CN103884504B - 一种弹性箔片动压气体推力轴承受轴向力测试结构 - Google Patents
一种弹性箔片动压气体推力轴承受轴向力测试结构 Download PDFInfo
- Publication number
- CN103884504B CN103884504B CN201410086336.4A CN201410086336A CN103884504B CN 103884504 B CN103884504 B CN 103884504B CN 201410086336 A CN201410086336 A CN 201410086336A CN 103884504 B CN103884504 B CN 103884504B
- Authority
- CN
- China
- Prior art keywords
- thrust
- aerodynamic
- dynamometry part
- thrust bearing
- axial force
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)
Abstract
一种弹性箔片动压气体推力轴承受轴向力测试结构,包括两个推力轴承测力件,两个推力轴承测力件贴有应变片,两个弹性箔片动压气体推力轴承分别固定在两个推力轴承座上,两个推力轴承座、隔环连接构成组件,通过隔环调整弹性箔片动压气体推力轴承与推力盘间的气隙厚度,组件通过桁磨保证在壳体内的沿轴向自由滑动,组件周向固定,并由端盖固定在壳体内,转子受到的轴向力会通过推力盘施加在两个推力轴承座上,两个推力轴承座上受到的轴向力就施加在了两个推力轴承测力件上,并被应变片准确测量,应变片所受的压力相加就是转子受到的轴向力,结构安全可靠。
Description
技术领域
本发明涉及传感测控技术领域,尤其涉及一种弹性箔片动压气体推力轴承受轴向力测试结构。
背景技术
在旋转流体机械(包括泵、风机、压缩机、膨胀机、透平机、水轮机、螺旋桨、涡轮发动机等)运行中,由于转子和流体相互作用,会产生轴向的作用力。转子轴向力是旋转流体机械结构设计中的重要指标之一。若轴向力不满足设计要求,其轴承可能长期处于超负荷的工作状态,直接会影响轴承的寿命,严重的会影响整机的寿命和稳定性。因此随着弹性箔片气体轴承在涡轮机、燃气轮机等高速旋转机械中的应用,通过实验确定其所受轴向力显得尤为重要。
传统的测量方法是通过测量压气机卸荷腔的压力来间接判定轴向力的大小。这种测量方法简单,但准确性差,需要进行大量的试验验证。在“TURBOMACHINE”(美国专利US200810095610A1)中提供了一种直接测量可倾瓦推力空气轴承的结构,其力传感器装在可倾瓦中,与外部电气控制装置连接,可用来补偿轴承受到的轴向力,使推力满足设计要求。但因为弹性箔片动压气体推力轴承厚度小,无法装入力传感器,因此不能采用上述结构进行测量。
发明内容
为了克服上述现有技术的不足,本发明的目的在于提供一种弹性箔片动压气体推力轴承受轴向力测试结构,可以测量弹性箔片动压气体推力轴承受到的轴向力。
为了实现上述目的,本发明采取的技术方案是:
一种弹性箔片动压气体推力轴承受轴向力测试结构,包括第一推力轴承测力件4和第二推力轴承测力件4’,第一推力轴承测力件4、第二推力轴承测力件4’分别由4个方形支柱10用来支撑圆环12,方形支柱10两个相对面贴有应变片,第一推力轴承测力件4、第二推力轴承测力件4’的圆环12分别与第一推力轴承座3、第二推力轴承座3’接触,第一弹性箔片动压气体推力轴承5、第二弹性箔片动压气体推力轴承5’分别固定在第一推力轴承座3和第二推力轴承座3’上,第一推力轴承座3、隔环7和第二推力轴承座3’通过螺栓连接构成组件,通过隔环7调整第一弹性箔片动压气体推力轴承5、第二弹性箔片动压气体推力轴承5’与推力盘6间的气隙厚度,组件通过桁磨保证在壳体1内的沿轴向自由滑动,组件周向通过第三销钉8固定,第一径向轴承座2和第二径向轴承座2’通过第一销钉9、第二销钉9’与第一推力轴承测力件4、第二推力轴承测力件4’连接,并由端盖固定在壳体1内。
所述第一推力轴承测力件4、第二推力轴承测力件4’的方形支柱10上粘贴有的应变片,四个为一组,沿周向均布,应变片采用全桥式粘贴法,经过标定,每4N对应一个微应变,最大量程2000N,通过圆环12与第一推力轴承座3、第二推力轴承座3’面接触。
所述第一推力轴承测力件4、第一推力轴承测力件4’的材料是铝合金,方形支柱10中心钻有小孔11。
本发明的有益效果是:提供了弹性箔片动压气体推力轴承所受轴承力的直接测量结构,为实时在线直接测量弹性箔片动压气体推力轴承所受轴承力提供了可能;经过试验,证明结构安全可靠,便于通过转子受到的轴向力对透平机械的运行工况进行实时控制。
附图说明
图1为本发明的整体结构视图。
图2为本发明第一推力轴承测力件4的右视图。
图3为本发明第一推力轴承测力件4的主视图。
具体实施方式:
下面结合附图对本发明作详细说明。
参见图1、图2和图3,一种弹性箔片动压气体推力轴承受轴向力测试结构,包括第一推力轴承测力件4和第二推力轴承测力件4’,第一推力轴承测力件4、第二推力轴承测力件4’分别由4个方形支柱10用来支撑圆环12,方形支柱10两个相对面贴有应变片,第一推力轴承测力件4、第二推力轴承测力件4’的圆环12分别与第一推力轴承座3、第二推力轴承座3’接触,第一弹性箔片动压气体推力轴承5、第二弹性箔片动压气体推力轴承5’分别固定在第一推力轴承座3和第二推力轴承座3’上,第一推力轴承座3、隔环7和第二推力轴承座3’通过螺栓连接构成组件,通过隔环7调整第一弹性箔片动压气体推力轴承5、第二弹性箔片动压气体推力轴承5’与推力盘6间的气隙厚度,组件通过桁磨保证在壳体1内的沿轴向自由滑动,组件周向通过第三销钉8固定,第一径向轴承座2和第二径向轴承座2’通过第一销钉9、第二销钉9’与第一推力轴承测力件4、第二推力轴承测力件4’连接,并由端盖固定在壳体1内。
所述第一推力轴承测力件4、第二推力轴承测力件4’的方形支柱10上粘贴有的应变片,四个为一组,沿周向均布,应变片采用全桥式粘贴法,用来消除方形支柱10弯曲的影响,经过标定,每4N对应一个微应变,最大量程2000N,通过圆环12与第一推力轴承座3、第二推力轴承座3’面接触,可以有效避免方形支柱10与推力轴承座直接接触所产生的如轴向力在方形支柱10间分布不均,方形支柱10本身需要精密加工等问题。
所述第一推力轴承测力件4、第一推力轴承测力件4’的材料是铝合金,方形支柱10中心钻有小孔11,目的是减小支柱的横截面积,即降低方形支柱10的刚度,在受到同样大小轴向力的时候增大变形,提高测量精度。
本发明的工作原理是:工作中,转子受到的轴向力会通过推力盘6施加在第一推力轴承座3、第二推力轴承座3’上,第一推力轴承座3、第二推力轴承座3’上受到的轴向力就施加在了第一推力轴承测力件4、第二推力轴承测力件4’的圆环12上,并被方形支柱10上粘贴的应变片准确测量,沿周向均布的4个方形支柱10上应变片所受的压力相加就是转子受到的轴向力。
Claims (3)
1.一种弹性箔片动压气体推力轴承受轴向力测试结构,包括第一推力轴承测力件(4)和第二推力轴承测力件(4’),其特征在于:第一推力轴承测力件(4)、第二推力轴承测力件(4’)分别由4个方形支柱(10)用来支撑圆环(12),方形支柱(10)两个相对面贴有应变片,第一推力轴承测力件(4)、第二推力轴承测力件(4’)的圆环(12)分别与第一推力轴承座(3)、第二推力轴承座(3’)接触,第一弹性箔片动压气体推力轴承(5)、第二弹性箔片动压气体推力轴承(5’)分别固定在第一推力轴承座(3)和第二推力轴承座(3’)上,第一推力轴承座(3)、隔环(7)和第二推力轴承座(3’)通过螺栓连接构成组件,通过隔环(7)调整第一弹性箔片动压气体推力轴承(5)、第二弹性箔片动压气体推力轴承(5’)与推力盘(6)间的气隙厚度,组件通过桁磨保证在壳体(1)内的沿轴向自由滑动,组件周向通过第三销钉(8)固定,第一径向轴承座(2)和第二径向轴承座(2’)通过第一销钉(9)、第二销钉(9’)与第一推力轴承测力件(4)、第二推力轴承测力件(4’)连接,并由端盖固定在壳体(1)内。
2.根据权利要求1所述的一种弹性箔片动压气体推力轴承受轴向力测试结构,其特征在于:所述第一推力轴承测力件(4)、第二推力轴承测力件(4’)的方形支柱(10)上粘贴有的应变片,四个为一组,沿周向均布,应变片采用全桥式粘贴法,经过标定,每4N对应一个微应变,最大量程2000N,通过圆环(12)与第一推力轴承座(3)、第二推力轴承座(3’)面接触。
3.根据权利要求1所述的一种弹性箔片动压气体推力轴承受轴向力测试结构,其特征在于:所述第一推力轴承测力件(4)、第一推力轴承测力件(4’)的材料是铝合金,方形支柱(10)中心钻有小孔(11)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410086336.4A CN103884504B (zh) | 2014-03-10 | 2014-03-10 | 一种弹性箔片动压气体推力轴承受轴向力测试结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410086336.4A CN103884504B (zh) | 2014-03-10 | 2014-03-10 | 一种弹性箔片动压气体推力轴承受轴向力测试结构 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103884504A CN103884504A (zh) | 2014-06-25 |
CN103884504B true CN103884504B (zh) | 2016-06-29 |
Family
ID=50953523
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410086336.4A Expired - Fee Related CN103884504B (zh) | 2014-03-10 | 2014-03-10 | 一种弹性箔片动压气体推力轴承受轴向力测试结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103884504B (zh) |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2526713B (en) | 2013-02-22 | 2019-09-11 | Borgwarner Inc | Electric rotor fit onto a turbomachine shaft |
CN104483055B (zh) * | 2014-12-09 | 2017-01-25 | 株洲联诚集团有限责任公司 | 一种三相感应电机转子轴承轴向力测量装置及测量方法 |
CN104727950B (zh) * | 2015-02-10 | 2019-10-01 | 北京华清燃气轮机与煤气化联合循环工程技术有限公司 | 一种燃气轮机轴向力控制装置及其控制方法 |
CN105547534B (zh) * | 2015-12-03 | 2018-08-24 | 中国航空动力机械研究所 | 可测量转子轴向载荷的弹性支承 |
CN107228725A (zh) * | 2017-05-26 | 2017-10-03 | 浙江万向精工有限公司 | 一种驱动轮毂轴承单元旋铆压力测量***及其测量方法 |
CN109357798B (zh) * | 2018-10-30 | 2021-01-15 | 中国北方发动机研究所(天津) | 一种涡轮增压器轴向力测试结构 |
CN109141880B (zh) * | 2018-11-09 | 2024-02-20 | 神钢无锡压缩机股份有限公司 | 一种滑动推力轴承性能测试试验台本体 |
CN110501102B (zh) * | 2019-09-05 | 2022-04-05 | 东方电气集团东方电机有限公司 | 一种推力负荷测试瓦的制作及使用方法 |
CN112697433B (zh) * | 2021-01-21 | 2022-05-20 | 中国科学院工程热物理研究所 | 一种止推滚动轴承轴向承载测试装置及方法 |
CN113358260B (zh) * | 2021-06-25 | 2022-06-21 | 北京化工大学 | 一种转-静盘腔轴向气动推力测试试验台 |
CN114184390B (zh) * | 2022-02-16 | 2022-05-06 | 成都中科翼能科技有限公司 | 一种燃气轮机转子轴向力测试传感器及参数设计方法 |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06137997A (ja) * | 1992-10-23 | 1994-05-20 | Fujitsu Ltd | 動圧気体軸受の評価方法、清掃方法、及び動圧気体軸受 |
JP2004117088A (ja) * | 2002-09-25 | 2004-04-15 | Mitsubishi Heavy Ind Ltd | 軸受特性の計測方法及び軸受 |
CN101226104A (zh) * | 2008-02-01 | 2008-07-23 | 西安交通大学 | 测试弹性箔片推力轴承起飞转速的装置 |
CN101881696B (zh) * | 2010-06-03 | 2012-05-23 | 西安交通大学 | 一种带滚动摩擦副的弹性箔片气体推力轴承性能测试台 |
CN101975656B (zh) * | 2010-09-06 | 2011-12-07 | 西安交通大学 | 一种微型燃气轮机模拟转子动态性能测试实验装置 |
CN201909714U (zh) * | 2010-12-17 | 2011-07-27 | 大连理工大学 | 气体轴承-转子***动态加载综合实验台 |
KR101303639B1 (ko) * | 2012-11-28 | 2013-09-11 | 한국기계연구원 | 스러스트 베어링 성능시험장치 |
CN203350039U (zh) * | 2013-04-10 | 2013-12-18 | 浙江工业大学 | 锥形空气轴承轴向承载力测试装置 |
-
2014
- 2014-03-10 CN CN201410086336.4A patent/CN103884504B/zh not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN103884504A (zh) | 2014-06-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103884504B (zh) | 一种弹性箔片动压气体推力轴承受轴向力测试结构 | |
CN104917333B (zh) | 旋转机械、轴承以及制造旋转机械的方法 | |
US9664593B2 (en) | Bearing apparatus | |
EP2960465B1 (en) | Compressor assembly | |
CN207556848U (zh) | 一种箔片空气轴承高速转子试验台的轴向加载装置 | |
CN104190959B (zh) | 具有回转误差监测功能的空气静压主轴 | |
CN103419088A (zh) | 一种数控机床切削力模拟加载装置及方法 | |
CN113343357B (zh) | 一种航空发动机高低压转子间径向间隙计算方法 | |
CN208366608U (zh) | 一种高速角接触球轴承温升检测试验装置 | |
CN107327474B (zh) | 一种能够检测旋转机械轴向力的可倾瓦推力轴承 | |
CN103162596A (zh) | 一种轴承轴向游隙检测装置及检测方法 | |
JP2012255688A (ja) | 軸受試験装置 | |
CN103352800A (zh) | 一种风电机组的独立变桨方法与独立变桨控制装置 | |
TW202012801A (zh) | 軸承裝置和工具機的主軸裝置 | |
CN201191172Y (zh) | 用于汽轮机轮盘锥销装配的间接测量工具 | |
CN113899558A (zh) | 一种航空发动机双转子***碰摩试验装置 | |
CN204301710U (zh) | 一种成对角接触球轴承轴向预游隙的测量装置 | |
CN103968982B (zh) | 基于气浮轴承的低阻尼滚转力矩测量装置 | |
Li et al. | Design and evaluation of a high-speed and precision microspindle | |
CN202101655U (zh) | 大型球轴承测量仪 | |
CN110243601B (zh) | 一种适用于超高速工况下的组合推力与径向轴承装置及其检测方法 | |
CN105628348A (zh) | 一种疲劳试验机构 | |
TW202006260A (zh) | 軸承裝置和工具機的主軸裝置 | |
CN110501102A (zh) | 一种推力负荷测试瓦的制作及使用方法 | |
CN114526705B (zh) | 一种航空发动机双转子动态不同心度测量方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160629 Termination date: 20210310 |