CN104358257A - Reinforced connection method for PHC (prestress high concrete) tubular pile - Google Patents

Reinforced connection method for PHC (prestress high concrete) tubular pile Download PDF

Info

Publication number
CN104358257A
CN104358257A CN201410638919.3A CN201410638919A CN104358257A CN 104358257 A CN104358257 A CN 104358257A CN 201410638919 A CN201410638919 A CN 201410638919A CN 104358257 A CN104358257 A CN 104358257A
Authority
CN
China
Prior art keywords
pile
phc
skirt
tubular pile
skirtboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410638919.3A
Other languages
Chinese (zh)
Inventor
同小敏
盛健
李华梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shipbuilding NDRI Engineering Co Ltd
Original Assignee
China Shipbuilding NDRI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shipbuilding NDRI Engineering Co Ltd filed Critical China Shipbuilding NDRI Engineering Co Ltd
Priority to CN201410638919.3A priority Critical patent/CN104358257A/en
Publication of CN104358257A publication Critical patent/CN104358257A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • E02D2250/0069Welding

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a reinforced connection method for a PHC (prestress high concrete) tubular pile. Connectors at the two ends of the PHC tubular pile are involved, wherein each connector consists of an end plate and a skirt piece; when the pile is connected, the two end plates are connected in a peripheral welding way. The method is characterized in that skirt boards are arranged in the skirt pieces in a sleeving way when the tubular pile is prefabricated, and are connected in a spot welding way, wherein the skirt board pieces outside the skirt boards are cut when the pile is connected; a plurality of cambered ribbed plates are welded outside the two skirt boards after the two end plates are connected in the peripheral welding way; the upper and lower connectors are integrally welded by virtue of the ribbed plates, so that the connection strength of the PHC tubular pile is strengthened. Compared with the prior art, the reinforced connection method has the advantages that high pulling resistance and high bending resistance are achieved, the connected PHC tubular pile can bear vertical force as well as horizontal force on the premise of meeting the pile manufacturing process requirement of preventing film clamping and mud leakage, the connection strength of the pile is strengthened, and a manufacturing process is simple, high in construction speed and overall structural performance and particularly suitable for the PHC tubular pile construction of inshore water transportation engineering.

Description

A kind of method that reinforces the connection of PHC pile tube
Technical field
The present invention relates to making and the technical field of construction of pile tube, specifically a kind of method that reinforces the connection for long piled wharf PHC pile tube.
Background technology
At present, long piled wharf engineering pile foundation all adopts marine piling ship to construct, and PHC pile tube adopts barge water transportation, and single-unit pile tube pile sinking length is maximum reaches nearly hundred meters, does not generally need to carry out pile extension, is conducive to guaranteeing pile foundation construction quality.But be substantially in land and water boundary, location, river levee shoal for offshore marine traffic engineering, part engineering ground is narrow again, according to floating piling scheme after heavy excavation, then difficulty is comparatively large, and soil excavation engineering quantity is large, exhausts the people and drains the treasury, unreasonable economically.Form land-based area according to backfill to construct PHC pile tube, then land pile sinking single-unit pile tube length is generally not more than 20m, need arrange 2 ~ 4 joints again.Because water body has corrosiveness to pipe pile joint, add tide bulge and fall, affect project durability, marine traffic engineering (particularly waters part) is extremely tight to PHC pipe pile joint quantity, quality control on construction, therefore suitably must reinforce this part pipe pile joint, to meet workmanship and life requirement.
The connector that PHC pile tube uses generally is made up of flange and skirt sheet; flange is arranged on the two ends of PHC pile tube; connect upper and lower pipe joint stake only the flange of connector end to be carried out welding the vertical applied force that can ensure pile tube; and the skirt sheet being arranged on pile tube two ends for preventing snap gauge or spillage in prefabricated PHC pile tube process; its thickness only has 2mm thick, and the connection be not used as between PHC pile tube is stressed.
The PHC pile tube of prior art connects, after pile extension the resistance to plucking of pile tube entirety and bending resistance poor, can not horizontal force be born, the requirement of structure stress cannot be met.
Summary of the invention
The object of the invention is a kind of method that reinforces the connection that PHC pile tube is provided for the deficiencies in the prior art, adopt the joint prefabricated tubular pile being provided with skirtboard, outside joint, weld several piece arc after cutting off skirt sheet during pile extension add powerful plate, not only meet and prevent card film, the stake technological requirement processed of spillage, and enhance resistance to plucking and the bending resistance of pile tube entirety after pile extension, cost of manufacture is low, be easy to promotion and implementation, improve the bonding strength between stake and stake, make the PHC pile tube after connecting can bear vertical vertical force and can bear horizontal force again, especially the PHC tube pile construction of offshore marine traffic engineering is applicable to.
The object of the present invention is achieved like this: a kind of method that reinforces the connection of PHC pile tube, comprise the connector being arranged on PHC pile tube two ends, connector is made up of end plate and skirt sheet, upper and lower two PHC pile tubes are connected by two end plates weld all around during pile extension, in skirt sheet, skirtboard is set with when being characterized in that PHC pile tube is prefabricated, skirtboard and skirt sheet are that spot welding is connected, during pile extension, the some skirt sheet be welded in outside skirtboard is cut off, two end plates weld all around adds powerful plate at two skirtboard external welding several piece arcs after connecting, add powerful plate upper and lower two connectors are welded as a whole, to increase PHC pile tube bonding strength; Described end plate and skirtboard and the reinforcement welding be arranged in PHC pile tube; Described skirtboard is be sleeved on the pipeline section in skirt sheet, its thickness G reatT.GreaT.GT5 mm; Described skirt sheet thickness≤2 mm.
The present invention compared with prior art has good resistance to plucking and bending resistance, meeting under the stake technological requirement processed preventing card film, spillage, make the PHC pile tube after pile extension can bear vertical vertical force and can bear horizontal force again, cost of manufacture is low, be easy to promotion and implementation, improve the bonding strength between stake and stake, manufacture craft is simple, speed of application is fast, overall structure is good, is especially applicable to the PHC tube pile construction of offshore marine traffic engineering.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the invention process illustration;
Fig. 3 is Fig. 2 top view.
Detailed description of the invention
Accompanying drawings 1, the present invention includes the connector 2 being arranged on PHC pile tube 1 two ends, and connector 2 is made up of end plate 3, skirt sheet 4 and skirtboard 5; Described skirtboard 5 is for being sleeved on pipeline section in skirt sheet 4 and with skirt sheet 4 for spot welding is connected; Described end plate 3 and skirtboard 5 and the reinforcement welding be arranged in PHC pile tube 1.
By following specific embodiment, the present invention is described in further detail.
Embodiment 1
Accompanying drawings 2 ~ accompanying drawing 3, the present invention makes like this and is connected: PHC pile tube 1(AB type) adopt φ 800 mm, skirtboard 5 thickness of its two ends connector 2 is 8mm, and height is that 250mm(is consistent with the height of skirt sheet 4); End plate 3 adopts φ 800 mm X15mm(thick); Skirt sheet 4 adopts 2mm(thick) X 250mm(is high), the snap gauge when setting of skirt sheet 4 is mainly for avoiding pile tube prefabricated and leakage.When PHC pile tube 1 is prefabricated, skirtboard 5 is sleeved in skirt sheet 4, skirtboard 5 with skirt sheet 4 for spot welding is connected, end plate 3 and skirtboard 5 and the reinforcement welding be arranged in PHC pile tube 1.
After completing stake processed, PHC pile tube 1 is transported to job site and carries out pile extension, the point skirt sheet 4 be welded in outside skirtboard 5 is cut off, two end plates 3 weld all around adds powerful plate 6 at two skirtboard 5 external weldings, four pieces of arcs after connecting, adding powerful plate 6 adopts 431.6mm(wide) X 350mm(is high) X 12mm(is thick), the connector 2 of upper and lower two PHC pile tubes 1 is welded as a whole.The present invention is after the weld all around pile extension of two end plates 3, add the pile tube connection adding powerful plate 6 in skirtboard 5 external welding, improve the bonding strength between stake and stake, make the upper and lower two PHC pile tubes 1 after pile extension can bear vertical vertical force and can bear horizontal force again, improve overall pulling test and the bending resistance of pile tube.
Just the invention will be further described for above embodiment, and be not used to limit patent of the present invention, allly implements for the present invention's equivalence, within the right that all should be contained in patent of the present invention.

Claims (1)

1. the method that reinforces the connection of a PHC pile tube, comprise the connector being arranged on PHC pile tube two ends, connector is made up of end plate and skirt sheet, upper and lower two PHC pile tubes are connected by two end plates weld all around during pile extension, in skirt sheet, skirtboard is set with when it is characterized in that PHC pile tube is prefabricated, skirtboard and skirt sheet are that spot welding is connected, during pile extension, the some skirt sheet be welded in outside skirtboard is cut off, two end plates weld all around adds powerful plate at two skirtboard external welding several piece arcs after connecting, add powerful plate upper and lower two connectors are welded as a whole, to increase the bonding strength of PHC pile tube; Described end plate and skirtboard and the reinforcement welding be arranged in PHC pile tube; Described skirtboard is be sleeved on the pipeline section in skirt sheet, its thickness G reatT.GreaT.GT5 mm; Described skirt sheet thickness≤2 mm.
CN201410638919.3A 2014-11-13 2014-11-13 Reinforced connection method for PHC (prestress high concrete) tubular pile Pending CN104358257A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410638919.3A CN104358257A (en) 2014-11-13 2014-11-13 Reinforced connection method for PHC (prestress high concrete) tubular pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410638919.3A CN104358257A (en) 2014-11-13 2014-11-13 Reinforced connection method for PHC (prestress high concrete) tubular pile

Publications (1)

Publication Number Publication Date
CN104358257A true CN104358257A (en) 2015-02-18

Family

ID=52525556

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410638919.3A Pending CN104358257A (en) 2014-11-13 2014-11-13 Reinforced connection method for PHC (prestress high concrete) tubular pile

Country Status (1)

Country Link
CN (1) CN104358257A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105735308A (en) * 2016-02-26 2016-07-06 广东工业大学 Prestressed pipe pile

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201367578Y (en) * 2009-01-22 2009-12-23 国鼎(南通)管桩有限公司 Large-bending-moment combined pile
CN201598635U (en) * 2009-12-16 2010-10-06 江苏建华管桩有限公司 Concrete tubular pile with high stress
CN202787248U (en) * 2012-09-21 2013-03-13 天津港航桩业有限公司 Hoop type mechanical quick connector for prestress concrete pipe piles
CN202850015U (en) * 2012-10-16 2013-04-03 温岭市呈隆管桩有限公司 Novel energy-saving thin-wall tubular pile
CN103184735A (en) * 2013-03-27 2013-07-03 上海中技桩业股份有限公司 Connection structure of prestressed reinforced concrete hollow square pile
CN203113318U (en) * 2013-02-04 2013-08-07 上海汤始建华管桩有限公司 Tubular pipe with welding of skirtboard and end board unnecessary
KR20130117604A (en) * 2012-04-18 2013-10-28 주식회사 파일텍씨앤이 Reinforcement device for foundation of steel pipe pile and construction method for foundation using the same
CN203373739U (en) * 2013-05-30 2014-01-01 上海大禺预制构件有限公司 Prestress centrifugal corrosion resistant hollow square pile

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201367578Y (en) * 2009-01-22 2009-12-23 国鼎(南通)管桩有限公司 Large-bending-moment combined pile
CN201598635U (en) * 2009-12-16 2010-10-06 江苏建华管桩有限公司 Concrete tubular pile with high stress
KR20130117604A (en) * 2012-04-18 2013-10-28 주식회사 파일텍씨앤이 Reinforcement device for foundation of steel pipe pile and construction method for foundation using the same
CN202787248U (en) * 2012-09-21 2013-03-13 天津港航桩业有限公司 Hoop type mechanical quick connector for prestress concrete pipe piles
CN202850015U (en) * 2012-10-16 2013-04-03 温岭市呈隆管桩有限公司 Novel energy-saving thin-wall tubular pile
CN203113318U (en) * 2013-02-04 2013-08-07 上海汤始建华管桩有限公司 Tubular pipe with welding of skirtboard and end board unnecessary
CN103184735A (en) * 2013-03-27 2013-07-03 上海中技桩业股份有限公司 Connection structure of prestressed reinforced concrete hollow square pile
CN203373739U (en) * 2013-05-30 2014-01-01 上海大禺预制构件有限公司 Prestress centrifugal corrosion resistant hollow square pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105735308A (en) * 2016-02-26 2016-07-06 广东工业大学 Prestressed pipe pile

Similar Documents

Publication Publication Date Title
CN108035337B (en) The construction method of a kind of diaphram wall and applied to the connector in this method
CN105156131A (en) Composite pipe joint structure of rectangular jacking pipe
CN112195962A (en) Offshore electric platform pile-sleeve foundation structure with anti-sinking box structure
CN202227332U (en) Hole guiding steel sheet pile
CN207775909U (en) A kind of cofferdam with combination shaped steel plate pile
CN103485356B (en) Overwater laying frame and method for filling sand pockets with same
CN103276752A (en) Construction method of underground continuous wall expansive concrete joint
CN104358257A (en) Reinforced connection method for PHC (prestress high concrete) tubular pile
CN208105923U (en) A kind of existing pond increases the connecting joint structure of water string
CN204199276U (en) A kind of PHC pile tube of reinforcement type joint
CN102619214A (en) U-shaped interface steel sheet pile and application thereof in enclosure for foundation pit
CN205501988U (en) Stake of binocular shape hasp
CN202117049U (en) Latch type steel pipe pile
CN204489133U (en) For the floating box device of the large-scale single pipe pile foundation construction in shallow sea
CN201424121Y (en) Double-crane piling boat for construction of offshore artificial island
CN107940102A (en) Underground raw water pipe protection construction method
CN204510256U (en) The steel cylinder-shaped foundation structure of offshore wind turbine
CN211171956U (en) Anchor rod pile feeder
CN207092133U (en) One kind welding shaped steel shear connector structure
CN207934019U (en) A kind of steel reinforcement cage of the diaphram wall with grouting device
JP3871937B2 (en) Construction method for underwater frame structures
CN207211168U (en) A kind of separable pier formula cofferdam
CN201006999Y (en) Shallow sea reducing internally ribbing independence support pile
CN205399376U (en) Simple and easy wellhead platform
CN213805510U (en) Anti structure of floating that underground continuous wall and roof combine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150218