CN104374637A - 基于高温高压条件下水压致裂实验的水密封装置 - Google Patents

基于高温高压条件下水压致裂实验的水密封装置 Download PDF

Info

Publication number
CN104374637A
CN104374637A CN201410610735.6A CN201410610735A CN104374637A CN 104374637 A CN104374637 A CN 104374637A CN 201410610735 A CN201410610735 A CN 201410610735A CN 104374637 A CN104374637 A CN 104374637A
Authority
CN
China
Prior art keywords
water pipe
wedge
rock sample
metallic water
sealing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410610735.6A
Other languages
English (en)
Other versions
CN104374637B (zh
Inventor
万志军
周鹏
周长冰
王志民
张源
程敬义
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201410610735.6A priority Critical patent/CN104374637B/zh
Publication of CN104374637A publication Critical patent/CN104374637A/zh
Application granted granted Critical
Publication of CN104374637B publication Critical patent/CN104374637B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

一种基于高温高压条件下水压致裂实验的水密封装置,包括封孔螺母、金属水管、锁紧螺母、金属垫圈和楔形密封紫铜圈。其中楔形密封紫铜圈套装于伸入岩石试样内部钻孔的金属水管上,楔形密封紫铜圈之间通过金属垫圈隔开,楔形密封紫铜圈由两片有斜面的铜封对扣构成,楔形密封紫铜圈的内外面均为竖直面。在试验机内最高可达600℃高温条件下,楔形密封紫铜圈膨胀,内外竖直面分别压紧金属水管和岩石孔壁,实现初期封孔。在实验机对岩石试样施加载荷过程中,楔形密封紫铜圈受压变形膨胀,外竖直面与岩石试样孔壁紧密接触,内竖直面与金属水管紧密接触,实现实验过程中的高压水密封。本发明通过在金属水管外增设楔形密封紫铜圈来实现高温、高载荷压力条件下的水密封。其装置结构简单、性能可靠、稳定性好,适用于高温高压条件下的岩石的水压致裂实验。

Description

基于高温高压条件下水压致裂实验的水密封装置
技术领域
本发明涉及一种水压致裂实验的水密封装置,尤其是一种适用于岩石试样在高温高压条件下水压致裂实验的水密封装置。 
背景技术
近年来,在开采地热的过程中,人工循环储留层的建造是整个工程的关键也是难点,其建造方法为巨型水压致裂。目前尚有众多问题如起裂压力、理裂隙扩规律等值得进一步研究。研究手段主要采用理论研究和数值计算的方法。而这两种研究手段都无法真实的反应现场工程的实际环境,由于边界条件的复杂性,目前仍然没有一种有效的设备和方法开展实验室实验。因此,设计了一种在高温高压下,对花岗岩进行水压致裂实验室研究的装置和方法。 
在装置的研制过程中,使用高压水射流设备提供最高400MPa的高压水,作为水压致裂的压力源。岩石内高压水的密封为岩石水压致裂实验设计需要解决的关键技术,也是相关实验能否成功开展的决定性因素。 
目前的水压致裂实验采用的水密封技术较为落后,多采用钻孔密封材料进行密封,主要采用水泥沙浆和聚氨脂作为压裂钻孔的密封材料。前者封孔后容易产生收缩,导致材料与孔壁结合处出现漏水现象,直接影响卸压增透措施的效果;后者不仅材料价格过高,而且抗压性能较差,只能满足一般水力压裂技术的抗压要求。综上所述,在高温高压下,常规的水密封方法都不能使用。在400MPa水压下,微小的缝隙也能出现大流量的泄漏,使水压加载不到目标压力。 
发明内容
本发明的目的是针对已有技术中存在的问题,提供一种结构简单、耐高温、价格低廉、密封效果好的基于高温高压条件下水压致裂实验的水密封装置。 
本发明解决其技术问题所采用的技术方案是:本发明的基于高温高压环境下岩石试样水压致裂实验的水密封装置,包括开有一盲孔的岩石试样,岩石试样的盲孔内插装有金属水管,盲孔内的金属水管上间隔套装有多个金属垫圈和楔形密封紫铜圈,多个金属垫圈和楔形密封紫铜圈之上设有与金属水管相匹配的锁紧螺母,金属水管的外露端上设有封住岩石试样孔口 的封孔螺母。 
所述的楔形密封紫铜圈包括楔形上方紫铜封、与上方紫铜封契合在一起的楔形下方紫铜封。 
所述的金属垫圈为圆柱环体,金属垫圈的内环直径略大于金属水管的外径,金属垫圈的外环直径略小于岩石试样的盲孔孔径。 
所述的金属水管为阶梯形的钢制铸件,金属水管中部的第一个阶梯处加工有螺纹一,金属水管上部第二阶梯处设有螺纹二,螺纹一的外径等于金属水管下部的水管外径,螺纹二的外径等于金属水管中部的水管外径;锁紧螺母与金属水管的金属水管中部螺纹配套,封孔螺母与金属水管顶部螺纹的螺纹配套。 
所述间隔套装的多个金属垫圈和楔形密封紫铜圈为2~4组。 
有益效果:本发明通过增设楔形密封紫铜圈,在预装楔形密封紫铜圈时,对楔形密封紫铜圈施加压力,使其贴紧岩石孔壁。随着实验压力室温度的升高,楔形密封紫铜圈和岩石在受热膨胀时,由于紫铜的膨胀系数大于岩石的膨胀系数,使两者进一步贴紧。当注入高压水时,水压从楔形密封紫铜圈下方挤压楔形密封紫铜圈下方铜封,使其向上运动并与上方铜封沿铜封接触斜面产生挫动,在试验机内最高可达600℃高温的条件下,紫铜***更容易变形,从而使楔形密封紫铜圈膨胀并起到封孔作用,克服了传统水密封材料或方法在高温高压环境下失效的缺点,特别适用于高温高压的工作环境,具有密封效果好、材料延展性好、抗腐蚀的优点。 
附图说明
图1是本发明的结构示意图; 
图2是本发明楔形密封紫铜圈的结构示意图;
图3是本发明金属水管的结构示意图;
图4是本发明金属水管结构示意图。
图中:1、封孔螺母;2、金属水管;3、锁紧螺母;4、岩石试样;5、金属垫圈;6、楔形密封紫铜圈;2-1、金属水管中部螺纹;2-2、金属水管顶部螺纹;6-1、楔形密封紫铜圈上方铜封;6-2、楔形密封紫铜圈下方铜封。 
具体实施方式
下面结合附图对本发明的一个实施例作进一步的描述: 
如图1所示,本发明基于高温高压环境下岩石试样水压致裂实验的水密封装置,主要由封孔螺母1、金属水管2、锁紧螺母3、岩石试样4、金属垫圈5和楔形密封紫铜圈6组成。在岩石试样4上开有一盲孔,向岩石试样4的盲孔内插装有金属水管2,盲孔内的金属水管2上间隔套装有多个金属垫圈5和楔形密封紫铜圈6,多个金属垫圈5和楔形密封紫铜圈6之上设有与金属水管2相配合的锁紧螺母3,金属水管2的外露端上设有封住岩石试样4孔口的封孔螺母1;所述间隔套装的多个金属垫圈5和楔形密封紫铜圈6为2~4组,图1所示为3组。 
图2为楔形密封紫铜圈6的结构原理图。所述的楔形密封紫铜圈6包括楔形上方紫铜封6-1、与上方紫铜封6-1契合在一起的楔形下方紫铜封6-2。楔形密封紫铜圈6的结构为两片有斜面的铜封对扣,包括上方铜封6-1和下方铜封6-2。下方铜封6-2的外边面为竖直面,紧贴岩石试样4的钻孔孔壁,内边面为斜面。上方铜封6-1的外边面为斜面,斜率与下方铜封6-2的斜面相同,对扣时两个铜封的斜面可紧密接触,内边面竖直,可与金属水管2紧密接触。所述的金属垫圈5为圆柱环体,金属垫圈5的内环直径略大于金属水管2的外径,金属垫圈5的外环直径略小于岩石试样4的钻孔孔径。楔形密封紫铜圈上、下方为金属垫圈5,可分别抵住上方铜封6-1和下方铜封6-2,安装时,按压上面的金属垫圈5使上、下铜封沿斜面相对挫动,上方铜封6-1向内膨胀压紧金属水管2,下方铜封6-2向外膨胀压紧岩石试样4的钻孔孔壁。 
所述的金属水管2为阶梯形的钢制铸件,金属水管2中部的第一个阶梯处加工有螺纹一2-1,金属水管2上部第二阶梯处设有螺纹二2-2,螺纹一2-1的外径等于金属水管2下部的水管外径,螺纹二2-2的外径等于金属水管2中部的水管外径;锁紧螺母3与金属水管2的金属水管中部螺纹2-1配套,封孔螺母1与金属水管顶部螺纹2-3的螺纹配套。 
使用时,首先在尺寸为的岩石试样4的端面中心,钻进直径25mm、深210mm的孔,将金属垫圈5放入孔中,再将金属水管2***孔中。将楔形密封紫铜圈6按顺序穿过金属水管2放入孔中,上面再放置金属垫圈5,使用工具按压金属垫圈5,使楔形密封紫铜圈6膨胀压紧金属水管2和岩石试样4孔壁。按以上方法依次装入第二、第三个楔形密封紫铜圈6,三个楔形密封紫铜圈6装完后,将锁紧螺母3和封孔螺母1旋紧于金属水管2面,并压住岩石试样4。实验时,把装有水密封装置的岩石试样4装入压力室,然后从 金属水管2的顶部开始注入高压水,高压水沿金属水管2渗入岩石试样4的裂隙中,随着温度的升高,楔形密封紫铜圈6和岩石试样4都产生膨胀,而楔形密封紫铜圈6的膨胀系数大于岩石试样4使得两者进一步贴紧。再经过金属水管2注入的高压水,水压从楔形密封紫铜圈6下方挤压下方铜封6-2,使其向上运动并与上方铜封6-1沿着斜面产生相对挫动。而在高温下,紫铜***更容易变形,从而使楔形密封紫铜圈6膨胀并起到封孔作用,从而使高压水集中作用于岩石试样4的裂隙,使岩石试样4破裂。 

Claims (5)

1.一种基于高温高压环境下岩石试样水压致裂实验的水密封装置,其特征在于:它包括开有一盲孔的岩石试样(4),岩石试样(4)的盲孔内插装有金属水管(2),盲孔内的金属水管(2)上间隔套装有多个金属垫圈(5)和楔形密封紫铜圈(6),多个金属垫圈(5)和楔形密封紫铜圈(6)之上设有与金属水管(2)相配合的锁紧螺母(3),金属水管(2)的外露端上设有封住岩石试样(4)孔口的封孔螺母(1)。
2.根据权利要求1所述的基于高温高压环境下岩石试样水压致裂实验的水密封装置,其特征在于:所述的楔形密封紫铜圈(6)包括楔形上方紫铜封(6-1)、可与上方紫铜封(6-1)契合在一起的楔形下方紫铜封(6-2)。
3.根据权利要求1所述的基于高温高压环境下岩石试样水压致裂实验的水密封装置,其特征在于:所述的金属垫圈(5)为圆柱环体,金属垫圈(5)的内环直径略大于金属水管(2)的外径,金属垫圈(5)的外环直径略小于岩石试样(4)的钻孔孔径。
4.根据权利要求1所述的基于高温高压环境下岩石试样水压致裂实验的水密封装置,其特征在于:所述的金属水管(2)为阶梯形的钢制铸件,金属水管(2)中部的第一个阶梯处加工有螺纹一(2-1),金属水管(2)上部第二阶梯处设有螺纹二(2-2),螺纹一(2-1)的外径等于金属水管(2)下部的水管外径,螺纹二(2-2)的外径等于金属水管(2)中部的水管外径;锁紧螺母(3)与金属水管(2)的金属水管中部螺纹(2-1)配套,封孔螺母(1)与金属水管顶部螺纹(2-3)的螺纹配套。
5.根据权利要求1所述的基于高温高压环境下岩石试样水压致裂实验的水密封装置,其特征在于:所述间隔套装的多个金属垫圈(5)和楔形密封紫铜圈(6)为2~4组。
CN201410610735.6A 2014-11-03 2014-11-03 基于高温高压条件下水压致裂实验的水密封装置 Active CN104374637B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410610735.6A CN104374637B (zh) 2014-11-03 2014-11-03 基于高温高压条件下水压致裂实验的水密封装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410610735.6A CN104374637B (zh) 2014-11-03 2014-11-03 基于高温高压条件下水压致裂实验的水密封装置

Publications (2)

Publication Number Publication Date
CN104374637A true CN104374637A (zh) 2015-02-25
CN104374637B CN104374637B (zh) 2017-01-11

Family

ID=52553685

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410610735.6A Active CN104374637B (zh) 2014-11-03 2014-11-03 基于高温高压条件下水压致裂实验的水密封装置

Country Status (1)

Country Link
CN (1) CN104374637B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109752249A (zh) * 2019-01-22 2019-05-14 北京交通大学 三轴泥水劈裂试验中试样与注浆底座的密封装置及密封方法
CN109870349A (zh) * 2019-03-29 2019-06-11 中国矿业大学 一种高温高压水压致裂夹持器及其试验方法
CN110501235A (zh) * 2019-09-24 2019-11-26 中国工程物理研究院化工材料研究所 一种基于液压致裂法的脆性材料拉伸强度测试***及方法
CN110514528A (zh) * 2019-09-24 2019-11-29 中国工程物理研究院化工材料研究所 一种***结构件拉伸强度分布情况的测试***及方法
CN113218773A (zh) * 2021-04-13 2021-08-06 赵雅清 一种水压致裂应力检测装置
WO2021202537A1 (en) * 2020-03-30 2021-10-07 Stratum Reservoir Intermediate, LLC System and device for analyzing fluid flow in unconventional hydraulically-fractured porous media
CN109870350B (zh) * 2019-03-29 2023-10-27 中国矿业大学 一种防漏液高温高压水压致裂***和试验方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63235863A (ja) * 1987-03-25 1988-09-30 Central Res Inst Of Electric Power Ind 水圧破砕による初期地圧計測方法
JPH0450636A (ja) * 1990-06-13 1992-02-19 Mitsubishi Materials Corp 岩石試料の高温高圧試験装置
CN201749062U (zh) * 2010-08-25 2011-02-16 安徽理工大学 一种高承压水作用的岩石裂隙破裂过程的试验装置
CN202330181U (zh) * 2011-12-06 2012-07-11 湖南科技大学 含裂纹类岩石材料水压致裂装置
CN103196762A (zh) * 2013-04-25 2013-07-10 重庆地质矿产研究院 一种脉冲水力压裂改造页岩气储层的实验装置及方法
CN204154571U (zh) * 2014-11-03 2015-02-11 中国矿业大学 基于高温高压条件下水压致裂实验的水密封装置

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63235863A (ja) * 1987-03-25 1988-09-30 Central Res Inst Of Electric Power Ind 水圧破砕による初期地圧計測方法
JPH0450636A (ja) * 1990-06-13 1992-02-19 Mitsubishi Materials Corp 岩石試料の高温高圧試験装置
CN201749062U (zh) * 2010-08-25 2011-02-16 安徽理工大学 一种高承压水作用的岩石裂隙破裂过程的试验装置
CN202330181U (zh) * 2011-12-06 2012-07-11 湖南科技大学 含裂纹类岩石材料水压致裂装置
CN103196762A (zh) * 2013-04-25 2013-07-10 重庆地质矿产研究院 一种脉冲水力压裂改造页岩气储层的实验装置及方法
CN204154571U (zh) * 2014-11-03 2015-02-11 中国矿业大学 基于高温高压条件下水压致裂实验的水密封装置

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109752249A (zh) * 2019-01-22 2019-05-14 北京交通大学 三轴泥水劈裂试验中试样与注浆底座的密封装置及密封方法
CN109752249B (zh) * 2019-01-22 2024-02-27 北京交通大学 三轴泥水劈裂试验中试样与注浆底座的密封装置及密封方法
CN109870349A (zh) * 2019-03-29 2019-06-11 中国矿业大学 一种高温高压水压致裂夹持器及其试验方法
CN109870349B (zh) * 2019-03-29 2023-10-27 中国矿业大学 一种高温高压水压致裂夹持器及其试验方法
CN109870350B (zh) * 2019-03-29 2023-10-27 中国矿业大学 一种防漏液高温高压水压致裂***和试验方法
CN110501235A (zh) * 2019-09-24 2019-11-26 中国工程物理研究院化工材料研究所 一种基于液压致裂法的脆性材料拉伸强度测试***及方法
CN110514528A (zh) * 2019-09-24 2019-11-29 中国工程物理研究院化工材料研究所 一种***结构件拉伸强度分布情况的测试***及方法
WO2021202537A1 (en) * 2020-03-30 2021-10-07 Stratum Reservoir Intermediate, LLC System and device for analyzing fluid flow in unconventional hydraulically-fractured porous media
US11287361B2 (en) 2020-03-30 2022-03-29 Stratum Reservoir Intermediate, LLC System and device for analyzing fluid flow in unconventional hydraulically-fractured porous media
US11913866B2 (en) 2020-03-30 2024-02-27 Stratum Reservoir Intermediate, LLC System and device for analyzing fluid flow in unconventional hydraulically-fractured porous media
CN113218773A (zh) * 2021-04-13 2021-08-06 赵雅清 一种水压致裂应力检测装置
CN113218773B (zh) * 2021-04-13 2024-06-18 天津成源化工设备有限公司 一种水压致裂应力检测装置

Also Published As

Publication number Publication date
CN104374637B (zh) 2017-01-11

Similar Documents

Publication Publication Date Title
CN104374637B (zh) 基于高温高压条件下水压致裂实验的水密封装置
CN108445193B (zh) 一种开挖应力下预制含裂纹岩体注浆试验***及使用方法
Yan et al. Shaft failure characteristics and the control effects of backfill body compression ratio at ultra-contiguous coal seams mining
CN204154571U (zh) 基于高温高压条件下水压致裂实验的水密封装置
CN109162755A (zh) 一种电脉冲与注浆加固相结合的石门揭煤方法
CN209011794U (zh) 一种设有增强密封性能结构的可溶桥塞
CN102071961A (zh) 一种下行瓦斯抽放钻孔和测压钻孔封孔方法
CN105484699A (zh) 压裂用免钻铣桥塞
Bu et al. A theoretical evaluation method for mechanical sealing integrity of cementing sheath
CN108256160B (zh) 一种热采工况特殊螺纹接头密封接触压应力的预测方法
CN106837420B (zh) 基于巷道围岩裂隙结构密闭煤矿采空区的装置和方法
CN112985982B (zh) 一种适用于真三轴加载的电法监测装置及其使用方法
CN207365759U (zh) 免固井中深层地热井内换热器
CN207159937U (zh) 一种混凝土防渗墙接头
Yu et al. Study on mining subsidence law of coal seam with thick overlying loess stratum
CN102182481B (zh) 锚索止浆塞
CN103670326B (zh) 裸眼封隔器
CN103541679B (zh) 煤矿井下水力压裂钻孔组合式封孔方法
CN107642343A (zh) 一种油气井冷冻桥塞带压更换阀门施工工艺
WO2021093122A1 (zh) 一种减少采煤工作面回采末期回撤通道顶板压力的方法
CN104088615A (zh) 一种套管固井分段压裂控制阀
CN204002744U (zh) 一种套管固井分段压裂控制阀
CN205135579U (zh) 水平井外套式复合射孔用锁紧降阻扶正装置
CN102926766A (zh) 一种能够壁后充填的u型棚
CN218953291U (zh) 一种顺煤层钻孔安装的固液复合型水力压裂增透管结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 221116 Research Institute of China University of Mining and Technology,, Jiangsu

Applicant after: China University of Mining & Technology

Address before: 221116 Research Institute, China University of Mining and Technology, Xuzhou University, Jiangsu, China,

Applicant before: China University of Mining & Technology

COR Change of bibliographic data
GR01 Patent grant
GR01 Patent grant