CN104070603A - Tensioning assembly for producing prestressed concrete pile without end plate - Google Patents

Tensioning assembly for producing prestressed concrete pile without end plate Download PDF

Info

Publication number
CN104070603A
CN104070603A CN201410241440.6A CN201410241440A CN104070603A CN 104070603 A CN104070603 A CN 104070603A CN 201410241440 A CN201410241440 A CN 201410241440A CN 104070603 A CN104070603 A CN 104070603A
Authority
CN
China
Prior art keywords
stretch
cutting ferrule
anchor ring
tensioning
baffle plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410241440.6A
Other languages
Chinese (zh)
Other versions
CN104070603B (en
Inventor
朱克平
张风臣
徐飞
陆军
吴海涛
张前永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lianyungang Guquan new building materials Co.,Ltd.
Original Assignee
JIANGSU GUFENG PIPE GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU GUFENG PIPE GROUP CO Ltd filed Critical JIANGSU GUFENG PIPE GROUP CO Ltd
Priority to CN201410241440.6A priority Critical patent/CN104070603B/en
Publication of CN104070603A publication Critical patent/CN104070603A/en
Application granted granted Critical
Publication of CN104070603B publication Critical patent/CN104070603B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/043Wire anchoring or tensioning means for the reinforcements

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a tensioning assembly for producing a prestressed concrete pile without an end plate. The tensioning assembly comprises a tensioning plate provided with a tensioning through hole, a plurality of matched tensioning screws, a clamping sleeve nut, an anchor ring, a support column, and a baffle provided with a rib threading hole, wherein the clamping sleeve nut is provided with cut-through thread end and clamping sleeve end, and the hole diameter of the clamping sleeve end is less than that of the thread end; a pair of anchor ring sleeves with semi-annular cross sections is arranged in each pair of clamping sleeve nut and tensioning screw which are in threaded connection; the inner diameter of the anchor ring sleeve is greater than the rib diameter of a prestressed rib and less than the diameter of the pier head thereof; the outer diameter of the anchor ring is greater than the hole diameter of the clamping sleeve end of the clamping sleeve nut and less than the hole diameter of the thread end thereof. The tensioning assembly provided by the invention is simple in structure and convenient to use; during production, by using the tensioning assembly provided by the invention, the use of end plates can be reduced, thus the finished pile is simple and reasonable in structure, and the quality of the finished pile is improved; the machining materials and expense of the end plates are saved, and a production cost is reduced; production procedures for the prestressed concrete pile are simplified, and a production efficiency is increased.

Description

Stretch-draw assembly for the production of end-plate-free prestressed-concrete pile
Technical field
The present invention relates to a kind of building mould, especially relate to a kind of accessory part of the mould for the production of prestressed concrete square pile or pile tube.
Background technology
China develops and applies prestressed-concrete pile since the sixties in 20th century.Through the development of five more than ten years, prestressed-concrete pile is widely used in the foundation engineering of all kinds of buildings or structures, as fields such as harbour, harbour, high-rise, public building, general industry and civil buildings, highway, bridges.At present, the prestressed-concrete pile that China is mainly used has pile tube and square pile.The structure member of these two kinds of stakes is similar, mainly comprises the parts such as steel reinforcement cage, concrete, end plate, anchor ear plate.Concrete and steel reinforcement cage form pile body.Steel reinforcement cage is comprised of non-prestressing tendon, deformed bar and tie hoop, by seam welder, tie hoop is welded on non-prestressed and presstressed reinforcing steel.End plate is assembled mutually with steel reinforcement cage, is located at pile body two ends, conventionally, the end plate near stretching end is called to end plate, and the end plate near stiff end is called to end tailgate.Anchor ear plate and end plate be by welding or the mode such as riveted joint is fixed together, thereby make the further anchor ear of end plate on pile body.
The assembling of end plate and steel reinforcement cage comprises following key step: (1) forms steel reinforcement cage by the presstressed reinforcing steel after non-prestressing tendon, heading and stirrup by seam welder roll welding; (2) end plate and the welding of anchor ear plate are formed to pile crown; (3) presstressed reinforcing steel after heading is first passed to end plate by wearing muscle hole, then move to counter sink, heading is stuck in counter sink.By above-mentioned steps, complete after the assembling of end plate and steel reinforcement cage, the mould that the assembly of end plate and steel reinforcement cage is moved into prefabricated pile carries out stretch-draw.
At present, utilize stretching machine to carry out prestressed stretch-draw, conventionally adopt tensioning head method.The pass order that adopts tensioning head method to carry out power in the process of stretch-draw is stretching machine → tensioning head → stretch-draw screw mandrel → stretch board → end tailgate → presstressed reinforcing steel → end plate → stiff end.From the pass order of above power, end plate and end tailgate all will bear prestressing force, thereby realize, presstressed reinforcing steel are applied to prestressing force.
When tensioned prestressing bar, end plate plays an important role.But, while utilizing end plate to carry out stretch-draw, there is following problem: the processing and fabricating program of (1) end plate is many, and material and processing charges are high; (2) when end plate and anchor ear plate are assembled, need to weld or rivet, increased operation, take cost of labor and device resource; (3) end plate material is thick and heavy, and anchor ear sheet material matter is thin light, all easily causes the distortion of anchor ear plate in the process of assembling, transportation, storage and use, affects finished peg quality; (4) in finished peg, include end plate, increased the cost of finished peg.
In sum, in prestressed-concrete pile, reduce the use of end plate, can reach and save finished peg production cost, improve finished peg quality, reduce production process, the object of enhancing productivity.
Summary of the invention
Technical problem: the deficiency existing for prior art, provides a kind of stretch-draw assembly for the production of end-plate-free prestressed-concrete pile.
Technical scheme: the stretch-draw assembly for the production of end-plate-free prestressed-concrete pile provided by the invention, comprise stretch board, some tensioning screw rods corresponding with each presstressed reinforcing steel position, described stretch board is provided with the stretch-draw through hole mating with tensioning screw rod, its innovation is, it also comprises support column, baffle plate, cutting ferrule nut and anchor ring;
Described baffle plate and stretch board be arranged in parallel, and its shape, size are mated with the mould of concrete-pile, and baffle plate is provided with corresponding with each presstressed reinforcing steel position muscle hole of wearing; Support column vertical support is between stretch board and baffle plate; The quantity of the quantity of cutting ferrule nut and tensioning screw rod with its coupling is identical, and cutting ferrule nut has the end of thread and the cutting ferrule end of perforation, and the aperture of cutting ferrule end is less than the aperture of the end of thread; The cutting ferrule nut linking together at each double thread and the inside of tensioning screw rod, being equipped with a pair of cross section is semiorbicular anchor ring cover; The internal diameter of every anchor ring cover is greater than the muscle portion diameter of presstressed reinforcing steel, is less than the pier nose diameter of presstressed reinforcing steel; The external diameter of every anchor ring is greater than the aperture of cutting ferrule nut cutting ferrule end, is less than the aperture of the cutting ferrule nut end of thread.
For being easy to realize the balanced support of support column between stretch board and baffle plate, described support column arranges four.
Installation for ease of support column between stretch board and baffle plate, described support column has at least one end to be fixed on stretch board or baffle plate.
Preferably, for making support column and stretch board form an integral body to be applicable to produce the concrete-pile of all size, one end of described support column is fixed on stretch board, and the other end is not fixed with baffle plate, and baffle plate becomes an independently flat board.
Beneficial effect: the present invention is simple in structure, easy to use.Use the present invention to produce prestressed-concrete pile, reduced the use of end plate, make the simple and reasonable of finished peg, improved the quality of finished peg; Rapidoprint and the expense of also having saved end plate, reduced production cost; Meanwhile, also simplify the production process of prestressed-concrete pile, improved production efficiency.
Accompanying drawing explanation
Fig. 1 is stretch-draw components side view.
Fig. 2 is stretch board front view
Fig. 3 is baffle plate front view.
Fig. 4 is cutting ferrule nut amplification view.
Fig. 5 is anchor ring cover enlarged diagram.
Fig. 6 is that stretch-draw assembly is used the schematic top plan view at stretching end.
Fig. 7 is that stretch-draw assembly is used rear-end schematic top plan view.
In figure, have: stretch board 1, short steel column 2, baffle plate 3, cutting ferrule nut 4, tensioning screw rod 5, anchor ring sheet 6, through hole 7, the cutting ferrule end perforate 9 of wearing muscle hole 8, cutting ferrule nut, stretch-draw silk hole 10, stretch-draw screw mandrel 11, presstressed reinforcing steel 12, termination clamp 13, tensioning nut 14.
The specific embodiment
Referring to accompanying drawing, below in conjunction with embodiment and accompanying drawing, the present invention is further illustrated.
Embodiment 1: use at stretching end, produce Endless board prestress concrete square pile.
The stretch-draw assembly of the present embodiment comprises stretch board 1, some tensioning screw rods 5 corresponding with each presstressed reinforcing steel 12 positions, and described stretch board 1 is provided with the stretch-draw through hole 7 mating with tensioning screw rod 5, also comprises support column 2, baffle plate 3, cutting ferrule nut 4 and anchor ring 6.One end vertical welding of four support columns 2 is fixed on stretch board 1, and baffle plate 3 is an independently flat board, and four support columns 2 are supported between stretch board 1 and baffle plate 3, make baffle plate 3 and stretch board 1 keeping parallelism, form the main body of the present embodiment.The shape of stretch board 1 and baffle plate 3 is square, and length and width size is all mated with the mould of concrete-pile, which is provided with corresponding with each presstressed reinforcing steel 12 positions muscle hole 8 of wearing.The quantity of cutting ferrule nut 4 is identical with the quantity of the tensioning screw rod 5 mating with its screw thread, and cutting ferrule nut 4 has the end of thread and the cutting ferrule end of perforation, and the aperture of cutting ferrule end perforate 9 is less than the aperture of the end of thread, referring to Fig. 5.Inside at every a pair of cutting ferrule nut 4 being together by a threaded connection and tensioning screw rod 5, being equipped with a pair of cross section is semiorbicular anchor ring cover 6, referring to Fig. 4, the internal diameter of every anchor ring cover 6 is greater than the muscle portion diameter of presstressed reinforcing steel 12, and is less than the pier nose diameter of presstressed reinforcing steel 12; The external diameter of every anchor ring cover 6 is greater than the aperture of cutting ferrule nut 4 cutting ferrule ends, and is less than the aperture of cutting ferrule nut 4 ends of thread, anchor ring cover 6 can be blocked and be placed in cutting ferrule nut 4.
The installation of stretch-draw assembly: the stretch-draw silk hole 10 on stretch board 1 is connected with stretch-draw screw mandrel 11.When producing Endless board prestress concrete square pile, utilize seam welder that presstressed reinforcing steel 12, non-prestressing tendon and stirrup are welded into after steel reinforcement cage, in one end of steel reinforcement cage, anchor ear plate and end plate are installed.The other end is installed stretch-draw assembly and stretching machine, be called stretching end, when stretch-draw assembly is installed, the wearing behind muscle hole 8 through baffle plate 3 by the presstressed reinforcing steel with heading 12, cutting ferrule nut 4 is enclosed within on presstressed reinforcing steel 12, and make on cutting ferrule nut 4 with the cutting ferrule end in cutting ferrule hole 9 towards baffle plate 3.Then, two anchor ring covers 6 are fastened on presstressed reinforcing steel 12 and are snapped in cutting ferrule nut 4.Mobile stretch-draw assembly, makes stretch-draw through hole 7 position alignment on cutting ferrule nut 4 and stretch board 1, and tensioning screw rod 5 is screwed in cutting ferrule nuts 4 through stretch-draw through hole 7, and presstressed reinforcing steel 12 is connected on stretch board 1.
After the installation of stretch-draw assembly, handling steel reinforcement cage body is put into the square pile mould of dimension size, make to be connected with stretch-draw assembly one end near stretching machine, steel reinforcement cage body with the other end of anchor ear plate and end plate away from stretching machine, referring to Fig. 6, Fig. 6 is that stretch-draw assembly is used the schematic top plan view at stretching end.At position, termination, stretch-draw screw mandrel 11, through termination clamp 13, is connected firmly end tail clamp and end plate in stake tail bit, and two clamps installing are all arranged on the outside of mould ends.The object that termination clamp 13 is set at the position, termination of stake is after presstressed reinforcing steel 12 stretch-draw complete, and by termination clamp 13, blocks mould ends, guarantees that stretch-draw assembly does not bounce back; The object that end tail clamp is set in the end tail bit of stake is in the process of tensioned prestressing bar 12, to guarantee that end plate does not move, thereby guarantees prestressedly in stretching process to apply smoothly, and removes the prestressing force in presstressed reinforcing steel 12 after stretching machine and can not lose.Install after two clamps, stretch-draw screw mandrel 11 is connected firmly with stretching machine, start stretching machine, tensioned prestressing bar 12.When the prestressing force in presstressed reinforcing steel 12 reaches regulation requirement, stop stretch-draw, termination clamp 13 is clamped on to mould ends, removal stretching machine.Afterwards, pass through cloth, vibrate, handling, the operations such as steam press maintenance, complete after the making of Endless board prestress concrete square pile, dismounting mould and stretch-draw assembly.When dismounting stretch-draw assembly, it should be noted that the presstressed reinforcing steel 12 first cutting off between stretch board 1 and baffle plate 3, remove after stretch-draw assembly, then the presstressed reinforcing steel 12 of the outstanding pile body of excision, make stake end keep smooth.
Then, dismantle stretch-draw assembly of the present invention, in order to reusing.Demounting procedure of the present invention is: turn on tensioning screw rod 5 and cutting ferrule nut 4, take out anchor ring cover 6 wherein and the broken end of presstressed reinforcing steel 12.
Embodiment 2: use at tail end, produce tailgate prestressed concrete square pile for no reason.
At the stake tail of single-unit stake, and the non-pile extension end of more piece stake, all can produce the prestressed concrete square pile of tailgate for no reason with the present invention, referring to Fig. 7.
The difference of the present embodiment and embodiment 1 is only, when using at the stake tail of single-unit stake or other non-pile extension end, stretching machine does not need to be connected with the present invention, thereby the present embodiment does not need the termination clamp 13 in embodiment 1, so, the stretch board 1 of the present embodiment is larger than baffle plate 3, and stretch board 1 is not to be placed in mould, and it is directly placed on outside mould tail end.
When using the present invention to produce end-plate-free pile for prestressed pipe, only the shape of stretch board 1, baffle plate 3 need be done to respective change, except rotary process, installation, production method and production Endless board prestress concrete square pile are basic identical, and this description repeats no more.

Claims (4)

1. the stretch-draw assembly for the production of end-plate-free prestressed-concrete pile, comprise stretch board (1), some tensioning screw rods (5) corresponding with each presstressed reinforcing steel (12) position, described stretch board (1) is provided with the stretch-draw through hole (7) mating with tensioning screw rod (5), it is characterized in that, it also comprises support column (2), baffle plate (3), cutting ferrule nut (4) and anchor ring (6);
Described baffle plate (3) and stretch board (1) be arranged in parallel, and its shape, size are mated with the mould of concrete-pile, and baffle plate (3) is provided with corresponding with each presstressed reinforcing steel (12) position muscle hole (8) of wearing;
Support column (2) vertical support is between stretch board (1) and baffle plate (3);
The quantity of the quantity of cutting ferrule nut (4) and tensioning screw rod (5) with its coupling is identical, and cutting ferrule nut (4) has the end of thread and the cutting ferrule end of perforation, and the aperture of cutting ferrule end is less than the aperture of the end of thread;
The cutting ferrule nut (4) linking together at each double thread and the inside of tensioning screw rod (5), being equipped with a pair of cross section is semiorbicular anchor ring cover (6); The internal diameter of every anchor ring cover (6) is greater than the muscle portion diameter of presstressed reinforcing steel (12), is less than the pier nose diameter of presstressed reinforcing steel (12); The external diameter of every anchor ring (6) is greater than the aperture of cutting ferrule nut (4) cutting ferrule end, is less than the aperture of cutting ferrule nut (4) end of thread.
2. stretch-draw assembly as claimed in claim 1, is characterized in that described support column (2) arranges four.
3. stretch-draw assembly as claimed in claim 2, is characterized in that described support column (2) has at least one end to be fixed on stretch board (1) or baffle plate (3).
4. stretch-draw assembly as claimed in claim 3, is characterized in that one end of described support column (2) is fixed on stretch board (1) above, and the other end is fixing with baffle plate (3).
CN201410241440.6A 2014-05-30 2014-05-30 For producing the tensioning component of end-plate-free prestressed-concrete pile Active CN104070603B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410241440.6A CN104070603B (en) 2014-05-30 2014-05-30 For producing the tensioning component of end-plate-free prestressed-concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410241440.6A CN104070603B (en) 2014-05-30 2014-05-30 For producing the tensioning component of end-plate-free prestressed-concrete pile

Publications (2)

Publication Number Publication Date
CN104070603A true CN104070603A (en) 2014-10-01
CN104070603B CN104070603B (en) 2018-06-01

Family

ID=51592415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410241440.6A Active CN104070603B (en) 2014-05-30 2014-05-30 For producing the tensioning component of end-plate-free prestressed-concrete pile

Country Status (1)

Country Link
CN (1) CN104070603B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989106A (en) * 2015-07-08 2015-10-21 宿迁市保祥重工有限公司 Full prestress tension plate external member
CN105239559A (en) * 2014-10-03 2016-01-13 威海齐德新型建材有限公司 Common deformed steel bar tensioning device, prefabricated square pile and process for prefabricated square pile
CN106976156A (en) * 2016-01-18 2017-07-25 周兆弟 A kind of tensioning board component of concrete prefabricated pile die
CN107599158A (en) * 2017-09-26 2018-01-19 汤始建华建材(苏州)有限公司 A kind of process for prestressed component two directions tension
CN109176864A (en) * 2018-09-12 2019-01-11 安徽中源建设有限公司 A kind of equipment for fixed stretching reinforcing bar
CN113152449A (en) * 2021-04-16 2021-07-23 建华建材(中国)有限公司 End plate sheet, precast pile, tensioning structure and method, pile splicing structure and method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2227159Y (en) * 1994-03-02 1996-05-15 四川省建筑科学研究院 Compound anchoring device for pre-stress tension fibre reinforcment
JPH09254133A (en) * 1996-03-25 1997-09-30 Asahi Chem Ind Co Ltd Attaching/detaching device of fixed plate for molding concrete pile
CN1718970A (en) * 2005-07-27 2006-01-11 同济大学 Intelligent prestress system
CN102390083A (en) * 2011-07-29 2012-03-28 广东建华管桩有限公司 Novel part assembly and method for stretching main steel bar in producing prestressed pipe pile
CN202200392U (en) * 2011-07-29 2012-04-25 广东建华管桩有限公司 Tensioning component for tensioning main reinforcements of pre-stressed pipe piles
CN202622987U (en) * 2012-05-24 2012-12-26 宁波浙东新冈建材设备有限公司 Tensioning tool for simultaneously manufacturing a plurality of prestressed concrete pipe piles
CN203937017U (en) * 2014-05-30 2014-11-12 江苏固丰管桩集团有限公司 Stretch-draw assembly for the production of end-plate-free prestressed-concrete pile

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2227159Y (en) * 1994-03-02 1996-05-15 四川省建筑科学研究院 Compound anchoring device for pre-stress tension fibre reinforcment
JPH09254133A (en) * 1996-03-25 1997-09-30 Asahi Chem Ind Co Ltd Attaching/detaching device of fixed plate for molding concrete pile
CN1718970A (en) * 2005-07-27 2006-01-11 同济大学 Intelligent prestress system
CN102390083A (en) * 2011-07-29 2012-03-28 广东建华管桩有限公司 Novel part assembly and method for stretching main steel bar in producing prestressed pipe pile
CN202200392U (en) * 2011-07-29 2012-04-25 广东建华管桩有限公司 Tensioning component for tensioning main reinforcements of pre-stressed pipe piles
CN202622987U (en) * 2012-05-24 2012-12-26 宁波浙东新冈建材设备有限公司 Tensioning tool for simultaneously manufacturing a plurality of prestressed concrete pipe piles
CN203937017U (en) * 2014-05-30 2014-11-12 江苏固丰管桩集团有限公司 Stretch-draw assembly for the production of end-plate-free prestressed-concrete pile

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239559A (en) * 2014-10-03 2016-01-13 威海齐德新型建材有限公司 Common deformed steel bar tensioning device, prefabricated square pile and process for prefabricated square pile
CN104989106A (en) * 2015-07-08 2015-10-21 宿迁市保祥重工有限公司 Full prestress tension plate external member
CN106976156A (en) * 2016-01-18 2017-07-25 周兆弟 A kind of tensioning board component of concrete prefabricated pile die
CN106976156B (en) * 2016-01-18 2022-09-09 周兆弟 Tensioning plate assembly of concrete precast pile mould
CN107599158A (en) * 2017-09-26 2018-01-19 汤始建华建材(苏州)有限公司 A kind of process for prestressed component two directions tension
CN109176864A (en) * 2018-09-12 2019-01-11 安徽中源建设有限公司 A kind of equipment for fixed stretching reinforcing bar
CN113152449A (en) * 2021-04-16 2021-07-23 建华建材(中国)有限公司 End plate sheet, precast pile, tensioning structure and method, pile splicing structure and method

Also Published As

Publication number Publication date
CN104070603B (en) 2018-06-01

Similar Documents

Publication Publication Date Title
CN104070603A (en) Tensioning assembly for producing prestressed concrete pile without end plate
CN103114717B (en) A kind of both sides, shrinkage joint shear wall formwork system
JP2009174233A (en) Form device for rectangular column-shaped concrete structure, and construction method of rectangular-column-shaped concrete structure using it
CN203937017U (en) Stretch-draw assembly for the production of end-plate-free prestressed-concrete pile
CN104060607B (en) Prestress steel pipe pile and production method of prestress steel pipe pile
CN102689358B (en) Tensioning component and tensioning method of prestressed endless sheet pile and pile including component
CN202157329U (en) Branch mold device for occluded pile guide wall
JP2009280971A (en) Joint structure of precast concrete pole and precast concrete beam
CN206245471U (en) A kind of dismountable assembled steel reinforced concrete column splices node with post
CN209429527U (en) A kind of cast-in-place column cap template of assembled architecture and accurate positioning device
CN203230178U (en) Column formwork and column hoop
CN102677593A (en) End mould fixing structure using beam section longitudinal embedded bars and fixing method
CN204676885U (en) A kind of steel concrete column template fast pacifies the system of tearing open
KR100865133B1 (en) A fixing device, a pre-fabricating forms for concrete-structure and the construction method thereof
CN207714747U (en) A kind of reinforced column formwork reinforcement fixture
CN107893419A (en) A kind of clip pile device of municipal road construction vibratory piling machine
CN104196023A (en) Precast concrete tubular pile tip with mechanical connection device and using method of precast concrete tubular pile tip
CN206360354U (en) A kind of channel-section steel back cord
CN219255980U (en) Fixing device for prefabricated box girder inner mold
KR100695491B1 (en) A fixing device, a pre-fabricating forms for concrete-structure and the construction method thereof
CN211074042U (en) Prefabricated case roof beam centre form fixing device
CN104831921B (en) The circumferential band to pull bar is not required to for the square column template of fixing concrete
CN202787969U (en) Cylindrical template
KR101412678B1 (en) Carbon fiber reinforced precast concrete column and its manufacturing method
CN208792303U (en) A kind of support member of steel reinforcement cage

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211014

Address after: 222047 room 337, building 2, Jiangsu Avenue SME Park, Xuwei new area, Lianyun District, Lianyungang City, Jiangsu Province

Patentee after: Lianyungang Guquan new building materials Co.,Ltd.

Address before: 223800 No. 1, Xuanyuan Avenue, Sucheng Economic Development Zone, Suqian City, Jiangsu Province

Patentee before: JIANGSU GUFENG PILE GROUP Co.,Ltd.

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Tensioning components for producing prestressed concrete piles without end plates

Effective date of registration: 20230407

Granted publication date: 20180601

Pledgee: Bank of China Limited Lianyungang Economic and Technological Development Zone Branch

Pledgor: Lianyungang Guquan new building materials Co.,Ltd.

Registration number: Y2023980037576