CN104154850B - Monitoring instrument and method for monitoring slippage and cracking on heading slope soil body of tunnel - Google Patents

Monitoring instrument and method for monitoring slippage and cracking on heading slope soil body of tunnel Download PDF

Info

Publication number
CN104154850B
CN104154850B CN201410377471.4A CN201410377471A CN104154850B CN 104154850 B CN104154850 B CN 104154850B CN 201410377471 A CN201410377471 A CN 201410377471A CN 104154850 B CN104154850 B CN 104154850B
Authority
CN
China
Prior art keywords
fixing device
monitoring
points
tunnel
backward
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410377471.4A
Other languages
Chinese (zh)
Other versions
CN104154850A (en
Inventor
杨为民
孙超群
林鹏
许振浩
李术才
李利平
郭明
张骞
王健华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
Original Assignee
Shandong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University filed Critical Shandong University
Priority to CN201410377471.4A priority Critical patent/CN104154850B/en
Publication of CN104154850A publication Critical patent/CN104154850A/en
Application granted granted Critical
Publication of CN104154850B publication Critical patent/CN104154850B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention relates to a monitoring instrument for monitoring slippage and cracking on the heading slope soil body of a tunnel. The monitoring instrument comprises a front monitoring point fixing device and a rear monitoring point fixing device, wherein the front monitoring point fixing device comprises a metal hard rod embedded into the soil body, a spherical valve and an electronic intelligence measuring instrument; the rear monitoring point fixing device comprises a metal hard rod embedded into the soil body, a steel tape, a spherical valve and a locating pin. Moreover, the invention further discloses a monitoring method for the monitoring instrument. The monitoring method for monitoring slippage and cracking of an inverted arch during tunnel excavation, disclosed by the invention solves the problems that the slippage and cracking of the inverted arch of the tunnel cannot be accurately measured, and is closer to engineering practical application in comparison with the previous research, and the monitoring instrument can be used more widely.

Description

Monitoring instrument for the cracking monitoring of upward slope in tunnel soil body slipping and monitoring method
Technical field
This patent is related to side/face upward slope monitoring technical field, ftractures prison particularly with regard to for upward slope in tunnel soil body slipping The monitoring instrument surveyed.
Background technology
China's mountain ridge distribution area is wide, builds underground tunnel project in mountain terrain, needs in time to facing upward slope in construction Sliding cracking situation is observed to ensure the safety of Tunnel Engineering, prevents from facing upward hill wash removing to split and causes disaster accident.China is Carry out substantial amounts of excavation slope, road slope monitoring, but due to upward slope in tunnel soil body complex geologic conditions and vegetation The reasons such as covering, are not easy to be found and early warning facing upward when slope occurs soil body slipping cracking;Meanwhile, both at home and abroad for upward slope in tunnel The instrument of monitoring is still few.
Content of the invention
The purpose of this patent is for realizing upward slope in tunnel soil body slipping cracking is monitored, designing a kind of structure simply real Monitoring instrument, can be used for the monitoring facing upward slope soil body slipping cracking of Tunnel Engineering, grasps in work progress in time and face upward The deformation rule of the slope soil body, is conducive to the safe construction of actual tunnel engineering.
The monitoring instrument for the cracking monitoring of upward slope in tunnel soil body slipping of the present invention, including two parts: the fixing dress of front point Put, put fixing device afterwards.
Described front fixing device, comprising: be sequentially connected fixing metal stiff rod, globe valve, electronic intelligence measuring instrument, institute State metal stiff rod and be earthed body, for fixing front point fixing device;Described globe valve, can be along the 360 degree of rotations of metal stiff rod, can To ensure to use under different gradient between 2 points;Described electronic intelligence measuring instrument, including miniscope and metal ring, uses Show the change in displacement between 2 points after producing displacement in metal ring tension, by recording forward and backward distance between two points Change, you can show that between 2 points, the soil body occurs the shift value ftractureing.
Point fixing device after described, comprising: metal stiff rod, steel tape, globe valve;Described steel tape, globe valve are solid successively It is scheduled on metal stiff rod, described metal stiff rod is earthed body, for putting fixing device after fixation;Described globe valve, can be along gold Belong to 360 degree of rotations of stiff rod it is ensured that using under different gradient between 2 points;The end of the chi bar of described steel tape is provided with extension Hook, this hook is connected with the metal ring of electronic intelligence measuring instrument, and forward and backward two measuring points can be connected by coil of strip ruler end part hook After tighten up chi bar.
As a further improvement on the present invention, the globe valve of described rear point fixing device is additionally provided with alignment pin, on steel ruler There is a circular hole every 10cm, alignment pin can be made to pass through fixed ruler bar.
Described metallic hard pole length is 1~3m, has globe valve it is ensured that not between 2 points near metallic hard masthead portion Use with the gradient.
When the present invention uses, former and later two devices are connected by steel tape, read number on front point-like electron intelligent measuring apparatus According to.
Present invention also offers a kind of for upward slope in tunnel sliding cracking monitoring monitoring instrument monitoring method, including with Lower step:
A. in tunnel inverted arch earth's surface along tunnel axis direction Zuan Dianwei hole, line and tunnel between 2 points are ensured as far as possible Move towards parallel;The metal stiff rod of the forward and backward fixing device of monitoring instrument is inserted in the hole, using cement mortar by 2 points of fix tightlies Gu, it is easy to DATA REASONING.
B., after before and after, fixing device fixes, the chi bar of the steel tape of rear fixing device is pulled open, pull-up alignment pin, The end hook of steel tape is connected with the end circular loop of the electronic intelligence measuring instrument in front fixing device.
C. tighten up the chi bar of steel tape, press alignment pin, the electronic intelligence measuring instrument of point fixing device, pending data before opening Initial reading is recorded after stable.
D. pass through to record the reading of electronic intelligence measuring instrument under different time, data variation rule between analyzing at 2 points, that is, Can draw between 2 points, whether soil-body landslide sliding.
The present invention needs to bury moving towards direction parallel to tunnel as far as possible in the arrangement of forward and backward 2 points of monitoring device, front/rear The line of fixing point ensures that moving towards direction along tunnel lays;During onsite application, forward and backward fixing device should vertically buried enter to monitor Fix in boring and using cement mortar.
Front fixing device includes imbedding soil body metallic hard bar, globe valve, electronic intelligence measuring instrument, puts fixing device bag afterwards Include embedment soil body metallic hard bar, steel tape, globe valve and alignment pin;After the completion of point layout, by rear fixing device steel Tape measure is connected with electronic intelligence measuring instrument hook, passes through rear securing dowel, write down initial reading between 2 points after straining;Pass through Under record different time, electronic intelligence gage readings face upward slope soil movement to monitor.
There is globe valve in forward and backward fixing device, 360 degree of electronic intelligence measuring instrument can be made to rotate and can meet and face upward slope Angle of inclination, is easy to automatically adjust according to facing upward hillside fields shape, surveyed data more closing to reality.
The invention has the beneficial effects as follows: there is globe valve in forward and backward fixing device, 360 degree of electronic intelligence measuring instrument can be made Rotation simultaneously can meet the angle of inclination facing upward slope, be easy to basis and face upward hillside fields shape and automatically adjust, surveyed data more presses close to reality Border;Monitoring instrument, can overcome the monitoring facing upward slope complicated earth surface situation for facing upward slope soil body slipping cracking;This monitoring instrument is divided into Two parts, are easy to carry;Instrument assembling is simple, is easy to operate;Instrument accurate measurement can face upward the deformation such as slope soil body slipping cracking Situation, carries out early warning to disasters such as upward slope in tunnel sliding crackings.
Brief description
Fig. 1 is structural representation when point fixing device chi bar stretches out after the present invention;
Fig. 2 is structural representation when point fixing device chi bar withdraws after the present invention;
Fig. 3 is the structural representation of point fixing device before the present invention.
Wherein 1. first metallic rod;2. steel tape;3. chi bar;4. alignment pin;5. the first rotatable globe valve;6. end hangs Hook;7. the second metallic rod;8. the second rotatable globe valve;9 electronic intelligence measuring instruments;10. end circular loop.
Specific embodiment
With reference to the accompanying drawings and examples this patent is further illustrated.
In Fig. 1~3, a kind of monitoring instrument for upward slope in tunnel sliding cracking monitoring, constitute including two parts: front solid point Determine device, put fixing device afterwards;
Described front fixing device, comprising: be sequentially connected the second fixing metallic rod 7, the second rotatable globe valve 8, electricity Sub- intelligent measuring apparatus 9, described second metallic rod 7 imbeds the soil body, for fixing front point fixing device;Described second is rotatably spherical Valve 8, can carry out 360 degree of rotations along the second metallic rod 7 it is ensured that using under different gradient between 2 points;Described electronics Intelligent measuring apparatus 9, including miniscope and end circular loop 10, for showing at 2 points after end circular loop 10 tension produces displacement Between change in displacement, by recording the change of forward and backward distance between two points, you can show that the soil body between 2 points occurs cracking Shift value.
Point fixing device after described, comprising: the first metallic rod 1, steel tape 2, the first rotatable globe valve 5;Described coil of strip Chi 2, the first rotatable globe valve 5 are sequentially fixed in the first metallic rod 1, and described first metallic rod 1 imbeds the soil body, for fixing Put fixing device afterwards;Described first rotatable globe valve 5, can carry out 360 degree of rotations along the first metallic rod 1 it is ensured that two Use under different gradient between point;The end of the chi bar 3 of described steel tape 2 is provided with end hook 6, this end hook 6 and electricity The end circular loop 10 of sub- intelligent measuring apparatus 9 is connected, and forward and backward two measuring points can be tightened up after being connected by the end hook 6 of steel tape 2 Chi bar 3;It is additionally provided with alignment pin 4 on described first rotatable globe valve 5, steel tape 2 has a circular hole every 10cm, it is fixed to make Position pin 4 passes through fixed ruler bar 3.
A kind of monitoring method of the monitoring instrument for upward slope in tunnel sliding cracking monitoring, comprises the following steps:
A. in tunnel inverted arch earth's surface along tunnel axis direction Zuan Dianwei hole, between 2 points, line moves towards parallel with tunnel; Second metallic rod 7 of the forward and backward fixing device of monitoring instrument, the first metallic rod 1 are inserted in the hole, will using appropriate cement mortar 2 points of fixations, are easy to DATA REASONING.
B. after before and after, fixing device fixes, the chi bar 3 of the steel tape 2 of rear fixing device is pulled open, pull-up positions Pin 4, the end hook 6 of steel tape 2 is connected with the end circular loop 10 of the electronic intelligence measuring instrument 9 in front fixing device.
C. tighten up the chi bar 3 of steel tape 2, press alignment pin 4, before opening, the electronic intelligence measuring instrument 9 of point fixing device, treats Initial reading is recorded after data stabilization.
D. pass through to record the reading of electronic intelligence measuring instrument 9 under different time, data variation rule between analyzing at 2 points, that is, Can draw between 2 points, whether soil-body landslide sliding.
Although the above-mentioned accompanying drawing that combines is described to the specific embodiment of the present invention, not model is protected to the present invention The restriction enclosed, one of ordinary skill in the art should be understood that on the basis of technical scheme, and those skilled in the art are not Need to pay the various modifications that creative work can make or deformation still within protection scope of the present invention.

Claims (3)

1. it is used for the monitoring instrument of upward slope in tunnel soil body slipping cracking monitoring, it is characterized in that, including two parts: the fixing dress of front point Put, put fixing device afterwards;
Described front fixing device, comprising: be sequentially connected fixing metal stiff rod, globe valve, electronic intelligence measuring instrument, described gold Belong to the stiff rod embedment soil body, for fixing front point fixing device;Described globe valve, can along the rotation of 360 degree of metal stiff rod it is ensured that Use under different gradient between forward and backward 2 points;Described electronic intelligence measuring instrument, including miniscope and metal ring, uses Show the change in displacement between forward and backward 2 points after producing displacement in metal ring tension, by recording forward and backward 2 points of spacing From change, show that the soil body between forward and backward 2 points occurs the shift value of cracking;
Point fixing device after described, comprising: metal stiff rod, steel tape, globe valve;Described steel tape, globe valve are sequentially fixed at On metal stiff rod, described metal stiff rod is earthed body, for putting fixing device after fixation;Described globe valve, can be along metallic hard 360 degree of rotations of bar are it is ensured that use between forward and backward 2 points under different gradient;The end of the chi bar of described steel tape is provided with hook, This hook is connected with the metal ring of electronic intelligence measuring instrument, and forward and backward two measuring points pass through to tighten up after coil of strip ruler end part hook is connected Chi bar;
It is additionally provided with alignment pin on the globe valve of point fixing device after described, steel tape has a circular hole every 10cm, alignment pin is worn Cross fixed ruler bar.
2. it is used for the monitoring instrument of upward slope in tunnel soil body slipping cracking monitoring as claimed in claim 1, it is characterized in that, described gold Genus stiff rod length is 1~3m.
3. a kind of monitoring side of the monitoring instrument for the cracking monitoring of upward slope in tunnel soil body slipping utilizing described in claim 1 Method, is characterized in that, comprises the following steps:
A. in tunnel inverted arch earth's surface along tunnel axis direction Zuan Dianwei hole, between forward and backward 2 points, line moves towards parallel with tunnel; Front fixing device of monitoring instrument and the metal stiff rod of rear fixing device are inserted in the hole, will be forward and backward using cement mortar 2 points of fixations, are easy to DATA REASONING;
B., after front fixing device is fixed with rear fixing device, the chi bar of the steel tape of rear fixing device is pulled open, Pull-up alignment pin, the end hook of steel tape is connected with the metal ring of the electronic intelligence measuring instrument in front fixing device;
C. tighten up the chi bar of steel tape, press alignment pin, the electronic intelligence measuring instrument of point fixing device before opening, pending data is stable After record initial reading;
D. pass through to record the reading of electronic intelligence measuring instrument under different time, data variation rule between analyzing at forward and backward 2 points, that is, Draw, between forward and backward 2 points, whether soil-body landslide sliding occurs.
CN201410377471.4A 2014-08-01 2014-08-01 Monitoring instrument and method for monitoring slippage and cracking on heading slope soil body of tunnel Active CN104154850B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410377471.4A CN104154850B (en) 2014-08-01 2014-08-01 Monitoring instrument and method for monitoring slippage and cracking on heading slope soil body of tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410377471.4A CN104154850B (en) 2014-08-01 2014-08-01 Monitoring instrument and method for monitoring slippage and cracking on heading slope soil body of tunnel

Publications (2)

Publication Number Publication Date
CN104154850A CN104154850A (en) 2014-11-19
CN104154850B true CN104154850B (en) 2017-01-25

Family

ID=51880416

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410377471.4A Active CN104154850B (en) 2014-08-01 2014-08-01 Monitoring instrument and method for monitoring slippage and cracking on heading slope soil body of tunnel

Country Status (1)

Country Link
CN (1) CN104154850B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104251681B (en) * 2014-09-25 2017-04-19 山东大学 Tunnel upward slope soil slippage and cracking monitoring method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102930692A (en) * 2012-11-23 2013-02-13 朱海涛 Method for mounting and applying road, bridge and tunnel safety comprehensive detection, monitoring and early warning device
CN204085436U (en) * 2014-08-01 2015-01-07 山东大学 For the monitoring instrument of upward slope in tunnel soil body slipping cracking monitoring

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102930692A (en) * 2012-11-23 2013-02-13 朱海涛 Method for mounting and applying road, bridge and tunnel safety comprehensive detection, monitoring and early warning device
CN204085436U (en) * 2014-08-01 2015-01-07 山东大学 For the monitoring instrument of upward slope in tunnel soil body slipping cracking monitoring

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《单轴压缩条件下锚杆对含三维表面裂隙试样的锚固效应试验研究》;张宁等;《岩土力学》;20111130;第32卷(第11期);第3288-3294、3305页 *

Also Published As

Publication number Publication date
CN104154850A (en) 2014-11-19

Similar Documents

Publication Publication Date Title
CN103913776B (en) The detection method of spherical boulder in shield-tunneling construction
CN105509628B (en) A kind of magnetic survey positioner and the method that landslide depth displacement monitoring is carried out using the device
CN104594881B (en) Method for determining relative special positions of adjacent well parallel sections
CN206847519U (en) A kind of simple geology crack measurement apparatus
CN103438820A (en) Borehole profile rock and soil mass layered deformation optical fiber measuring method
CN109115168A (en) Talus slide large deformation flexible monitoring device and monitoring and analysis method
CN109869140B (en) Adjacent well distance measuring method based on magnetic field gradient
CN203684198U (en) Soil in-situ resistivity test device utilizing static penetration device
CN106569283A (en) Buried iron pipeline detection and accurate positioning method based on magnetic field indirect detection
CN105952487B (en) The device of broken swollen degree and stability inside and outside a kind of analysis deep weak surrounding rock anchoring body
CN105334545A (en) Directional-drilling three-dimensional geological information acquisition method
CN104154850B (en) Monitoring instrument and method for monitoring slippage and cracking on heading slope soil body of tunnel
CN103089243B (en) Measuring method of drilling well azimuth in magnetic casing pipe
CN204085436U (en) For the monitoring instrument of upward slope in tunnel soil body slipping cracking monitoring
CN105842738B (en) A kind of buried target body quantitatively judges method and apparatus extremely
CN103472499A (en) Detection and positioning method for mine underground water diversion tectonic zone
CN104251681B (en) Tunnel upward slope soil slippage and cracking monitoring method
CN206270503U (en) The system that mining blasting point is positioned in real time is realized in shallow layer surface
CN204142216U (en) A kind of upward slope in tunnel soil body slipping cracking monitoring instrument
CN208568650U (en) Earth tunnel country rock moisture content monitoring device
CN112505746A (en) Detection system based on tunnel drilling and blasting construction and corresponding method thereof
CN203465432U (en) Multi-parameter measuring proton magnetometer
CN103698821A (en) Method for detecting deep underground pipeline by using orientation instrument
CN105044789B (en) A kind of the tunnel effect removing method and device of Mine transient electromagnetic forward probe
CN208736396U (en) Talus slide large deformation flexible monitoring device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant