, and main rope suspension centre is by module center of gravity, and other four suspension centres carry out the adjustment of relative pose to module by Chain block;
Step 5, module hoisting, module adopts crawler crane to lift, and is slowly off the hook when module drops on directly over moulding bed, and module differs 2mm during with the moulding bed strong point, off the hook stops, and uses total powerstation three-dimensional localization, and module locates errorless rear off the hook, and lifting puts in place.
2. the Complex Different Shape Multilayered net frame construction method of delamination modularization assembling process according to claim 1, is characterized in that, described step one also comprises the division of unit:
First, formal approximation between the junior unit that division is formed, processing length is similar to
Secondly, divide the gradual change that the junior unit formed utilizes net shell curved surface, accomplish structure unification substantially, assembled complexity is close, is convenient to the difficulty reducing field technician and constructor's manipulation, improves quality,
Finally, the consumption at utmost reducing auxiliary moulding bed to be considered when junior unit divides.
3. the Complex Different Shape Multilayered net frame construction method of delamination modularization assembling process according to claim 1, it is characterized in that, in the middle of described step 3, module relative pose is not by regulating at the relative relief of three centre ofs sphere of the same face on module lower edge.
4. the Complex Different Shape Multilayered net frame construction method of delamination modularization assembling process according to claim 1, it is characterized in that, described step 4 is when assembled, first mark assembled unit ground line-transect, then platform for lining is set up, the chord member girder unit made is gone up tire successively according to the position of unit combination, finally with time beam element, girder is connected.
5. the Complex Different Shape Multilayered net frame construction method of delamination modularization assembling process according to claim 1, is characterized in that, in described step 5, when junior unit divides, has formulated unique erection sequence, has numbered in order and install one by one during installation.
CN201310436434.1A 2013-09-24 2013-09-24 Complex irregular-shaped multi-layer net rack construction method based on layered modular assembling technology Active CN104453248B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310436434.1A CN104453248B (en) 2013-09-24 2013-09-24 Complex irregular-shaped multi-layer net rack construction method based on layered modular assembling technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310436434.1A CN104453248B (en) 2013-09-24 2013-09-24 Complex irregular-shaped multi-layer net rack construction method based on layered modular assembling technology

Publications (2)

Publication Number Publication Date
CN104453248A true CN104453248A (en) 2015-03-25
CN104453248B CN104453248B (en) 2017-01-25

Family

ID=52899937

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310436434.1A Active CN104453248B (en) 2013-09-24 2013-09-24 Complex irregular-shaped multi-layer net rack construction method based on layered modular assembling technology

Country Status (1)

Country Link
CN (1) CN104453248B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831939A (en) * 2015-05-22 2015-08-12 常州第一建筑集团有限公司 Bolt ball welding ball mixed node large span cantilever grid structure construction method
CN105569358A (en) * 2015-12-15 2016-05-11 中国建筑第八工程局有限公司 Construction method of special-shaped curved surface roof with large span and multiple curvatures
CN106609561A (en) * 2015-10-22 2017-05-03 江苏沪宁钢机股份有限公司 A spherical net shell block stacked assembly method
CN111005454A (en) * 2019-12-09 2020-04-14 中国电建集团河南工程有限公司 Flue gas purification room net rack block hoisting construction method
CN111335648A (en) * 2020-03-31 2020-06-26 五冶集团上海有限公司 Layered and segmented installation method for large-span spherical crown-shaped grid structure
CN111335647A (en) * 2020-03-31 2020-06-26 五冶集团上海有限公司 Sectional hoisting construction method for large-span spherical crown-shaped grid structure
CN112814247A (en) * 2021-01-04 2021-05-18 上海市机械施工集团有限公司 Method for installing middle-mounted compression ring spoke type tensioning structure
CN113123469A (en) * 2021-03-24 2021-07-16 中国五冶集团有限公司 Method for constructing complex curved surface modeling roof grid structure
CN113833277A (en) * 2021-08-26 2021-12-24 中铁建设集团北京工程有限公司 Construction method for decomposing primary and secondary beams of steel latticed shell
CN114086669A (en) * 2021-11-30 2022-02-25 中国五冶集团有限公司 Large-scale space special-shaped curved surface steel net rack modular rapid construction method
CN115162813A (en) * 2022-07-14 2022-10-11 中国三冶集团有限公司 Ground assembling method for cylindrical thin oil tank piston module

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06180029A (en) * 1992-12-15 1994-06-28 Takenaka Komuten Co Ltd Lift-up construction method of single layer truss roof
CN101519913A (en) * 2008-12-29 2009-09-02 青建集团股份公司 Construction method for lifting whole steel structural roof with large span and complicated design
CN101988308A (en) * 2010-09-30 2011-03-23 中国华西企业有限公司 Non-support installation method of long-span spatial bolt ball steel reticulated shell dome
CN102102445A (en) * 2011-03-09 2011-06-22 中国建筑第八工程局有限公司 Partitioning lifting construction method for huge weld ball net rack
CN102179651A (en) * 2011-04-06 2011-09-14 中国建筑第八工程局有限公司 On-site plane trusses of extra-large welded ball net frame and method for splicing three-dimensional sections

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06180029A (en) * 1992-12-15 1994-06-28 Takenaka Komuten Co Ltd Lift-up construction method of single layer truss roof
CN101519913A (en) * 2008-12-29 2009-09-02 青建集团股份公司 Construction method for lifting whole steel structural roof with large span and complicated design
CN101988308A (en) * 2010-09-30 2011-03-23 中国华西企业有限公司 Non-support installation method of long-span spatial bolt ball steel reticulated shell dome
CN102102445A (en) * 2011-03-09 2011-06-22 中国建筑第八工程局有限公司 Partitioning lifting construction method for huge weld ball net rack
CN102179651A (en) * 2011-04-06 2011-09-14 中国建筑第八工程局有限公司 On-site plane trusses of extra-large welded ball net frame and method for splicing three-dimensional sections

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831939A (en) * 2015-05-22 2015-08-12 常州第一建筑集团有限公司 Bolt ball welding ball mixed node large span cantilever grid structure construction method
CN104831939B (en) * 2015-05-22 2017-06-30 常州第一建筑集团有限公司 Bolt sphere solder sphere mixed node Long-span Cantilever spatial mesh structure construction method
CN106609561A (en) * 2015-10-22 2017-05-03 江苏沪宁钢机股份有限公司 A spherical net shell block stacked assembly method
CN105569358A (en) * 2015-12-15 2016-05-11 中国建筑第八工程局有限公司 Construction method of special-shaped curved surface roof with large span and multiple curvatures
CN111005454A (en) * 2019-12-09 2020-04-14 中国电建集团河南工程有限公司 Flue gas purification room net rack block hoisting construction method
CN111335647A (en) * 2020-03-31 2020-06-26 五冶集团上海有限公司 Sectional hoisting construction method for large-span spherical crown-shaped grid structure
CN111335648A (en) * 2020-03-31 2020-06-26 五冶集团上海有限公司 Layered and segmented installation method for large-span spherical crown-shaped grid structure
CN112814247A (en) * 2021-01-04 2021-05-18 上海市机械施工集团有限公司 Method for installing middle-mounted compression ring spoke type tensioning structure
CN113123469A (en) * 2021-03-24 2021-07-16 中国五冶集团有限公司 Method for constructing complex curved surface modeling roof grid structure
CN113833277A (en) * 2021-08-26 2021-12-24 中铁建设集团北京工程有限公司 Construction method for decomposing primary and secondary beams of steel latticed shell
CN114086669A (en) * 2021-11-30 2022-02-25 中国五冶集团有限公司 Large-scale space special-shaped curved surface steel net rack modular rapid construction method
CN114086669B (en) * 2021-11-30 2024-03-19 中国五冶集团有限公司 Modularized rapid construction method for large-scale space special-shaped curved surface steel net rack
CN115162813A (en) * 2022-07-14 2022-10-11 中国三冶集团有限公司 Ground assembling method for cylindrical thin oil tank piston module
CN115162813B (en) * 2022-07-14 2024-05-03 中国三冶集团有限公司 Ground assembling method for cylindrical thin oil tank piston module

Also Published As

Publication number Publication date
CN104453248B (en) 2017-01-25

Similar Documents

Publication Publication Date Title
CN104453248A (en) Complex irregular-shaped multi-layer net rack construction method based on layered modular assembling technology
CN103243930B (en) System and method for modularized construction of super high-rise steel structures
CN109098454B (en) Hydraulic lifting construction method for high-altitude large-span curved roof
CN109779272A (en) A kind of high-altitude steel structure corridor construction method
CN103572763B (en) Large-span steel supports pattern foundation pit supporting structure Demolition Construction method
CN107762159A (en) Large-span steel truss high-altitude sliding in place method
CN109747775A (en) The parallel building technology of FPSO modular unitization
CN106544959B (en) The construction method of king-tower lifting segment and bridge main tower saddle containing saddle
CN103086276B (en) Construction method for hoisting bridge type crane in high-rise well tower type building
CN105569375A (en) Large complex steel structure tank protective demolition and installation method
CN104278779B (en) The rope net of a kind of larger decorative curtain wall and the method for installation Tension Forming thereof
CN203603455U (en) Tool type hanger suitable for construction of vertical structure of super high-rise building
CN206562827U (en) A kind of modularization steel-frame structure for tower equipment
CN104775363A (en) Assembling method of upper tower column reinforcing steel bar segment
CN104264781B (en) Latticed cylinder Steel Shell and construction method thereof
CN104328922B (en) High-altitude multilayer is dangled steel construction against way Hoisting Construction Technology
CN108952002B (en) Oversized and ultra-wide double-spliced combined I-shaped steel beam and sectional division and installation method thereof
CN204311622U (en) A kind of shape of a saddle prestressed cable net
CN102259794B (en) Method for installing overall combined type crane beam
CN204850469U (en) Commercial mansion system that builds
CN212249263U (en) Mounting structure of roof truss and arc multilayer packway
CN104060838B (en) A kind of vestibule divides into groups aerial group to Method for Installation
CN202655839U (en) Movable pipe truss assembling clamping fixture
CN107201846A (en) A kind of installing flare tower frame and its modularization installation method
CN101774516B (en) Lifting device and construction method for replacing rake crane bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant