CN104060614B - 一种先筑冠梁的支护桩施工方法 - Google Patents

一种先筑冠梁的支护桩施工方法 Download PDF

Info

Publication number
CN104060614B
CN104060614B CN201310089861.7A CN201310089861A CN104060614B CN 104060614 B CN104060614 B CN 104060614B CN 201310089861 A CN201310089861 A CN 201310089861A CN 104060614 B CN104060614 B CN 104060614B
Authority
CN
China
Prior art keywords
concrete
pile
hat beam
guan liang
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310089861.7A
Other languages
English (en)
Other versions
CN104060614A (zh
Inventor
黄凯
谢非
许海岩
李剑
叶志翔
邹树荣
王丽丽
王寒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201310089861.7A priority Critical patent/CN104060614B/zh
Publication of CN104060614A publication Critical patent/CN104060614A/zh
Application granted granted Critical
Publication of CN104060614B publication Critical patent/CN104060614B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Foundations (AREA)

Abstract

本发明涉及支护桩施工方法。一种先筑冠梁的支护桩施工方法,它包括:步骤一,在地面测量放线冠梁位置及标高,开挖冠梁基础沟槽后在梁底铺设砼垫层,在冠梁沟槽内放置圆柱状可拆卸活动钢模板;步骤二,测量定位高压旋喷桩位置,安装固定PVC管或钢管;步骤三,安装固定冠梁钢筋并做冠梁侧模,浇筑冠梁砼,冠梁成型拆模后,在冠梁预留洞口开始冲孔灌注桩施工,在浇筑桩混凝土时浇到冠梁底部位置停止浇筑,待混凝土凝固后,在冠梁的洞口内浇筑混凝土;步骤四,待灌注支护桩成桩后便可在冠梁上预留的PVC管进行高压旋喷桩施工。本发明能提高施工质量,加快施工进度,杜绝安全隐患。

Description

一种先筑冠梁的支护桩施工方法
技术领域
本发明涉及支护桩,尤其设计一种支护桩施工方法。
背景技术
常规方法灌注支护桩冠梁施工方法是:灌注支护桩冠梁施工是待灌注支护桩的混凝土强度达到设计强度的70%后进行施工,再对桩头进行破除,露出桩顶钢筋。在桩顶制作冠梁钢筋笼及预埋横支撑埋件,将桩顶钢筋嵌入冠梁钢筋笼内,最后支模浇筑砼,让冠梁与支护桩形成整体结构。并在支护桩外侧桩间做止水桩幕墙,最后安装横撑进行挖土施工。这种施工方法在支护桩内的基坑开挖后桩底参差不齐,支护桩位移后侵占结构、漏水等安全隐患的经常发生。
发明内容
本发明旨在克服现有技术的缺陷,提供一种先筑冠梁的支护桩施工方法。本发明能提高施工质量,加快施工进度,杜绝安全隐患。
为了解决上述技术问题,本发明一种先筑冠梁的支护桩施工方法,它包括:
步骤一,在地面测量放线冠梁位置及标高,开挖冠梁基础沟槽后在梁底铺设砼垫层,在冠梁沟槽内放置圆柱状可拆卸活动钢模板;
步骤二,测量定位高压旋喷桩位置,安装固定PVC管或钢管;
步骤三,安装固定冠梁钢筋并做冠梁侧模,浇筑冠梁砼,冠梁成型拆模后,在冠梁预留洞口开始冲孔灌注桩施工,在浇筑桩混凝土时浇到冠梁底部位置停止浇筑,待混凝土凝固后,在冠梁的洞口内浇筑比冠梁混凝土标号高一等级的混凝土;为提高桩体与冠梁整体强度,后浇混凝土内可加微膨胀剂;
步骤四,待灌注支护桩成桩后便可在冠梁上预留的PVC管进行高压旋喷桩施工。
所述一种先筑冠梁的支护桩施工方法,所述步骤一中圆柱型活动模板直径尺寸以支护桩直径为参数,比灌注支护桩直径超出5cm-10cm。
所述一种先筑冠梁的支护桩施工方法,所述PVC管或钢管的直径以高压旋喷桩机转杆直径为参数,比转杆直径超出2~3cm,数量1~3个。
所述一种先筑冠梁的支护桩施工方法,所述步骤三中的后浇混凝土内加有微膨胀剂。
本发明改变了以往先做支护桩再施工冠梁的施工方法,为先施工冠梁,在冠梁上先留置预留孔(直径大小以支护桩直径为参数),以先筑的冠梁预留的孔作为钢护筒,基本解决支护桩内的基坑开挖后桩的参差不齐,侵占结构、漏水等安全隐患的发生,最主要是提高支护桩施工质量,缩短支护桩施工工期,提高了经济和社会效益,节约了工程造价。
具体实施方式
下面结合具体实施方式对本发明作进一步的说明,
本发明做法为先施工冠梁再施工支护桩,首先在地面测量冠梁位置及标高,冠梁沟槽开挖后在梁底铺设砼垫层,沟槽内放置圆柱状可拆卸活动钢模板(圆柱活动模板直径尺寸以支护桩直径为参数,一般比支护桩直径超出5cm-10cm为宜),同时测量定位注浆加固位置,安装固定预留注浆管(PVC管/钢管直径以高压旋喷桩机转杆直径为参数,比转杆直径超出2~3cm为佳,数量1~3个,位置参照图纸要求),后安装固定冠梁钢筋并做冠梁侧模,浇筑冠梁砼。达到设计强度后拆除钢模板,在预留洞口处开始支护桩施工,在浇筑桩混凝土时浇到冠梁底部位置停止浇筑,待混凝土凝固后,在冠梁的洞口内浇筑比冠梁混凝土标号高一等级的混凝土,混凝土内加微膨胀剂。为提高桩体与冠梁整体强度,后浇混凝土内可加微膨胀剂。待灌注支护桩成桩后便可在冠梁上预留的PVC管/钢管进行止水桩(高压旋喷桩)施工。

Claims (4)

1.一种先筑冠梁的支护桩施工方法,其特征在于,它包括:
步骤一,在地面测量放线冠梁位置及标高,开挖冠梁基础沟槽后在梁底铺设砼垫层,在冠梁沟槽内放置圆柱状可拆卸活动钢模板;
步骤二,测量定位高压旋喷桩位置,安装固定PVC管或钢管;
步骤三,安装固定冠梁钢筋并做冠梁侧模,浇筑冠梁砼,冠梁成型拆模后,在冠梁沟槽内放置圆柱状可拆卸活动钢模板的预留洞口开始冲孔灌注桩施工,在浇筑桩混凝土时浇到冠梁底部位置停止浇筑,待混凝土凝固后,在冠梁的洞口内浇筑比冠梁混凝土标号高一等级的混凝土;
步骤四,待冲孔灌注桩成桩后便可在冠梁上预留的PVC管或钢管进行高压旋喷桩施工。
2.根据权利要求1所述一种先筑冠梁的支护桩施工方法,其特征在于,所述步骤一中圆柱状可拆卸活动钢模板直径尺寸以冲孔灌注桩直径为参数,比冲孔灌注桩直径大5cm-10cm。
3.根据权利要求1所述一种先筑冠梁的支护桩施工方法,其特征在于,所述PVC管或钢管的直径以高压旋喷桩机转杆直径为参数,比转杆直径大2~3cm,数量1~3个。
4.根据权利要求1所述一种先筑冠梁的支护桩施工方法,其特征在于,所述步骤三中,待混凝土凝固后,在冠梁的洞口内浇筑的混凝土内加有微膨胀剂。
CN201310089861.7A 2013-03-20 2013-03-20 一种先筑冠梁的支护桩施工方法 Active CN104060614B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310089861.7A CN104060614B (zh) 2013-03-20 2013-03-20 一种先筑冠梁的支护桩施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310089861.7A CN104060614B (zh) 2013-03-20 2013-03-20 一种先筑冠梁的支护桩施工方法

Publications (2)

Publication Number Publication Date
CN104060614A CN104060614A (zh) 2014-09-24
CN104060614B true CN104060614B (zh) 2016-03-30

Family

ID=51548528

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310089861.7A Active CN104060614B (zh) 2013-03-20 2013-03-20 一种先筑冠梁的支护桩施工方法

Country Status (1)

Country Link
CN (1) CN104060614B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105002891B (zh) * 2015-07-29 2017-08-25 北京城建北方建设有限责任公司 一种钻孔灌注桩免桩间土开挖施工方法
CN108086329A (zh) * 2017-11-30 2018-05-29 中国二十冶集团有限公司 代替冠梁受力钢筋和模板的钢模的制作方法
CN113047300A (zh) * 2021-03-22 2021-06-29 武汉建工集团股份有限公司 一种先筑冠梁的phc支护管桩施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2434172A (en) * 2006-01-13 2007-07-18 Mowlem Plc A retaining wall for an excavation
CN101328713A (zh) * 2008-07-18 2008-12-24 华丰建设股份有限公司 圆形深基坑支护的施工方法
CN101545260A (zh) * 2008-03-27 2009-09-30 中国二十冶建设有限公司 基坑群坑中坑搅拌桩套打钻孔灌注桩支护方法
CN101560770A (zh) * 2008-04-15 2009-10-21 广东省六建集团有限公司 一种新型深建筑基坑支护体系
CN102383443A (zh) * 2011-11-28 2012-03-21 大荣建设集团有限公司 基坑支护桩与地下室外墙之间的连接结构及施工方法
CN202627000U (zh) * 2012-05-31 2012-12-26 中科院广州化灌工程有限公司 一种拉锚式双排桩基坑支护结构

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2434172A (en) * 2006-01-13 2007-07-18 Mowlem Plc A retaining wall for an excavation
CN101545260A (zh) * 2008-03-27 2009-09-30 中国二十冶建设有限公司 基坑群坑中坑搅拌桩套打钻孔灌注桩支护方法
CN101560770A (zh) * 2008-04-15 2009-10-21 广东省六建集团有限公司 一种新型深建筑基坑支护体系
CN101328713A (zh) * 2008-07-18 2008-12-24 华丰建设股份有限公司 圆形深基坑支护的施工方法
CN102383443A (zh) * 2011-11-28 2012-03-21 大荣建设集团有限公司 基坑支护桩与地下室外墙之间的连接结构及施工方法
CN202627000U (zh) * 2012-05-31 2012-12-26 中科院广州化灌工程有限公司 一种拉锚式双排桩基坑支护结构

Also Published As

Publication number Publication date
CN104060614A (zh) 2014-09-24

Similar Documents

Publication Publication Date Title
CN111075454B (zh) 双连拱隧道五洞开挖方法
CN105064397B (zh) 一种在地铁区间盾构隧道基础上扩挖车站的明挖施工方法
CN205742213U (zh) 基坑支护结构
CN104264688A (zh) 人工挖孔变截面桩支护施工工艺
CN104912098A (zh) 一种深基坑支撑梁板与结构板结合施工方法
CN203905018U (zh) 组合双排桩结合斜向锚杆支护体系
CN105089670B (zh) 一种在并行区间盾构隧道基础上扩挖地铁车站施工方法
CN103184734A (zh) 一种植入注浆组合桩及施工方法
CN105274998A (zh) 装配式桩-板-锚-梁组合式岩基支护施工方法
CN105201516A (zh) 一种地铁车站主体结构及其四联拱pba暗挖施工方法
CN105256812A (zh) 基坑预制装配式混凝土支撑结构及其施工方法
CN105464685A (zh) 一种洞桩法暗挖隧道止水帷幕及其施工方法
CN104060614B (zh) 一种先筑冠梁的支护桩施工方法
CN103541371B (zh) 应用承托平台的热力管沟跨越预留地铁车站的施工方法
CN105839946A (zh) 砖混结构建筑物提升增层方法
CN107653889A (zh) 一种型钢压灌水泥土帷幕支护桩的施工方法
CN206752667U (zh) 一种地下室挡墙结构
CN104328790B (zh) 现浇喷射混凝土暗承台及暗地梁胎模
CN102561362A (zh) 一种强夯置换淤泥质土的基坑支护施工方法
CN205036380U (zh) 一种四联拱pba暗挖地铁车站主体结构
CN204311456U (zh) 基坑加固结构
CN102220764B (zh) 深基坑支护体系的施工方法
CN204059417U (zh) 一种全逆法墙梁抗渗节点结构
CN105350575A (zh) 一种地下连续墙的逆作施工方法
CN105421488A (zh) 地下复合围护体系中基础底板换撑的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant