CN104133989B - Meter and the wind power plant sequential export power calculation algorithms of icing loss - Google Patents
Meter and the wind power plant sequential export power calculation algorithms of icing loss Download PDFInfo
- Publication number
- CN104133989B CN104133989B CN201410336900.3A CN201410336900A CN104133989B CN 104133989 B CN104133989 B CN 104133989B CN 201410336900 A CN201410336900 A CN 201410336900A CN 104133989 B CN104133989 B CN 104133989B
- Authority
- CN
- China
- Prior art keywords
- wind
- wind speed
- wind turbines
- turbines
- power plant
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Wind Motors (AREA)
Abstract
The invention discloses under the situation that meter and icing lose, the computational methods of mountain area complexity landform leeward electric field power output consider the influence of Wind turbines and wind power plant inside cable and/or trolley line to power output while calculating;The result of gained is intended to the assessment of the power system Generation System Reliability accessed for wind power plant;The multimode probabilistic model that wind power plant is set up in cluster analysis is done to sequential export power, the reliability assessment of generating and transmitting system can be further used for.The method perfect influence factor of Power Output for Wind Power Field, particularly wind power plant icing congeal influence of the loss to Power Output for Wind Power Field, simulation ice-coating congeal loss result be actually consistent, the Evaluation accuracy of wind power plant reliability can be improved.
Description
Technical field
The invention belongs to field of power, more particularly to a kind of meter and the wind power plant sequential export power meter of icing loss
Calculation method.
Background technology
As wind-powered electricity generation large-scale cluster formula is accessed, certain influence is also brought to power system.Therefore need to be to containing big rule
The power system of mould wind power plant carries out reliability assessment.With being actually incorporated into the power networks for wind-powered electricity generation, many problems also begin to highlight
Come.In February, 2011 to April causes Jiuquan, Guazhou County and body in Zhangjiakou Area, Hebei Province to recur three big rule due to cable fault
The Wind turbines off-grid of mould, harsh weather can also affect greatly to the power output of wind power plant, such as Southwestern China portion area
Annual December to Second Year March between, in the presence of the external elements such as temperature, humidity, circuit in wind power plant and
Wind turbines can produce icing, cause that Wind turbines fault rate is high, power output weakens.
At present in the reliability assessment of electricity generation system, the model of wind power plant is defeated using multimode probabilistic model and sequential
Go out power module.But do not counted in existing numerous models and above-mentioned factor influence.
By considering the factors such as icing loss, cable fault, analogue simulation obtains the power output mould of wind power plant to the present invention
Type, temporal model can be used for the assessment of the reliability of electricity generation system, it is also possible to obtained after output power model is clustered
The multimode probabilistic model of wind power plant, for generating and transmitting system reliability assessment.
For the use of theoretical icing model, major problem is that be input into, due to being influenceed by icing, the wind speed for measuring
Data are not necessarily accurate.Additionally, the beginning and end in order to detect nature icing, in addition it is also necessary to which accurate air themperature and cloud base are high
Angle value.And the acquisition of these parameters is very difficult, it may be said that icing theoretical modeling additionally depends on the development of this system with prediction.
And icing model is often presented certain periodicity.A part be due to temperature cycles rise and fall round the clock, additionally, due to
Disengaging caused by dynamics.So far, the detailed modeling of the process is also very limited, therefore the present invention is damaged for this icing
Lose, after service data and icing loss data is obtained, the relation of power output and equivalent wind speed is built from external characteristics.Improve wind
The influence factor of electric field power output.
Output power curve is obtained, the timing curve data can be used for the reliability assessment of temporal model, during one side pair
The data of overture line are clustered, and can more be met actual and accurate multimode probabilistic model, are further used for hair transmission of electricity
The assessment of system.
The content of the invention
In order to analyze influence of the icing loss to wind power plant sequential export power, the present invention proposes a kind of meter and icing is damaged
The wind power plant sequential export power calculation algorithms of mistake, comprise the following steps:
Step 1, the data for gathering each Wind turbines of wind power plant, including:Wind turbines quantity NWT, each height above sea levelWind speed { v in the T of wind power plant time period t=1,2 ...1,v2,…vt,…,vTAnd wind direction { d (v1),d
(v2),…d(vt),…,d(vT)};
Collection Wind turbines inherent parameters, including:Wind wheel radius r0, sweeping area Arotor, incision wind speed vin, rated wind speed
vrated, cut-out wind speed vout, rated power Prated, hub height H;
Collection wind power plant inner member fault rate and repair rate, including:Wind turbines fault rate λWT, Wind turbines repair rate
μWT, cable fault rate λCA, cable repair rate μCA;
Statistics during collection icing loss in each time period, including:Time period T during icingiceInterior tice
The actual wind speed of the i-th Fans of icing hourBlower fan power output under corresponding wind speedTiceThe individual time period
The loss electricity that congeals of interior i-th Fans
Step 2, by wind power plant time period tice=1 ... TiceInterior wind speedStatistics, calculate
Equivalent wind speed is calculated as follows during icing loses:
It is ticeThe actual wind speed of the i-th Fans in the individual icing time period,It is the blower fan under corresponding wind speed
Power output,It is ticeThe loss electricity that congeals of the i-th Fans in the individual time period,It is ticeThe individual time period
The equivalent wind speed of interior i-th Fans,It is the blower fan power output under corresponding equivalent wind speed;Statistical equivalent wind speed probability
Distribution, is simulated with piecewise function;
Step 3, carry out simulation calculation;The sequential Wind speed model of wind power plant is obtained with Monte Carlo sampling, it is considered to
During icing loses, corresponding wind speed is modified, obtain sequential equivalent wind speed model;Obtain each with the sampling of Taka sieve is covered
The time sequence status of Wind turbines and each cable and/or trolley line;Mountain area complexity relief model is set up, variant height wind-powered electricity generation is tried to achieve
Wind speed at unit;The wake effect model of multi-overlapped is set up, the wind speed at each Wind turbines is corrected;With reference to Wind turbines
The power characteristic of time sequence status and Wind turbines, tries to achieve the power output of each Wind turbines;With reference to cable and/or trolley line
Time sequence status and wind power plant internal electric wiring, try to achieve the sequential export power of wind power plant.
