CN104110015A - Tunnel safety protection net and installation method thereof - Google Patents

Tunnel safety protection net and installation method thereof Download PDF

Info

Publication number
CN104110015A
CN104110015A CN201410368704.4A CN201410368704A CN104110015A CN 104110015 A CN104110015 A CN 104110015A CN 201410368704 A CN201410368704 A CN 201410368704A CN 104110015 A CN104110015 A CN 104110015A
Authority
CN
China
Prior art keywords
net
tunnel
netting
steel wire
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410368704.4A
Other languages
Chinese (zh)
Other versions
CN104110015B (en
Inventor
金怀峰
王红军
刘卫东
杨小红
楚占旭
李坤鹏
梁皓
张永红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201410368704.4A priority Critical patent/CN104110015B/en
Publication of CN104110015A publication Critical patent/CN104110015A/en
Application granted granted Critical
Publication of CN104110015B publication Critical patent/CN104110015B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a tunnel safety protection net and an installation method thereof, and aims at providing the tunnel safety protection net which is convenient to install and dismantle, good in protective performance and low in cost. When installed, the tunnel safety protection net is fixedly connected with an anchor rod on the top arch of a tunnel. The tunnel safety protection net comprises a support steel rope net fixedly connected with the anchor rod, an SO/2.2/50 type steel wire grating net fixedly connected with the lower portion of the support steel rope net and a DO/08/300 type steel rope net arranged below the SO/2.2/50 type steel wire grating net, wherein the DO/08/300 type steel rope net is made of wire ropes 16mm in diameter, each mesh interval of the DO/08/300 type steel rope net is 4500*4500mm, and the DO/08/300 type steel rope net is made of sewing ropes 8mm in diameter and fixedly connected with the support steel rope net. When the tunnel safety protection net is installed, menace to construction under the top arch of the tunnel, caused by pieces which fall off the top arch of the tunnel, can be greatly reduced, potential safety hazards of the falling pieces of the tunnel are eliminated, safety of constructors and devices in the tunnel is guaranteed, and good economic and social benefits are generated.

Description

A kind of tunnel safety guard net and mounting method
Technical field
The present invention relates to, in water conservancy and hydropower civil works technical field, especially relate to a kind of tunnel safety guard net and mounting method.
Background technology
Tunnel of large section excavation all adopts stage excavation from top to bottom, after tunnel top layer excavation supporting completes, in Zhong lower floor digging process, the adjustment of tunnel crown stress has one to last process, thereby cause concrete or a part of rock of the spray of tunnel crown to come off, fall piece, tunnel bottom constructor and machinery are caused to certain security threat.For this situation, conventional process mode is mainly to adopt regularly artificial or irregular tour, investigation, finds that crack appears in concrete or the rock stratum of tunnel crown spray, takes artificial cooperative mechanical to prize clearly processing, and its construction risk is high, safety randomness is very big.
Summary of the invention
The present invention has overcome shortcoming of the prior art, the tunnel safety guard net and the mounting method that provide a kind of and install and remove conveniently, barrier propterty are good.
In order to solve the problems of the technologies described above, the present invention is achieved by the following technical solutions: a kind of tunnel safety guard net, during installation, be fixedly connected with the anchor pole of tunnel crown, it comprises the supporting steel netting being fixedly connected with anchor pole, is fixedly connected on the SO/2.2/50 shaped steel wire grid below supporting steel netting and is arranged at the DO/08/300 shaped steel wire netting below SO/2.2/50 shaped steel wire grid; The steel cable that described supporting steel netting employing diameter is φ 16 ㎜ is made, and Mesh distance is 4500 * 4500 ㎜; Described DO/08/300 shaped steel wire netting adopts the stitching rope of φ 8 ㎜ to be fixedly connected with supporting steel netting.
Preferably, described supporting steel netting adopts 32U shape card to be fixedly connected with anchor pole.
Preferably, the spacing between described 32U shape card is not more than 3m.
Preferably, described SO/2.2/50 shaped steel wire grid adopts the iron wire of diameter 1.2mm to be connected with the colligation of supporting steel netting, and colligation node spacing is not more than 1m.
Preferably, between described SO/2.2/50 shaped steel wire grid, lap width is not less than 5cm.
The mounting method of this tunnel protective screening is as follows:
1) installation of supporting steel netting
Supporting steel netting is tunnel protective screening main bearing member, and supporting steel netting all adopts φ 16 steel cables, and Mesh distance is 4500 ㎜ * 4500 ㎜.During supporting steel netting dress, to adopting the anchor pole on 32U shape card and crown to fix, constant spacing is not more than 3m, is not less than the stringing cucurbit tensioning of 10kN in the time of fixedly with tightening force in length and breadth.
2) paving is hung grid
Tunnel safety guard net is used the SO/2.2/50 shaped steel wire grid of GPS2 type active protecting net Plays, and the steel wire diameter of this steel wire grid net is 2.2mm, mesh size 50m * 50mm, and steel wire grid net installation requirement is as follows:
After supporting steel netting installs, whole zone of protection is laid steel wire grid net, and steel wire grid net is positioned at system intermediate layer and is close to concrete surface, and supporting steel netting above it;
Steel wire grid net adopts the iron wire of diameter 1.2mm to be connected with the colligation of supporting steel netting, and colligation node spacing is not more than 1m;
Between steel wire grid net, lap width is not less than 5cm, can adopt the iron wire ligation of diameter 1.2mm;
3) stitching of wire rope net is installed
Tunnel protective screening is used the DO/08/300 shaped steel wire netting of GPS2 type active protecting net Plays, this steel rope net cable diameter 8mm, mesh size 300m * 300mm;
In each linked network region, order paving is hung wire rope net, with φ 8, sew up rope sews up wire rope net to be connected with supporting rope or adjacent net piece edge simultaneously, sewing up rope two ends should the stacked length that is not less than 0.5m, and two ends are respectively fixedly connected with steel rope net with two wire clips;
When single stitching rope error in length is larger, unnecessary end may extend into adjacent linked network unit, and not enough length is also supplemented by the stitching rope of next adjacent linked network.
This tunnel protective screening is between active and passive protective screening, it is the combination of active and passive protective screening, during installation, be almost close to the scar of tunnel crown, the anchor pole and the tunnel protective screening coaction that utilize tunnel to expose, effectively pocket protects tunnel top pneumatically placed concrete or rock falls piece.
Compared with prior art, tool of the present invention has the following advantages:
(1) this tunnel protective screening is between active and passive protective screening, it is the combination of active and passive protective screening, during installation, be almost close to the scar of tunnel crown, the anchor pole and the tunnel protective screening coaction that utilize tunnel to expose, effectively pocket protects tunnel top pneumatically placed concrete or rock falls piece, and the utilization of this new technology can reduce the construction safety of lower floor's excavation supporting in tunnel greatly, accelerating construction progress, saves the duration.Its reliable in structure, processing and fabricating is simple, and use suits large area to popularize very much.
(2) this tunnel protective screening is especially very effective to high tunnel of large section, can eliminate the potential safety hazard that tunnel crown falls piece, greatly reduce tunnel and push away the threat of piece to below construction, constructor and device security in tunnel have been ensured, reduce unnecessary economic loss, produce good economic and social benefit.
Accompanying drawing explanation
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, to the accompanying drawing of required use in embodiment or description of the Prior Art be briefly described below, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skills, do not paying under the prerequisite of creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 is partial structurtes scheme of installation of the present invention.
Fig. 2 is partial structurtes planar development schematic diagram of the present invention.
The specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, obviously, described embodiment is only the present invention's part embodiment, rather than whole embodiment.Embodiment based in the present invention, those of ordinary skills, not paying the every other embodiment obtaining under creative work prerequisite, belong to the scope of protection of the invention.
Tunnel safety guard net shown in Fig. 1 and Fig. 2, during installation, be fixedly connected with the anchor pole 1 of tunnel crown 8, comprise the supporting steel netting 2 being fixedly connected with anchor pole 1, be fixedly connected on SO/2.2/50 shaped steel wire grid 3 below of supporting steel netting 2 and be arranged at SO/2.2/50 shaped steel wire grid 3 DO/08/300 shaped steel wire netting 4 below; The steel cable that described supporting steel netting 2 employing diameters are φ 16 ㎜ is made, and Mesh distance is 4500 * 4500 ㎜; Described DO/08/300 shaped steel wire netting 4 adopts the stitching rope 5 of φ 8 ㎜ to be fixedly connected with supporting steel netting 2.
Described supporting steel netting 2 preferably adopts 32U shape card 6 to be fixedly connected with anchor pole 1, and the spacing between described 32U shape card 6 is not more than 3m.Described SO/2.2/50 shaped steel wire grid 3 preferably adopts the iron wire 7 of diameter 1.2mm to be connected with 2 colligations of supporting steel netting, and colligation node spacing is not more than 1m.Between described SO/2.2/50 shaped steel wire grid 3, lap width is not less than 5cm.
The mounting method of tunnel protective screening is as follows:
1) installation of supporting steel netting
Supporting steel netting is tunnel protective screening main bearing member, and supporting steel netting all adopts φ 16 steel cables, and Mesh distance is 4500 ㎜ * 4500 ㎜.During supporting steel netting dress, to adopting the anchor pole on 32U shape card and crown to fix, constant spacing is not more than 3m, is not less than the stringing cucurbit tensioning of 10kN in the time of fixedly with tightening force in length and breadth.
2) paving is hung grid
Tunnel safety guard net is used the SO/2.2/50 shaped steel wire grid of GPS2 type active protecting net Plays, and the steel wire diameter of this steel wire grid net is 2.2mm, mesh size 50m * 50mm.Steel wire grid net installation requirement is as follows:
After supporting steel netting installs, whole zone of protection is laid steel wire grid net, and steel wire grid net is positioned at system intermediate layer and is close to concrete surface, and supporting steel netting above it.
Steel wire grid net adopts the iron wire of diameter 1.2mm to be connected with the colligation of supporting steel netting, and colligation node spacing is not more than 1m.
Between steel wire grid net, lap width is not less than 5cm, can adopt the iron wire ligation of diameter 1.2mm.
3) stitching of wire rope net is installed
Tunnel protective screening is used the DO/08/300 shaped steel wire netting of GPS2 type active protecting net Plays, this steel rope net cable diameter 8mm, mesh size 300m * 300mm.
In each linked network region, order paving is hung wire rope net, with φ 8, sew up rope sews up wire rope net to be connected with supporting rope or adjacent net piece edge simultaneously, sewing up rope two ends should the stacked length that is not less than 0.5m, and two ends are respectively fixedly connected with steel rope net with two wire clips.
When single stitching rope error in length is larger, unnecessary end may extend into adjacent linked network unit, and not enough length is also supplemented by the stitching rope of next adjacent linked network.
This tunnel protective screening is between active and passive protective screening, it is the combination of active and passive protective screening, during installation, be almost close to the scar of tunnel crown, the anchor pole and the tunnel protective screening coaction that utilize tunnel to expose, effectively pocket protects tunnel top pneumatically placed concrete or rock falls piece.The utilization of this new technology, can reduce the construction safety of lower floor's excavation supporting in tunnel greatly, and accelerating construction progress is saved the duration.Its reliable in structure, processing and fabricating is simple, and use suits large area to popularize very much.
The foregoing is only preferred embodiment of the present invention, in order to limit the present invention, within the spirit and principles in the present invention not all, any modification of doing, be equal to replacement, improvement etc., within all should being included in protection scope of the present invention.

Claims (6)

1. a tunnel safety guard net, during installation, be fixedly connected with the anchor pole (1) of tunnel crown (8), it is characterized in that: comprise the supporting steel netting (2) being fixedly connected with anchor pole (1), be fixedly connected on SO/2.2/50 shaped steel wire grid (3) below of supporting steel netting (2) and be arranged at SO/2.2/50 shaped steel wire grid (3) DO/08/300 shaped steel wire netting (4) below; Described supporting steel netting (2) employing diameter is that the steel cable of φ 16 ㎜ is made, and Mesh distance is 4500 * 4500 ㎜; Described DO/08/300 shaped steel wire netting (4) adopts the stitching rope (5) of φ 8 ㎜ to be fixedly connected with supporting steel netting (2).
2. tunnel safety guard net according to claim 1, is characterized in that: described supporting steel netting (2) adopts 32U shape card (6) to be fixedly connected with anchor pole (1).
3. tunnel safety guard net according to claim 2, is characterized in that: the spacing between described 32U shape card (6) is not more than 3m.
4. tunnel safety guard net according to claim 1, is characterized in that: described SO/2.2/50 shaped steel wire grid (3) adopts the iron wire (7) of diameter 1.2mm to be connected with supporting steel netting (2) colligation, and colligation node spacing is not more than 1m.
5. tunnel safety guard net according to claim 1, is characterized in that: between described SO/2.2/50 shaped steel wire grid (3), lap width is not less than 5cm.
6. the mounting method of tunnel safety guard net claimed in claim 1, is characterized in that being carried out as follows:
1) installation of supporting steel netting
Supporting steel netting is tunnel protective screening main bearing member, and supporting steel netting all adopts φ 16 steel cables, and Mesh distance is 4500 ㎜ * 4500 ㎜;
During supporting steel netting dress, to adopting the anchor pole on 32U shape card and crown to fix, constant spacing is not more than 3m, is not less than the stringing cucurbit tensioning of 10kN in the time of fixedly with tightening force in length and breadth;
2) paving is hung grid
Tunnel safety guard net is used the SO/2.2/50 shaped steel wire grid of GPS2 type active protecting net Plays, and the steel wire diameter of this steel wire grid net is 2.2mm, mesh size 50m * 50mm, and steel wire grid net installation requirement is as follows:
After supporting steel netting installs, whole zone of protection is laid steel wire grid net, and steel wire grid net is positioned at system intermediate layer and is close to concrete surface, and supporting steel netting above it;
Steel wire grid net adopts the iron wire of diameter 1.2mm to be connected with the colligation of supporting steel netting, and colligation node spacing is not more than 1m;
Between steel wire grid net, lap width is not less than 5cm, can adopt the iron wire ligation of diameter 1.2mm;
3) stitching of wire rope net is installed
Tunnel protective screening is used the DO/08/300 shaped steel wire netting of GPS2 type active protecting net Plays, this steel rope net cable diameter 8mm, mesh size 300m * 300mm;
In each linked network region, order paving is hung wire rope net, with φ 8, sew up rope sews up wire rope net to be connected with supporting rope or adjacent net piece edge simultaneously, sewing up rope two ends should the stacked length that is not less than 0.5m, and two ends are respectively fixedly connected with steel rope net with two wire clips;
When single stitching rope error in length is larger, unnecessary end may extend into adjacent linked network unit, and not enough length is also supplemented by the stitching rope of next adjacent linked network.
CN201410368704.4A 2014-07-30 2014-07-30 A kind of installation method of tunnel safety guard net Active CN104110015B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410368704.4A CN104110015B (en) 2014-07-30 2014-07-30 A kind of installation method of tunnel safety guard net

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410368704.4A CN104110015B (en) 2014-07-30 2014-07-30 A kind of installation method of tunnel safety guard net

Publications (2)

Publication Number Publication Date
CN104110015A true CN104110015A (en) 2014-10-22
CN104110015B CN104110015B (en) 2016-06-29

Family

ID=51706993

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410368704.4A Active CN104110015B (en) 2014-07-30 2014-07-30 A kind of installation method of tunnel safety guard net

Country Status (1)

Country Link
CN (1) CN104110015B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401956A (en) * 2015-12-24 2016-03-16 四川川交路桥有限责任公司 Anti-rock burst and anti-rockfall flexible protection device and construction method for tunnel excavation
CN108411924A (en) * 2018-02-09 2018-08-17 中建五局第三建设有限公司 Construction method for mine pit wall safety protection
CN108505755A (en) * 2018-04-13 2018-09-07 方高健 One kind preventing fire-retardant protection network
CN108661663A (en) * 2017-03-28 2018-10-16 北京爱卓达科技有限公司 A kind of method of reinforcing insulating protection net in rough tunnel

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101709650A (en) * 2009-12-03 2010-05-19 中冶集团华冶资源开发有限责任公司 Method for supporting steel grating
KR20120050605A (en) * 2010-11-11 2012-05-21 디앤씨건설 주식회사 Structure of reinforcing net of tunnel
CN102926549A (en) * 2012-11-22 2013-02-13 中冶建工集团有限公司 Manufacturing method for building safety vertical net
CN103572761A (en) * 2012-07-19 2014-02-12 中铁十九局集团第二工程有限公司 Protection method for existing line nearby construction by using brook protective screenings

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101709650A (en) * 2009-12-03 2010-05-19 中冶集团华冶资源开发有限责任公司 Method for supporting steel grating
KR20120050605A (en) * 2010-11-11 2012-05-21 디앤씨건설 주식회사 Structure of reinforcing net of tunnel
CN103572761A (en) * 2012-07-19 2014-02-12 中铁十九局集团第二工程有限公司 Protection method for existing line nearby construction by using brook protective screenings
CN102926549A (en) * 2012-11-22 2013-02-13 中冶建工集团有限公司 Manufacturing method for building safety vertical net

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401956A (en) * 2015-12-24 2016-03-16 四川川交路桥有限责任公司 Anti-rock burst and anti-rockfall flexible protection device and construction method for tunnel excavation
CN105401956B (en) * 2015-12-24 2018-10-12 四川川交路桥有限责任公司 A kind of flexible protective device and construction method of the anti-rock burst falling rocks of tunnel excavation
CN108661663A (en) * 2017-03-28 2018-10-16 北京爱卓达科技有限公司 A kind of method of reinforcing insulating protection net in rough tunnel
CN108661663B (en) * 2017-03-28 2020-06-30 北京爱卓达科技有限公司 Method for reinforcing insulating protective net in lining-free tunnel
CN108411924A (en) * 2018-02-09 2018-08-17 中建五局第三建设有限公司 Construction method for mine pit wall safety protection
CN108411924B (en) * 2018-02-09 2020-03-13 中建五局第三建设有限公司 Construction method for mine pit wall safety protection
CN108505755A (en) * 2018-04-13 2018-09-07 方高健 One kind preventing fire-retardant protection network

Also Published As

Publication number Publication date
CN104110015B (en) 2016-06-29

Similar Documents

Publication Publication Date Title
CN104110015A (en) Tunnel safety protection net and installation method thereof
CN105134216B (en) Anti- slump structure by the engineering method lane of breaking roof 110
CN103277114A (en) Non-sprayed-concrete anchor net supporting method of underground construction broken surrounding rocks
CN208328952U (en) Side slope Initiative Defence System
CN105401956B (en) A kind of flexible protective device and construction method of the anti-rock burst falling rocks of tunnel excavation
CN108203984A (en) A kind of Dangerous Rock Body bolting with wire mesh method
CN102425181A (en) Side slope greening restoration method
CN204000779U (en) Arch dam abutment side slope supporting construction
CN202865757U (en) Flexible protective screening
CN204266179U (en) A kind of tunnel safety guard net
CN209798761U (en) Foundation pit covering protection system
CN203430546U (en) Roadway roof protective net of coal face
CN208749380U (en) A kind of roadway support anchor cable snaps safety guards
CN103742193B (en) The mounting method of the soft filter pipe of a kind of underground goaf hydraulic fill
CN102611057A (en) Crossing mesh
CN206328751U (en) The safeguard structure of anchorage cable anchoring section
CN206428980U (en) A kind of assembled architecture safety protection component
CN205329567U (en) A multiplely should slide parallel suo bushe structure of type for flexible protection structure
CN104695991A (en) Coal mine multiple seam bolting-grouting process
CN203476364U (en) Colliery steel wire rope reinforced polyester fiber flexible composite net
CN204941571U (en) A kind of railway tunnel supporting and protection structure of improvement
CN204456175U (en) There is the retaining wall system of supporting mesh structure
CN204152229U (en) A kind of large span horizontal safety protector
CN203961258U (en) Builder's jack foot guard structure
CN203821443U (en) Cave opening protecting device for blasting excavation at light and shade junction part of subway tunnel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant