CN103711131A - Ultra-soft soil large-area deep foundation pit guard post support changing method - Google Patents

Ultra-soft soil large-area deep foundation pit guard post support changing method Download PDF

Info

Publication number
CN103711131A
CN103711131A CN201310727817.4A CN201310727817A CN103711131A CN 103711131 A CN103711131 A CN 103711131A CN 201310727817 A CN201310727817 A CN 201310727817A CN 103711131 A CN103711131 A CN 103711131A
Authority
CN
China
Prior art keywords
foundation pit
ultra
construction
soft soil
deep foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310727817.4A
Other languages
Chinese (zh)
Inventor
李佳
翟强
贲林
颜廷丰
刘宏宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd
Original Assignee
Sixth Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd filed Critical Sixth Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd
Priority to CN201310727817.4A priority Critical patent/CN103711131A/en
Publication of CN103711131A publication Critical patent/CN103711131A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The invention provides an ultra-soft soil large-area deep foundation pit guard post support changing method, and belongs to the technical field of construction. The method includes the steps of firstly, welding and fixing steel corbels and an embedded board, fixedly connecting a fixed end, a middle rod and a movable end to form a supporting rod, and embedding and fixing the supporting rod between the corbels; secondly, connecting and fixing the two ends of each I-beam to end plates, and embedding and fixing the I-beams and the end plates to the two ends of rear pouring belts or the middle portion of a floor or the middle portion of a wall; thirdly, conducting construction of a first concrete belt after the first step and the second step are completed, and then conducting backfilling of graded sand and stone and construction of a second concrete belt; fourthly, detaching an inner support after the first step, the second step and the third step are completed; fifthly, repeatedly executing the steps to conduct support changing of corresponding floors if a plurality of inner supports are arranged on a guard post. The ultra-soft soil large-area deep foundation pit guard post support changing method has the advantages that the uniformity of force transmission of the graded sand and stone, the strength of the concrete structure and the advantages that the steel structure is high in splicing speed and high in efficiency are simultaneously used for conducting inner support change of foundation pit supporting, the influences of the inner supports on structure construction are eliminated, project quality is improved, and the operation is easy to conduct.

Description

A kind of ultra-soft soil property large-area deep foundation pit fender post support replacement method
Technical field
The invention belongs to technical field of building construction.
Background technology
At present, drill-pouring inner support of pile is that more a kind of combined supporting form is applied in China's Coastal Areas, particularly for the excavation of soft clay area large-area deep foundation pit, inner support system can be according to foundation ditch shape independent assortment, and can bring into play good pattern foundation pit supporting structure effect.But, inner support has a very large drawback, be that very large obstacle has been manufactured in the follow-up construction of existing for of inner support, before follow-up construction, must process inner support, make construction have to stop herein, form constuction joint, both affected the progress of construction, affected again the quality of construction.
Summary of the invention
The object of the invention is: a kind of ultra-soft soil property large-area deep foundation pit fender post support replacement method is provided, and it can realize the stressed conversion of fender post inner support and structure self, and simple to operate, easily capable.
Method of the present invention is:
1, steel corbel and buried plate are welded and fixed, fixed end, king-rod, movable end are connected and fixed from the flanged bolt that carries out by end, form strut, strut is mounted between bracket.
2, i iron two ends and end plate are welded to connect fixing, are then mounted in two ends, ater-casting, floor or body of wall middle part; Equipment box out place i iron span centre 1-4 root setting up and down reinforcing bar carry out cross-cut.
3, after above-mentioned " 1 ", " 2 " step complete, carry out the construction of first concrete belt, after it reaches concrete design strength, carry out the backfill of graded sand and stone and the construction of second concrete belt, the absolute altitude of concrete belt is identical with floor absolute altitude, and thickness is identical with slab thickness.
4, until above-mentioned " 1 ", " 2 ", " 3 " step complete and structure self concrete strength reach design strength 80% after, carry out the dismounting of inner support.
If 5 fender posts have multiple tracks inner support, can repeat the step of " 1 ", " 2 ", " 3 " " 4 " and carry out the support replacement of respective storey.
Steel pipe diagonal brace angle is between 40-50 °.
Adopt aggregate grading ratio to be:
Component title Particle diameter (mm) Content (%)
Rubble 2-15 30-40
Sand grains 0.1-2 40-50
Powder <0.1 10-20
The invention has the beneficial effects as follows: utilize the uniformity of graded sand and stone power transmission and the intensity of concrete structure itself, utilize the advantage that steel structure assembling speed is fast, efficiency is high to carry out the inner support conversion of pattern foundation pit supporting structure simultaneously, eliminated the impact of inner support on structure construction, improved workmanship, and operated simply, easily go.
Accompanying drawing explanation
Fig. 1 is support replacement layout plan of the present invention;
Fig. 2 is A-A sectional drawing of the present invention;
Fig. 3 is B-B sectional drawing of the present invention;
Fig. 4 is C-C sectional drawing of the present invention.
The specific embodiment
Embodiment 1
Below in conjunction with accompanying drawing, the present invention is described further:
As shown in the figure, the 1st, steel corbel, the 2nd, fixed end, the 3rd, king-rod, the 4th, movable end, the 5th, buried plate, the 6th, concrete belt, the 7th, graded sand and stone, the 8th, i iron, the 9th, end plate, the 10th, reinforcing bar, the 11st, fender post, the 12nd, equipment boxes out, the 13rd, ater-casting, the 14th, B1, the 15th, underground two layers.
Steel corbel 1 adopts Plate Welding to form, and fixed end 2, king-rod 3, movable end 4 main bodys adopt steel pipe, and diagonal brace angle is 40-50 degree.Its concrete implementation step is as Figure 1-4:
1, steel corbel 1 and buried plate 5 are welded and fixed, fixed end 2, king-rod 3, movable end 4 are carried out to bolt connection by end from flanged, form strut, strut is mounted between bracket.
2, i iron 8 two ends and end plate 9 are welded to connect, are then mounted in 13 two ends, ater-casting, floor or body of wall middle part; Box out span centre two reinforcing bars 10 setting up and down of 12 place's i iron 8 of equipment carry out cross-cut, guarantee the stable of i iron.
3, after " 1 ", " 2 " step complete, carry out the construction of first concrete belt 6, after it reaches concrete design strength, carry out the backfill of graded sand and stone 7 and the construction of second concrete belt 6, the absolute altitude of concrete belt 6 is identical with floor absolute altitude, the same slab thickness of thickness.
4, until " 1 ", " 2 ", " 3 " step complete and structure self concrete strength reach design strength 80% after, carry out the dismounting of inner support.
If 5 fender posts have multiple tracks inner support, can repeat the step of " 1 ", " 2 ", " 3 " " 4 " and carry out the support replacement of respective storey.
By said method, can successfully realize the stressed conversion of ultra-soft soil property large-area deep foundation pit fender post inner support and structure self.

Claims (3)

1. a ultra-soft soil property large-area deep foundation pit fender post support replacement method, its method is:
A, steel corbel and buried plate are welded and fixed, fixed end, king-rod, movable end are connected and fixed from the flanged bolt that carries out by end, form strut, strut is mounted between bracket;
B, i iron two ends and end plate are welded to connect fixing, are then mounted in two ends, ater-casting, floor or body of wall middle part; Equipment box out place i iron span centre 1-4 root setting up and down reinforcing bar carry out cross-cut;
C, after above-mentioned a, b step complete, carry out the construction of first concrete belt, after it reaches concrete design strength, carry out the backfill of graded sand and stone and the construction of second concrete belt, the absolute altitude of concrete belt is identical with floor absolute altitude, and thickness is identical with slab thickness;
D, until above-mentioned a, b, c step complete and structure self concrete strength reach design strength 80% after, carry out the dismounting of inner support;
If e fender post has multiple tracks inner support, the step that can repeat a, b, c, d is carried out the support replacement of respective storey.
2. a kind of ultra-soft soil property large-area deep foundation pit fender post support replacement method as claimed in claim 1, is characterized in that: steel pipe diagonal brace angle is between 40-50 °.
3. a kind of ultra-soft soil property large-area deep foundation pit fender post support replacement method as claimed in claim 1, is characterized in that:
Adopt aggregate grading ratio to be
The rubble of 2-15 mm is 30-40%;
The sand grains of 0.1-2 mm is 40-50%;
The powder of <0.1 mm be 10-20%.
CN201310727817.4A 2013-12-26 2013-12-26 Ultra-soft soil large-area deep foundation pit guard post support changing method Pending CN103711131A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310727817.4A CN103711131A (en) 2013-12-26 2013-12-26 Ultra-soft soil large-area deep foundation pit guard post support changing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310727817.4A CN103711131A (en) 2013-12-26 2013-12-26 Ultra-soft soil large-area deep foundation pit guard post support changing method

Publications (1)

Publication Number Publication Date
CN103711131A true CN103711131A (en) 2014-04-09

Family

ID=50404451

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310727817.4A Pending CN103711131A (en) 2013-12-26 2013-12-26 Ultra-soft soil large-area deep foundation pit guard post support changing method

Country Status (1)

Country Link
CN (1) CN103711131A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040709A (en) * 2015-08-11 2015-11-11 中铁建大桥工程局集团第五工程有限公司 Construction method for support replacement of fender-post retaining and protecting of deep foundation pit
CN105442613A (en) * 2015-11-16 2016-03-30 广西建工集团第一建筑工程有限责任公司 Fixing installation method for steel tube vertical inclined brace support pre-embedded steel plate and reinforcing cage
CN105507329A (en) * 2015-11-27 2016-04-20 中国一冶集团有限公司 Support replacement system for base plates of foundation pit of mucky soil layer in deep foundation pit support construction
CN107288137A (en) * 2017-08-21 2017-10-24 中建八局浙江建设有限公司 Detachable support replacement device and its construction method
CN110185043A (en) * 2019-06-14 2019-08-30 中国十七冶集团有限公司 A kind of deep foundation pit support inner support support replacement method
CN110318403A (en) * 2019-07-15 2019-10-11 重庆建工第七建筑工程有限责任公司 A kind of deep basal pit inner support assembled support replacement construction tool and construction method
CN114411757A (en) * 2022-02-08 2022-04-29 中建八局南方建设有限公司 Early-dismantling construction method for inner support partition of deep foundation pit
CN115012428A (en) * 2022-06-22 2022-09-06 中国二十二冶集团有限公司 Basement deep foundation pit replacing support and construction method thereof
CN115559323A (en) * 2022-11-11 2023-01-03 中交第一航务工程局有限公司 Construction method for conversion of deep foundation pit supporting system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004031510A2 (en) * 2002-10-07 2004-04-15 Man-Yop Han Innovative prestressed scaffolding system
CN201151909Y (en) * 2007-11-15 2008-11-19 王平 Deep foundation pit composite structure annular inner support
CN101718094A (en) * 2009-11-10 2010-06-02 朱奎 Construction method for retaining and protecting foundation pit of building with basemen
CN103225307A (en) * 2013-04-08 2013-07-31 广东省基础工程公司 Construction method for dynamic steel supporting system of deep foundation pit

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004031510A2 (en) * 2002-10-07 2004-04-15 Man-Yop Han Innovative prestressed scaffolding system
WO2004031510A3 (en) * 2002-10-07 2004-06-24 Man-Yop Han Innovative prestressed scaffolding system
CN201151909Y (en) * 2007-11-15 2008-11-19 王平 Deep foundation pit composite structure annular inner support
CN101718094A (en) * 2009-11-10 2010-06-02 朱奎 Construction method for retaining and protecting foundation pit of building with basemen
CN103225307A (en) * 2013-04-08 2013-07-31 广东省基础工程公司 Construction method for dynamic steel supporting system of deep foundation pit

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张斌: "滨海地区超高层建筑群共同围护体系支撑转换施工技术", 《建筑施工》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040709A (en) * 2015-08-11 2015-11-11 中铁建大桥工程局集团第五工程有限公司 Construction method for support replacement of fender-post retaining and protecting of deep foundation pit
CN105442613A (en) * 2015-11-16 2016-03-30 广西建工集团第一建筑工程有限责任公司 Fixing installation method for steel tube vertical inclined brace support pre-embedded steel plate and reinforcing cage
CN105507329A (en) * 2015-11-27 2016-04-20 中国一冶集团有限公司 Support replacement system for base plates of foundation pit of mucky soil layer in deep foundation pit support construction
CN107288137A (en) * 2017-08-21 2017-10-24 中建八局浙江建设有限公司 Detachable support replacement device and its construction method
CN107288137B (en) * 2017-08-21 2019-05-17 中建八局浙江建设有限公司 Detachable support replacement device and its construction method
CN110185043A (en) * 2019-06-14 2019-08-30 中国十七冶集团有限公司 A kind of deep foundation pit support inner support support replacement method
CN110318403A (en) * 2019-07-15 2019-10-11 重庆建工第七建筑工程有限责任公司 A kind of deep basal pit inner support assembled support replacement construction tool and construction method
CN114411757A (en) * 2022-02-08 2022-04-29 中建八局南方建设有限公司 Early-dismantling construction method for inner support partition of deep foundation pit
CN115012428A (en) * 2022-06-22 2022-09-06 中国二十二冶集团有限公司 Basement deep foundation pit replacing support and construction method thereof
CN115559323A (en) * 2022-11-11 2023-01-03 中交第一航务工程局有限公司 Construction method for conversion of deep foundation pit supporting system

Similar Documents

Publication Publication Date Title
CN103711131A (en) Ultra-soft soil large-area deep foundation pit guard post support changing method
CN101775844B (en) Connecting joint of ring beam of steel core concrete column used for topdown construction method foundation pit engineering
CN103669866B (en) The construction method of basement reinforced concrete post node connecting structure
CN105386454B (en) A kind of joint assembling type base for power transmission tower
CN104097253A (en) Environment-friendly movable precast track beam formwork system in straddle type monorail transit
CN104179249A (en) Assembled composite-structure earthquake-resistant wall and assembly method thereof
CN205806684U (en) A kind of across base pit engineering conduit wiring suspension structure
CN201962844U (en) Hollow composition board internally provided with steel pipes and steel plates
CN104532856A (en) Fabricated lattice unit for foundation pit supporting and installation method
CN103643681B (en) A kind of Metro station excavation is inverse makes supporting and protection structure and construction method thereof
CN107313628A (en) A kind of basic digging-free assembled tower-type space garage and its construction method
CN102733406B (en) Railway construction method of solid concrete roadbed in large-size industrial plant
CN107938498B (en) Assembled steel pier column and assembled gate-type steel pier
CN106592777A (en) Assembly type steel-concrete combined beam column joint structure and implementation method thereof
CN116607558A (en) Prefabricated assembled foundation of main transformer equipment of transformer substation and construction method of prefabricated assembled foundation
CN103437349B (en) The construction method of steel concrete perfusion shaped pile
CN202767281U (en) Assembly type reinforced concrete combination back wall
CN207211869U (en) A kind of basic digging-free assembled tower-type space garage
CN201598734U (en) Concrete filled steel tubular column ring beam joint for topdown construction method foundation pit engineering
CN202346643U (en) Assembled tower crane base
CN213508572U (en) Piping lane supporting construction
CN106337373B (en) Construction method for obliquely penetrating existing line overhead jacking box culvert
CN204040058U (en) Combined tower crane foundation structure
CN202509490U (en) Steel-concrete combined pile capable of being disassembled under load by segments and being repeatedly used
CN204960366U (en) Tunnel passes through device that underpins of existing large diameter pile building

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140409