Sequential Wind speed model uses Weibull fittings of distribution in the step 3, and Weibull probability distribution is as follows:
K is form parameter, and c is scale parameter, and v is wind speed;Form parameter and scale parameter are obtained by actual-structure measurement
Go out;Using maximum likelihood estimate, it is assumed that wind farm wind velocity statistical sample is v={ v1,v2,v3,…,vn, n represents statistics sample
This number, the then specific calculation expression that form parameter k and scale parameter c are solved using maximum likelihood estimate is as follows:
Form parameter k is solved using iterative method in formula, so as to try to achieve dimensional parameters c.
The mountain area complexity relief model is the place installed based on Lissaman wake effect models, different Wind turbines
Difference, with different height above sea levels, and wind speed with altitude changes and changes, and causes the wind speed profile of wind power plant uneven, its change
Change situation is represented with following formula:
In formula:v0It is being highly h to be0The wind speed for measuring, m/s;V (h) is the wind speed measured for h in height, m/s;α is wind
Speed typically takes α=1/7 with height change factor;Thus obtain wind speed and increase as height increases;By lossless bernoulli side
Cheng get, the wind speed decreased coefficient d of level terrainFWith the wind speed decreased coefficient d of complicated landformCRelation is as follows:
Then wind speed everywhere is:
Wherein, CTIt is thrust coefficient, r is the radius influenceed by wake effect.
The wake effect model of the multi-overlapped is based on Lissaman wake effect models, it is assumed that be apart xij's
WTiAnd WTjHeight above sea level be respectively hi、hj, then downstream Wind turbines WTjBy upstream Wind turbines WTiWind speed after influence
Computing formula is as follows:
In formula:ArotorIt is wind wheel sweeping area,Ashad.ijIt is the area of lap, riAnd rjRespectively
Upstream Wind turbines WTiWith downstream Wind turbines WTjWind wheel radius;Computing formula is tried to achieve by following formula:
Δ h=in formula | hj-hi|, it is that the height above sea level of two Wind turbines is poor;dijIt is upstream Wind turbines WTiWith lower urticaria
Group of motors WTjBetween level interval;Wake effect is not paid attention in the situation of sowing:The Wind turbines failure of upstream, under
Urticaria group of motors has no influence;Wind turbines power characteristic is as follows:
V, vin, vrated, voutRespectively currently practical wind speed, incision wind speed, rated wind speed and cut-out wind speed, PratedIt is wind
The rated power of machine.
Time sequence status { the S of Wind turbines is obtained in the step 3WT.1,SWT.2,…SWT.t... .SWT.T, wherein, some time
The Wind turbines state at quarterSWTi.t(i=1 ... NWT, t=1,2,
3 ... T) states of the Wind turbines i in t is represented, its value is only 0 and 1, blower fan is represented respectively and is in stoppage in transit and operation shape
State, NWTIt is blower fan sum, T is simulation total time;Obtain the time sequence status { S of cable and/or trolley lineCL.1,SCL.2,…
SCL.t,…SCL.T, wherein, certain moment cable and/or trolley line state
SCLm.t(m=1,2,3 ... NCL, t=1 ... T) and the state of cable and/or trolley line m in t is represented, its value is only 0 and 1,
Cable is represented respectively and/or trolley line is in and stops transport and running status, NCLIt is cable and/or trolley line number, when T is for simulation
Between;
Bring the equivalent wind speed in step 2 into the P that exerts oneself that formula (9) tries to achieve t Wind turbines iWTi.t, then try to achieve and combine wind
It is P that the t Wind turbines i of group of motors state exerts oneselfWTi.tWith SWTi.tProduct:PWTi.t·SWTi.t;
Try to achieve the t Wind turbines i with reference to Wind turbines state and cable and/or trolley line state exert oneself forSo this branch road power output sum isWind power plant
Comprising a plurality of chain type branch road, after trying to achieve every branch road sum, addition obtains the output of wind power plant t.
The idiographic flow of the simulation calculation in the step 3, including:
1) the location of each Wind turbines of wind power plant coordinate is read in;
2) simulation time initialization, t is hourage, since t=1;
3) during judging whether to enter icing;According to the characteristics of ice-covering area, during 2 months December to next years were icing, meter
Simulated time is calculated when 1 day 1 January, during 1- is icing in the 8760th hour the 1416th hour and 8017-, and with this
It is criterion;
If 4) into during icing, using equivalent wind speed modeling wind speed;Otherwise, using Weibull distribution simulations
Wind speed;
5) wind speed and direction of t hours is read in;
6) Monte Carlo sampling obtains the Wind turbines that normal operation and failure are stopped transport;
7) wind speed at each Wind turbines is calculated according to wake effect correlation formula (4)-(8);
8) output of each Wind turbines actual power is calculated according to Wind turbines power characteristic formula (9);
9) simulation time is set Y=8760 hours herein, i.e., 1 year, hourage t=t+1 judged whether simulation time is tied
Beam, t>Y then terminates to calculate, t<Y is then transferred to calculation process 3).
It is perfect the beneficial effects of the present invention are there is provided a kind of method for setting up wind power plant Wind turbines icing model
The influence factor of Power Output for Wind Power Field, particularly wind power plant icing are congealed influence of the loss to Power Output for Wind Power Field, simulation
Icing congeal loss result be actually consistent, the Evaluation accuracy of wind power plant reliability can be improved.
Brief description of the drawings
Fig. 1 is the flow of simulation calculation;
Fig. 2 is wind farm wind velocity probability distribution statistical and fitted figure, and column curve is the distribution of actual count wind speed, is smoothed
Curve is Weibull Probability Distribution Fittings;
The wind direction statistics of Fig. 3 wind power plants, rose circle diagram, N in figure, NNE, NE, ENE, E, ESE, SE, SSE, S, SSW, SW,
WSW, W, WNW, NW, NNW, represent respectively north, northeast by north, northeast, northeast by east, east, southeast by east, the southeast, southeast by south,
South, swbs, southwest, southwest by west, west, northwest by west, northwest, north-west by north;
Fig. 4 is the probability distribution of equivalent wind speed during icing as obtained by calculating loses, it can be seen that Weibull is distributed
Cannot well be fitted, then be simulated using piecewise function;
Fig. 5 is the power curve of Wind turbines;
Fig. 6 is that wake effect model, v are blocked in complicated landform bottom point0It is original wind speed, WTiUpwindturbine,
WTjDownwindturbine is respectively upstream Wind turbines and the downstream Wind turbines (x influenceed by wake effecti, yi, zi)
(xj, yj, zj) it is respectively its coordinate, dij, xijFor not Wei two Wind turbines horizontal axis away from, anterior-posterior horizontal distance, vTBe by
WTiAfterwards with the Wind turbines at wind speed, vj(xij) it is downstream Wind turbines WTjBy upstream Wind turbines WTiWind after influence
Speed, A0It is sweeping area, AX, jIt is Wind turbines WTiIn Wind turbines WTjGo out wake effect influence area, ri(yij) it is the area
Radius, AshadowIt is preceding two-part lap area, angle, θ is the corresponding central angle of overlapping area, r0It is wind wheel half
Footpath;
Fig. 7 is corresponding multiple wake effect model, v0It is original wind speed, 1#, 2# etc. are respectively Wind turbines numbering;
Fig. 8 is wind power plant Wind turbines layout, and transverse and longitudinal axle difference denotation coordination, black side's point represents that Wind turbines are installed
Place, the height of Wind turbines is labeled in Wind turbines installation place;
Fig. 9 is cabling diagram;
Figure 10 is the sequential export power curve of wind power plant;
Figure 11 is one cabling diagram of branch road in wind power plant inside, and bus represents bus, and arrow represents power flow direction, WT
Wind turbines are represented, WT1 ... WT9, WT10 represent Wind turbines numbering, and CL represents cable or trolley line CL1, CL10 representative
Cable number.
Specific embodiment
Below in conjunction with the accompanying drawings, preferred embodiment is elaborated.It should be emphasized that the description below is merely exemplary
, rather than in order to limit the scope of the present invention and its application.
The present invention proposes the wind power plant sequential export power calculation algorithms of a kind of meter and icing loss, including following step
Suddenly:
Step 1, the data for gathering each Wind turbines of wind power plant, including:Wind turbines quantity NWT, each height above sea levelWind speed { v in the T of wind power plant time period t=1,2 ...1,v2,…vt,…,vTAnd wind direction { d (v1),d
(v2),…d(vt),…,d(vT)};The wind direction statistics of wind power plant is illustrated in figure 3, wind direction is angularly divided into 16 directions, presents
Go out rose circle diagram;
Collection Wind turbines inherent parameters, obtain under the parameter of Wind turbines:
Wind wheel radius r0=45m
Sweeping area Arotor=6232m2
Incision wind speed vin=3m/s
Rated wind speed vrated=12m/s
Cut-out wind speed vout=25m/s
Rated power Prated=2MW
Hub height H=60m
Wind power plant inner member fault rate and repair rate:Wind turbines fault rate λWT=0.012 times/year, Wind turbines are repaiied
Multiple rate μWT=30 days;Cable fault rate λCA=0.008 times/year, cable repair rate μCA=12 days.
