CN104036667A - Method for realizing intelligent substation virtual terminal connection design training - Google Patents

Method for realizing intelligent substation virtual terminal connection design training Download PDF

Info

Publication number
CN104036667A
CN104036667A CN201410210499.9A CN201410210499A CN104036667A CN 104036667 A CN104036667 A CN 104036667A CN 201410210499 A CN201410210499 A CN 201410210499A CN 104036667 A CN104036667 A CN 104036667A
Authority
CN
China
Prior art keywords
training
design
intelligent substation
empty terminal
configuration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410210499.9A
Other languages
Chinese (zh)
Other versions
CN104036667B (en
Inventor
仇群辉
纪陵
裘愉涛
周卫国
方磊
江伟建
史建立
檀庭芳
俞兴坤
朱群
蔡溢行
费云中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Guodiannanzi Software Engineering Co Ltd
State Grid Corp of China SGCC
Jiaxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Nanjing SAC Automation Co Ltd
Zhoushan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Nanjing Guodiannanzi Software Engineering Co Ltd
State Grid Corp of China SGCC
Jiaxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Nanjing SAC Automation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Guodiannanzi Software Engineering Co Ltd, State Grid Corp of China SGCC, Jiaxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd, Nanjing SAC Automation Co Ltd filed Critical Nanjing Guodiannanzi Software Engineering Co Ltd
Priority to CN201410210499.9A priority Critical patent/CN104036667B/en
Publication of CN104036667A publication Critical patent/CN104036667A/en
Application granted granted Critical
Publication of CN104036667B publication Critical patent/CN104036667B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Instructional Devices (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A method for realizing intelligent substation virtual terminal connection design training is provided. The method includes the following steps that: a) file libraries of three types are added in an SCD system configurator, and the three types of file libraries are correspondingly used for storing benchmark configuration files containing correct virtual terminal connection configuration, for storing training project files which are used for performing virtual terminal connection design training for students, and for storing training submission files which are formed after students accomplish virtual terminal connection configuration; b) training teachers accomplish configuration of the benchmark configuration files of each training project and construction of the training project files through intelligent substation virtual terminal design training teacher man-machine interfaces; c) through intelligent substation virtual terminal design training student man-machine interactive interfaces, trained students select proper training projects, accomplish intelligent substation virtual terminal design training operation, form the training submission files and store the training submission files in the file library; d) an intelligent substation virtual terminal design configuration verification module is additionally arranged in the SCD system configurator, so as to check virtual terminal connection definition contents in benchmark training files and training submission files which are corresponding to the same training projects.

Description

A kind of virtual terminals of intelligent substation connects the implementation method of design training
Technical field
The present invention relates to a kind of technical method of intelligent substation design training, relate in particular to the implementation method that the empty terminal of a kind of secondary equipment of intelligent converting station connects design training, belong to lation training course for power system field.
Background technology
The cable of tradition Substation secondary circuit and secondary device external terminal is connected design and conventionally utilizes AutoCAD instrument to realize, and by power construction personnel, according to design drawing, is carried out the connection construction of on-the-spot secondary cable.Compare with traditional transformer station, the secondary circuit of intelligent substation is connected and has a very large change with arrangement terminal, the empty loop of intelligent substation digitizing has replaced the secondary circuit of traditional transformer station, and the empty terminal of secondary equipment of intelligent converting station has replaced the external physical terminal of traditional substation secondary device.By completing the connection of the empty terminal in each secondary device of intelligent substation CID file, configure, can complete design and configuration that intelligent substation secondary circuit is connected with the empty terminal of secondary device.Connection design and the configuration effort of the empty terminal of secondary equipment of intelligent converting station all utilize SCD system configuration device finally to complete substantially at present.
At present, the substation secondary designer of Electric Power Design Institute is also unfamiliar with for the design and the configuration that utilize SCD system configuration device to complete the empty terminal of secondary equipment of intelligent converting station very much, substantially the secondary circuit that still adopts the Design Mode of traditional transformer station to complete substation secondary device connects design, and configured by the connection that integrated manufacturer completes the empty terminal of secondary equipment of intelligent converting station, the Design Mode that the secondary circuit of this intelligent substation of present stage is connected with empty terminal greatly reduces the work efficiency of intelligent substation secondary circuit and empty terminal design, and the definition mode that is connected the connection design of design and the empty terminal of secondary equipment of intelligent converting station due to traditional secondary loop with terminal exists difference, this Design Mode connects design also can to the empty terminal of secondary device of intelligent substation and bring certain hidden danger, therefore, urgent need will strengthen the substation secondary designer of Electric Power Design Institute directly to carry out based on SCD system configuration device the training of the empty terminal design of secondary equipment of intelligent converting station and configuration technical ability, allow the substation secondary designer grasp of Electric Power Design Institute directly complete the connection design of intelligent substation Quadratic Imaginary loop and empty terminal and the using method of configuration by SCD system configuration device, thereby effectively promote the work efficiency that the empty terminal of secondary equipment of intelligent converting station connects design and configuration.
Summary of the invention
The object of the invention is to overcome the deficiency that prior art exists, and provide a kind of, based on SCD system configuration device, the substation secondary designer of Electric Power Design Institute is carried out to the method that intelligent substation secondary circuit is connected design with the empty terminal of secondary device and configures training, utilizing the method to realize uses SCD system configuration device directly to carry out the connection design of intelligent substation Quadratic Imaginary loop and empty terminal and the training of configuration technical ability to the substation secondary designer of Electric Power Design Institute, thereby the substation secondary designer who makes Electric Power Design Institute grasps the using method that directly completes intelligent substation Quadratic Imaginary loop and the empty terminal design of secondary device and configuration by SCD system configuration device, the substation secondary designer who promotes Electric Power Design Institute carries out the empty terminal of secondary equipment of intelligent converting station based on SCD system configuration device and connects design and configuration technical ability, also further improve the work efficiency that the empty terminal of secondary equipment of intelligent converting station connects design and configuration simultaneously, reduced by system integrator and carried out again the link that the empty terminal of secondary device connects configuration, improved the correctness that the empty terminal of secondary equipment of intelligent converting station connects design and configures.
For achieving the above object, realization carries out to the substation secondary designer of Electric Power Design Institute the training that virtual terminals of intelligent substation connects design, the present invention is achieved through the following technical solutions: a kind of implementation method of virtual terminals of intelligent substation design training, and this implementation method comprises the following steps:
A) at SCD system configuration device, increase the library of three types, the library of three types is respectively benchmark library, training documentation storehouse and the storehouse of presenting a paper, the library of this three types comprises to being applied to deposit the baseline configuration file that correct empty terminal connects configuration respectively, for depositing to student, carries out training project file that empty terminal connects design training and completes empty terminal and be connected the training forming after design configurations and present a paper for depositing student;
B) training teacher, by the virtual terminals of intelligent substation design training teacher human-computer interaction interface providing, completes the configuration of baseline configuration file and the establishment of training project file of each training project;
The virtual terminals of intelligent substation design trainee human-computer interaction interface of c trainee by providing, chooses appropriate training project, completes virtual terminals of intelligent substation design training operation, and forms training and present a paper, and is saved in and presents a paper in storehouse;
D) by increasing virtual terminals of intelligent substation design configurations at SCD system configuration device, check module, the benchmark training documentation of realizing corresponding identical training project and the training middle empty terminal of presenting a paper is connected the check that defines content, by increase virtual terminals of intelligent substation at SCD system configuration device, connect design visual presentation module simultaneously, realize the visual presentation that virtual terminals of intelligent substation connects, thereby the empty terminal that student is carried out connects design and visual guidance and displaying are carried out in configuration.
Described step a), choose in advance several for carrying out the typical transforming plant primary wiring of virtual terminals of intelligent substation connection design training and corresponding typical secondary device configuration thereof, first in the increase of SCD system configuration device, comprise the benchmark library that the empty terminal of typical transformer station connects configuration, by training teacher, according to typical Substation secondary circuit, design the correct empty terminal of each secondary device and connected configuration, and formed the baseline configuration file of empty terminal design training; Then on SCD system configuration device, increase by trainee and carry out the training documentation storehouse that empty terminal connects design training, the training project file giveing training for student is kept to training documentation storehouse, student from training documentation storehouse, choose again by teacher, provided in advance for carrying out empty terminal, connect the training project file of design training use, then student is based on SCD system configuration device, complete the operation that the empty terminal of secondary device connects design and configuration, and form training present a paper, be kept at and present a paper in storehouse.
It is that training project file prefix name by identical is mated that baseline configuration file of the present invention, training project file and training are presented a paper, and by different file suffixes names, carries out the differentiation of type, finally on SCD system configuration device, increasing empty terminal connects relatively and visual presentation function, by thering is the baseline configuration file of identical training project file prefix name and training, present a paper and compare, and according to the modeling standard of < < IEC 61850 engineering relay protection application model > >, to thering is the definition of GOOSE line or the definition of SV line that under identical IED Name, the Inputs in LLNO logic node partly defines in two files, compare, find out difference wherein, and training under identical IED is presented a paper in the definition of middle GOOSE line or the definition of SV line and baseline configuration file to GOOSE line defines or SV line defines inconsistent entry and identifies, so that can be by visual mode, show clearly in empty terminal connection design to student and connect wrong empty terminal, realization connects visual guidance and the training of design to virtual terminals of intelligent substation.
The invention has the beneficial effects as follows: it can effectively allow the substation secondary designer of Electric Power Design Institute grasp fast the using method that completes secondary equipment of intelligent converting station empty terminal connection design and configuration by SCD system configuration device, the substation secondary designer who has promoted Electric Power Design Institute directly carries out by system configuration device ability and the level that empty terminal connects design, so that the substation secondary designer that can realize as early as possible by Electric Power Design Institute directly carries out Substation secondary circuit design and the transformation that is connected the working method of configuration based on SCD system configuration device, improve the empty loop of intelligent substation electrical secondary system is connected design and configuration work efficiency with empty terminal, the designer who simultaneously also adapts to intelligent substation electrical secondary system new design pattern for cultivating tempers troop.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of implementation method of the present invention;
Fig. 2 is file structure schematic diagram of the present invention.
Embodiment
Below in conjunction with accompanying drawing, the present invention is done to detailed introduction: shown in Fig. 1, the implementation method of a kind of virtual terminals of intelligent substation design training of the present invention, this implementation method comprises the following steps:
A) at SCD system configuration device, increase the library of three types, the library of three types is respectively benchmark library, training documentation storehouse and the storehouse of presenting a paper, the library of this three types comprises to being applied to deposit the baseline configuration file that correct empty terminal connects configuration respectively, for depositing to student, carries out training project file that empty terminal connects design training and completes empty terminal and be connected the training forming after design configurations and present a paper for depositing student;
B) training teacher, by the virtual terminals of intelligent substation design training teacher human-computer interaction interface providing, completes the configuration of baseline configuration file and the establishment of training project file of each training project;
The virtual terminals of intelligent substation design trainee human-computer interaction interface of c trainee by providing, chooses appropriate training project, completes virtual terminals of intelligent substation design training operation, and forms training and present a paper, and is saved in and presents a paper in storehouse;
D) by increasing virtual terminals of intelligent substation design configurations at SCD system configuration device, check module, the benchmark training documentation of realizing corresponding identical training project and the training middle empty terminal of presenting a paper is connected the check that defines content, by increase virtual terminals of intelligent substation at SCD system configuration device, connect design visual presentation module simultaneously, realize the visual presentation that virtual terminals of intelligent substation connects, thereby the empty terminal that student is carried out connects design and visual guidance and displaying are carried out in configuration.
Described step a), choose in advance several for carrying out the typical transforming plant primary wiring of virtual terminals of intelligent substation connection design training and corresponding typical secondary device configuration thereof, first in the increase of SCD system configuration device, comprise the benchmark library that the empty terminal of typical transformer station connects configuration, by training teacher, according to typical Substation secondary circuit, design the correct empty terminal of each secondary device and connected configuration, and formed the baseline configuration file of empty terminal design training; Then on SCD system configuration device, increase by trainee and carry out the training documentation storehouse that empty terminal connects design training, the training project file giveing training for student is kept to training documentation storehouse, student from training documentation storehouse, choose again by teacher, provided in advance for carrying out empty terminal, connect the training project file of design training use, then student is based on SCD system configuration device, complete the operation that the empty terminal of secondary device connects design and configuration, and form training present a paper, be kept at and present a paper in storehouse.
Figure 2 shows that the file structure schematic diagram of the three types file that the present invention generates in described virtual terminals of intelligent substation connection design training implementation method, wherein: baseline configuration file, training project file and training are presented a paper and mated by identical training project file prefix name, and by different file suffixes names, carry out the differentiation of type.The filename form of three types as shown in the figure, the file content form of three types should meet the code requirement of < < IEC 61850 engineering relay protection application model > >, in the file of every type, all by the Inputs in LLN0 logic node under IED Name, partly define the empty terminal line of GOOSE or the empty terminal line of SV, being defined in every ExtRef that each empty terminal connects reflects, the output signal information that wherein in baseline configuration file, ExtRef item comprises the inner empty terminal input signal of this logical device and external device (ED), inner empty terminal is corresponding one by one with the output signal of external device (ED), to reflect the annexation of the empty terminal of this equipment and external unit, in training project file, ExtRef item only comprises the inner empty terminal input signal information of this logical device, the output signal information that does not comprise connected outside secondary device, so that completed the connection of the empty terminal of this part defines by trainee, the training middle ExtRef item of presenting a paper comprises by student and completes the output signal information that empty terminal connects the inner empty terminal input signal of this logical device and external device (ED) after configuration, in presenting a paper by the baseline configuration file to identical training project and training, having the definition of GOOSE line or the definition of SV line that under identical IED Name, the Inputs in LLNO logic node partly defines compares, find out difference wherein, and training under identical IED is presented a paper in the definition of middle GOOSE line or the definition of SV line and baseline configuration file to GOOSE line defines or SV line defines inconsistent item entries and identifies, so that can be by visual mode, show clearly in empty terminal connection design to student and connect wrong empty terminal, realization connects visual guidance and the training of design to virtual terminals of intelligent substation.
The present invention can effectively allow the substation secondary designer of Electric Power Design Institute grasp fast by SCD system configuration device and complete the using method that the empty terminal of secondary equipment of intelligent converting station connects design and configuration, the substation secondary designer who has promoted Electric Power Design Institute directly carries out by system configuration device ability and the level that empty terminal connects design, so that the substation secondary designer that can realize as early as possible by Electric Power Design Institute directly carries out Substation secondary circuit design and the transformation that is connected the working method of configuration based on SCD system configuration device, improve the empty loop of intelligent substation electrical secondary system is connected design and configuration work efficiency with empty terminal, the designer who simultaneously also adapts to intelligent substation electrical secondary system new design pattern for cultivating tempers troop.

Claims (3)

1. the implementation method that virtual terminals of intelligent substation design is trained, is characterized in that this implementation method comprises the following steps:
A) at SCD system configuration device, increase the library of three types, the library of three types is respectively benchmark library, training documentation storehouse and the storehouse of presenting a paper, the library of this three types comprises to being applied to deposit the baseline configuration file that correct empty terminal connects configuration respectively, for depositing to student, carries out training project file that empty terminal connects design training and completes empty terminal and be connected the training forming after design configurations and present a paper for depositing student;
B) training teacher, by the virtual terminals of intelligent substation design training teacher human-computer interaction interface providing, completes the configuration of baseline configuration file and the establishment of training project file of each training project;
The virtual terminals of intelligent substation design trainee human-computer interaction interface of c trainee by providing, chooses appropriate training project, completes virtual terminals of intelligent substation design training operation, and forms training and present a paper, and is saved in and presents a paper in storehouse;
D) by increasing virtual terminals of intelligent substation design configurations at SCD system configuration device, check module, the benchmark training documentation of realizing corresponding identical training project and the training middle empty terminal of presenting a paper is connected the check that defines content, by increase virtual terminals of intelligent substation at SCD system configuration device, connect design visual presentation module simultaneously, realize the visual presentation that virtual terminals of intelligent substation connects, thereby the empty terminal that student is carried out connects design and visual guidance and displaying are carried out in configuration.
2. the implementation method that virtual terminals of intelligent substation design according to claim 1 is trained, is characterized in that in described step:
Step a), choose in advance several for carrying out the typical transforming plant primary wiring of virtual terminals of intelligent substation connection design training and corresponding typical secondary device configuration thereof, first in the increase of SCD system configuration device, comprise the benchmark library that the empty terminal of typical transformer station connects configuration, by training teacher, according to typical Substation secondary circuit, design the correct empty terminal of each secondary device and connected configuration, and formed the baseline configuration file of empty terminal design training; Then on SCD system configuration device, increase by trainee and carry out the training documentation storehouse that empty terminal connects design training, the training project file giveing training for student is kept to training documentation storehouse, student from training documentation storehouse, choose again by teacher, provided in advance for carrying out empty terminal, connect the training project file of design training use, then student is based on SCD system configuration device, complete the operation that the empty terminal of secondary device connects design and configuration, and form training present a paper, be kept at and present a paper in storehouse.
3. the implementation method that virtual terminals of intelligent substation design according to claim 1 and 2 is trained, it is characterized in that it is that training project file prefix name by identical is mated that described baseline configuration file, training project file and training are presented a paper, and by different file suffixes names, carry out the differentiation of type, finally on SCD system configuration device, increasing empty terminal connects relatively and visual presentation function, by thering is the baseline configuration file of identical training project file prefix name and training, present a paper and compare, and according to the modeling standard of < < IEC 61850 engineering relay protection application model > >, to thering is the definition of GOOSE line or the definition of SV line that under identical IED Name, the Inputs in LLNO logic node partly defines in two files, compare, find out difference wherein, and training under identical IED is presented a paper in the definition of middle GOOSE line or the definition of SV line and baseline configuration file to GOOSE line defines or SV line defines inconsistent entry and identifies, so that can be by visual mode, show clearly in empty terminal connection design to student and connect wrong empty terminal, realization connects visual guidance and the training of design to virtual terminals of intelligent substation.
CN201410210499.9A 2014-05-19 2014-05-19 A kind of virtual terminals of intelligent substation connects the implementation method of design training Active CN104036667B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410210499.9A CN104036667B (en) 2014-05-19 2014-05-19 A kind of virtual terminals of intelligent substation connects the implementation method of design training

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410210499.9A CN104036667B (en) 2014-05-19 2014-05-19 A kind of virtual terminals of intelligent substation connects the implementation method of design training

Publications (2)

Publication Number Publication Date
CN104036667A true CN104036667A (en) 2014-09-10
CN104036667B CN104036667B (en) 2016-08-24

Family

ID=51467420

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410210499.9A Active CN104036667B (en) 2014-05-19 2014-05-19 A kind of virtual terminals of intelligent substation connects the implementation method of design training

Country Status (1)

Country Link
CN (1) CN104036667B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106199323A (en) * 2016-07-27 2016-12-07 国网河北省电力公司电力科学研究院 A kind of virtual terminals of intelligent substation connects correctness method of discrimination
CN107481598A (en) * 2017-08-08 2017-12-15 国网四川省电力公司电力科学研究院 A kind of emulation training platform of intelligent substation
CN107741952A (en) * 2017-09-12 2018-02-27 国网江苏省电力公司技能培训中心 The auto-scoring and examination system compared based on intelligent substation SCD configuration files
CN109884422A (en) * 2019-01-22 2019-06-14 许昌许继软件技术有限公司 A kind of site protective device loading tests method and apparatus

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102291277A (en) * 2011-08-09 2011-12-21 上海思源弘瑞自动化有限公司 Automatic test system and method for intelligent substation spacing apparatus
CN102647025A (en) * 2012-04-13 2012-08-22 广东省电力调度中心 Method for realizing plug and play of protective device based on center server manner
CN102801213A (en) * 2012-08-10 2012-11-28 广东省电力调度中心 Integrated method and integrated device of SCD (System Configuration Document) of transformer station
CN103441571A (en) * 2013-06-18 2013-12-11 国家电网公司 Integrated monitoring system information platform for transformer substation
CN103439592A (en) * 2013-06-27 2013-12-11 国家电网公司 Method for intelligently testing intelligent substation on site
CN103647717A (en) * 2013-11-26 2014-03-19 华南理工大学 Message accurate recognition-based substation communication network deterministic path switching method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102291277A (en) * 2011-08-09 2011-12-21 上海思源弘瑞自动化有限公司 Automatic test system and method for intelligent substation spacing apparatus
CN102647025A (en) * 2012-04-13 2012-08-22 广东省电力调度中心 Method for realizing plug and play of protective device based on center server manner
CN102801213A (en) * 2012-08-10 2012-11-28 广东省电力调度中心 Integrated method and integrated device of SCD (System Configuration Document) of transformer station
CN103441571A (en) * 2013-06-18 2013-12-11 国家电网公司 Integrated monitoring system information platform for transformer substation
CN103439592A (en) * 2013-06-27 2013-12-11 国家电网公司 Method for intelligently testing intelligent substation on site
CN103647717A (en) * 2013-11-26 2014-03-19 华南理工大学 Message accurate recognition-based substation communication network deterministic path switching method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106199323A (en) * 2016-07-27 2016-12-07 国网河北省电力公司电力科学研究院 A kind of virtual terminals of intelligent substation connects correctness method of discrimination
CN107481598A (en) * 2017-08-08 2017-12-15 国网四川省电力公司电力科学研究院 A kind of emulation training platform of intelligent substation
CN107741952A (en) * 2017-09-12 2018-02-27 国网江苏省电力公司技能培训中心 The auto-scoring and examination system compared based on intelligent substation SCD configuration files
CN107741952B (en) * 2017-09-12 2021-05-25 国网江苏省电力公司技能培训中心 Automatic scoring and examination system based on SCD configuration file comparison of intelligent substation
CN109884422A (en) * 2019-01-22 2019-06-14 许昌许继软件技术有限公司 A kind of site protective device loading tests method and apparatus
CN109884422B (en) * 2019-01-22 2020-12-11 许昌许继软件技术有限公司 On-site protection device load testing method and device

Also Published As

Publication number Publication date
CN104036667B (en) 2016-08-24

Similar Documents

Publication Publication Date Title
CN104008223B (en) Graphical expressing method for connection of virtual terminals of secondary system of intelligent substation
CN102622463B (en) Drawing-model uniformity based method for automatic check of design drawings
CN110852023B (en) Automatic generation method and device for primary main wiring diagram of intelligent substation
CN110535236B (en) Intelligent substation bay level simulation self-acceptance system and method
CN103593809A (en) Intelligent operation-ticket semanteme verification method of automatic power dispatching system
CN107741952B (en) Automatic scoring and examination system based on SCD configuration file comparison of intelligent substation
CN103235223B (en) A kind of micro-capacitance sensor experimental test platform based on RTDS
CN103902763A (en) Automatic matching method of virtual terminals of cross-interval device of intelligent substation
CN104036667A (en) Method for realizing intelligent substation virtual terminal connection design training
CN104007978A (en) Intelligent substation secondary equipment logic emulation system
CN102779156A (en) Configuration method for database of communication device in digital substation
CN203178388U (en) Micro-grid test platform based on RTDS (Real Time Digital Simulator)
CN110110454B (en) Circuit diagram automatic conversion system and method thereof
CN106485599A (en) A kind of visual presentation method of intelligent substation SSD configuration file
CN106066888A (en) The source database building method of transformer station secondary system and deficiency and excess corresponding method
CN103677815A (en) Method for generating program to automatically test electrical performance of spacecraft low-frequency cable
CN110611312B (en) On-line simulation system and method for panoramic data of substation bay level
CN102156795B (en) Simulation information system of digital transformer station based on transformer station configuration description file
CN105606947A (en) Fast secondary cable loop line checking instrument
CN108492660A (en) Substation&#39;s peace arranges analogy method, device and system
CN106301976A (en) A kind of intelligent substation schedule information automated testing method
CN203951261U (en) switchyard fault simulator
CN106647419B (en) The matrix form mapping method of protective relaying device hardware corridor
CN203480745U (en) Commercial power complementary type photovoltaic generation practical training device
CN109521300A (en) A kind of test method of multifunctional digital tester

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: JIAXING POWER SUPPLY COMPANY, STATE GRID ZHEJIANG

Free format text: FORMER OWNER: JIAXING POWER SUPPLY COMPANY, STATE GRID ZHEJIANG ELECTRIC POWER COMPANY NANJING GUODIAN NANJING AUTOMATION SOFTWARE ENGINEERING CO., LTD. NANJING GUODIAN NANJING-AUTOMATION POWER GRID AUTOMATION CO., LTD.

Effective date: 20140910

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Chou Qunhui

Inventor after: Zhu Qun

Inventor after: Cai Yixing

Inventor after: Fei Yunzhong

Inventor after: Yan Yan

Inventor after: Qian Haidong

Inventor after: Luo Shuojun

Inventor after: Ji Ling

Inventor after: Qiu Yutao

Inventor after: Zhou Weiguo

Inventor after: Fang Lei

Inventor after: Jiang Weijian

Inventor after: Shi Jianli

Inventor after: Tan Tingfang

Inventor after: Yu Xingkun

Inventor before: Chou Qunhui

Inventor before: Zhu Qun

Inventor before: Cai Yixing

Inventor before: Fei Yunzhong

Inventor before: Ji Ling

Inventor before: Qiu Yutao

Inventor before: Zhou Weiguo

Inventor before: Fang Lei

Inventor before: Jiang Weijian

Inventor before: Shi Jianli

Inventor before: Tan Tingfang

Inventor before: Yu Xingkun

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: CHOU QUNHUI JI LING QIU YUTAO ZHOU WEIGUO FANG LEI JIANG WEIJIAN SHI JIANLI TAN TINGFANG YU XINGKUN ZHU QUN CAI YIXING FEI YUNZHONG TO: CHOU QUNHUI JI LING QIU YUTAO ZHOU WEIGUO FANG LEI JIANG WEIJIAN SHI JIANLI TAN TINGFANG YU XINGKUN ZHU QUN CAI YIXING FEI YUNZHONG YAN YAN QIAN HAIDONG LUO SHUOJUN

TA01 Transfer of patent application right

Effective date of registration: 20140910

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: Jiaxing Power Supply Company, State Grid Zhejiang Electronic Power Company

Applicant after: Nanjing Guodiannanzi Software Engineering Co., Ltd

Applicant after: Nanjing Guodian Nanjing Grid Automation Co., Ltd.

Applicant after: ZHOUSHAN POWER SUPPLY COMPANY OF STATE GRID ZHEJIANG ELECTRIC POWER COMPANY

Address before: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant before: State Grid Corporation of China

Applicant before: Jiaxing Power Supply Company, State Grid Zhejiang Electronic Power Company

Applicant before: Nanjing Guodiannanzi Software Engineering Co., Ltd

Applicant before: Nanjing Guodian Nanjing Grid Automation Co., Ltd.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant