CN1039502C - Reinforced concrete pile and its construction method - Google Patents

Reinforced concrete pile and its construction method Download PDF

Info

Publication number
CN1039502C
CN1039502C CN92113272A CN92113272A CN1039502C CN 1039502 C CN1039502 C CN 1039502C CN 92113272 A CN92113272 A CN 92113272A CN 92113272 A CN92113272 A CN 92113272A CN 1039502 C CN1039502 C CN 1039502C
Authority
CN
China
Prior art keywords
pile
reinforced concrete
coupling
cylinder
shape
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN92113272A
Other languages
Chinese (zh)
Other versions
CN1074002A (en
Inventor
张平潮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN92113272A priority Critical patent/CN1039502C/en
Publication of CN1074002A publication Critical patent/CN1074002A/en
Application granted granted Critical
Publication of CN1039502C publication Critical patent/CN1039502C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a spin pile made of reinforced concrete, which is divided into the upper and the lower parts. The upper part is in a cylinder shape, the lower part is about 1 to 3 meters, the surface layer of the cylinder is manufactured into a shallow helical tooth shape, the flushing liquid sprays out through a rubber pipe, a passage and a nozzle under the rotation of a rotary disk of a drill by the self weight or the defined pressure and the pressure of a liquid pump; under the action that the spin pile rotates and is flushed, washed, cut, and is stirred, the spin pile is drilled to designed depth of a stratum, and the great vibration sound of a hammering pile or an impact-driven pile and the adverse effects of the surrounding buildings can be avoided. The present invention improves the engineering quality and the work efficiency, and has the advantage of low cost.

Description

Reinforced concrete pile and job practices thereof
The present invention relates to stake and job practices thereof used in a kind of builing industry, especially adopt the job practices of slope protection pile and foundation pile.
Present known job practices is to adopt the method for paddle type mill or impact type piling, vibrations are big, to around building harmful effect is arranged and civic noise jamming etc. is all brought a lot of inconvenience, after also having the stake hole to accomplish fluently, will do reinforcing cage on the spot, lifting is the hole down, dashes and fills out concrete, the cost height, the time is long.The U.S. also has a kind of pile in addition, (patent No. is US3,842,608 see Appendix) it is to be made of two metal tubes (outer tube and interior pipe), making on whole outer tube top layer on the tube wall of helical form (metal) outer tube and interior pipe has several through holes, as the come out duct of mud of compression, can influence the stake position in case certain duct is blocked around the basis unstable, and this stake cost height, bad popularization.
The objective of the invention is to make a kind of not big bang, and low-cost stake with and job practices.
The object of the present invention is achieved like this: the stake that will originally make at the scene, change into the preformed pile of in factory, producing, can improve the quality of stake greatly, but also saving material, save on-the-spot placing of material ground, save construction area, save reinforcing cage processing and take up an area of, reduction of erection time, enhance productivity greatly.
The present invention is also available present existing machinery equipment except that using special-purpose rotation type rig, comprise rotary drilling machine, long-spiral drilling machine here, need only suitably make a little modifications, just can satisfy the requirement of existing technology.
The present invention is the pile that adopts steel concrete to make, under the rotating disk rotation of rig drives, with own wt or to certain pressure, utilize the pressure of liquid pump again, passing through sebific duct, passage, nozzle towards Xian's liquid, eject, wash away while rotating, get into the design level bit depth under the effect of cutting and stirring at pile.
Reinforced concrete pile of the present invention leaves passage in pile body, there is the device that connects with the sebific duct fluid pump its upper end, and its lower end is provided with nozzle arrangements, it is characterized in that:
1) material of pile is made by steel concrete;
2) pile is divided into two parts up and down, and its top is bar shape, and its underpart is about 1 to 3 meter long, makes shallow spiral dentation (shown in Figure 1) on its cylinder top layer;
3) top, upper end of pile also is provided with and the joining structure of coupling, and its lower end is taper;
4) pile is shaped as the cylinder bodily form (Fig. 3 a), hexahedro column shape (Fig. 3 b), three-flute cylinder shape (Fig. 3 c) and four groove cylinder shapes (Fig. 3 d);
5) the made shallow helical form of lower post body surface layer of this reinforced concrete pile is square waveform (Fig. 4 e), groove shape (Fig. 4 f), waveform (Fig. 4 g), ramp waveform (Fig. 4 h).
The job practices of reinforced concrete pile of the present invention the steps include:
1) on the brill dish of rig, the through hole coupling mean supporting with pile is installed earlier; Use that long screw auger is confidential joins a special-purpose coupling, use rotary disk driller will join conduit and lead;
2) prefabricated pile is sling with coupling unit head and pile are linked up (Fig. 5, i) or put into guide pipe and lead, and the align piles position (Fig. 5, j);
3) connect the sebific duct and the liquid pump of coupling upper end;
4) start the liquid pump, start rig, pile just washes away while rotate under the usefulness of cutting and stirring, creep into the design level bit depth (Fig. 5, k)
5) unload coupling, sebific duct and liquid pump be connected on pile the upper end (Fig. 5, l);
6) if slope protection pile after the projected depth of driving piles, should be aimed at position, slope direction to the one side of many reinforcing bars in the pile, to increase pile body lateral pressure resistant power and shearing resistance;
7) behind the pile location, can be pumped into some by liquid and be added with the cement grout that solidifies early strength admixture strengthening the adhesion of stake and soil layer, and the lower end bearing capacity (Fig. 5, m).
Be described further below in conjunction with drawings and Examples:
Fig. 1 is the structural representation of reinforced concrete pile;
Fig. 2 is the vertical view of reinforced concrete pile;
Fig. 3 is the sectional view of 4 kinds of reinforced concrete piles;
Wherein a is the cylinder bodily form, and b is a hexahedro column shape, and c is a three-flute cylinder shape, and d is four groove cylinder shapes.
Fig. 4 is a pile bottom helical tooth oscillogram, and wherein e is a square waveform, and f is the tooth waveform, and g is a waveform, and h is a ramp waveform.
Fig. 5 is the construction sequence figure of reinforced concrete pile.
Among the figure: (1) reinforcing bar, (2) passage, (3) helical tooth, (4) nozzle, (5) drill bit, (6) blind hole, (7) sebific duct, (8) coupling, (9) pile, (10) rotating disk.
Present embodiment is the reinforced concrete pile (Fig. 1) that adopts hexahedro column shape, and its diameter is 600mm, and spiral groove shape (Fig. 4 of 2 meters long is made in the bottom of stake, f) Zhuan lower end is taper, get into smooth, vibrate lessly, more successfully pierce the stratum projected depth and reach 14 meters.

Claims (4)

1, the reinforced concrete pile of using in a kind of building operations leaves passage in pile body, and there is the device that connects with the sebific duct fluid pump its upper end, and its lower end is provided with nozzle arrangements, it is characterized in that:
1) material of pile is made by steel concrete;
2) pile is divided into two parts up and down, and its top is bar shape, and its underpart is about 1 to 3 meter long, makes shallow spiral dentation on its cylinder top layer;
3) top, upper end of pile also is provided with and the joining structure of coupling, and its lower end is taper.
2, the reinforced concrete pile of using in the building operations according to claim 1, what it is characterized in that it is shaped as the cylinder bodily form, hexahedro column shape, three-flute cylinder shape and four groove cylinder shapes.
3, according to the reinforced concrete pile of using in claim 1, the 2 described building operations, it is characterized in that the made shallow helical form of lower post body surface layer of described pile, be square waveform, groove shape, waveform, ramp waveform.
4, the job practices of the reinforced concrete pile that uses in a kind of architecture construction the steps include:
1) on the brill dish of rig, the through hole coupling mean supporting with pile is installed earlier; Use that long screw auger is confidential joins a special-purpose coupling, use rotary disk driller will join conduit and lead;
2) prefabricated pile is sling with coupling unit head and pile are linked up or put into guide pipe and lead, and the align piles position;
3) connect the sebific duct and the liquid pump of coupling upper end;
4) start the liquid pump, start rig, pile creeps into the design level bit depth with regard under the effect of washing away cutting while rotating and stirring;
5) unload coupling, sebific duct and liquid pump are connected on the upper end of pile;
6) behind the pile location, can be pumped into some by liquid and be added with the cement grout that solidifies early strength admixture strengthening the adhesion of stake and soil layer, and the bearing capacity of lower end.
CN92113272A 1992-12-04 1992-12-04 Reinforced concrete pile and its construction method Expired - Fee Related CN1039502C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN92113272A CN1039502C (en) 1992-12-04 1992-12-04 Reinforced concrete pile and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN92113272A CN1039502C (en) 1992-12-04 1992-12-04 Reinforced concrete pile and its construction method

Publications (2)

Publication Number Publication Date
CN1074002A CN1074002A (en) 1993-07-07
CN1039502C true CN1039502C (en) 1998-08-12

Family

ID=4946329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN92113272A Expired - Fee Related CN1039502C (en) 1992-12-04 1992-12-04 Reinforced concrete pile and its construction method

Country Status (1)

Country Link
CN (1) CN1039502C (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101560768B (en) * 2009-05-20 2011-06-08 毕建东 Overall process construction method for hammering pile, special device therefor and application thereof
CN101984191B (en) * 2010-11-05 2012-01-04 湖南长大建设集团股份有限公司 High pressure jet grouting pile driving machine
CN102619225A (en) * 2012-04-01 2012-08-01 赵立华 Embedding construction method of screw pile
CN103195055A (en) * 2013-04-03 2013-07-10 天津大学 Prefabricated helical pile head for assisting prestressed high-strength concrete (PHC) pipe pile in pile sinking and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3842608A (en) * 1972-11-28 1974-10-22 L Turzillo Method and means for installing load bearing piles in situ
EP0127221A1 (en) * 1983-05-03 1984-12-05 Pieter Faber Concrete foundation pile and device for driving the same into the ground
SU1337478A1 (en) * 1985-12-04 1987-09-15 Научно-исследовательский институт оснований и подземных сооружений им.Н.М.Герсеванова Screw-type support structure
EP0246589A1 (en) * 1986-05-21 1987-11-25 Delmag-Maschinenfabrik Reinhold Dornfeld GmbH & Co. Precast concrete pile and method and apparatus for introducing it into the soil

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3842608A (en) * 1972-11-28 1974-10-22 L Turzillo Method and means for installing load bearing piles in situ
EP0127221A1 (en) * 1983-05-03 1984-12-05 Pieter Faber Concrete foundation pile and device for driving the same into the ground
SU1337478A1 (en) * 1985-12-04 1987-09-15 Научно-исследовательский институт оснований и подземных сооружений им.Н.М.Герсеванова Screw-type support structure
EP0246589A1 (en) * 1986-05-21 1987-11-25 Delmag-Maschinenfabrik Reinhold Dornfeld GmbH & Co. Precast concrete pile and method and apparatus for introducing it into the soil

Also Published As

Publication number Publication date
CN1074002A (en) 1993-07-07

Similar Documents

Publication Publication Date Title
CN110886295A (en) Static pressure pile sinking device and method adopting through method
CN1206419C (en) Combined rock-embedding pile and its construction method
CN1039502C (en) Reinforced concrete pile and its construction method
CN113969581A (en) Construction method for rock-entering pile planting
JP3170756B1 (en) Screw-in type steel pipe pile and its construction method
KR101042271B1 (en) Connector of boring casings pipe for micro-pile
CN112901074A (en) Rock-socketed drilling pore-forming process of marine large-diameter inclined pile rotary excavator
JP3216048B2 (en) Screw-in type steel pipe pile
CN2141434Y (en) Reinforced concrete rotary flushing pile
KR101042272B1 (en) Boring casings pipe for micro-pile with connector
CN2561820Y (en) Steel bar reinforced section-varied composite pile operation apparatus
CN2202795Y (en) Big head anchor rod drill machine
CN2511782Y (en) Screw pile driver drilling rod
CN102767337A (en) Sleeve type screw pile machine drill and construction method for eliminating barriers
CN208330239U (en) A kind of reacting cycle hole cleaning device
CN112252992A (en) Device for cleaning soil of spiral drill rod, assisting drill rig leveling device and construction method
CN1233902C (en) Concrete pile, and spiral drilling machine and method for forming said pile
CN1082133A (en) Cross castinplace pile and piling method thereof
JP4645091B2 (en) Expanded pile and construction method of the expanded pile
CN218509446U (en) Stone fishing device of drilling machine
CN2538850Y (en) Pile end paste prepressing device for long screw drilling bored concrete pile and CFG pile
CN2166156Y (en) Borehole plie driving drill set
CN101059062A (en) Catch hoop tube adaptor type drill rod construction drill machine
CN116291250B (en) Long spiral drill rod and long spiral hole guiding construction method
CN2381671Y (en) Boring bit for vibrating and jetting bored concrete piles

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee