CN103726448A - Prestress concrete beam construction tension process - Google Patents

Prestress concrete beam construction tension process Download PDF

Info

Publication number
CN103726448A
CN103726448A CN201310708431.9A CN201310708431A CN103726448A CN 103726448 A CN103726448 A CN 103726448A CN 201310708431 A CN201310708431 A CN 201310708431A CN 103726448 A CN103726448 A CN 103726448A
Authority
CN
China
Prior art keywords
prestress
concrete
reinforcing steel
prestressed
concrete beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310708431.9A
Other languages
Chinese (zh)
Inventor
王赞芝
宝瑙珉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University of Science and Technology
Original Assignee
Guangxi University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University of Science and Technology filed Critical Guangxi University of Science and Technology
Priority to CN201310708431.9A priority Critical patent/CN103726448A/en
Publication of CN103726448A publication Critical patent/CN103726448A/en
Pending legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The invention discloses a prestress concrete beam construction tension process which includes the steps of firstly, penetrating a prestress reinforcing steel bar into a steel die; secondly, tensioning the prestress reinforcing steel bar through a jack; thirdly, fixing the prestress reinforcing steel bar on a support pier through a clamp; fourthly, pouring concrete; fifthly, cutting off and loosening the prestress reinforcing steel bar when the strength of the concrete reach more than 75% of the design strength. By the prestress concrete beam construction tension process, prestress is uniformized effectively, and prestress loss is small.

Description

A kind of construction stretching technique of prestressed concrete beam
Technical field
The present invention relates to a kind of construction stretching technique of prestressed concrete beam.
Background technology
In the structure of prestressed concrete, the tension stress control of presstressed reinforcing steel, can produce directly impact to prestressed effect, and in structure, effective prestress value is excessive or too small to the stress of structure with use safety all can produce adverse influence apart from design load.
The disease of prestressed concrete beam is mainly downwarp and the cracking of beam body, the particularly downwarp of beam body, this can not display when bridge has just built up and detect and test, but in the stage of coming into operation, owing to there being the effect of traveling load, in bridge span, will produce lasting downwarp, this is all because the excessive loss of prestress causing of effective prestress unevenness is excessive, for effective prestress indication is mainly that in concrete beam, reinforcing bar is subject to the stress after stretch-draw, beam being produced, therefore the quality of prestressed stretch-draw processing quality control, can set up accurately, meet the key of the effective prestress value of designing requirement.
Summary of the invention
The technical problem to be solved in the present invention is to overcome existing defect, and a kind of construction stretching technique of prestressed concrete beam is provided.
In order to solve the problems of the technologies described above, the invention provides following technical scheme:
The construction stretching technique of a kind of prestressed concrete beam of the present invention, comprises the following steps:
(1) prestressed reinforcement is placed to fixing punching block;
(2) by jack tension presstressed reinforcing steel;
(3) by fixture, presstressed reinforcing steel is fixed on to buttress;
(4) concrete is built;
(5) until concrete strength, be about 75% when above of design strength, just can cut off, loosen reinforcing bar.
Further, before stretch-draw, check the intensity data of prestressed girder concrete test block, in order to confirm whether modulus of elasticity reaches designing requirement; Confirm requirement when whether concrete strength reaches stretch-draw, and check that template has or not sinkage.
Further, in step (2), during by jack tension presstressed reinforcing steel, adopt the mode of two ends stretch-draw to carry out.
The beneficial effect that the present invention reaches is:
The construction stretching technique of a kind of prestressed concrete beam provided by the invention, effective prestress is even, and loss of prestress is less.
The specific embodiment
Below the preferred embodiments of the present invention are described, should be appreciated that preferred embodiment described herein, only for description and interpretation the present invention, is not intended to limit the present invention.
The construction stretching technique of a kind of prestressed concrete beam of the present invention, comprises the following steps:
(1) prestressed reinforcement is placed to fixing punching block;
(2) by jack tension presstressed reinforcing steel;
(3) by fixture, presstressed reinforcing steel is fixed on to buttress;
(4) concrete is built;
(5) until concrete strength, be about 75% when above of design strength, just can cut off, loosen reinforcing bar.
Before stretch-draw, check the intensity data of prestressed girder concrete test block, in order to confirm whether modulus of elasticity reaches designing requirement; Confirm requirement when whether concrete strength reaches stretch-draw, and check that template has or not sinkage.
In step (2), during by jack tension presstressed reinforcing steel, adopt the mode of two ends stretch-draw to carry out.
The construction stretching technique of a kind of prestressed concrete beam provided by the invention, effective prestress is even, and loss of prestress is less.
Finally it should be noted that: the foregoing is only the preferred embodiments of the present invention, be not limited to the present invention, although the present invention is had been described in detail with reference to previous embodiment, for a person skilled in the art, its technical scheme that still can record aforementioned each embodiment is modified, or part technical characterictic is wherein equal to replacement.Within the spirit and principles in the present invention all, any modification of doing, be equal to replacement, improvement etc., within all should being included in protection scope of the present invention.

Claims (3)

1. a construction stretching technique for prestressed concrete beam, is characterized in that, comprises the following steps:
(1) prestressed reinforcement is placed to fixing punching block;
(2) by jack tension presstressed reinforcing steel;
(3) by fixture, presstressed reinforcing steel is fixed on to buttress;
(4) concrete is built;
(5) until concrete strength, be about 75% when above of design strength, just can cut off reinforcing bar.
2. the construction stretching technique of a kind of prestressed concrete beam according to claim 1, is characterized in that, before stretch-draw, checks the intensity data of prestressed girder concrete test block, in order to confirm whether modulus of elasticity reaches designing requirement; Confirm requirement when whether concrete strength reaches stretch-draw, and check that template has or not sinkage.
3. the construction stretching technique of a kind of prestressed concrete beam according to claim 1, is characterized in that, in step (2), adopts the mode of two ends stretch-draw to carry out during by jack tension presstressed reinforcing steel.
CN201310708431.9A 2013-12-20 2013-12-20 Prestress concrete beam construction tension process Pending CN103726448A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310708431.9A CN103726448A (en) 2013-12-20 2013-12-20 Prestress concrete beam construction tension process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310708431.9A CN103726448A (en) 2013-12-20 2013-12-20 Prestress concrete beam construction tension process

Publications (1)

Publication Number Publication Date
CN103726448A true CN103726448A (en) 2014-04-16

Family

ID=50450719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310708431.9A Pending CN103726448A (en) 2013-12-20 2013-12-20 Prestress concrete beam construction tension process

Country Status (1)

Country Link
CN (1) CN103726448A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2773186A1 (en) * 1997-12-31 1999-07-02 Jae Man Park Pre-stressed structural component cable re-tensioner
KR101140433B1 (en) * 2011-08-11 2012-04-30 삼우건설 주식회사 Method for fabricating prestressed steel composite girder
CN202323717U (en) * 2011-10-28 2012-07-11 科达集团股份有限公司 Cantilever type pre-stress hoop and special tensioning device thereof
CN102747677A (en) * 2012-07-27 2012-10-24 中铁三局集团有限公司 Bridge and construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2773186A1 (en) * 1997-12-31 1999-07-02 Jae Man Park Pre-stressed structural component cable re-tensioner
KR101140433B1 (en) * 2011-08-11 2012-04-30 삼우건설 주식회사 Method for fabricating prestressed steel composite girder
CN202323717U (en) * 2011-10-28 2012-07-11 科达集团股份有限公司 Cantilever type pre-stress hoop and special tensioning device thereof
CN102747677A (en) * 2012-07-27 2012-10-24 中铁三局集团有限公司 Bridge and construction method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李子桥等: ""高架桥箱梁施工技术及质量检查要点"", 《建筑安全》 *
袁辉等: ""大型预应力混凝土闸墩模型试验预应力加载方法研究"", 《人民珠江》 *

Similar Documents

Publication Publication Date Title
CN101440604B (en) Cable opposite pulling type pier-side bracket
CN103953078B (en) Pile tube resistance to plucking single pole power transmission experimental rig
CN102561210B (en) Carbon fiber bar in-vitro prestressed tensioning device and using method thereof
CN104032945A (en) Recyclable rebar anchor pull ring and mounting support thereof
CN103306214A (en) Novel reinforcement device for reinforced concrete beam and floor slab and construction method thereof
CN103243863A (en) Tension anchoring system of pre-stressed wire reinforcing column and construction method
CN104328747A (en) Reinforcement method for single beam bearing of bridge and construction method thereof
CN204551256U (en) One has prestressed simply supported girder bridge bridge floor continuous structure
CN103334541A (en) Steel rib-steel pipe concrete combination column
CN103306495B (en) Wooden construction truncated cylinder reinforced construction method
CN106012834B (en) A kind of spatial warping curve abnormal shape antisymmetry steel king-tower inner support and tensioning system
CN103726448A (en) Prestress concrete beam construction tension process
CN203007855U (en) Stretch-draw anchoring system of pre-stress fiber composite plate
CN205557349U (en) Device is changed to jib
CN204663000U (en) A kind of concreting frame column bar reinforcement positioning device
CN103469737A (en) Method for reinforcing concrete bending member by using variable-bonding prestress carbon fiber plate
CN107503527B (en) Detachable anchorage device for prestressed carbon fiber plates
CN204000644U (en) Large-span prestressed concrete bridge bracing means under tropical monsson climate
CN205874988U (en) Case back board prestressing tendons positioner
CN202099748U (en) Hoisting device used for box girder embedding erection of box girder
CN204325948U (en) A kind of external prestressing unloading consolidation device utilizing assembly pulley principle
CN105155675B (en) A kind of node structure of steel bar girder floor plates integral installation
CN104294751B (en) Reinforcing structure for cross section of large-span prestressed concrete box girder
CN204225098U (en) Overweight reinforcing cage
CN207435921U (en) Build beam body ruggedized construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140416