CN103730861B - Electric transmission line stay wire manufacturing tool - Google Patents
Electric transmission line stay wire manufacturing tool Download PDFInfo
- Publication number
- CN103730861B CN103730861B CN201310486391.8A CN201310486391A CN103730861B CN 103730861 B CN103730861 B CN 103730861B CN 201310486391 A CN201310486391 A CN 201310486391A CN 103730861 B CN103730861 B CN 103730861B
- Authority
- CN
- China
- Prior art keywords
- wire
- stay
- tie
- support
- transmission line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000005540 biological transmission Effects 0.000 title claims abstract description 15
- 238000004519 manufacturing process Methods 0.000 title abstract description 9
- 238000004804 winding Methods 0.000 claims abstract description 17
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 claims abstract description 7
- 229910052802 copper Inorganic materials 0.000 claims abstract description 7
- 239000010949 copper Substances 0.000 claims abstract description 7
- 230000005611 electricity Effects 0.000 claims description 12
- 238000007789 sealing Methods 0.000 claims description 7
- 238000012423 maintenance Methods 0.000 abstract description 8
- HCHKCACWOHOZIP-UHFFFAOYSA-N Zinc Chemical compound [Zn] HCHKCACWOHOZIP-UHFFFAOYSA-N 0.000 abstract description 5
- 239000011701 zinc Substances 0.000 abstract description 5
- 229910052725 zinc Inorganic materials 0.000 abstract description 5
- 238000005516 engineering process Methods 0.000 abstract description 2
- 238000000576 coating method Methods 0.000 abstract 1
- 230000002035 prolonged effect Effects 0.000 abstract 1
- 230000006378 damage Effects 0.000 description 4
- 230000007797 corrosion Effects 0.000 description 3
- 238000005260 corrosion Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 230000001105 regulatory effect Effects 0.000 description 3
- 208000027418 Wounds and injury Diseases 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 208000014674 injury Diseases 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
The invention relates to an electric transmission line stay wire manufacturing tool. The electric transmission line stay wire manufacturing tool is composed of a guide wire support and tie wire winding tools, the guide wire support is formed by fixing guide wire clamping grooves, guide wire fastening and adjusting bolts and support adjusting bolts on the two sides of the top of a support keel in a bolting mode, and the guide wire support mainly plays a guide wire supporting and fixing role; each tie wire winding tool is composed of a threaded adjusting rod, a wire clamping copper block and a seal bolt, the tie wire winding tools are horizontally arranged on the guide wire fastening and adjusting bolts on the two sides, and the tie wire winding tools are mainly used for winding tie wires of stay wires. Tie wire zinc coatings can not be damaged in the stay wire manufacturing process, work efficiency can be improved, staff investment is reduced, the level of stay wire manufacturing technology is improved, the manufactured stay wires are tightly wound, gaps between turns of the tie wires are not larger than 1mm, and cycle of operation and maintenance of the stay wires under the natural environment is prolonged.
Description
Technical field
The present invention relates to a kind of power circuit stay wire binding tool, applicable electric pressure is 10kV-750kV power circuit bracing wire
Make.
Background technology
Existing transmission line of electricity stay wire binding tool is mainly pliers or the interim stay wire binding tool of other easy making, to bracing wire
Tied silk top layer is zinc-plated to easily cause damage, part pole wire in the administered 35kV-110kV transmission line of electricity of current Hainan electric company
Rust is serious, and company renovates energetically to corrosion bracing wire, and corrosion bracing wire is changed, but due to making at the beginning of just to bracing wire bundle
The destruction of silk zinc coat, and manufacture craft is poor, leads to the bracing wire operation maintenance cycle to be significantly shorter, significantly increases circuit
Maintenance cost and the burst rate of accident potential.
Content of the invention
During the present invention is in order to overcome the shortcomings of to play bracing wire with pliers or other instrument in routine work, provide a kind of suitable
With 10kV-750kV power circuit stay wire making tool, for playing the injury to bracing wire tied silk zinc coat for the bracing wire, work in work
The problem that the aspect such as efficiency and manufacture craft exists, provides a kind of transmission line of electricity stay wire binding tool.
A kind of transmission line of electricity stay wire binding tool of the present invention, this transmission line of electricity stay wire binding tool is twined by wire support and tied silk
Around instrument composition, described wire support is fixed with wire draw-in groove, wire fastening adjustment spiral shell by support keel upper top both sides bolt
Bolt, bracket adjustment bolt composition, act primarily as support fixing wire effect;Described tied silk winding tool is by threaded adjusting bar, card line
Copper billet, sealing bolt composition, lie in a horizontal plane on the wire fastening adjustment bolt of both sides, Main Function is that bracing wire tied silk is twined
Around.So that it can be met to play bracing wire and do not hinder tied silk zinc coat and can improve operating efficiency again, reduce personnel and put into, lifting bracing wire making
Technological level, makes the guy winding made closely, it is characterized in that:Between tied silk circle and circle, gap is not more than 1mm, extends
The cycle of operation maintenance under bracing wire natural environment.
Beneficial effects of the present invention
First, can effectively reduce in bracing wire manufacturing process and bracing wire corrosion phenomena is led to the damage of bracing wire tied silk zinc coat,
Extend the natural environment pull-down line operation maintenance cycle.
2nd, use transmission line of electricity stay wire binding tool, operating efficiency can be improved, the personnel that save put into it is only necessary to a people can be complete
Bracing wire is become to make.
3rd, this instrument can lift bracing wire manufacture craft, makes the bracing wire tied silk colligation produced closely, between circle and circle between
Gap is less than 1mm, more meets bracing wire and makes standard.
4th, this instrument has good practicality, adaptability, has extensive promotional value.
5th, waste of material, reduce loss can be prevented effectively from, meet the demand of circuit regular maintenance and maintenance, for circuit
Engineering construction aspect improves operating efficiency, and the personnel that save put into especially pronounced.
Brief description
Below in conjunction with the drawings and specific embodiments, the present invention is described in further detail.
Fig. 1 is transmission line of electricity stay wire binding tool main structure diagram;
Fig. 2 is the left view structural representation of Fig. 1;
Fig. 3 is wherein, wire notch schematic diagram;
Fig. 4 is the right side structural representation of Fig. 3;
Fig. 5 is the overlooking the structure diagram of Fig. 3;
Fig. 6 is wherein tied silk winding tool structural representation;
Fig. 7 is the right side structural representation of Fig. 6.
Specific embodiment
Referring to the drawings shown in 1-7, wherein:1. wire support, 1.1 support keel, 1.2 wire draw-in grooves, 1.3 wire fastenings
Regulating bolt, 1.4 bracket adjustment bolts;2. tied silk winding tool, 2.1 threaded adjusting bars, 2.2 card line copper billets, 2.3 sealing spiral shells
Bolt.
A kind of transmission line of electricity stay wire binding tool of the present invention, this transmission line of electricity stay wire binding tool is by wire support 1 and tied silk
Winding tool 2 forms, and described wire support 1 is fixed with wire draw-in groove 1.2, wire by support keel 1.1 upper top both sides bolt
Fastening adjustment bolt 1.3, bracket adjustment bolt 1.4 form, and act primarily as support fixing wire effect;Described tied silk winding tool 2
It is made up of threaded adjusting bar 2.1, card line copper billet 2.2, sealing bolt 2.3, during operation, lie in a horizontal plane in both sides wire fastening adjustment
On bolt 1.3, Main Function is the winding to bracing wire tied silk.
The course of work:One. wire support 1 is opened, places steadily, adjusting bracket regulating bolt 1.4, according to real work
In beat the length adjustment of tied silk to suitable position;Two. wire is put in wire support wire draw-in groove 1.2, adjusts wire tight
Gu regulating bolt 1.3, wire is fixed on wire support 1;Three. the sealing bolt 2.3 of tied silk winding tool 2 is unclamped, beats
Opening, tied silk is put between two card line copper billets 2.2, then sealing is closed, and tightens sealing bolt 2.3;Four. adjust binding
Winding tool 2 two ends threaded adjusting bar 2.1, card line copper billet 2.2 is compressed tied silk, and then tied silk is fixed on leading of will being wound around
Winding action colligation tied silk is done around wire on line.Between tied silk circle and circle, gap is not more than 1mm, extends bracing wire nature ring
The cycle of operation maintenance under border.
Claims (1)
1. a kind of transmission line of electricity stay wire binding tool, this transmission line of electricity stay wire binding tool is by wire support(1)And tied silk winding tool
(2)Composition, described wire support(1)By support keel(1.1)Upper top both sides bolt is fixed with wire draw-in groove (1.2), wire
Fastening adjustment bolt (1.3), bracket adjustment bolt (1.4) composition;Described tied silk winding tool(2)By threaded adjusting bar (2.1),
Card line copper billet (2.2), sealing bolt (2.3) composition, lie in a horizontal plane on both sides wire fastening adjustment bolt (1.3), its feature
It is:Between tied silk circle and circle, gap is not more than 1mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310486391.8A CN103730861B (en) | 2013-10-17 | 2013-10-17 | Electric transmission line stay wire manufacturing tool |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310486391.8A CN103730861B (en) | 2013-10-17 | 2013-10-17 | Electric transmission line stay wire manufacturing tool |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103730861A CN103730861A (en) | 2014-04-16 |
CN103730861B true CN103730861B (en) | 2017-02-08 |
Family
ID=50454840
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310486391.8A Active CN103730861B (en) | 2013-10-17 | 2013-10-17 | Electric transmission line stay wire manufacturing tool |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103730861B (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201169949Y (en) * | 2008-03-29 | 2008-12-24 | 安徽省电力公司蚌埠供电公司 | Tools for banding pole guy |
CN201181816Y (en) * | 2008-03-06 | 2009-01-14 | 安徽省电力公司芜湖供电公司 | Drawing wire binding tool |
CN201705001U (en) * | 2010-06-28 | 2011-01-12 | 河南省电力公司平顶山供电公司 | Transmission line tower stay wire manufacturing and fixing device |
CN201913591U (en) * | 2010-12-21 | 2011-08-03 | 宁夏电力公司中卫供电局 | Stay wire bundling and fixing device |
CN202441101U (en) * | 2012-02-24 | 2012-09-19 | 宁夏电力公司吴忠供电局 | Manufacturing support for electric pole stay wire |
CN102946070A (en) * | 2012-11-29 | 2013-02-27 | 宁夏电力公司固原供电局 | Fiber strand device used for wire drawing of electric transmission line |
CN102979350A (en) * | 2012-11-23 | 2013-03-20 | 沧州供电公司 | Stay wire binding tool |
CN202997426U (en) * | 2012-11-29 | 2013-06-12 | 中国石油化工股份有限公司 | Metal binding thread binding tool |
CN203522030U (en) * | 2013-10-17 | 2014-04-02 | 国家电网公司 | Tool for the binding and bracing of power transmission line |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012115037A (en) * | 2010-11-24 | 2012-06-14 | Chugoku Electric Power Co Inc:The | Linear body temporary support tool |
-
2013
- 2013-10-17 CN CN201310486391.8A patent/CN103730861B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201181816Y (en) * | 2008-03-06 | 2009-01-14 | 安徽省电力公司芜湖供电公司 | Drawing wire binding tool |
CN201169949Y (en) * | 2008-03-29 | 2008-12-24 | 安徽省电力公司蚌埠供电公司 | Tools for banding pole guy |
CN201705001U (en) * | 2010-06-28 | 2011-01-12 | 河南省电力公司平顶山供电公司 | Transmission line tower stay wire manufacturing and fixing device |
CN201913591U (en) * | 2010-12-21 | 2011-08-03 | 宁夏电力公司中卫供电局 | Stay wire bundling and fixing device |
CN202441101U (en) * | 2012-02-24 | 2012-09-19 | 宁夏电力公司吴忠供电局 | Manufacturing support for electric pole stay wire |
CN102979350A (en) * | 2012-11-23 | 2013-03-20 | 沧州供电公司 | Stay wire binding tool |
CN102946070A (en) * | 2012-11-29 | 2013-02-27 | 宁夏电力公司固原供电局 | Fiber strand device used for wire drawing of electric transmission line |
CN202997426U (en) * | 2012-11-29 | 2013-06-12 | 中国石油化工股份有限公司 | Metal binding thread binding tool |
CN203522030U (en) * | 2013-10-17 | 2014-04-02 | 国家电网公司 | Tool for the binding and bracing of power transmission line |
Also Published As
Publication number | Publication date |
---|---|
CN103730861A (en) | 2014-04-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108382847A (en) | A kind of aluminium bar production handling device | |
CN103730861B (en) | Electric transmission line stay wire manufacturing tool | |
CN206546747U (en) | A kind of wind-deviation insulator chain | |
CN205428692U (en) | Transformer elliptical coil wire winding steel mould | |
CN203522030U (en) | Tool for the binding and bracing of power transmission line | |
CN201438617U (en) | Electric lifting tool for linear insulator string on ZM tower | |
CN201933831U (en) | Power transmission iron tower shared by +/-800 kV direct-current line and grounding electrode line | |
CN202260254U (en) | Adjustable fixture for live line work of replacing linear whole-string insulator of four-split conductor | |
CN206323068U (en) | A kind of 10kV needle porcelain bottles wire fixing device | |
CN203966781U (en) | A kind of oil-filled transformer | |
CN201478732U (en) | Paying-off block of ultrahigh voltage power transmission line | |
CN201780866U (en) | 90-degree bending spanner for lead wire of coil | |
CN207632245U (en) | A kind of tool of Quick-acting aluminium metallurgy wiring winding | |
CN106602465A (en) | Power transmission line tangent tower first insulator replacement tool | |
CN202688375U (en) | Clamp for iron core annealing process | |
CN207116190U (en) | A kind of amorphous alloy roll-core | |
CN206814111U (en) | A kind of cable maintenance dragging servicing unit | |
CN202564818U (en) | Substation equipment bolt charged fastening device | |
CN207490436U (en) | The double models for hanging V-type composite insulator string replacing options of ± 500kV DC power transmission lines duplex | |
CN202405723U (en) | Combined structure for suspension insulator strings and strain clamps | |
CN206658003U (en) | A kind of strain insulator drainage overlap joint ladder | |
CN203760280U (en) | Lead structure at network side of three-dimensional rolled-iron-core phase-shifting rectification dry-type transformer | |
CN204947467U (en) | Vertical two elevator | |
CN202352362U (en) | Low-wind-pressure conducting wire | |
CN204131058U (en) | Transmission line jumper clamp |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |