CN104234671A - Water-gathering same-well layering same-injection process pipe column - Google Patents

Water-gathering same-well layering same-injection process pipe column Download PDF

Info

Publication number
CN104234671A
CN104234671A CN201410490267.3A CN201410490267A CN104234671A CN 104234671 A CN104234671 A CN 104234671A CN 201410490267 A CN201410490267 A CN 201410490267A CN 104234671 A CN104234671 A CN 104234671A
Authority
CN
China
Prior art keywords
oil pipe
pipe
well
water
sealing device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410490267.3A
Other languages
Chinese (zh)
Inventor
黄有泉
孙晓明
郝伟东
李东雷
赵亚男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Daqing Oilfield Co Ltd
Original Assignee
Petrochina Co Ltd
Daqing Oilfield Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd, Daqing Oilfield Co Ltd filed Critical Petrochina Co Ltd
Priority to CN201410490267.3A priority Critical patent/CN104234671A/en
Publication of CN104234671A publication Critical patent/CN104234671A/en
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention relates to a water-accumulation same-well layering and simultaneous-injection process pipe column. The method mainly solves the problems that the oilfield polymer injection well exploitation mode adopting the existing oilfield process pipe column has great influence on the oilfield output and is greatly influenced by the thickness of an interlayer. The method is characterized in that: the annular space between sleeve pipe (1) and outer oil pipe (2) separate into different levels by a plurality of cable packer (10) of passing that can wash the well, outer oil pipe (2) inside put inlayer oil pipe (3), and be provided with grafting sealing device (5) between inlayer oil pipe (3) bottom and outer oil pipe (2), the level on grafting sealing device (5) upper portion embeds there is eccentric notes to gather ware (4), the level of grafting sealing device (5) lower part embeds there is eccentric water injection mandrel (6). The water-polymer same-well layered and co-injection process pipe column can realize simultaneous proceeding of the follow-up water drive and polymer drive of the same well after polymer drive returns upwards, and the layered injection is equally distributed, so that the development effect is improved, and the influence of the thickness of an interlayer is avoided.

Description

Water is poly-notes process pipe string with well layering is same
Technical field
The present invention relates to oilfield, a kind of water is poly-specifically notes process pipe string with well layering is same.
Background technology
Due to by the restriction of oil field process pipe string structure, injection well, penetrating out after oil reservoir position notes coalescent bundle, returns shutoff on carrying out, top is not employed oil reservoir dead chick and open, continue the poly-exploitation of note the poly-oil reservoir terminated of note.But this development mode is comparatively large to the yield effect in oil field, by minimizing sequent water flooding to the contribution to yield in oil field, and this development mode is larger by the impact of compartment thickness.
Summary of the invention
The oilfield injection well mining type of existing oil field process pipe string is adopted to affect greatly, by the larger deficiency of the impact of compartment thickness field output in order to overcome, the invention provides a kind of water to gather with well layering with noting process pipe string, this water is poly-can be realized poly-driving with well layering with note process pipe string and return rear same well sequent water flooding and carry out with poly-driving simultaneously, equal layering is injected, improve development effectiveness, and do not affect by compartment thickness.
Technical scheme of the present invention is: a kind of water is poly-notes process pipe string with well layering is same, comprise sleeve pipe, inside pipe casing is equipped with outer oil pipe, annular space between described sleeve pipe from outer oil pipe is separated into different layer positions by several washing well cable-passing packers, described outer oil pipe inside is equipped with internal layer oil pipe, and be provided with grafting sealing device between internal layer oil pipe bottom and outer oil pipe, the layer position on grafting sealing device top is built-in with the poly-device of eccentric note, and the layer position of grafting sealing device bottom is built-in with eccentric injection mandrel;
Described grafting sealing device comprises insertion pipe, hermetically sealed case, described insertion pipe top is connected with internal layer oil pipe, and hermetically sealed case top is connected with outer oil pipe, and bottom is connected with lower contact, insertion pipe is placed in hermetically sealed case inside, and sealing inner sleeve is provided therebetween.
The present invention has following beneficial effect: owing to taking such scheme, adopt inside and outside two-layer oil pipe, stratum is divided into two-layer up and down by the sealing device of grafting simultaneously, and levels is divided into different layer positions by packer, layered polymer injection is carried out by the annular space between inside and outside layer oil pipe in upper strata, and lower floor carries out seperated layer water injection by internal layer oil pipe inner chamber, realizes poly-play being returned rear same well sequent water flooding and carries out with poly-driving simultaneously, and each layer injection rate injection pressure is measurable and controllable, improves displacement efficiency further from face.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the structural representation of grafting sealing device.
1-sleeve pipe in figure, the outer oil pipe of 2-, 3-internal layer oil pipe, the poly-device of 4-note, 5-grafting sealing device, 6-eccentric injection mandrel, 7-steel ball, 8-screen casing, 9-cable, 10-washing well cable-passing packer, 51-insertion pipe, 52-hermetically sealed case, 53-O type circle, 54-skeleton ring, 55-seals inner sleeve, 56-lower contact.
Detailed description of the invention
Below in conjunction with accompanying drawing, the invention will be further described:
Shown in Fig. 1, Fig. 2, a kind of water is poly-notes process pipe string with well layering is same, comprise sleeve pipe 1, sleeve pipe 1 inside is equipped with outer oil pipe 2, outer oil pipe 2 is 2 cun of half plain end oil well pipe, and the annular space between described sleeve pipe 1 from outer oil pipe 2 is separated into different layer positions by several washing well cable-passing packers 10, and cable 9 can through above-mentioned washing well cable-passing packer 10, the each layer of equal correspondence in position is provided with the poly-device 4 of eccentric note, and the poly-device 4 of note adopts electric-controlled type.Described outer oil pipe 2 inside is equipped with internal layer oil pipe 3, and is provided with grafting sealing device 5 between internal layer oil pipe 3 bottom and outer oil pipe 2, and the layer position of grafting sealing device 5 bottom is built-in with eccentric injection mandrel 6.Described grafting sealing device 5 comprises insertion pipe 51, hermetically sealed case 52, and wherein insertion pipe 51 top is connected with internal layer oil pipe 3, and hermetically sealed case 52 top is connected with outer oil pipe 2, and bottom is connected with lower contact 56.After tubing string connects, insertion pipe 51 is placed in hermetically sealed case 52 inside, toroidal cavity is formed between hermetically sealed case about 52 two ends and insertion pipe 51, sealing inner sleeve 55 is provided with in this cavity, and sealed by O type circle 53 between sealing inner sleeve 55 and hermetically sealed case 52, skeleton ring 54 is provided with, to ensure sealing between hermetically sealed case 52, sealing inner sleeve 55 and insertion pipe 51 between sealing inner sleeve 55 end and hermetically sealed case 52.
When lower tubular column, first lower outer oil pipe 2, rear lower internal layer oil pipe 3, wherein cable 9 is together transferred with outer oil pipe 2, and the hermetically sealed case 52 of grafting sealing device 5 and sealing inner sleeve 55 are together transferred after being connected with outer oil pipe 2; Insertion pipe 51 is connected to internal layer oil pipe 3 lower end, transfers be placed in hermetically sealed case 52 with internal layer oil pipe 3.Oil reservoir is divided into two-layer up and down by grafting sealing device 5, and wherein upper layer position is note poly layer, and jointly form two annular spaces by sleeve pipe 1, outer oil pipe 2, internal layer oil pipe 3, lower layer position is water filling layer, then form an annular space by sleeve pipe 1, outer oil pipe 2.After having descended tubing string, suppress the packer of release note poly layer position from ectonexine oil pipe annular space, suppress the packer of release water filling layer position from internal layer oil pipe 2 inside.The pressure that the sealing situation of packer at different levels gathers the inlet and outlet pressure sensor collection of device 4 or automatically controlled eccentric injection mandrel 6 by automatically controlled bias note judges.Grafting sealing device sealing situation can adopt following methods: keep ectonexine oil pipe annular space with no pressure, suppress in internal layer oil pipe 3, as returned water from ectonexine oil pipe annular space, the blow-by of grafting sealing device is described, does not return water and one-way sealing is described; Keep with no pressure in internal layer oil pipe 3, ectonexine oil pipe annular space is suppressed, and internal layer oil pipe returns water and the blow-by of grafting sealing device is described, does not return water and the sealing of grafting sealing device is described.
Adopt this tubing string, note poly layer position and water filling layer position anti-flushing well are for carry out simultaneously, anti-flushing well liquid enters from oil jacket annular space, and after note poly layer position washing well cable-passing packer 10 well-flushing passage, the poly-device 4 of automatically controlled bias note, enter ectonexine oil pipe annular space, realization is poly-drives layer position anti-flushing well.Anti-flushing well liquid enters interior pipe through water filling layer position washing well cable-passing packer well-flushing passage, screen casing 8, steel ball 7, realizes water filling layer position anti-flushing well.

Claims (1)

1. a water gathers with well layering with noting process pipe string, comprise sleeve pipe (1), sleeve pipe (1) inside is equipped with outer oil pipe (2), it is characterized in that: described sleeve pipe (1) is separated into different layer positions from the annular space between outer oil pipe (2) by several washing well cable-passing packers (10), described outer oil pipe (2) inside is equipped with internal layer oil pipe (3), and be provided with grafting sealing device (5) between internal layer oil pipe (3) bottom and outer oil pipe (2), the layer position on grafting sealing device (5) top is built-in with the poly-device (4) of eccentric note, the layer position of grafting sealing device (5) bottom is built-in with eccentric injection mandrel (6),
Described grafting sealing device (5) comprises insertion pipe (51), hermetically sealed case (52), described insertion pipe (51) top is connected with internal layer oil pipe (3), hermetically sealed case (52) top is connected with outer oil pipe (2), bottom is connected with lower contact (56), it is inner that insertion pipe (51) is placed in hermetically sealed case (52), and sealing inner sleeve (55) is provided therebetween.
CN201410490267.3A 2014-09-23 2014-09-23 Water-gathering same-well layering same-injection process pipe column Pending CN104234671A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410490267.3A CN104234671A (en) 2014-09-23 2014-09-23 Water-gathering same-well layering same-injection process pipe column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410490267.3A CN104234671A (en) 2014-09-23 2014-09-23 Water-gathering same-well layering same-injection process pipe column

Publications (1)

Publication Number Publication Date
CN104234671A true CN104234671A (en) 2014-12-24

Family

ID=52223478

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410490267.3A Pending CN104234671A (en) 2014-09-23 2014-09-23 Water-gathering same-well layering same-injection process pipe column

Country Status (1)

Country Link
CN (1) CN104234671A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105332677A (en) * 2015-11-06 2016-02-17 中国石油天然气股份有限公司 Cable direct control type water distribution system
CN106285588A (en) * 2015-06-11 2017-01-04 中国石油天然气股份有限公司 Preset cable direct control type electric control layered polymer injection process pipe column and polymer injection method
CN109252834A (en) * 2017-07-13 2019-01-22 中国石油化工股份有限公司 The concentric long-acting layered water filler of binary channels and method
CN111441752A (en) * 2020-04-15 2020-07-24 王皓 Multilayer polymer injection well washing method for coiled tubing

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2893141Y (en) * 2005-10-08 2007-04-25 中国石化胜利油田有限公司桩西采油厂 Spigot type hollow integrated separated layer water-flooding process pipe column
CN101059073A (en) * 2007-05-11 2007-10-24 大庆油田有限责任公司 Same-well double-medium synchronous separate injection tubing string tool and its separate injection method
WO2008115359A1 (en) * 2007-03-22 2008-09-25 Exxonmobil Upstream Research Company Granular electrical connections for in situ formation heating
CN201416430Y (en) * 2009-01-16 2010-03-03 中国石油化工股份有限公司胜利油田分公司采油工艺研究院 Hydraulic controlled type concentric dual-pipe separate injection pipe string
CN101705812A (en) * 2009-11-17 2010-05-12 中国海洋石油总公司 Large-discharge single pipe layered polymer injection and injection allocation method and device
CN101775977A (en) * 2010-01-22 2010-07-14 中国石油化工股份有限公司 Dual-tube injection well safety production string
CN202628059U (en) * 2012-06-08 2012-12-26 中国石油化工股份有限公司 Concentric double-pipe polymer injection pipe column
CN203008880U (en) * 2012-12-09 2013-06-19 李杨 Insertion-tube type release layered water injection tubular column
CN103452524A (en) * 2013-08-27 2013-12-18 中国海洋石油总公司 Electrically-flushable packer and electrically-flushable insert seal for flooding well
CN204126617U (en) * 2014-09-23 2015-01-28 中国石油天然气股份有限公司 Water-gathering same-well layering same-injection process pipe column

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2893141Y (en) * 2005-10-08 2007-04-25 中国石化胜利油田有限公司桩西采油厂 Spigot type hollow integrated separated layer water-flooding process pipe column
WO2008115359A1 (en) * 2007-03-22 2008-09-25 Exxonmobil Upstream Research Company Granular electrical connections for in situ formation heating
CN101059073A (en) * 2007-05-11 2007-10-24 大庆油田有限责任公司 Same-well double-medium synchronous separate injection tubing string tool and its separate injection method
CN201416430Y (en) * 2009-01-16 2010-03-03 中国石油化工股份有限公司胜利油田分公司采油工艺研究院 Hydraulic controlled type concentric dual-pipe separate injection pipe string
CN101705812A (en) * 2009-11-17 2010-05-12 中国海洋石油总公司 Large-discharge single pipe layered polymer injection and injection allocation method and device
CN101775977A (en) * 2010-01-22 2010-07-14 中国石油化工股份有限公司 Dual-tube injection well safety production string
CN202628059U (en) * 2012-06-08 2012-12-26 中国石油化工股份有限公司 Concentric double-pipe polymer injection pipe column
CN203008880U (en) * 2012-12-09 2013-06-19 李杨 Insertion-tube type release layered water injection tubular column
CN103452524A (en) * 2013-08-27 2013-12-18 中国海洋石油总公司 Electrically-flushable packer and electrically-flushable insert seal for flooding well
CN204126617U (en) * 2014-09-23 2015-01-28 中国石油天然气股份有限公司 Water-gathering same-well layering same-injection process pipe column

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106285588A (en) * 2015-06-11 2017-01-04 中国石油天然气股份有限公司 Preset cable direct control type electric control layered polymer injection process pipe column and polymer injection method
CN105332677A (en) * 2015-11-06 2016-02-17 中国石油天然气股份有限公司 Cable direct control type water distribution system
CN109252834A (en) * 2017-07-13 2019-01-22 中国石油化工股份有限公司 The concentric long-acting layered water filler of binary channels and method
CN109252834B (en) * 2017-07-13 2024-05-24 中国石油化工股份有限公司 Concentric double-channel long-acting layered water injection device and method
CN111441752A (en) * 2020-04-15 2020-07-24 王皓 Multilayer polymer injection well washing method for coiled tubing
CN111441752B (en) * 2020-04-15 2021-12-10 江苏瑞亿石油机械有限公司 Multilayer polymer injection well washing method for coiled tubing

Similar Documents

Publication Publication Date Title
CN103806879B (en) Safety production tubular column for same-well production and injection in offshore oilfield
CN104234671A (en) Water-gathering same-well layering same-injection process pipe column
CN101624904A (en) Open hole completion well sand resistant pipe string of sidetracking branch well and inserting type acid cleaning filling inner pipe string thereof
CN103089204B (en) Double-coal-bed layered pressure control device combining coal discharging and coal mining
CN105649585B (en) Flood suction integrated pipe column and its operating procedure
CN204126617U (en) Water-gathering same-well layering same-injection process pipe column
CN108266173A (en) A kind of method for being segmented transformation completion
CN205744381U (en) Multilamellar is divided to adopt and is separated oil well pump
CN218862588U (en) Hot dry rock horizontal well exploitation tubular column structure
CN106930764B (en) Multilayer sandstone-type uranium mineralization with respect separate zone production technique
CN201372779Y (en) Oil jacket communicating vessel
CN204212753U (en) Upper-layer layered polymer-injection lower-layer general water injection process pipe column
CN103161432B (en) Lift separate-layer production string
CN203729968U (en) Simulation structure for bottom water control
CN201486538U (en) Sand prevention pipe string used for open-hole well completion of side-drilled multilateral well and plug-in type acid cleaning filling inner pipe string thereof
RU2354810C1 (en) Method for simultaneous-separate operation of pressure well
CN208137872U (en) A kind of jet stream de-plugging tubing string
CN203175503U (en) Tubular column for safety production in fluid producing and injecting process through one well of offshore oilfield
CN204252929U (en) Oil production water shutoff pipe column
CN108071365A (en) Coal bed gas production, drainage and water injection integrated tubular column
CN203188969U (en) Thermal washing paraffin removal packer
CN206190240U (en) Pumpingh well tubular column
CN202645512U (en) Lift-type separate layer production string
CN204126618U (en) Upper-layer cage-system water injection process pipe column and lower-layer cage-system water injection process pipe column
CN109252834B (en) Concentric double-channel long-acting layered water injection device and method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20141224

WD01 Invention patent application deemed withdrawn after publication