- CN104348100A CN104348100A CN201410661792.7A CN201410661792A CN104348100A CN 104348100 A CN104348100 A CN 104348100A CN 201410661792 A CN201410661792 A CN 201410661792A CN 104348100 A CN104348100 A CN 104348100A
- Authority
- CN
- China
- Prior art keywords
- steel
- channel
- horizontal longitudinal
- section steel
- power transformation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02B—BOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
- H02B3/00—Apparatus specially adapted for the manufacture, assembly, or maintenance of boards or switchgear
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Power Engineering (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The invention relates to a substation maintenance platform with multiple installation modes and an installation method thereof. The substation maintenance platform comprises a stand platform, a guardrail, a base, a locking device, two clamping connecting rods and fasteners; horizontal longitudinal connecting rods are respectively arranged at two sides of the bottom part of the base; the two clamping connecting rods are respectively and correspondingly arranged at the lower sides of the horizontal longitudinal connecting rods; at least two through holes are formed in each horizontal longitudinal connecting rod and at least two through holes are formed in each clamping connecting rod, and each horizontal longitudinal connecting rod and the corresponding clamping connecting rod are connected through the fasteners so as to clamp a non-channel steel and joist steel-class steel structure when a to-be-installed object is of the non-channel steel and joist steel-class steel structure; the locking device is straddled between the two horizontal longitudinal connecting rods, and the upper sides and the lower sides of the horizontal longitudinal connecting rods are respectively clamped by the upper part and the lower part of the locking device; a longitudinal bayonet is formed in the locking device so as to clamp the upper edge of a channel steel and joist steel-class steel structure when a to-be-installed object is of the channel steel and joist steel-class steel structure and to enable the substation maintenance platform to be fixedly arranged on the channel steel and joist steel-class steel structure. The substation maintenance platform and the installation method thereof are strong in adaptability, easy to assemble and disassemble and regulate, and are simple and fast to use.
Description
Technical field
The present invention relates to substation equipment maintenance and repair technical field, particularly a kind of power transformation overhaul platform and installation method thereof being applied to many mounting meanss of substation equipment maintenance and repair operation.
Background technology
The hitch point of safety belt is only provided by use Anti-dropping rack when carrying out substation equipment maintenance and repair high-rise working both at home and abroad, the locking device nargin of the Anti-dropping rack of current use is less, only be suitable for single frame size, substation equipment maintenance and repair, unit in charge of construction have to prepare the Anti-dropping rack of various model, management, use very inconvenience.
Summary of the invention
The object of the present invention is to provide a kind of power transformation overhaul platform and installation method thereof of many mounting meanss, this platform and installation method strong adaptability thereof, be easy to handling, regulate, use simple and fast.
For achieving the above object, technical scheme of the present invention is: a kind of power transformation overhaul platform of many mounting meanss, comprise standing platform, be located at the guardrail on standing platform and the base being located at standing platform lower end, also comprise locking device, clamping connecting rod and securing member, the left and right sides of described base bottom is respectively equipped with horizontal longitudinal rod, clamping connecting rod correspondence described in two is located on the downside of described horizontal longitudinal rod, described horizontal longitudinal rod and described clamping connecting rod offer the through hole being no less than two respectively, and be connected through described securing member, being non-channel-section steel at mounting object, described non-channel-section steel is clamped during I-steel class steel construction, I-steel class steel construction, described locking device is located between described two horizontal longitudinal rods, and its upper and lower part clamps the upper and lower side of horizontal longitudinal rod respectively, described locking device offers longitudinal bayonet socket, with be channel-section steel at mounting object, I-steel class steel construction time block edge on described channel-section steel, I-steel class steel construction, power transformation overhaul platform is fixed on described channel-section steel, I-steel class steel construction.
Further, described securing member is threaded fastener, be made up of stay bolt and locking nut, when described horizontal longitudinal rod and described clamping connecting rod clamp described non-channel-section steel, I-steel class steel construction respectively from upper and lower both sides, through described stay bolt and locking nut locking described non-channel-section steel, I-steel class steel construction, power transformation overhaul platform is fixed on described non-channel-section steel, I-steel class steel construction.
Further, the through hole be opened on described horizontal longitudinal rod and described clamping connecting rod is the strip through hole longitudinally with preseting length, with the locked position of the width adjustment securing member according to described non-channel-section steel, I-steel class steel construction.
Further, described locking device comprises upside fixture block, clamping screw and the cross struts under being located at described upside fixture block, described upside fixture block length is greater than the spacing between described two horizontal longitudinal rods, to clamp the upside of described horizontal longitudinal rod downwards, described cross struts is left, right both sides are connected to a vertical connecting plate, distance between described two vertical connecting plates and the spacing between described two horizontal longitudinal rods adapt, to block described two horizontal longitudinal rods to both sides, described vertical connecting plate is connected with horizontal clamping plate laterally, upwards to clamp the downside of described horizontal longitudinal rod, vertical through holes is offered in the middle part of the fixture block of described upside, vertical screwed hole is offered in the middle part of described cross struts, described clamping screw runs through described vertical through holes and is connected with described vertical screwed hole, the upper of described horizontal longitudinal rod is clamped to make described upside fixture block and described horizontal clamping plate, downside, described longitudinal bayonet socket is opened on front side of described vertical connecting plate, to block forward edge on described channel-section steel, I-steel class steel construction.
Further, described standing platform is provided with vertical supports, and described guardrail is located in described vertical supports, described vertical supports is also provided with for detaining the hook establishing safety belt.
The invention also discloses a kind of installation method of the power transformation overhaul platform of above-mentioned many mounting meanss, when mounting object is non-channel-section steel, I-steel class steel construction, described power transformation overhaul platform be installed as follows:
101) base of described power transformation overhaul platform is placed on described non-channel-section steel, I-steel class steel construction, makes the horizontal longitudinal rod of the base left and right sides touch the upper side of described non-channel-section steel, I-steel class steel construction;
102) under described two clamping connecting rods being placed in described non-channel-section steel, I-steel class steel construction, and its correspondence is made to be positioned at the positive downside of described two horizontal longitudinal rods;
103) described securing member is adopted by described horizontal longitudinal rod together with described clamping connecting bar locking, with described non-channel-section steel, the I-steel class steel construction of clamping between described horizontal longitudinal rod and described clamping connecting rod, thus described power transformation overhaul platform is fixed on described non-channel-section steel, I-steel class steel construction.
The invention also discloses the another kind of installation method of the power transformation overhaul platform of above-mentioned many mounting meanss, when mounting object is channel-section steel, I-steel class steel construction, described power transformation overhaul platform be installed as follows:
201) base of described power transformation overhaul platform is placed on described channel-section steel, I-steel class steel construction, makes the horizontal longitudinal rod of the base left and right sides touch edge on described channel-section steel, I-steel class steel construction;
202) described locking device is inserted between described two flat longitudinal rods, described two vertical connecting plates are made to block described two horizontal longitudinal rods to both sides, the downside of described horizontal longitudinal rod upwards clamped by the horizontal clamping plate be then connected to outside described vertical connecting plate, then adjust the orientation of described upside fixture block, make it clamp the upside of described horizontal longitudinal rod downwards;
203) locking device described in driven forward, makes its longitudinal bayonet socket block edge on described channel-section steel, I-steel class steel construction;
204) described clamping screw is adopted to run through the vertical through holes of described upside fixture block and be connected with the vertical screwed hole of described cross struts, described locking device is fixed on described horizontal longitudinal rod, make described locking device keep blocking the state of described channel-section steel, I-steel class steel construction, thus described power transformation overhaul platform is fixed on described channel-section steel, I-steel class steel construction.
The invention has the beneficial effects as follows:
1, the present invention can be installed on various different non-channel-section steel, I-steel class steel construction, and regulates according to the difference of framework height, width.
2, the present invention can carry out very efficiently locking and fixing on channel-section steel, I-steel class steel construction, and is easy to regulate, dismantle, and installs adjustment for installation channel-section steel different directions.
3, strong adaptability of the present invention, can meet the mounting condition of Overhaul site in most transformer station, the needs of maintainer's anti-height pendant when meeting upkeep operation on-the-spot high-rise working.
Accompanying drawing explanation
Fig. 1 is the structural representation of the power transformation overhaul platform (during removal locking device) of the embodiment of the present invention.
Fig. 2 is the structural representation of locking device in the embodiment of the present invention.
Fig. 3 is the end view of locking device in the embodiment of the present invention.
In figure, 1-standing platform, 2-guardrail, 3-base, 4-locking device, fixture block on the upside of 401-, 402-clamping screw, 403-cross struts, the vertical connecting plate of 404-, the horizontal clamping plate of 405-, 406-vertical through holes, the vertical screwed hole of 407-, the longitudinal bayonet socket of 408-, 5-clamps connecting rod, the horizontal longitudinal rod of 6-, 7-through hole, 8-stay bolt, 9-locking nut, 10-vertical supports, 11-links up with.
Embodiment
Below in conjunction with drawings and the specific embodiments, the present invention is described in further detail.
The power transformation overhaul platform of the many mounting meanss of the present invention, as shown in Figure 1, comprise standing platform 1, be located at the guardrail 2 on standing platform 1, be located at the base 3 of standing platform 1 lower end, locking device 4, clamping connecting rod 5 and securing member, the left and right sides bottom base 3 is respectively equipped with horizontal longitudinal rod 6, two clamping connecting rod 5 correspondences are located on the downside of horizontal longitudinal rod 6, horizontal longitudinal rod 6 and clamping connecting rod 5 offer the through hole 7 being no less than two respectively, and be connected through securing member, being non-channel-section steel at mounting object, non-channel-section steel is clamped during I-steel class steel construction, I-steel class steel construction, locking device 4 is located between two horizontal longitudinal rods 6, and its upper and lower part clamps the upper and lower side of horizontal longitudinal rod 6 respectively, locking device 4 offers longitudinal bayonet socket 408, with be channel-section steel at mounting object, I-steel class steel construction time block edge on channel-section steel, I-steel class steel construction, power transformation overhaul platform is fixed on channel-section steel, I-steel class steel construction.
In the present embodiment, securing member is threaded fastener, be made up of stay bolt 8 and locking nut 9, when horizontal longitudinal rod 6 and clamping connecting rod 5 clamp non-channel-section steel, I-steel class steel construction respectively from upper and lower both sides, lock non-channel-section steel, I-steel class steel construction through stay bolt 8 and locking nut 9, power transformation overhaul platform is fixed on non-channel-section steel, I-steel class steel construction.The through hole 7 be opened on horizontal longitudinal rod 6 and clamping connecting rod 5 is the strip through hole longitudinally with preseting length, with the locked position of the width adjustment securing member according to non-channel-section steel, I-steel class steel construction.
As Fig. 2, shown in 3, locking device 4 comprises upside fixture block 401, clamping screw 402 and the cross struts 403 under being located at upside fixture block 401, upside fixture block 401 length is greater than the spacing between two horizontal longitudinal rods 6, to clamp the upside of horizontal longitudinal rod 6 downwards, cross struts 403 is left, right both sides are connected to a vertical connecting plate 404, distance between two vertical connecting plates 404 and the spacing between two horizontal longitudinal rods 6 adapt, to block two horizontal longitudinal rods 6 to both sides, vertical connecting plate 404 is connected with horizontal clamping plate 405 laterally, upwards to clamp the downside of horizontal longitudinal rod 6, vertical through holes 406 is offered in the middle part of the fixture block 401 of upside, vertical screwed hole 407 is offered in the middle part of cross struts 403, clamping screw 402 runs through vertical through holes 406 and is connected with vertical screwed hole 407, to make upside fixture block 401 and the horizontal longitudinal rod of horizontal clamping plate 405 clamping 6 upper, downside, longitudinal bayonet socket 408 is opened on front side of vertical connecting plate 404, to block forward edge on channel-section steel, I-steel class steel construction.
Standing platform 1 is provided with vertical supports 10, and guardrail 2 is located in vertical supports 10, vertical supports 10 is also provided with for detaining the hook 11 establishing safety belt.During maintenance, maintainer stands on standing platform 1, and uses guardrail 2 to protect maintainer, the risk prevent personnel from toppling over from eminence, dropping.Also can by buckle of safety belt on hook 11 during high-rise working.
The power transformation overhaul platform of the many mounting meanss of the present invention, when mounting object is non-channel-section steel, I-steel class steel construction, its installation method carries out as follows:
101) base 3 of power transformation overhaul platform is placed on non-channel-section steel, I-steel class steel construction, makes the horizontal longitudinal rod 6 of base 3 left and right sides touch the upper side of non-channel-section steel, I-steel class steel construction;
102) under two clamping connecting rods 5 being placed in non-channel-section steel, I-steel class steel construction, and its correspondence is made to be positioned at the positive downside of two horizontal longitudinal rods 6;
103) securing member is adopted horizontal longitudinal rod 6 and clamping connecting rod 5 to be locked together, namely stay bolt 8 is adopted to run through the through hole clamped on connecting rod 5 and horizontal longitudinal rod 6, and lock through locking nut 9, with non-channel-section steel, the I-steel class steel construction of clamping between horizontal longitudinal rod 6 and clamping connecting rod 5, thus power transformation overhaul platform is fixed on non-channel-section steel, I-steel class steel construction.
The power transformation overhaul platform of the many mounting meanss of the present invention, when mounting object is channel-section steel, I-steel class steel construction, its installation method carries out as follows:
201) base 3 of power transformation overhaul platform is placed on channel-section steel, I-steel class steel construction, makes the horizontal longitudinal rod 6 of base 3 left and right sides touch edge on channel-section steel, I-steel class steel construction;
202) locking device 4 is inserted between two flat longitudinal rods 6, two vertical connecting plates 404 are made to block two horizontal longitudinal rods 6 to both sides, the downside of horizontal longitudinal rod 6 upwards clamped by the horizontal clamping plate 405 be then connected to outside vertical connecting plate 404, then the orientation of adjustment upside fixture block 401, makes it clamp the upside of horizontal longitudinal rod 6 downwards;
203) driven forward locking device 4, makes its longitudinal bayonet socket 408 block edge on channel-section steel, I-steel class steel construction;
204) clamping screw 402 is adopted to run through the vertical through holes 406 of upside fixture block 401 and be connected with the vertical screwed hole 407 of cross struts 403, locking device 4 is fixed on horizontal longitudinal rod 6, make locking device 4 keep blocking the state of channel-section steel, I-steel class steel construction, thus power transformation overhaul platform is fixed on channel-section steel, I-steel class steel construction.
Be more than preferred embodiment of the present invention, all changes done according to technical solution of the present invention, when the function produced does not exceed the scope of technical solution of the present invention, all belong to protection scope of the present invention.
Claims (7)
1. the power transformation overhaul platform of mounting means more than a kind, comprise standing platform, be located at the guardrail on standing platform and the base being located at standing platform lower end, it is characterized in that, also comprise locking device, clamping connecting rod and securing member, the left and right sides of described base bottom is respectively equipped with horizontal longitudinal rod, clamping connecting rod correspondence described in two is located on the downside of described horizontal longitudinal rod, described horizontal longitudinal rod and described clamping connecting rod offer the through hole being no less than two respectively, and be connected through described securing member, being non-channel-section steel at mounting object, described non-channel-section steel is clamped during I-steel class steel construction, I-steel class steel construction, described locking device is located between described two horizontal longitudinal rods, and its upper and lower part clamps the upper and lower side of horizontal longitudinal rod respectively, described locking device offers longitudinal bayonet socket, with be channel-section steel at mounting object, I-steel class steel construction time block edge on described channel-section steel, I-steel class steel construction, power transformation overhaul platform is fixed on described channel-section steel, I-steel class steel construction.
2. the power transformation overhaul platform of a kind of many mounting meanss according to claim 1, it is characterized in that, described securing member is threaded fastener, be made up of stay bolt and locking nut, when described horizontal longitudinal rod and described clamping connecting rod clamp described non-channel-section steel, I-steel class steel construction respectively from upper and lower both sides, through described stay bolt and locking nut locking described non-channel-section steel, I-steel class steel construction, power transformation overhaul platform is fixed on described non-channel-section steel, I-steel class steel construction.
3. the power transformation overhaul platform of a kind of many mounting meanss according to claim 1, it is characterized in that, the through hole be opened on described horizontal longitudinal rod and described clamping connecting rod is the strip through hole longitudinally with preseting length, with the locked position of the width adjustment securing member according to described non-channel-section steel, I-steel class steel construction.
4. the power transformation overhaul platform of a kind of many mounting meanss according to claim 1, it is characterized in that, described locking device comprises upside fixture block, clamping screw and the cross struts under being located at described upside fixture block, described upside fixture block length is greater than the spacing between described two horizontal longitudinal rods, to clamp the upside of described horizontal longitudinal rod downwards, described cross struts is left, right both sides are connected to a vertical connecting plate, distance between described two vertical connecting plates and the spacing between described two horizontal longitudinal rods adapt, to block described two horizontal longitudinal rods to both sides, described vertical connecting plate is connected with horizontal clamping plate laterally, upwards to clamp the downside of described horizontal longitudinal rod, vertical through holes is offered in the middle part of the fixture block of described upside, vertical screwed hole is offered in the middle part of described cross struts, described clamping screw runs through described vertical through holes and is connected with described vertical screwed hole, the upper of described horizontal longitudinal rod is clamped to make described upside fixture block and described horizontal clamping plate, downside, described longitudinal bayonet socket is opened on front side of described vertical connecting plate, to block forward edge on described channel-section steel, I-steel class steel construction.
5. the power transformation overhaul platform of a kind of many mounting meanss according to claim 1, it is characterized in that, described standing platform is provided with vertical supports, and described guardrail is located in described vertical supports, described vertical supports is also provided with for detaining the hook establishing safety belt.
6. the installation method of the power transformation overhaul platform of a kind of many mounting meanss according to claim 1,2,3 or 5, is characterized in that, when mounting object is non-channel-section steel, I-steel class steel construction, installs described power transformation overhaul platform as follows:
101) base of described power transformation overhaul platform is placed on described non-channel-section steel, I-steel class steel construction, makes the horizontal longitudinal rod of the base left and right sides touch the upper side of described non-channel-section steel, I-steel class steel construction;
102) under described two clamping connecting rods being placed in described non-channel-section steel, I-steel class steel construction, and its correspondence is made to be positioned at the positive downside of described two horizontal longitudinal rods;
103) described securing member is adopted by described horizontal longitudinal rod together with described clamping connecting bar locking, with described non-channel-section steel, the I-steel class steel construction of clamping between described horizontal longitudinal rod and described clamping connecting rod, thus described power transformation overhaul platform is fixed on described non-channel-section steel, I-steel class steel construction.
7. the installation method of the power transformation overhaul platform of a kind of many mounting meanss according to claim 4, is characterized in that, when mounting object is channel-section steel, I-steel class steel construction, installs described power transformation overhaul platform as follows:
201) base of described power transformation overhaul platform is placed on described channel-section steel, I-steel class steel construction, makes the horizontal longitudinal rod of the base left and right sides touch edge on described channel-section steel, I-steel class steel construction;
202) described locking device is inserted between described two flat longitudinal rods, described two vertical connecting plates are made to block described two horizontal longitudinal rods to both sides, the downside of described horizontal longitudinal rod upwards clamped by the horizontal clamping plate be then connected to outside described vertical connecting plate, then adjust the orientation of described upside fixture block, make it clamp the upside of described horizontal longitudinal rod downwards;
203) locking device described in driven forward, makes its longitudinal bayonet socket block edge on described channel-section steel, I-steel class steel construction;
204) described clamping screw is adopted to run through the vertical through holes of described upside fixture block and be connected with the vertical screwed hole of described cross struts, described locking device is fixed on described horizontal longitudinal rod, make described locking device keep blocking the state of described channel-section steel, I-steel class steel construction, thus described power transformation overhaul platform is fixed on described channel-section steel, I-steel class steel construction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410661792.7A CN104348100B (en) | 2014-11-19 | 2014-11-19 | Substation maintenance platform with multiple installation modes and installation method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410661792.7A CN104348100B (en) | 2014-11-19 | 2014-11-19 | Substation maintenance platform with multiple installation modes and installation method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104348100A true CN104348100A (en) | 2015-02-11 |
CN104348100B CN104348100B (en) | 2017-02-01 |
Family
ID=52503161
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410661792.7A Active CN104348100B (en) | 2014-11-19 | 2014-11-19 | Substation maintenance platform with multiple installation modes and installation method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104348100B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105261983A (en) * | 2015-11-18 | 2016-01-20 | 国家电网公司 | Mutual inductor overhaul platform |
CN109926987A (en) * | 2019-04-17 | 2019-06-25 | 北京铠钺防护科技有限公司 | A kind of driving maintenance aid |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101694925A (en) * | 2009-09-28 | 2010-04-14 | 江苏省电力公司宜兴市供电公司 | Maintenance platform |
CN201554218U (en) * | 2009-09-11 | 2010-08-18 | 宁波电业局 | Common inspection platform |
DE102009049869A1 (en) * | 2009-10-20 | 2011-04-28 | Hymer-Leichtmetallbau Gmbh & Co. Kg | Ladder scaffold for use in e.g. building site, has working platform connected with guide bars, which are displaced by displacement guide at longitudinal bars of ladder, and hooks fastened to guide bars |
CN202004347U (en) * | 2011-03-17 | 2011-10-05 | 邢台供电公司 | Overhauling working platform |
CN204144756U (en) * | 2014-11-19 | 2015-02-04 | 国家电网公司 | A kind of power transformation overhaul platform of many mounting meanss |
-
2014
- 2014-11-19 CN CN201410661792.7A patent/CN104348100B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201554218U (en) * | 2009-09-11 | 2010-08-18 | 宁波电业局 | Common inspection platform |
CN101694925A (en) * | 2009-09-28 | 2010-04-14 | 江苏省电力公司宜兴市供电公司 | Maintenance platform |
DE102009049869A1 (en) * | 2009-10-20 | 2011-04-28 | Hymer-Leichtmetallbau Gmbh & Co. Kg | Ladder scaffold for use in e.g. building site, has working platform connected with guide bars, which are displaced by displacement guide at longitudinal bars of ladder, and hooks fastened to guide bars |
CN202004347U (en) * | 2011-03-17 | 2011-10-05 | 邢台供电公司 | Overhauling working platform |
CN204144756U (en) * | 2014-11-19 | 2015-02-04 | 国家电网公司 | A kind of power transformation overhaul platform of many mounting meanss |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105261983A (en) * | 2015-11-18 | 2016-01-20 | 国家电网公司 | Mutual inductor overhaul platform |
CN109926987A (en) * | 2019-04-17 | 2019-06-25 | 北京铠钺防护科技有限公司 | A kind of driving maintenance aid |
CN109926987B (en) * | 2019-04-17 | 2024-02-13 | 北京铠钺防护科技有限公司 | Auxiliary device for driving maintenance |
Also Published As
Publication number | Publication date |
---|---|
CN104348100B (en) | 2017-02-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201862167U (en) | Safety belt hanging stand for overhaul of isolating switch | |
CN204212399U (en) | Flip-shell is to clasp | |
CN204144756U (en) | A kind of power transformation overhaul platform of many mounting meanss | |
CN203878958U (en) | Hanging basket | |
CN104348100A (en) | Substation maintenance platform with multiple installation modes and installation method thereof | |
CN106019150A (en) | Generator test clamping device | |
CN202920859U (en) | Slot type safety belt hanger | |
CN203756015U (en) | Aerial work platform for power transmission iron tower | |
CN211675960U (en) | Safety rope mechanism for mounting main transformer | |
CN209805218U (en) | Mobile transformer maintenance auxiliary platform | |
CN204947504U (en) | A kind of distribution transforming stand line pipe clamp | |
CN210331418U (en) | Fixing upright rod device for hanging safety belt | |
CN103520852A (en) | Spacing-adjustable safety belt hanging device for disconnecting switch overhaul | |
US20090166130A1 (en) | Apparatus and Method for Securing Fall Arrest Equipment | |
CN205215984U (en) | Fast -assembling type safety belt support anchor clamps | |
KR200465907Y1 (en) | scaffolding frame for turbine case | |
CN204050726U (en) | Fixed connector between framework and safety belt during work high above the ground | |
CN210254381U (en) | Drilling machine support frame | |
CN203447667U (en) | Interval-adjustable safety belt suspension device for maintaining isolating switch | |
CN105257966A (en) | Rack of power transmission and distribution equipment | |
CN208956380U (en) | Battery support device for outdoor cabinet | |
CN205730031U (en) | A kind of hanging rack for safety belt | |
CN210873819U (en) | Safety belt installing support | |
CN202940494U (en) | Electric power overhauling rack | |
CN210041118U (en) | Maintenance auxiliary device for overhead high-voltage direct-current transmission line |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |