CN103955197A - Linkage production line control method applied to intake manifold accessory installation - Google Patents

Linkage production line control method applied to intake manifold accessory installation Download PDF

Info

Publication number
CN103955197A
CN103955197A CN201410202235.9A CN201410202235A CN103955197A CN 103955197 A CN103955197 A CN 103955197A CN 201410202235 A CN201410202235 A CN 201410202235A CN 103955197 A CN103955197 A CN 103955197A
Authority
CN
China
Prior art keywords
equipment
product
airtight
qualified
production line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410202235.9A
Other languages
Chinese (zh)
Other versions
CN103955197B (en
Inventor
***
潘国运
乐旭辉
张银辉
于春霞
李淑华
张恺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGDAO HUATAO AUTOMOBILE MOULD CO Ltd
Original Assignee
QINGDAO HUATAO AUTOMOBILE MOULD CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO HUATAO AUTOMOBILE MOULD CO Ltd filed Critical QINGDAO HUATAO AUTOMOBILE MOULD CO Ltd
Priority to CN201410202235.9A priority Critical patent/CN103955197B/en
Publication of CN103955197A publication Critical patent/CN103955197A/en
Application granted granted Critical
Publication of CN103955197B publication Critical patent/CN103955197B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a linkage production line control method applied to intake manifold accessory installation. A production line sequentially comprises an air tightness initial inspection device used for detecting whether welding is qualified or not, a cold insertion device used for pressing stop collars, a nut embedment device used for pressing copper nuts, a tool device used for installing accessories such as an intake manifold actuator and a solenoid valve, and an air tightness final inspection device used for detecting whether overall welding and accessory installation are qualified or not. According to the linkage production line control method applied to intake manifold accessory installation, before the devices operate, product number retrieval is carried out through a database system, whether missing installation or error installation exist or not is judged according to retrieval information, then, a whether a system meets operation conditions or not is judged, the working procedure error and the part missing installation error are avoided, the reject ratio of products is reduced, and production efficiency is improved; production and processing quality of each product can be tracked in the whole process through a two-dimension code technology, and therefore machining quality is improved; in addition, a client can carry out product quality tracing through two-dimension code scanning or database information retrieval.

Description

A kind of linkage production line control method that is applied to the installation of inlet manifold annex
Technical field
The present invention relates to automobile manufacturing field, particularly a kind of linkage production line control method that is applied to the installation of inlet manifold annex.
Background technology
In China, the development of automobile industry and plastic manufacturing process is advanced by leaps and bounds, the engine fittings that metal is made are replaced by the engine fittings of the plastic production taking inlet manifold as representative gradually, as one of parts of engine most critical, inlet manifold has obtained application widely in automobile industry, its Core Feature is for the each cylinder of engine provides full and uniform combination gas, is the key factor that machine power and oil consumption are started in impact.
Mostly the assembling of existing domestic inlet manifold annex is manual assembly or single device production, and annex neglected loading, operation misloading are all to check artificially, and mistake proofing performance is not high.
Summary of the invention
The present invention is directed to annex neglected loading, operation misloading, the low inferior problem of production efficiency, disclose a kind of linkage production line control method that inlet manifold annex is installed that is applied to.
Technical scheme of the present invention is achieved in that
A kind of linkage production line control method that is applied to the installation of inlet manifold annex, described production line comprises successively: for detection of the whether qualified airtight initial survey equipment of welding, for press-fit stop collar cold plug standby, for press-fiting the nut heeling-in equipment of copper nut, for the tooling device of the annexes such as inlet manifold actuator, solenoid valve is installed, and for detection of integral solder, the whether qualified airtight whole inspection equipment of annex installation; Production line control method comprises the following steps:
Step (a), on described airtight initial survey equipment, Quick Response Code coder is set, airtight initial survey is printed the production code member of unique Quick Response Code form after qualified on inlet manifold product, and production code member and the qualified information exchange of welding are crossed to OPC interface sends airtight whole inspection equipment to;
Step (b), airtight whole inspection equipment is by industrial computer building database, after the product coding receiving in step (a), set up and this product coding data storage cell one to one, the qualified information of storage welding, and by OPC communication line to follow-up coldly plugging standby, nut heeling-in equipment, tooling device is unified to control;
Step (c), described cold plug standby, nut heeling-in equipment, the linking transition portion of tooling device and airtight whole inspection equipment, Quick Response Code scanner is set respectively, send production code member to airtight whole inspection equipment by Quick Response Code scanner and OPC communication line, airtight whole inspection equipment is retrieved in described database the product information in data space under this product coding, judge that whether product information is qualified: if product information is qualified, airtight whole inspection equipment sends instruction to be continued to detect to this product, the product information of current detection is stored in to the data space under this production code member of database simultaneously, if product information is defective, airtight whole inspection equipment sends instruction make the to make mistakes equipment at product place and sends alerting signal, and miscellaneous equipment continues operation.
Alternatively, in described step (c), in the time that product occurs that operation mistake, production code member mistake or last process are defective, the industrial computer system of airtight whole inspection equipment judges that product information is defective, send instruction make the to make mistakes equipment at product place and provide alerting signal, miscellaneous equipment continues operation, until replacement of products is while meeting working condition, panalarm puts into operation automatically.
The invention has the beneficial effects as follows:
(1) before equipment operation, carry out production code member retrieval by Database Systems, judge whether neglected loading, misloading according to retrieving information, and then judge whether system meets service condition, avoid operation mistake, neglected loading part mistake, reduced product disqualification rate, improved production efficiency;
(2) make the production and processing quality of every product be able to tracking control of full process by planar bar code technology, improved crudy, simultaneously client can be scanned or database information retrieval carries out product quality and reviews by Quick Response Code.
Brief description of the drawings
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, to the accompanying drawing of required use in embodiment or description of the Prior Art be briefly described below, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skill in the art, do not paying under the prerequisite of creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 is the process chart that inlet manifold annex is installed;
Fig. 2 is the process flow diagram of the linkage production line control method that is applied to the installation of inlet manifold annex of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, obviously, described embodiment is only the present invention's part embodiment, instead of whole embodiment.Based on the embodiment in the present invention, those of ordinary skill in the art, not making the every other embodiment obtaining under creative work prerequisite, belong to the scope of protection of the invention.
As shown in Figure 1, inlet manifold technological process of the present invention comprises: baking material, injection moulding, umbrella valve assembling, the assembling of VIS system, vibration friction welding (FW), spin friction weldering, airtight initial survey, cold slotting stop collar, the slotting copper nut of heat, actuator, solenoid valve, vacuum hose assembling, EGR pipe, the assembling of panel beating support, O-ring seal assembling, airtight whole inspection, packaging.
The inlet manifold annex erecting equipment linkage production line the present invention relates to is from the airtight initial survey after spin friction weldering.Wherein, the assembling unification of actuator, solenoid valve, vacuum hose, EGR pipe, panel beating support, O-ring seal is multiple frocks realizations of an equipment.
As shown in Figure 2, the linkage production line that inlet manifold annex of the present invention is installed by airtight initial survey equipment, coldly plug standby, nut heeling-in equipment, tooling device 4 that actuator, solenoid valve etc. are installed overlaps independently PLC control system and airtight whole inspection equipment PLC system and industrial computer control system form.
Database information storage and retrieval is the basis of setting up linkage production line, therefore by the airtight whole inspection equipment using PLC and industrial computer as control system as main equipment, building database system on industrial computer, miscellaneous equipment is from equipment, carry out information transmission by the OPC communication line between equipment, realize online control.
The control procedure of linkage production line comprises the following steps:
Step (a), on described airtight initial survey equipment, Quick Response Code coder is set, after airtight initial survey equipment Inspection Product jointing is qualified, on inlet manifold product, print the production code member of unique Quick Response Code form by Quick Response Code printer, production code member and the qualified information exchange of welding are crossed OPC communication line and are sent airtight whole inspection equipment to;
Step (b), airtight whole inspection equipment is by industrial computer building database, after the product coding receiving in step (a), set up and this product coding data storage cell one to one, the qualified information of storage welding, and by OPC communication line to follow-up coldly plugging standby, nut heeling-in equipment, tooling device is unified to control;
Step (c), described cold plug standby, nut heeling-in equipment, the linking transition portion of tooling device and airtight whole inspection equipment, Quick Response Code scanner is set respectively, send production code member to airtight whole inspection equipment by Quick Response Code scanner and OPC communication line, airtight whole inspection equipment is retrieved in described database the product information in data space under this product coding, judge that whether product information is qualified: if product information is qualified, airtight whole inspection equipment sends instruction to be continued to detect to this product, the product information of current detection is stored in to the data space under this production code member of database simultaneously, if product information is defective, airtight whole inspection equipment sends instruction make the to make mistakes equipment at product place and sends alerting signal, and miscellaneous equipment continues operation.
Step (c) is specially, when completing airtight initial survey, product enters next process---cold inserting, cold plug received shipment capable before, send production code member to airtight whole inspection equipment by Quick Response Code scanner and OPC communication line, by retrieval production code member, after obtaining the qualified information of airtight initial survey, move, after operation, deposit information in database; Product introduction next process---nut heeling-in, retrieves production code member before the operation of nut heeling-in equipment, obtains the operation afterwards of airtight initial survey and the qualified information of cold slotting stop collar, after operation, deposits information in database; Product introduction next process---actuator, solenoid valve are installed, the tooling device operation of the annexes such as actuator, solenoid valve is installed and retrieves production code member before, after obtaining airtight initial survey, cold slotting stop collar and press-fiting the qualified information of copper nut, move, after operation, deposit information in database; Product introduction next process---airtight inspection eventually, airtight whole inspection equipment retrieval production code member, moves after the qualified information of all process steps before obtaining, and after operation, deposits information in database, and whole linkage production line completes production.
The linkage production line control method that is applied to the installation of inlet manifold annex of the present invention, before equipment operation, carry out production code member retrieval by Database Systems, judge whether neglected loading, misloading according to retrieving information, and then judge whether system meets service condition, avoid operation mistake, neglected loading part mistake, reduced product disqualification rate, improved production efficiency; Production and processing quality by every product of planar bar code technology is able to tracking control of full process, has improved crudy, and simultaneously client can be scanned or database information retrieval carries out product quality and reviews by Quick Response Code.
The foregoing is only preferred embodiment of the present invention, in order to limit the present invention, within the spirit and principles in the present invention not all, any amendment of doing, be equal to replacement, improvement etc., within all should being included in protection scope of the present invention.

Claims (2)

1. one kind is applied to the linkage production line control method that inlet manifold annex is installed, it is characterized in that, described production line comprises successively: for detection of the whether qualified airtight initial survey equipment of welding, for press-fit stop collar cold plug standby, for press-fiting the nut heeling-in equipment of copper nut, for the tooling device of the annexes such as inlet manifold actuator, solenoid valve is installed, and for detection of integral solder, the whether qualified airtight whole inspection equipment of annex installation; Production line control method comprises the following steps:
Step (a), on described airtight initial survey equipment, Quick Response Code coder is set, airtight initial survey is printed the production code member of unique Quick Response Code form after qualified on inlet manifold product, and production code member and the qualified information exchange of welding are crossed to OPC interface sends airtight whole inspection equipment to;
Step (b), airtight whole inspection equipment is by industrial computer building database, after the product coding receiving in step (a), set up and this product coding data storage cell one to one, the qualified information of storage welding, and by OPC communication line to follow-up coldly plugging standby, nut heeling-in equipment, tooling device is unified to control;
Step (c), described cold plug standby, nut heeling-in equipment, the linking transition portion of tooling device and airtight whole inspection equipment, Quick Response Code scanner is set respectively, send production code member to airtight whole inspection equipment by Quick Response Code scanner and OPC communication line, airtight whole inspection equipment is retrieved in described database the product information in data space under this product coding, judge that whether product information is qualified: if product information is qualified, airtight whole inspection equipment sends instruction to be continued to detect to this product, the product information of current detection is stored in to the data space under this production code member of database simultaneously, if product information is defective, airtight whole inspection equipment sends instruction make the to make mistakes equipment at product place and sends alerting signal, and miscellaneous equipment continues operation.
2. the linkage production line control method that is applied to the installation of inlet manifold annex as claimed in claim 1, it is characterized in that, in described step (c), in the time that product occurs that operation mistake, production code member mistake or last process are defective, the industrial computer system of airtight whole inspection equipment judges that product information is defective, sends instruction make the to make mistakes equipment at product place and provides alerting signal, and miscellaneous equipment continues operation, until replacement of products is while meeting working condition, panalarm puts into operation automatically.
CN201410202235.9A 2014-05-08 2014-05-08 Linkage production line control method applied to intake manifold accessory installation Active CN103955197B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410202235.9A CN103955197B (en) 2014-05-08 2014-05-08 Linkage production line control method applied to intake manifold accessory installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410202235.9A CN103955197B (en) 2014-05-08 2014-05-08 Linkage production line control method applied to intake manifold accessory installation

Publications (2)

Publication Number Publication Date
CN103955197A true CN103955197A (en) 2014-07-30
CN103955197B CN103955197B (en) 2017-01-25

Family

ID=51332482

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410202235.9A Active CN103955197B (en) 2014-05-08 2014-05-08 Linkage production line control method applied to intake manifold accessory installation

Country Status (1)

Country Link
CN (1) CN103955197B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104237967A (en) * 2014-08-29 2014-12-24 辽宁丰迪发动机进气***有限公司 Detection device for metal embedded pieces of plastic intake manifold
CN106078199A (en) * 2016-08-01 2016-11-09 上海超路自动化设备有限公司 A kind of automation integrated equipment processing inlet manifold
CN106226008A (en) * 2016-08-26 2016-12-14 青岛华涛汽车模具有限公司 A kind of airtight cold plug in all-in-one
CN106945296A (en) * 2017-04-24 2017-07-14 苏州科技大学 Inlet manifold assembling test production system
CN107862237A (en) * 2017-11-29 2018-03-30 德盛镁汽车部件(芜湖)有限公司 A kind of parts two-dimensional code scanning fail-safe system
CN108145411A (en) * 2017-12-29 2018-06-12 博格华纳排放***(宁波)有限公司 EGR valve assembling line and its assembly method
CN108458834A (en) * 2018-03-27 2018-08-28 苏州科技大学 Manifold assembles p-wire and test method
CN109117908A (en) * 2018-07-05 2019-01-01 安徽胜利精密制造科技有限公司 Material frame two dimensional code trace-back technique
CN109884998A (en) * 2019-02-19 2019-06-14 保定智通自动化技术有限公司 Traceable quality control system
CN110494035A (en) * 2018-05-15 2019-11-22 Juki株式会社 Production system, mounting device, production method
CN112222690A (en) * 2020-09-30 2021-01-15 中石化第四建设有限公司 Method for establishing pipeline weld joint management information

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070028891A1 (en) * 2005-08-05 2007-02-08 Denso Corporation Intake device and mounting structure of valve unit
KR20090055255A (en) * 2007-11-28 2009-06-02 기아자동차주식회사 Judging method for erreor of a intake manifold turning valve
CN102147607A (en) * 2010-02-09 2011-08-10 科博达技术有限公司 Flexible general production line and production method of electronic product
CN102166821A (en) * 2011-01-24 2011-08-31 青岛华涛汽车模具有限公司 Nut-embedding machine
CN202008429U (en) * 2011-03-07 2011-10-12 青岛华涛汽车模具有限公司 Air tightness detector
CN102354210A (en) * 2011-09-07 2012-02-15 华中科技大学 Quality early warning system and method for automobile assembling workshop
CN102749881A (en) * 2012-06-29 2012-10-24 大连交通大学 Error-proofing monitoring system and method for automobile engine valve assembling process
CN103279063A (en) * 2013-06-18 2013-09-04 华高王氏科技(深圳)有限公司 Detecting mistake-proof system applicable to electronic part production line and method thereof
CN103761550A (en) * 2014-01-18 2014-04-30 苏州亿铂信息科技有限公司 Method and system used for correlating product bar codes and production data

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070028891A1 (en) * 2005-08-05 2007-02-08 Denso Corporation Intake device and mounting structure of valve unit
KR20090055255A (en) * 2007-11-28 2009-06-02 기아자동차주식회사 Judging method for erreor of a intake manifold turning valve
CN102147607A (en) * 2010-02-09 2011-08-10 科博达技术有限公司 Flexible general production line and production method of electronic product
CN102166821A (en) * 2011-01-24 2011-08-31 青岛华涛汽车模具有限公司 Nut-embedding machine
CN202008429U (en) * 2011-03-07 2011-10-12 青岛华涛汽车模具有限公司 Air tightness detector
CN102354210A (en) * 2011-09-07 2012-02-15 华中科技大学 Quality early warning system and method for automobile assembling workshop
CN102749881A (en) * 2012-06-29 2012-10-24 大连交通大学 Error-proofing monitoring system and method for automobile engine valve assembling process
CN103279063A (en) * 2013-06-18 2013-09-04 华高王氏科技(深圳)有限公司 Detecting mistake-proof system applicable to electronic part production line and method thereof
CN103761550A (en) * 2014-01-18 2014-04-30 苏州亿铂信息科技有限公司 Method and system used for correlating product bar codes and production data

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王龙: "柴油发动机塑料进气歧管设计研究", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 *
靳红蕾: "基于可装配性分析的塑料进气歧管设计研究", 《中国优秀硕士学位论文全文数据库工程科技II辑》 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104237967A (en) * 2014-08-29 2014-12-24 辽宁丰迪发动机进气***有限公司 Detection device for metal embedded pieces of plastic intake manifold
CN106078199B (en) * 2016-08-01 2018-11-30 上海超路自动化设备有限公司 A kind of automation integrated equipment handling inlet manifold
CN106078199A (en) * 2016-08-01 2016-11-09 上海超路自动化设备有限公司 A kind of automation integrated equipment processing inlet manifold
CN106226008A (en) * 2016-08-26 2016-12-14 青岛华涛汽车模具有限公司 A kind of airtight cold plug in all-in-one
CN108982025B (en) * 2016-08-26 2020-04-28 青岛华涛汽车模具有限公司 All-in-one machine with air tightness detection and metal sleeve cold insertion functions
CN108982025A (en) * 2016-08-26 2018-12-11 青岛华涛汽车模具有限公司 A kind of all-in-one machine having both airtight detection and the cold plugging function of metallic sheath
CN106226008B (en) * 2016-08-26 2018-09-28 青岛华涛汽车模具有限公司 A kind of airtight cold plug in all-in-one machine
CN106945296A (en) * 2017-04-24 2017-07-14 苏州科技大学 Inlet manifold assembling test production system
CN107862237A (en) * 2017-11-29 2018-03-30 德盛镁汽车部件(芜湖)有限公司 A kind of parts two-dimensional code scanning fail-safe system
CN108145411A (en) * 2017-12-29 2018-06-12 博格华纳排放***(宁波)有限公司 EGR valve assembling line and its assembly method
CN108145411B (en) * 2017-12-29 2024-04-05 博格华纳排放***(宁波)有限公司 EGR valve assembly production line and assembly method thereof
CN108458834A (en) * 2018-03-27 2018-08-28 苏州科技大学 Manifold assembles p-wire and test method
CN108458834B (en) * 2018-03-27 2024-04-26 苏州科技大学 Engine manifold assembly test line and test method
CN110494035A (en) * 2018-05-15 2019-11-22 Juki株式会社 Production system, mounting device, production method
CN109117908A (en) * 2018-07-05 2019-01-01 安徽胜利精密制造科技有限公司 Material frame two dimensional code trace-back technique
CN109884998A (en) * 2019-02-19 2019-06-14 保定智通自动化技术有限公司 Traceable quality control system
CN112222690A (en) * 2020-09-30 2021-01-15 中石化第四建设有限公司 Method for establishing pipeline weld joint management information
CN112222690B (en) * 2020-09-30 2022-08-30 中石化第四建设有限公司 Method for establishing pipeline weld joint management information

Also Published As

Publication number Publication date
CN103955197B (en) 2017-01-25

Similar Documents

Publication Publication Date Title
CN103955197A (en) Linkage production line control method applied to intake manifold accessory installation
CN106094746B (en) A kind of automobile exterior product manufacturing execution system and method
CN103345235B (en) Method and module for establishing data acquisition rule of statistical process control system
CN102147607A (en) Flexible general production line and production method of electronic product
CN111311735B (en) Ship piping weld data management method and device, readable storage medium and terminal
CN110340636B (en) Compressor assembling method and system
CN105690694A (en) System and method for setting process parameters of injection molding machine based on data recording
CN103064055A (en) Single phase intelligent electric energy meter collector compatibility type automation verification system and method
CN103440542A (en) Quality tracing system and method of expansion valves
CN103488562A (en) Automated testing method and device
CN105090755A (en) Method and system for locating suspicious gas leakage and leakage points based on pressure monitoring
Ardi et al. Design of pokayoke systems to increase the efficiency of function check oxygen sensor machine using programmable logic controller in manufacturing industry
CN103077255A (en) Identification method and system for 3D (three-dimensional) model of nuclear power station
CN109800833A (en) A kind of material tracing and positioning management control system based on B/S framework
CN106873437A (en) Nuclear power station real-time information monitoring system picture is detected and automatic configuration system and method
CN109508466A (en) A kind of hydraulic power station Fast design method
CN105657021A (en) Method, apparatus and cloud server for processing power system defects
CN204462824U (en) A kind of refrigerating module assembly line on-line control device
CN116186951A (en) Method and device for checking connection relation of three-dimensional pipeline model
CN106271235A (en) Welding bead localization method based on machine vision and device
KR101594607B1 (en) Construction method using a semiconductor fab modular design utilities
CN203949762U (en) Take out soon suction type dry leak-detecting apparatus
CN114970821A (en) Boiler installation calibration method and system based on reliability prediction
CN103150641B (en) Implementation method and the system of the quick quality judging of parts logistics
KR101600068B1 (en) modular design system of a semiconductor fab utilities

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant