CN104110024B - Drainage consolidation method for reinforcement treatment of hydraulic filling soft clay - Google Patents
Drainage consolidation method for reinforcement treatment of hydraulic filling soft clay Download PDFInfo
- Publication number
- CN104110024B CN104110024B CN201310134647.9A CN201310134647A CN104110024B CN 104110024 B CN104110024 B CN 104110024B CN 201310134647 A CN201310134647 A CN 201310134647A CN 104110024 B CN104110024 B CN 104110024B
- Authority
- CN
- China
- Prior art keywords
- curtain wall
- hydraulic
- soft clay
- operating area
- draining curtain
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310134647.9A CN104110024B (en) | 2013-04-18 | 2013-04-18 | Drainage consolidation method for reinforcement treatment of hydraulic filling soft clay |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310134647.9A CN104110024B (en) | 2013-04-18 | 2013-04-18 | Drainage consolidation method for reinforcement treatment of hydraulic filling soft clay |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104110024A CN104110024A (en) | 2014-10-22 |
CN104110024B true CN104110024B (en) | 2015-12-02 |
Family
ID=51707002
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310134647.9A Active CN104110024B (en) | 2013-04-18 | 2013-04-18 | Drainage consolidation method for reinforcement treatment of hydraulic filling soft clay |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104110024B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107338711A (en) * | 2017-06-20 | 2017-11-10 | 中交天津港湾工程研究院有限公司 | A kind of construction method that road is built on soft soil foundation |
CN109706914A (en) * | 2019-01-21 | 2019-05-03 | 吴慧明 | It is a kind of to be layered the blast-filled ground method for processing foundation drained downwards |
CN109826159B (en) * | 2019-03-11 | 2024-05-10 | 广东海工建设工程有限公司 | Quick reinforcement method and structure for soft foundation of hydraulic filling area |
CN112411795B (en) * | 2020-11-06 | 2021-12-21 | 中国港湾工程有限责任公司 | Method for treating foundation in hydraulic filling soft and weak area |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100201320B1 (en) * | 1996-12-31 | 1999-06-15 | 임철웅 | Construction method of filled-up-land for solid waste treatment plant and soild waste treatment plant |
CN102071675A (en) * | 2011-01-10 | 2011-05-25 | 广东省建筑科学研究院 | Soft soil foundation consolidation method combining drainage pile loading prepressing and deep mixing piles |
CN102226335A (en) * | 2011-04-18 | 2011-10-26 | 中交四航工程研究院有限公司 | Foundation treatment method for controlling post-construction settlement and deformation of soft soil |
CN102926375A (en) * | 2011-08-10 | 2013-02-13 | 同济大学 | Sludge discharge field constructing method for speeding up dehydration, solidification and stabilization of dredged sediment |
-
2013
- 2013-04-18 CN CN201310134647.9A patent/CN104110024B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100201320B1 (en) * | 1996-12-31 | 1999-06-15 | 임철웅 | Construction method of filled-up-land for solid waste treatment plant and soild waste treatment plant |
CN102071675A (en) * | 2011-01-10 | 2011-05-25 | 广东省建筑科学研究院 | Soft soil foundation consolidation method combining drainage pile loading prepressing and deep mixing piles |
CN102226335A (en) * | 2011-04-18 | 2011-10-26 | 中交四航工程研究院有限公司 | Foundation treatment method for controlling post-construction settlement and deformation of soft soil |
CN102926375A (en) * | 2011-08-10 | 2013-02-13 | 同济大学 | Sludge discharge field constructing method for speeding up dehydration, solidification and stabilization of dredged sediment |
Also Published As
Publication number | Publication date |
---|---|
CN104110024A (en) | 2014-10-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201362845Y (en) | Plastic draining board and composite negative pressure well point pipe concreting system for soft soil foundation | |
CN102704463B (en) | Vacuum pre-compaction and electro-osmosis combined reinforcing device and method for muck foundation | |
CN103806437B (en) | Double-layer vacuum preloading and hydraulic reclamation soft foundation processing method | |
CN104110024B (en) | Drainage consolidation method for reinforcement treatment of hydraulic filling soft clay | |
CN103758110B (en) | Reinforce the method for Soft Clay Foundation | |
CN102561308A (en) | Light-well plastic-strip superposition vacuum preloading method for soft soil foundation | |
CN107419717A (en) | It is pressurized compound vacuum pre-pressed soft soil foundation processing constructing device and technique | |
CN104818706B (en) | A kind of novel evacuated pre-pressed soft soil foundation handling process | |
CN104120711B (en) | A kind of piling prepressing united vacuum precompressed soft foundation consolidation process structure and method | |
CN201165659Y (en) | Direct discharging type vacuum preloading reinforced soft soil function structure | |
CN101949153A (en) | Foundation drainage control method | |
CN102322054B (en) | Method for processing ultra-soft soil through combining shallow-surface-layer intermittent strong water-pumping/draining with short-term air-curing | |
CN106677158B (en) | A kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently | |
CN109610436A (en) | A kind of sectional type blast-filled ground processing method | |
CN114108597A (en) | Vacuum drainage grouting method | |
CN103031835A (en) | Method for increasing foundation bearing capacity | |
CN102051875A (en) | Method for reinforcing deep silt foundation | |
CN105453748A (en) | Stereo totally-closed greening vacuum alkali removing device and application method thereof | |
CN201785743U (en) | Vacuum preloading consolidated soft soil foundation for combining sand wells and water discharging plates | |
CN203200742U (en) | Drainage consolidation device for processing hydraulic reclamation soft clay | |
CN109295969A (en) | The construction technology of different length drain bar series turbocharging vacuum pre-pressed soft soil foundation | |
CN105804045A (en) | Equipment for strengthening deep soft soil foundation by vacuum preloading of filter well and method | |
CN104746506A (en) | Soft soil combined preloading structure and construction method | |
CN102912787B (en) | Vacuum preloading method for fine sand mats and filter tube sealing | |
CN103046534A (en) | Method for improving bearing capacity of foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20211112 Address after: No. 850, Pudong Avenue, Pudong New Area, Shanghai 200120 Patentee after: CCCC Shanghai channel survey, design and Research Institute Co., Ltd Patentee after: CCCC dredging technology and equipment National Engineering Research Center Co., Ltd Address before: No. 850, Pudong Avenue, Pudong New Area, Shanghai 200120 Patentee before: CCCC Shanghai channel survey, design and Research Institute Co., Ltd |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20220512 Address after: 200120 No. 850, Pudong Avenue, Pudong New Area, Shanghai Patentee after: SHANGHAI WATERWAY ENGINEERING DESIGN AND CONSULTING Co.,Ltd. Address before: 200120 No. 850, Pudong Avenue, Pudong New Area, Shanghai Patentee before: SHANGHAI WATERWAY ENGINEERING DESIGN AND CONSULTING Co.,Ltd. Patentee before: CCCC dredging technology and equipment National Engineering Research Center Co., Ltd |
|
TR01 | Transfer of patent right |