CN104018657A - Method for constructing high and large cornice through horizontal sliding platform - Google Patents

Method for constructing high and large cornice through horizontal sliding platform Download PDF

Info

Publication number
CN104018657A
CN104018657A CN201410245625.4A CN201410245625A CN104018657A CN 104018657 A CN104018657 A CN 104018657A CN 201410245625 A CN201410245625 A CN 201410245625A CN 104018657 A CN104018657 A CN 104018657A
Authority
CN
China
Prior art keywords
horizontal sliding
sliding platform
tall
big
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410245625.4A
Other languages
Chinese (zh)
Inventor
刘志宏
王彦理
王建宏
程勇俊
杨志军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG DONGYANG THIRD CONSTRUCTION ENGINEERING Co Ltd
Original Assignee
ZHEJIANG DONGYANG THIRD CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG DONGYANG THIRD CONSTRUCTION ENGINEERING Co Ltd filed Critical ZHEJIANG DONGYANG THIRD CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201410245625.4A priority Critical patent/CN104018657A/en
Publication of CN104018657A publication Critical patent/CN104018657A/en
Pending legal-status Critical Current

Links

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The invention belongs to the field of building construction, and relates to a cornice construction method which is particularly applicable to construction on a cornice which is large in ground clearance and overhanging width, in particular to a method for constructing a high and large cornice through a horizontal sliding platform. According to the method, the horizontal sliding platform is arranged on a main stress structure of the high and large cornice, and construction on the high and large cornice is finished through the horizontal sliding platform. The method has the advantages that safety and reliability are achieved, operation is flexible, assembly and disassembly are convenient and fast, construction cost is low, and the project period can be shortened.

Description

A kind of tall and big method of cornicing of horizontal sliding platform construction that adopts
Technical field
A kind of method that the present invention relates to construction of cornicing, is particularly useful for the construction of cornicing that terrain clearance is high, the width of encorbelmenting is large, belongs to the realm of building construction.
Background technology
For highlighting facade effect, a lot of building engineerings are designed with tall and big cornicing.In tall and big when construction of cornicing, conventionally need below tall and big cornicing, set up console mode or overhanging type operating platform.Console mode operating platform is set up cost, and affected by terrain clearance larger, scaffolding height is higher, and to set up cost larger, set up and the dismounting cycle is long, workload is large, and the construction of cornicing, platform Demolition Construction progress directly impact set up the construction speed of the subsequent projects such as region decorating inner and external walls, surface line laying, hardened ground.Overhanging type operating platform must depend on major structure of construction supporting construction is set, and has certain use limitation, and supporting construction adopts shaped steel or steel pipe manufacturing more, be subject to the quality of connection such as Site Welding to affect reliability low, assembled cumbersome with dismounting, hanging operation amount is many, and security risk is large.
Summary of the invention
Object of the present invention is exactly for fear of the weak point in background technology, provide a kind of safe and reliable, construction cost is low, the tall and big construction method of cornicing of easy construction, short construction period.
In order to achieve the above object, the present invention adopts following technical scheme: by horizontal sliding platform being set in the tall and big main stress structure of cornicing, utilize horizontal sliding platform to complete the tall and big construction of cornicing.
Described horizontal sliding platform can be by the tall and big side plate inclination angle of cornicing, choose width, upper and lower cornice discrepancy in elevation design team is synthetic and the tall and big C type structure that cornices and adapt.
Described horizontal sliding platform slides onto after assigned address, and top is fixed with overturn-preventing and horizontal sliding device, and bottom is fixed with anti-swing device.
A kind of tall and big method of cornicing of horizontal sliding platform construction has the following advantages:
1, in horizontal sliding platform focus point drops on and cornices, stressed clear and definite, reliable in structure.
2, horizontal sliding platform can be along sliding rail horizontal sliding, and flexible operation is convenient to the tall and big construction of cornicing.
3, horizontal sliding platform is installed with demolishing process easy, quick.
4, exempt scaffold etc. and set up and demolition cost, the tall and big construction cost that cornices is obviously reduced.
5, the tall and big construction of cornicing does not affect other project construction of below that cornices, and is conducive to the reduction of erection time.
6, horizontal sliding platform slides onto after assigned address, and top is fixed with overturn-preventing and horizontal sliding device, and bottom is fixed with anti-swing device, job execution safety on platform.
Accompanying drawing explanation
Fig. 1 is that horizontal sliding platform slides onto the tall and big fixedly generalized section of assigned address of cornicing;
Wherein: 1, horizontal sliding platform; 2, sliding rail; 3, horizontally tracting device; 4, anti-swing device; 5, overturn-preventing and horizontal sliding device; 6, tall and big cornicing.
The specific embodiment
Below by embodiment, and by reference to the accompanying drawings, technical scheme of the present invention is done further and illustrated.
Embodiment: a kind of tall and big method of cornicing of horizontal sliding platform construction.
In conjunction with tall and big building size and the design feature of cornicing, by horizontal sliding platform being set in the tall and big main stress structure of cornicing, utilize horizontal sliding platform to complete the tall and big construction of cornicing.The method comprises the following steps:
A. according to Force Calculation result, design and fabrication horizontal sliding platform;
B., horizontal sliding platform sliding rail is installed on tall and big cornice structure;
C. lift horizontal sliding platform, horizontal sliding platform is mounted on the sliding rail being arranged on tall and big cornice structure;
D., horizontal sliding draw-gear is installed;
E. open horizontal sliding draw-gear horizontal sliding platform is moved to assigned address fixing along sliding rail;
F. the tall and big construction of cornicing is removed to horizontal sliding platform to the tall and big events in operation of cornicing in construction level sliding platform region with material and facility;
G. removing horizontal sliding platform fixes;
H. continuously e, f, g step, the construction of cornicing until tall and big is complete;
I. utilize the hanging devices such as tower crane, mobile crane that the lifting of horizontal sliding platform is removed to ground.
During construction, horizontal sliding platform can be by the tall and big side plate inclination angle of cornicing, choose width, upper and lower cornice discrepancy in elevation design team is synthetic and the tall and big C type structure that cornices and adapt.Horizontal sliding platform slides onto after assigned address, and top is fixed with overturn-preventing and horizontal sliding device, and bottom is fixed with anti-swing device.
It is to be understood that: although above-mentioned example is to the present invention's detailed explanation of contrasting; but these explanations, just to simple declaration of the present invention, rather than limitation of the present invention; any innovation and creation that do not exceed in connotation of the present invention, all fall within the scope of protection of the present invention.

Claims (3)

1. adopt the tall and big method of cornicing of horizontal sliding platform construction, it is characterized in that, by horizontal sliding platform being set in the tall and big main stress structure of cornicing, utilize horizontal sliding platform to complete the tall and big construction of cornicing.
2. according to a kind of tall and big method of cornicing of horizontal sliding platform construction described in claims 1, it is characterized in that, described horizontal sliding platform can be by the tall and big side plate inclination angle of cornicing, choose width, upper and lower cornice discrepancy in elevation design team is synthetic and the tall and big C type structure that cornices and adapt.
3. according to a kind of tall and big method of cornicing of horizontal sliding platform construction described in power claim 1, it is characterized in that, described horizontal sliding platform slides onto after assigned address, and top is fixed with overturn-preventing and horizontal sliding device, and bottom is fixed with anti-swing device.
CN201410245625.4A 2014-05-30 2014-05-30 Method for constructing high and large cornice through horizontal sliding platform Pending CN104018657A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410245625.4A CN104018657A (en) 2014-05-30 2014-05-30 Method for constructing high and large cornice through horizontal sliding platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410245625.4A CN104018657A (en) 2014-05-30 2014-05-30 Method for constructing high and large cornice through horizontal sliding platform

Publications (1)

Publication Number Publication Date
CN104018657A true CN104018657A (en) 2014-09-03

Family

ID=51435623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410245625.4A Pending CN104018657A (en) 2014-05-30 2014-05-30 Method for constructing high and large cornice through horizontal sliding platform

Country Status (1)

Country Link
CN (1) CN104018657A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105197845A (en) * 2015-09-19 2015-12-30 山东德建集团有限公司 Lifting hanging type hanging basket roof cornice construction device and use method
CN110905181A (en) * 2019-11-07 2020-03-24 广西建工集团第五建筑工程有限责任公司 7-shaped large-angle inner-inclined high-altitude sliding operation platform and construction method thereof
CN114809574A (en) * 2022-05-16 2022-07-29 北京江河幕墙***工程有限公司 Construction device and construction method for building with oblique cornice structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09256625A (en) * 1996-03-25 1997-09-30 Nihon Bisoh Co Ltd Hangingly supporting device of external wall working machine for building
US20030079940A1 (en) * 1997-05-16 2003-05-01 Preston John Clement Partly retractable construction platform
CN201158933Y (en) * 2007-12-27 2008-12-03 上海市第七建筑有限公司 High-rise maintaining scaffold device with extruding structure
CN201972084U (en) * 2010-12-28 2011-09-14 海波重型工程科技股份有限公司 Self-lock hanging slide type operating platform for construction of viaduct overhanging arm
CN102877637A (en) * 2012-09-29 2013-01-16 深圳市建工集团股份有限公司 Method for implementing operating platform in bottom wall construction of cantilever beam
CN202731272U (en) * 2012-07-22 2013-02-13 中国水利水电第三工程局有限公司 Suspended construction assisting trolley
CN103114712A (en) * 2013-03-04 2013-05-22 温州建设集团有限公司 Buckle steel platform support system and construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09256625A (en) * 1996-03-25 1997-09-30 Nihon Bisoh Co Ltd Hangingly supporting device of external wall working machine for building
US20030079940A1 (en) * 1997-05-16 2003-05-01 Preston John Clement Partly retractable construction platform
CN201158933Y (en) * 2007-12-27 2008-12-03 上海市第七建筑有限公司 High-rise maintaining scaffold device with extruding structure
CN201972084U (en) * 2010-12-28 2011-09-14 海波重型工程科技股份有限公司 Self-lock hanging slide type operating platform for construction of viaduct overhanging arm
CN202731272U (en) * 2012-07-22 2013-02-13 中国水利水电第三工程局有限公司 Suspended construction assisting trolley
CN102877637A (en) * 2012-09-29 2013-01-16 深圳市建工集团股份有限公司 Method for implementing operating platform in bottom wall construction of cantilever beam
CN103114712A (en) * 2013-03-04 2013-05-22 温州建设集团有限公司 Buckle steel platform support system and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105197845A (en) * 2015-09-19 2015-12-30 山东德建集团有限公司 Lifting hanging type hanging basket roof cornice construction device and use method
CN110905181A (en) * 2019-11-07 2020-03-24 广西建工集团第五建筑工程有限责任公司 7-shaped large-angle inner-inclined high-altitude sliding operation platform and construction method thereof
CN114809574A (en) * 2022-05-16 2022-07-29 北京江河幕墙***工程有限公司 Construction device and construction method for building with oblique cornice structure

Similar Documents

Publication Publication Date Title
CN102979311B (en) Auxiliary device for binding reinforcements of reinforced concrete beam and application thereof
CN102587659A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
CN103790398B (en) Non-pre-support dismantling method for large concrete structure
CN102561690A (en) Construction method for supporting structures on two sides of post-cast strip by use of brick column
CN104032678A (en) H-shaped tower column inner force adjustable temporary cross supporting structure and construction method thereof
CN203034779U (en) Self-lifting-type scaffold operating platform
CN104018657A (en) Method for constructing high and large cornice through horizontal sliding platform
CN104234447B (en) Deep foundation ditch tool-type hangs stair
CN203113793U (en) Large formwork installation system of oblique structure
CN203213019U (en) Long cantilever bent cap cast-in-place construction support system
CN202125061U (en) Scaffold of large-space concrete structure
CN204024010U (en) The flat sliding platform of a kind of high long cornice construction water
CN109113335A (en) Parapet falsework and construction method
CN104499706A (en) Elevator well template platform and construction method thereof
CN203497150U (en) Scaffold for hatch coaming of ship
CN104045014A (en) Pole arraying frame for pole welding
CN205276846U (en) Fixing device of builder's jack pole setting
CN203961258U (en) Builder's jack foot guard structure
CN104695717A (en) Upwarp degree precontrol adjusting equipment of revolving platform
CN209874434U (en) Simple and easy scaffold frame of encorbelmenting of building high latitude
CN204199657U (en) The construction operation platform of irregular ceiling
CN102277957B (en) Overhaul platform of desulfurizing tower
CN203514753U (en) Mobile elevator shaft operation device
CN203430023U (en) Slip form support device for bin top roof
CN102660304B (en) Monorail crane installation construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140903