Statistics during collection icing loss in each time period, including:Time period T during icingiceInterior tice
The actual wind speed of the i-th Fans of icing hourBlower fan power output under corresponding wind speedTiceThe individual time
The loss electricity that congeals of the i-th Fans in section
Step 2, by wind power plant time period tice=1 ... TiceInterior wind speedStatistics, calculate
Equivalent wind speed is calculated as follows during icing loses:
It is ticeThe actual wind speed of the i-th Fans in the individual icing time period,It is the blower fan under corresponding wind speed
Power output,It is ticeThe loss electricity that congeals of the i-th Fans in the individual time period,It is ticeIn the individual time period
The equivalent wind speed of the i-th Fans,It is the blower fan power output under corresponding equivalent wind speed;Statistical equivalent wind speed probability point
Cloth, is simulated with piecewise function;
Step 3, the sequential Wind speed model that wind power plant is obtained with Monte Carlo sampling, it is considered to during icing loses, to phase
The wind speed answered is modified, and obtains sequential equivalent wind speed model;Each Wind turbines and each cable are obtained with the sampling of Taka sieve is covered
And/or the time sequence status of trolley line;Mountain area complexity relief model is set up, the wind speed at variant height Wind turbines is tried to achieve;Build
The wake effect model of vertical multi-overlapped, corrects the wind speed at each Wind turbines;With reference to the time sequence status and wind-powered electricity generation of Wind turbines
The power characteristic of unit, tries to achieve the power output of each Wind turbines;With reference to cable and/or the time sequence status and wind of trolley line
Electric field internal electric wiring, tries to achieve the sequential export power of wind power plant.
Wherein, sequential Wind speed model uses Weibull fittings of distribution in step 3, is as shown in Figure 2 wind farm wind velocity probability
Distribution statisticses and fitting, column curve are the distribution of actual count wind speed, and smoothed curve is Weibull Probability Distribution Fittings.
Weibull probability distribution is as follows:
K is form parameter, and c is scale parameter, and v is wind speed;Form parameter and scale parameter are obtained by actual-structure measurement
Go out.Using maximum likelihood estimate, it is assumed that wind farm wind velocity statistical sample is v={ v1,v2,v3,…,vn, n represents statistics sample
This number, the then specific calculation expression that form parameter k and scale parameter c are solved using maximum likelihood estimate is as follows:
Form parameter k can be solved using iterative method in formula, so as to try to achieve dimensional parameters c.
Equivalent wind speed is changed with piecewise function during icing, is calculated as follows:
It is ticeThe actual wind speed of the i-th Fans in the individual icing time period,It is the blower fan under corresponding wind speed
Power output,It is ticeThe loss electricity that congeals of the i-th Fans in the individual time period,It is ticeIn the individual time period
The equivalent wind speed of the i-th Fans,It is the blower fan power output under corresponding equivalent wind speed.
Mountain area complexity relief model is that the place that different Wind turbines are installed is not based on Lissaman wake effect models
Together, with different height above sea levels, and wind speed with altitude changes and changes, and causes the wind speed profile of wind power plant uneven.Specific mould
Type is shown in Fig. 6, v0It is original wind speed, WTiUpwindturbine, WTjDownwind turbine be respectively upstream Wind turbines and
Downstream Wind turbines (the x influenceed by wake effecti, yi, zi)(xj, yj, zj) it is respectively its coordinate, dij, xijFor Wei not two wind-powered electricity generations
The horizontal axis of unit away from, anterior-posterior horizontal distance, vTIt is by WTiAfterwards with the Wind turbines at wind speed, vj(xij) it is lower urticaria
Group of motors WTjBy upstream Wind turbines WTiWind speed after influence, A0It is sweeping area, AX, jIt is Wind turbines WTiIn wind turbine
Group WTjGo out wake effect influence area, ri(yij) be the area radius, AshadowIt is preceding two-part lap area, angle
Degree θ is the corresponding central angle of overlapping area, r0It is wind wheel radius.Its situation of change can have following formula to represent:
In formula:v0It is being highly h to be0The wind speed for measuring, m/s;V (h) is the wind speed measured for h in height, m/s;α is wind
Speed typically takes α=1/7 with height change factor.Thus obtain wind speed and increase as height increases.By lossless bernoulli side
Journey can be obtained, the wind speed decreased coefficient d of level terrainFWith the wind speed decreased coefficient d of complicated landformCRelation is as follows:
Then wind speed everywhere is:
Wherein, CTIt is thrust coefficient, r is the radius influenceed by wake effect.
It, based on Lissaman wake effect models, is as shown in Figure 7 corresponding many that the wake effect model of multi-overlapped is
Heavy-tailed flow effect model, v0It is original wind speed, 1#, 2# etc. are respectively Wind turbines numbering.Assuming that being apart xijWTiAnd WTj's
Height above sea level is respectively hi、hj, then downstream Wind turbines WTjBy upstream Wind turbines WTiWind speed computing formula after influence is such as
Under:
In formula:ArotorIt is wind wheel sweeping area,Ashad.ijIt is the area of lap, riAnd rjRespectively
Upstream Wind turbines WTiWith downstream Wind turbines WTjWind wheel radius;Computing formula can be tried to achieve by following formula:
Δ h=in formula | hj-hi|, it is that the height above sea level of two Wind turbines is poor, dijIt is upstream Wind turbines WTiWith lower urticaria
Group of motors WTjBetween level interval.Wake effect is not paid attention in the situation of sowing:The Wind turbines failure of upstream, under
Urticaria group of motors has no influence.Wind turbines power characteristic is as follows:
V, vin, vrated, voutRespectively currently practical wind speed, incision wind speed, rated wind speed and cut-out wind speed, PratedIt is wind
The rated power of machine.It is as shown in Figure 5 the power curve of Wind turbines, incision wind speed vin=3m/s;Rated wind speed vrated=
12m/s, cut-out wind speed vout=25m/s, rated power Prated=2MW.
Fig. 9 is cabling diagram, including power supply is Wind turbines, bus, transformer and cable connection, and connected mode is chain
Formula is connected, and 10 typhoon group of motors is connected on every cable, totally 8 typhoon group of motors of cable 80, total installation of generating capacity 160MW.Wind-powered electricity generation
Unit after boosting after step-up transformer by, through cable connection to bus, further accessing power network.With reference to cable and/or trolley line
Time sequence status and wind power plant internal electric wiring, try to achieve the sequential export power of wind power plant, be as shown in Figure 10 wind power plant
Sequential export power curve.
Time sequence status { the S of resulting Wind turbinesWT.1,SWT.2,…SWT.t... .SWT.T, wherein, the wind turbine at certain moment
Group stateSWTi.t(i=1 ... NWT, t=1,2,3 ... T) and represent wind
In the state of t, its value is only 0 and 1 to group of motors i, blower fan is represented respectively is in and stop transport and running status, NWTFor blower fan is total
Number, T is simulation total time;Obtain the time sequence status { S of cable and/or trolley lineCL.1,SCL.2,…SCL.t,…SCL.T, wherein,
Certain moment cable and/or trolley line stateSCLm.t(m=1,2,3 ...
NCL, t=1 ... T) represent the state of cable and/or trolley line m in t, its value is only 0 and 1, represent respectively cable and/or
Trolley line is in stops transport and running status, NCLIt is cable and/or trolley line number, T is simulated time.
With reference to the time sequence status and the power characteristic of Wind turbines of Wind turbines, the output work of each Wind turbines is tried to achieve
Rate.Bring the equivalent wind speed in step 2 into the P that exerts oneself that formula (9) tries to achieve t Wind turbines iWTi.t, with reference to the shape of Wind turbines
State, it is P that final t Wind turbines i exerts oneselfWTi.tWith SWTi.tProduct:PWTi.t·SWTi.t。
With reference to the time sequence status and wind power plant internal electric wiring of cable and/or trolley line, the sequential for trying to achieve wind power plant is defeated
Go out power.Internal electric connection figure is shown in Fig. 9 and Figure 11
By taking Figure 11 as an example, work as t, Wind turbines i exert oneself forSo this branch road
Power output sum isWind power plant includes a plurality of chain type branch road, tries to achieve every branch road sum
Afterwards, it is added the output for obtaining wind power plant t.
The idiographic flow of the simulation calculation in step 3 as shown in figure 1, including:
1) the location of each Wind turbines of wind power plant coordinate is read in, as shown in figure 8, transverse and longitudinal axle represents seat respectively
Mark, black side's point represents Wind turbines installation place, and the height of Wind turbines is labeled in Wind turbines installation place;
2) simulation time initialization, t is hourage, since t=1;
3) during judging whether to enter icing.According to the characteristics of ice-covering area, during 2 months December to next years were icing.Meter
Simulated time is calculated when 1 day 1 January, during 1- is icing in the 8760th hour the 1416th hour and 8017-, and with this
It is criterion;
If 4) into during icing, using equivalent wind speed modeling wind speed;Otherwise, using Weibull distribution simulations
Wind speed.The asking for of equivalent wind speed sees formula (3), and the probability distribution graph of equivalent wind speed is shown in Fig. 4, it can be seen that Weibull distributions cannot
Fitting well, is then simulated using piecewise function.
5) wind speed and direction of t hours is read in;
6) Monte Carlo sampling obtains the Wind turbines that normal operation and failure are stopped transport;
7) wind speed at each Wind turbines is calculated according to wake effect correlation formula (4)-(8);Single wind energy conversion system wake flow
Computation model-Lissaman models
8) output of each Wind turbines actual power is calculated according to Wind turbines power characteristic formula (9);
9) simulation time is set Y=8760 hours, i.e., 1 year herein.Hourage t=t+1, judges whether simulation time is tied
Beam, t>Y then terminates to calculate, t<Y is then transferred to calculation process 3).
The above, the only present invention preferably specific embodiment, but protection scope of the present invention is not limited thereto,
Any one skilled in the art the invention discloses technical scope in, the change or replacement that can be readily occurred in,
Should all be included within the scope of the present invention.Therefore, protection scope of the present invention should be with scope of the claims
It is defined.
Claims (6)
1. the wind power plant sequential export power calculation algorithms that a kind of meter and icing lose, it is characterised in that comprise the following steps:
Step 1, the data for gathering each Wind turbines of wind power plant, including:Wind turbines quantity NWT, each height above sea levelWind speed { v in the T of wind power plant time period t=1,2 ...1,v2,…vt,…,vTAnd wind direction { d (v1),d
(v2),…d(vt),…,d(vT)};
Collection Wind turbines inherent parameters, including:Wind wheel radius r0, sweeping area Arotor, incision wind speed vin, rated wind speed
vrated, cut-out wind speed vout, rated power Prated, hub height H;
Collection wind power plant inner member fault rate and repair rate, including:Wind turbines fault rate λWT, Wind turbines repair rate μWT,
Cable fault rate λCA, cable repair rate μCA;
Statistics during collection icing loss in each time period, including:Time period T during icingiceInterior ticeIcing
The actual wind speed of the i-th Fans of hourBlower fan power output under corresponding wind speedTiceIn the individual time period
The loss electricity that congeals of i Fans
Step 2, by wind power plant time period tice=1 ... TiceInterior wind speedStatistics, calculate icing
Equivalent wind speed is calculated as follows during loss:
It is ticeThe actual wind speed of the i-th Fans in the individual icing time period,It is the blower fan output under corresponding wind speed
Power,It is ticeThe loss electricity that congeals of the i-th Fans in the individual time period,It is ticeI-th in the individual time period
The equivalent wind speed of Fans,It is the blower fan power output under corresponding equivalent wind speed;Statistical equivalent wind velocity distributing paremeter,
It is simulated with piecewise function;
Step 3, carry out simulation calculation;The sequential Wind speed model of wind power plant is obtained with Monte Carlo sampling, it is considered to icing
During loss, corresponding wind speed is modified, obtain sequential equivalent wind speed model;Each wind-powered electricity generation is obtained with Monte Carlo sampling
The time sequence status of unit and each cable and/or trolley line;Mountain area complexity relief model is set up, variant height Wind turbines are tried to achieve
The wind speed at place;The wake effect model of multi-overlapped is set up, the wind speed at each Wind turbines is corrected;With reference to the sequential of Wind turbines
The power characteristic of state and Wind turbines, tries to achieve the power output of each Wind turbines;With reference to cable and/or trolley line when
Sequence state and wind power plant internal electric wiring, try to achieve the sequential export power of wind power plant.
2. method according to claim 1, it is characterised in that sequential Wind speed model is using Weibull points in the step 3
Cloth is fitted, and Weibull probability distribution is as follows:
K is form parameter, and c is scale parameter, and v is wind speed;Form parameter and scale parameter draw by actual-structure measurement;Adopt
With maximum likelihood estimate, it is assumed that wind farm wind velocity statistical sample is v={ v1,v2,v3,…,vn, n represents statistical sample
Number, the then specific calculation expression that form parameter k and scale parameter c are solved using maximum likelihood estimate is as follows:
Form parameter k is solved using iterative method in formula, so as to try to achieve dimensional parameters c.
3. method according to claim 1, it is characterised in that the mountain area complexity relief model is based on Lissaman tails
Stream effect model, the place that different Wind turbines are installed is different, and with different height above sea levels, and wind speed with altitude changes and becomes
Change, cause the wind speed profile inequality of wind power plant, its situation of change to be represented with following formula:
In formula:v0It is being highly h to be0The wind speed for measuring, m/s;V (h) is the wind speed measured for h in height, m/s;α be wind speed with
Height change factor, takes α=1/7;Thus obtain wind speed and increase as height increases;Obtained by lossless D.Bernolli equation, put down
The wind speed decreased coefficient d of smooth landformFWith the wind speed decreased coefficient d of complicated landformCRelation is as follows:
Then wind speed everywhere is:
Wherein, CTIt is thrust coefficient, r is the radius influenceed by wake effect.
4. method according to claim 1, it is characterised in that the wake effect model of the multi-overlapped be based on
Lissaman wake effect models, it is assumed that be apart xijWTiAnd WTjHeight above sea level be respectively hi、hj, then downstream wind turbine
Group WTjBy upstream Wind turbines WTiWind speed computing formula after influence is as follows:
In formula:ArotorIt is wind wheel sweeping area, Arotor=π rj 2;Ashad.ijIt is the area of lap, riAnd rjRespectively upstream
Wind turbines WTiWith downstream Wind turbines WTjWind wheel radius;Computing formula is tried to achieve by following formula:
Δ h=in formula | hj-hi|, it is that the height above sea level of two Wind turbines is poor;dijIt is upstream Wind turbines WTiWith downstream wind turbine
Group WTjBetween level interval;Wake effect is not paid attention in the situation of sowing:The Wind turbines failure of upstream, to lower urticaria
Group of motors has no influence;Wind turbines power characteristic is as follows:
V, vin, vrated, voutRespectively currently practical wind speed, incision wind speed, rated wind speed and cut-out wind speed, PratedIt is blower fan
Rated power.
5. method according to claim 1, it is characterised in that the time sequence status of Wind turbines are obtained in the step 3
{SWT.1,SWT.2,…SWT.t... .SWT.T, wherein, the Wind turbines state at certain momentSWTi.t(i=1 ... NWT, t=1,2,3 ... T) and represent Wind turbines i
In the state of t, its value is only 0 and 1, blower fan is represented respectively and is in stoppage in transit and running status, NWTIt is blower fan sum, T is
Simulation total time;Obtain the time sequence status { S of cable and/or trolley lineCL.1,SCL.2,…SCL.t,…SCL.T, wherein, certain moment
Cable and/or trolley line stateSCLm.t(m=1,2,3 ... NCL, t=
1 ... T) state of cable and/or trolley line m in t is represented, its value is only 0 and 1, cable and/or trolley line is represented respectively
In stoppage in transit and running status, NCLIt is cable and/or trolley line number, T is simulated time;
Equivalent wind speed in step 2 is substituted into the P that exerts oneself that formula (9) tries to achieve t Wind turbines iWTi.t,
V, vin, vrated, voutRespectively currently practical wind speed, incision wind speed, rated wind speed and cut-out wind speed, PratedIt is blower fan
Rated power;
The exerting oneself for t Wind turbines i tried to achieve again with reference to Wind turbines state is PWTi.tWith SWTi.tProduct:PWTi.t·
SWTi.t;
Try to achieve the t Wind turbines i with reference to Wind turbines state and cable and/or trolley line state exert oneself forSo this branch road power output sum isWind power plant
Comprising a plurality of chain type branch road, after trying to achieve every branch road sum, addition obtains the output of wind power plant t.
6. method according to claim 1, it is characterised in that the idiographic flow of the simulation calculation in the step 3,
Including:
1) the location of each Wind turbines of wind power plant coordinate is read in;
2) simulation time initialization, t is hourage, since t=1;
3) during judging whether to enter icing;According to the characteristics of ice-covering area, during 2 months December to next years were icing, mould is calculated
Pseudotime is when 1 day 1 January, during 1- the 8760th hour the 1416th hour and 8017- is icing, and as sentencing
According to;
If 4) into during icing, using equivalent wind speed modeling wind speed;Otherwise, using Weibull distribution simulation wind speed;
5) wind speed and direction of t hours is read in;
6) Monte Carlo sampling obtains the Wind turbines that normal operation and failure are stopped transport;
7) wind speed at each Wind turbines is calculated according to wake effect correlation formula (4)-(8);
In formula:v0It is being highly h to be0The wind speed for measuring, m/s;V (h) is the wind speed measured for h in height, m/s;α be wind speed with
Height change factor, takes α=1/7;Thus obtain wind speed and increase as height increases;Obtained by lossless D.Bernolli equation, put down
The wind speed decreased coefficient d of smooth landformFWith the wind speed decreased coefficient d of complicated landformCRelation is as follows:
Then wind speed everywhere is:
Wherein, CTIt is thrust coefficient, r is the radius influenceed by wake effect;
Assuming that being apart xijWTiAnd WTjHeight above sea level be respectively hi、hj, then downstream Wind turbines WTjBy upstream wind turbine
Group WTiWind speed computing formula after influence is as follows:
In formula:ArotorIt is wind wheel sweeping area, Arotor=π rj 2;Ashad.ijIt is the area of lap, riAnd rjRespectively upstream
Wind turbines WTiWith downstream Wind turbines WTjWind wheel radius;Computing formula is tried to achieve by following formula:
8) output of each Wind turbines actual power is calculated according to Wind turbines power characteristic formula (9);
Wind turbines power characteristic is as follows:
V, vin, vrated, voutRespectively currently practical wind speed, incision wind speed, rated wind speed and cut-out wind speed, PratedIt is blower fan
Rated power
9) simulation time is set Y=8760 hours herein, i.e., 1 year, hourage t=t+1 judged whether simulation time terminates, t>
Y then terminates to calculate, t<Y is then transferred to calculation process 3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410336900.3A CN104133989B (en) | 2014-07-15 | 2014-07-15 | Meter and the wind power plant sequential export power calculation algorithms of icing loss |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410336900.3A CN104133989B (en) | 2014-07-15 | 2014-07-15 | Meter and the wind power plant sequential export power calculation algorithms of icing loss |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104133989A CN104133989A (en) | 2014-11-05 |
CN104133989B true CN104133989B (en) | 2017-07-07 |
Family
ID=51806664
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410336900.3A Active CN104133989B (en) | 2014-07-15 | 2014-07-15 | Meter and the wind power plant sequential export power calculation algorithms of icing loss |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104133989B (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104502800B (en) * | 2014-12-17 | 2018-05-04 | 华北电力大学(保定) | A kind of electric power system fault ratio characteristics extracting method |
CN104951654A (en) * | 2015-06-05 | 2015-09-30 | 华南理工大学 | Method for evaluating reliability of large-scale wind power plant based on control variable sampling |
CN106485602A (en) * | 2016-10-21 | 2017-03-08 | 上海电力学院 | A kind of little blower fan planing method improving wind energy turbine set power benefit |
CN106503341A (en) * | 2016-10-31 | 2017-03-15 | 上海电力学院 | A kind of wind electric field blower blade Lectotype Optimization method |
CN106875293B (en) * | 2017-03-08 | 2019-09-10 | 江苏农林职业技术学院 | A kind of wind power plant booster stations main transformer failure generated energy loss acquisition methods |
CN109359896B (en) * | 2018-12-10 | 2021-11-12 | 国网福建省电力有限公司 | SVM-based power grid line fault risk early warning method |
CN111709112B (en) * | 2020-04-30 | 2023-05-16 | 广东电网有限责任公司电网规划研究中心 | Offshore wind power operation simulation method, device and storage medium |
CN113298389A (en) * | 2021-05-28 | 2021-08-24 | 国网北京市电力公司 | Method and device for evaluating cable running state |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2213875A1 (en) * | 2009-01-30 | 2010-08-04 | Siemens Aktiengesellschaft | Method and arrangement to forecast an output-power of at least one wind-turbine |
CN102411729A (en) * | 2011-11-04 | 2012-04-11 | 国电南京自动化股份有限公司 | Wind power prediction method based on adaptive linear logic network |
CN102536657A (en) * | 2010-12-21 | 2012-07-04 | 通用电气公司 | System and method for controlling wind turbine power output |
CN102606395A (en) * | 2012-03-20 | 2012-07-25 | 东南大学 | Wind farm active power optimal control method based on power prediction information |
CN102682185A (en) * | 2011-03-10 | 2012-09-19 | 华锐风电科技(集团)股份有限公司 | Single wind turbine wind power prediction method |
CN103138294A (en) * | 2013-03-25 | 2013-06-05 | 国电联合动力技术有限公司 | Operation and control method of large-scale wind turbine generator in micro grid system |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8185331B2 (en) * | 2011-09-02 | 2012-05-22 | Onsemble LLC | Systems, methods and apparatus for indexing and predicting wind power output from virtual wind farms |
US9606518B2 (en) * | 2011-12-28 | 2017-03-28 | General Electric Company | Control system and method of predicting wind turbine power generation |
-
2014
- 2014-07-15 CN CN201410336900.3A patent/CN104133989B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2213875A1 (en) * | 2009-01-30 | 2010-08-04 | Siemens Aktiengesellschaft | Method and arrangement to forecast an output-power of at least one wind-turbine |
CN102536657A (en) * | 2010-12-21 | 2012-07-04 | 通用电气公司 | System and method for controlling wind turbine power output |
CN102682185A (en) * | 2011-03-10 | 2012-09-19 | 华锐风电科技(集团)股份有限公司 | Single wind turbine wind power prediction method |
CN102411729A (en) * | 2011-11-04 | 2012-04-11 | 国电南京自动化股份有限公司 | Wind power prediction method based on adaptive linear logic network |
CN102606395A (en) * | 2012-03-20 | 2012-07-25 | 东南大学 | Wind farm active power optimal control method based on power prediction information |
CN103138294A (en) * | 2013-03-25 | 2013-06-05 | 国电联合动力技术有限公司 | Operation and control method of large-scale wind turbine generator in micro grid system |
Also Published As
Publication number | Publication date |
---|---|
CN104133989A (en) | 2014-11-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104133989B (en) | Meter and the wind power plant sequential export power calculation algorithms of icing loss | |
Ciulla et al. | Modelling and analysis of real-world wind turbine power curves: Assessing deviations from nominal curve by neural networks | |
CN102663251B (en) | Physical prediction method for wind power station power based on computational fluid mechanics model | |
Mabel et al. | Analysis of wind power generation and prediction using ANN: A case study | |
Nor et al. | Feasibility assessment of wind energy resources in Malaysia based on NWP models | |
CN103020462B (en) | Take into account the wind energy turbine set probability output power calculation algorithms of complicated wake effect model | |
Mabel et al. | Estimation of energy yield from wind farms using artificial neural networks | |
CN104123682B (en) | A kind of Distribution Network Failure methods of risk assessment based on meteorological effect factor | |
Li et al. | A physical approach of the short-term wind power prediction based on CFD pre-calculated flow fields | |
Hayes et al. | Equivalent power curve model of a wind farm based on field measurement data | |
CN104699936A (en) | Sector management method based on CFD short-term wind speed forecasting wind power plant | |
CN109784563B (en) | Ultra-short-term power prediction method based on virtual anemometer tower technology | |
CN101794996A (en) | Real-time predicting method for output of wind electric field | |
CN104217077A (en) | Method for establishing wind-driven generator power output random model capable of reflecting wind speed variation characteristics | |
CN106815773A (en) | A kind of wind power method of evaluating characteristic | |
CN105279384A (en) | Wind turbine cabin wind speed-based method and device for calculating wind speed of incoming flow | |
CN108269197A (en) | Wind turbines power characteristic appraisal procedure and device | |
CN107194141A (en) | A kind of region wind energy resources becomes more meticulous appraisal procedure | |
CN109948864A (en) | A kind of mima type microrelief regional wind power icing prediction technique and system | |
Bo et al. | Hybrid PSO-BP neural network approach for wind power forecasting | |
Cuevas-Figueroa et al. | Accuracy of WRF for prediction of operational wind farm data and assessment of influence of upwind farms on power production | |
CN103996087A (en) | Method and system for forecasting new energy power generation power | |
CN109636019B (en) | Wind measuring tower arrangement scheme determination method based on neural network algorithm | |
Ohunakin | Wind Characteristics and VVind Energy Potential Assessment in Uyo, Nigeria | |
Yang et al. | Improved nonlinear mapping network for wind power forecasting in renewable energy power system dispatch |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |