CN103848357A - Wall-attached device of tower crane - Google Patents

Wall-attached device of tower crane Download PDF

Info

Publication number
CN103848357A
CN103848357A CN201410099272.1A CN201410099272A CN103848357A CN 103848357 A CN103848357 A CN 103848357A CN 201410099272 A CN201410099272 A CN 201410099272A CN 103848357 A CN103848357 A CN 103848357A
Authority
CN
China
Prior art keywords
tower crane
support beam
wall
adjust bar
attaching equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410099272.1A
Other languages
Chinese (zh)
Inventor
张亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410099272.1A priority Critical patent/CN103848357A/en
Publication of CN103848357A publication Critical patent/CN103848357A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a wall-attached device of a tower crane. The wall-attached device comprises a pre-embedded part, a wall-attached framework and a support beam, wherein one end of the support beam is connected with the pre-embedded part; the other end of the support beam is connected with the wall-attached framework; the support beam comprises at least two sections of beam bodies; a length adjusting mechanism for adjusting the distance between two beam bodies is arranged between every two adjacent beam bodies. By adopting the scheme, since the length of the support beam is adjustable, when the tower crane is fixed, if the length of the support beam does not meet requirements, the length of the support beam can be adjusted according to the distance from the tower crane to a building, therefore, the support beam can be used repeatedly, a newly manufactured support beam with length meeting the requirements is not needed, the universality of the support beam is enhanced and waste is avoided.

Description

Tower crane wall-attaching equipment
Technical field
The invention belongs to the technical field of building operation apparatus, specifically, the present invention relates to tower crane wall-attaching equipment.
Background technology
In the construction of skyscraper, tower crane is its main construction machinery and equipment, and plays an important role therein.Tower crane major part is to adopt adhesion type, take root from basis, ground, add up to promote with standard section of tower crane, owing to thering is certain distance between tower crane and building, in order to guarantee the stability of tower crane, all tower cranes all need to be connected with building by wall-attaching equipment.
Current wall-attaching equipment is mainly made up of built-in fitting, attached wall framework and support beam, because the length dimension of the support beam of the wall-attaching equipment of this structure is fixed, need make according to the distance between tower crane and building the support beam of respective length, cause support beam not to be reused, cause waste.
Summary of the invention
The invention provides a kind of tower crane wall-attaching equipment, object is to guarantee that support beam can be reused.
To achieve these goals, the technical scheme that the present invention takes is: tower crane wall-attaching equipment, comprise built-in fitting, attached wall framework and support beam, support beam one end is connected with built-in fitting, the other end is connected with attached wall framework, described support beam comprises at least two joint beam bodies, between adjacent two beam bodies, is provided with the length adjustment mechanism for regulating two beam body distances.
Described length adjustment mechanism comprises the adjust bar being threaded with described adjacent two beam bodies.
The two ends of described adjust bar are provided with outside thread, and described beam end of body is provided with the negative thread coordinating with adjust bar.
The two ends of described adjust bar are provided with the jam nut being threaded with adjust bar.
Described adjust bar is provided with the jack that allows tommy bar insert.
Described jack is vertical with the axis of described adjust bar and runs through the through hole of adjust bar.
Described support beam is provided with two joint beam bodies, is respectively the first beam body being connected with described built-in fitting and the second beam body being connected with described attached wall framework, and the length of the Length Ratio second beam body of the first beam body is little.
The two ends of described support beam are provided with engaging lug, and described attached wall framework and built-in fitting are provided with mount pad, and engaging lug is connected with mount pad by latch.
Described attached wall framework is the rectangular configuration being connected and composed by two C shape frames.
Described support beam is provided with three, and three support beams are N font and arrange.
Tower crane wall-attaching equipment of the present invention adopts such scheme, support beam is arranged to adjustable in length, in the time of fixing tower crane, if the length violation of support beam closes requirement, can be according to the distance between tower crane and building the length of corresponding adjusting support beam, thereby can guarantee that support beam can be reused, without the support beam of again making again the new length that conforms with the regulations, the commonality that has improved support beam, avoids waste.
Accompanying drawing explanation
This specification sheets comprises the following drawings, shown in content respectively:
Fig. 1 is the structural representation of tower crane wall-attaching equipment of the present invention;
Fig. 2 is the structural representation of support beam;
In figure, be labeled as:
1, body of wall; 2, built-in fitting; 3, attached wall framework; 31, C shape frame; 32, connecting panel; 33, mount pad; 34, locating part; 4, support beam; 41, the first beam body; 42, the second beam body; 43, adjust bar; 44, jam nut; 45, jack; 46, engaging lug; 5, the first support beam; 6, the second support beam; 7, the 3rd support beam.
The specific embodiment
Contrast accompanying drawing below, by the description to embodiment, the specific embodiment of the present invention is described in further detail, and object is to help those skilled in the art to have more complete, accurate and deep understanding to design of the present invention, technical scheme, and contributes to its enforcement.
As depicted in figs. 1 and 2, a kind of tower crane wall-attaching equipment of the present invention, comprises built-in fitting 2, attached wall framework 3 and support beam 4.Built-in fitting 2 is identical with prior art, for being directly installed on the body of wall 1 of building.Attached wall framework 3 is the tower bodies for being enclosed within tower crane, and one end of support beam 4 is connected with built-in fitting 2, and the other end is connected with attached wall framework 3, and support beam 4 plays a part to support fixing, can in horizontal surface, arrange many.The problem existing in order to solve prior art, the support beam 4 of this device comprises at least two joint beam bodies, between adjacent two beam bodies, be provided with the length adjustment mechanism for regulating two beam body distances, thereby it is adjustable to realize support beam 4 entire length, the length of support beam 4 is met the requirements, guarantee that support beam 4 can be reused.
Specifically, the length adjustment mechanism on support beam 4 comprises the adjust bar 43 being threaded with adjacent two beam bodies.In the present embodiment, 4 of support beams are provided with two joint beam bodies, be respectively the first beam body 41 being connected with built-in fitting 2 and the second beam body 42 being connected with attached wall framework 3, the first beam body 41 is provided with tapped bore with the second relative end of beam body 42, for being connected with adjust bar 43, the two ends shaft of corresponding adjust bar 43 is provided with the negative thread outside thread with tapped bore, and the two externally threaded rotation directions in place are contrary, to guarantee that adjust bar 43 is in rotation process, the first beam body 41 at two ends can move or deviate from mutually movement in opposite directions with the second beam body 42, to reach the object that regulates support beam 4 length.The mode that adopts screw thread rotation to regulate, has advantages of good, the accurate height of accommodation accuracy and easy to adjust.
Be fixed at Liang Tishang in order to ensure adjust bar 43, two ends at adjust bar 43 are also respectively provided with the jam nut 44 being threaded with adjust bar 43, turn jam nut 44, each jam nut 44 is moved towards the first adjacent with it beam body 41 or the second beam body 42 respectively, finally make adjust bar 43 and the first beam body 41 and the second beam body 42 tight, realize adjust bar 43 fixing, guarantee that strut bar length in support process remains unchanged, thereby can guarantee that tower crane obtains firm support, unlikelyly topple over.
On adjust bar 43, be also provided with the jack 45 that allows tommy bar insert, this jack 45 is for vertical with the axis of adjust bar 43 and run through the through hole of adjust bar 43, and this jack 45 is also positioned at the medium position place of adjust bar 43.This jack 45 is set, in the time regulating the length of support beam 4, can uses a tommy bar to insert in the jack 45 of adjust bar 43, by tommy bar is applied to external force, adjust bar 43 is rotated, it is easy to operate, time saving and energy saving to make.
The first beam body 41 is for being connected with the built-in fitting 2 on body of wall 1, so the length of the Length Ratio second beam body 42 of the first beam body 41 is little, can make like this adjust bar 43 nearer apart from body of wall 1, owing on the body of wall 1 built-in fitting 2 is installed, scaffold being generally all installed, workmen operates on scaffold, adjust bar 43 is nearer apart from body of wall 1, and operation that can convenient construction personnel, to facilitate it regulate length of support beam 4 and be locked.In addition, the first beam body 41 to the second beam bodies 42 are short, can also reduce the warping property of beam body self, avoid the distortion that is distorted of beam body.
As shown in the figure, for the ease of connecting, be provided with engaging lug 46 at the two ends of support beam 4, the end for being connected with built-in fitting 2 of the first beam body 41 is provided with engaging lug 46, the end for being connected with attached wall framework 3 of the second beam body 42 is provided with engaging lug 46, engaging lug 46 is to be made up of two ear pieces that are welded on beam end of body that parallel, and engaging lug 46 is provided with the mounting hole that runs through two ear pieces.Attached wall framework 3 and built-in fitting 2 are all provided with mount pad 33, on mount pad 33, be also provided with mounting hole, the engaging lug 46 at the two ends of support beam 4 is connected with mount pad 33 by latch, and latch will insert in the mounting hole of engaging lug 46 and mount pad 33, realizes the fixing of support beam 4.
The first beam body 41 and the second beam body 42 all adopt solid drawn pipe to make, one end sealing, other end opening, one end of sealing is provided with engaging lug 46, open end inside is provided with a circular nut, circular nut is provided with tapped bore, and the two ends of adjust bar 43 are inserted respectively to realize in the circular nut of the first beam body 41 and the second beam body 42 inside and are threaded and the adjusting of support beam 4 length.Adopt this structure to connect, without process negative thread on the first beam body 41 and the second beam body 42, directly by circular nut being set in the first beam body 41 and the second beam body 42, make processing become simple, and circular nut is to be weldingly fixed in the first beam body 41 and the second beam body 42, Joint strenght is high, safe and reliable.In addition, between the thread surface at adjust bar 43 two ends and the first beam body 41 and the circular nut of the second beam body 42, be also filled with butter, good airproof performance, can prevent that liquid from entering the first beam body 41 and the second beam body 42 inside as rainwater etc., avoid the first beam body 41 and the second beam body 42 to occur the situation of corrosion in inside, thereby can extend the service life of support beam 4.
As shown in the figure, attached wall framework 3 is the rectangular configuration that connected and composed by two C shape frames 31, C shape frame 31 two ends respectively arrange a connecting panel 32, connecting panel 32 is parallel with body of wall 1, the connecting panel 32 at the two ends of two C shape frames 31 contacts respectively, and fix by bolt tightening, thereby make attached wall framework 3 form an entirety, for being enclosed within the tower body of tower crane.
On two C shape frames 31 of attached wall framework 3, be also provided with locating part 34, this locating part 34 is to be the state vertical with curb girder at three curb girders of C shape frame 31 to be located on curb girder, specifically as shown in the figure, on curb girder in the middle of C shape frame 31, be respectively provided with a locating part 34 in the position near two ends, on the curb girder of both sides, be respectively provided with a locating part 34 close with middle curb girder junction, be to be respectively equipped with four locating parts 34 on each C shape frame 31, on attached wall framework 3, be provided with altogether eight locating parts 34, and locating part 34 is all in same level.Owing to generally can having gap between attached wall framework 3 and middle tower crane tower body, locating part 34 is set on attached wall framework 3, by regulating the position of locating part 34, make locating part 34 push against tower body in tower crane tower body outside, by the common fixed tower of eight locating parts 34, further to improve the stability to tower crane tower body, prevent and rock.Locating part 34 on C shape frame 31 can directly adopt bolt or make and the similar structure of bolt, corresponding installed position on the curb girder of C shape frame 31 arranges tapped bore, locating part 34 is threaded with the curb girder of C shape frame 31, not only facilitate the adjusting of position-limited lever position, and facilitate processing and fabricating.
On the C shape frame 31 of the close body of wall 1 of attached wall framework 3, be provided with two mount pads 33 towards the sidepiece of body of wall 1, lay respectively at the Liang Ge corner of C shape frame 31, the position being located in the same horizontal plane with this C shape frame 31 on body of wall 1 accordingly is also provided with two built-in fittings 2.
In addition, the support beam 4 of the tower crane wall-attaching equipment of the present embodiment is provided with three altogether, is respectively the first support beam 5, the second support beam 6 and 7, three support beams of the 3rd support beam and is N font layout.One end of the first support beam 5 is connected with the mount pad 33 of attached wall framework 3 one of them corner, the other end is connected with a built-in fitting 2 on body of wall 1, one end of the 3rd support beam 7 is connected with the mount pad 33 of attached wall framework 3 another corners, the other end is connected with another built-in fitting 2 on body of wall 1, one end of the second support beam 6 and the first support beam 5 are connected on same built-in fitting 2, and the other end and the 3rd support beam 7 are connected on same mount pad 33.This layout that is N font, good stability.
Below by reference to the accompanying drawings the present invention is exemplarily described.Obviously, specific implementation of the present invention is not subject to the restrictions described above.As long as having adopted the improvement of the various unsubstantialities that method of the present invention design and technical scheme carry out; Or without improvement, above-mentioned design of the present invention and technical scheme are directly applied to other occasion, all within protection scope of the present invention.

Claims (10)

1. tower crane wall-attaching equipment, comprise built-in fitting, attached wall framework and support beam, support beam one end is connected with built-in fitting, and the other end is connected with attached wall framework, it is characterized in that: described support beam comprises at least two joint beam bodies, between adjacent two beam bodies, is provided with the length adjustment mechanism for regulating two beam body distances.
2. tower crane wall-attaching equipment according to claim 1, is characterized in that: described length adjustment mechanism comprises the adjust bar being threaded with described adjacent two beam bodies.
3. tower crane wall-attaching equipment according to claim 2, is characterized in that: the two ends of described adjust bar are provided with outside thread, described beam end of body is provided with the negative thread coordinating with adjust bar.
4. tower crane wall-attaching equipment according to claim 3, is characterized in that: the two ends of described adjust bar are provided with the jam nut being threaded with adjust bar.
5. according to the tower crane wall-attaching equipment described in claim 2 or 3 or 4, it is characterized in that: described adjust bar is provided with the jack that allows tommy bar insert.
6. tower crane wall-attaching equipment according to claim 5, is characterized in that: described jack is vertical with the axis of described adjust bar and runs through the through hole of adjust bar.
7. tower crane wall-attaching equipment according to claim 6, it is characterized in that: described support beam is provided with two joint beam bodies, be respectively the first beam body being connected with described built-in fitting and the second beam body being connected with described attached wall framework, the length of the Length Ratio second beam body of the first beam body is little.
8. tower crane wall-attaching equipment according to claim 7, is characterized in that: the two ends of described support beam are provided with engaging lug, described attached wall framework and built-in fitting are provided with mount pad, and engaging lug is connected with mount pad by latch.
9. tower crane wall-attaching equipment according to claim 8, is characterized in that: described attached wall framework is the rectangular configuration being connected and composed by two C shape frames.
10. tower crane wall-attaching equipment according to claim 9, is characterized in that: described support beam is provided with three, and three support beams are N font and arrange.
CN201410099272.1A 2014-03-17 2014-03-17 Wall-attached device of tower crane Pending CN103848357A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410099272.1A CN103848357A (en) 2014-03-17 2014-03-17 Wall-attached device of tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410099272.1A CN103848357A (en) 2014-03-17 2014-03-17 Wall-attached device of tower crane

Publications (1)

Publication Number Publication Date
CN103848357A true CN103848357A (en) 2014-06-11

Family

ID=50856540

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410099272.1A Pending CN103848357A (en) 2014-03-17 2014-03-17 Wall-attached device of tower crane

Country Status (1)

Country Link
CN (1) CN103848357A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105152039A (en) * 2015-09-07 2015-12-16 中国建筑一局(集团)有限公司 Slope building tower crane ultralong attachment device and slope building inverted sequence construction method
CN108016994A (en) * 2018-01-10 2018-05-11 山西三建集团有限公司 A kind of repeatable tower crane attached wall stent and installation method utilized
CN111287542A (en) * 2018-12-06 2020-06-16 深圳京创重工特种工程有限公司 Construction method of concrete tower tube
CN112443147A (en) * 2019-09-02 2021-03-05 广东博智林机器人有限公司 Anti-deflection device for outer wall jacking tower and mounting and dismounting method thereof
CN112443149A (en) * 2019-09-02 2021-03-05 广东博智林机器人有限公司 Method for mounting and dismounting anti-deflection device of outer wall jacking tower

Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2866437Y (en) * 2005-06-02 2007-02-07 大连华锐股份有限公司 Adjustable anchoring device
CN201121101Y (en) * 2007-11-05 2008-09-24 江苏南通三建集团有限公司 Engaged mechanism of tower crane headframe
CN201217618Y (en) * 2008-05-23 2009-04-08 中核华兴达丰机械工程有限公司 Universal adjustable stay rod attachment apparatus of tower crane
CN201343397Y (en) * 2008-12-19 2009-11-11 青岛市胶州建设集团有限公司 Retractable wall-adhering device of tower crane
CN101579926A (en) * 2009-03-24 2009-11-18 无锡宝通带业股份有限公司 Carding device for producing steel cable belts
CN101670977A (en) * 2009-09-30 2010-03-17 长沙中联重工科技发展股份有限公司 Landing-lag gap adjusting device
CN102079489A (en) * 2011-01-30 2011-06-01 沈阳建筑大学 Suspended-rising support system of tower crane
CN201923799U (en) * 2010-12-28 2011-08-10 徐州重型机械有限公司 Telescopic arm of crane and arm head structure of telescopic arm
CN202007090U (en) * 2011-04-14 2011-10-12 武汉益达建设机械有限公司 Wall-attaching device of tower crane
CN202245825U (en) * 2010-12-03 2012-05-30 中建四局第一建筑工程有限公司 Steel tube wall-attaching device for long-distance tower crane
CN202529755U (en) * 2012-05-15 2012-11-14 安徽建筑机械有限责任公司 Standard combined wall attaching inclined support device for self-elevating tower crane
CN202575768U (en) * 2011-10-31 2012-12-05 劳升浩 Wall attaching device for construction tower crane
CN203003727U (en) * 2012-11-17 2013-06-19 常州信息职业技术学院 Portable pressure plate
CN103395409A (en) * 2013-07-22 2013-11-20 包钢集团巴润矿业有限责任公司 Adjustable strut
CN103407904A (en) * 2012-12-30 2013-11-27 上海庞源机械租赁股份有限公司 Hoop type wall-attached connection piece for tower crane and construction method thereof
EP2677094A2 (en) * 2012-06-21 2013-12-25 GESTA Gesellschaft für Stahlrohrgerüste mit beschränkter Haftung Upper structure of an access system
CN203392759U (en) * 2013-08-21 2014-01-15 山东大汉建设机械有限公司 Telescopic adjustable wall attaching device of tower crane with angle limit function
CN203474329U (en) * 2013-09-27 2014-03-12 山东明威起重设备有限公司 Novel tower crane buttress frame
CN203767885U (en) * 2014-03-17 2014-08-13 张亮 Tower crane wall attaching device

Patent Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2866437Y (en) * 2005-06-02 2007-02-07 大连华锐股份有限公司 Adjustable anchoring device
CN201121101Y (en) * 2007-11-05 2008-09-24 江苏南通三建集团有限公司 Engaged mechanism of tower crane headframe
CN201217618Y (en) * 2008-05-23 2009-04-08 中核华兴达丰机械工程有限公司 Universal adjustable stay rod attachment apparatus of tower crane
CN201343397Y (en) * 2008-12-19 2009-11-11 青岛市胶州建设集团有限公司 Retractable wall-adhering device of tower crane
CN101579926A (en) * 2009-03-24 2009-11-18 无锡宝通带业股份有限公司 Carding device for producing steel cable belts
CN101670977A (en) * 2009-09-30 2010-03-17 长沙中联重工科技发展股份有限公司 Landing-lag gap adjusting device
CN202245825U (en) * 2010-12-03 2012-05-30 中建四局第一建筑工程有限公司 Steel tube wall-attaching device for long-distance tower crane
CN201923799U (en) * 2010-12-28 2011-08-10 徐州重型机械有限公司 Telescopic arm of crane and arm head structure of telescopic arm
CN102079489A (en) * 2011-01-30 2011-06-01 沈阳建筑大学 Suspended-rising support system of tower crane
CN202007090U (en) * 2011-04-14 2011-10-12 武汉益达建设机械有限公司 Wall-attaching device of tower crane
CN202575768U (en) * 2011-10-31 2012-12-05 劳升浩 Wall attaching device for construction tower crane
CN202529755U (en) * 2012-05-15 2012-11-14 安徽建筑机械有限责任公司 Standard combined wall attaching inclined support device for self-elevating tower crane
EP2677094A2 (en) * 2012-06-21 2013-12-25 GESTA Gesellschaft für Stahlrohrgerüste mit beschränkter Haftung Upper structure of an access system
CN203003727U (en) * 2012-11-17 2013-06-19 常州信息职业技术学院 Portable pressure plate
CN103407904A (en) * 2012-12-30 2013-11-27 上海庞源机械租赁股份有限公司 Hoop type wall-attached connection piece for tower crane and construction method thereof
CN103395409A (en) * 2013-07-22 2013-11-20 包钢集团巴润矿业有限责任公司 Adjustable strut
CN203392759U (en) * 2013-08-21 2014-01-15 山东大汉建设机械有限公司 Telescopic adjustable wall attaching device of tower crane with angle limit function
CN203474329U (en) * 2013-09-27 2014-03-12 山东明威起重设备有限公司 Novel tower crane buttress frame
CN203767885U (en) * 2014-03-17 2014-08-13 张亮 Tower crane wall attaching device

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105152039A (en) * 2015-09-07 2015-12-16 中国建筑一局(集团)有限公司 Slope building tower crane ultralong attachment device and slope building inverted sequence construction method
CN105152039B (en) * 2015-09-07 2017-12-08 中国建筑一局(集团)有限公司 Slope Architectural tower crane overlength attachment device and Slope Architectural inverted construction method
CN108016994A (en) * 2018-01-10 2018-05-11 山西三建集团有限公司 A kind of repeatable tower crane attached wall stent and installation method utilized
CN111287542A (en) * 2018-12-06 2020-06-16 深圳京创重工特种工程有限公司 Construction method of concrete tower tube
CN112443147A (en) * 2019-09-02 2021-03-05 广东博智林机器人有限公司 Anti-deflection device for outer wall jacking tower and mounting and dismounting method thereof
CN112443149A (en) * 2019-09-02 2021-03-05 广东博智林机器人有限公司 Method for mounting and dismounting anti-deflection device of outer wall jacking tower
CN112443149B (en) * 2019-09-02 2022-06-14 广东博智林机器人有限公司 Method for mounting and dismounting anti-deflection device of outer wall jacking tower

Similar Documents

Publication Publication Date Title
CN103848357A (en) Wall-attached device of tower crane
CN103848361A (en) Supporting beam for wall-attached device of tower crane
CN204098422U (en) A kind of mounting mounting structure of stone material
CN203767885U (en) Tower crane wall attaching device
CN204357150U (en) Wall support frame
CN205424196U (en) Shaft wind pipe connection
CN203639005U (en) Reinforcing device of tower crane
CN103835527B (en) A kind of dismountable supporting device
CN203613651U (en) Connection structure for steel pipe columns and beam
CN104499618A (en) Out-hung wall panel bottom regulating assembly
CN103173582A (en) Method for integral in-position mounting of blast-furnace five-way ball and eduction tubes thereof aloft
CN203767898U (en) Support beam of wall attaching device for tower crane
CN204848023U (en) Braced system that climbing tower hung in external
CN203270443U (en) Support
CN104675095A (en) Adjustable steel pipe support
CN204112729U (en) Pipe well inner sleeve reserves fixed support
CN103291042B (en) A kind of can the curtain wall pendant of three-dimensional regulation
CN205502621U (en) Reinforcing apparatus that is connected of assemblyization building wall and post
CN203247718U (en) Steel column butt-joint mounting device
CN203079591U (en) Crane wall-attaching steel-structure switch connection support
CN203742200U (en) Detachable jacking and supporting device
CN204492135U (en) Adjustable steel tube supports
CN104047387A (en) Short cantilever dry hanging device for stone curtain wall
CN204059898U (en) A kind of convenient inner scaffold regulating height
CN205770186U (en) A kind of airborne equipment mounting bracket

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140611

RJ01 Rejection of invention patent application after publication