CN103696374A - Straddle method of cantilever of long-span simply supported steel truss beam of horizontal curve section - Google Patents

Straddle method of cantilever of long-span simply supported steel truss beam of horizontal curve section Download PDF

Info

Publication number
CN103696374A
CN103696374A CN201310726919.4A CN201310726919A CN103696374A CN 103696374 A CN103696374 A CN 103696374A CN 201310726919 A CN201310726919 A CN 201310726919A CN 103696374 A CN103696374 A CN 103696374A
Authority
CN
China
Prior art keywords
cantilever
span
curve
main truss
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310726919.4A
Other languages
Chinese (zh)
Other versions
CN103696374B (en
Inventor
高宗余
徐伟
肖海珠
张燕飞
彭振华
侯健
梅新咏
徐力
郑清刚
龚俊
张建强
胡文军
罗扣
何东升
张金涛
苑仁安
王恒
刘厚军
唐斌
戴慧敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Railway Group Co Ltd
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Original Assignee
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Reconnaissance and Design Institute Co Ltd filed Critical China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority to CN201310726919.4A priority Critical patent/CN103696374B/en
Publication of CN103696374A publication Critical patent/CN103696374A/en
Application granted granted Critical
Publication of CN103696374B publication Critical patent/CN103696374B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a straddle method of a cantilever of a long-span simply supported steel truss beam of the horizontal curve section. The straddle method comprises calculating the lengths of main truss rods arranged on the inner side and the outer side of a cantilever span curve and main truss rods arranged on the inner side and the outer side of an anchor span curve according to the radius of a horizontal curve, the position on the horizontal curve of a bridge span structure and the main truss spacing; hoisting the main truss rods arranged on the inner side and the outer side of the cantilever span curve to the position of a permanent support arranged at the top of an Nth pier, enabling the permanent support arranged at the pier top and the main truss rods arranged on the inner side and the outer side of the anchor span curve to be connected together through a temporary connection structure and performing cantilever construction of steel beam rods along the design axis; removing the temporary connection structure after the bridge span is straddled in place. According to the straddle method of the cantilever of the long-span simply supported steel truss beam of the horizontal curve section, the horizontal pushing in-place operation of the steel beam in the process of construction is avoided successfully, the construction process is simplified, the straddle construction of the cantilever of the long-span simply supported steel truss beam of the horizontal curve section can be greatly simplified, the stress is reliable, the construction is convenient, the operation is simple, temporary construction facilities and field workloads of the pier top are reduced, the construction progress greatly speeds up, the construction cost is saved, and the economic benefit is remarkable.

Description

Horizontal curve section is greatly across freely-supported steel trussed beam cantilever erection method
Technical field
The present invention relates to a kind of horizontal curve section greatly across freely-supported steel trussed beam cantilever erection method.
Background technology
At present the length of highway, railroad bridge building project general all more than several kilometers, even tens kilometers, due to the demand of beam section wiring, so long circuit can not be all on straightway, therefore a large amount of non-navigation bridges may be disposed on curved section.For reducing design, manufacture and the difficulty of construction, general by the structure design section of being in line of multispan freely-supported, on horizontal curve, " to roll over Dai Qu " carries out span distribution.For greatly, across freely-supported steel truss girder bridge, free cantilever erection is a kind of economically viable method, in construction, is widely adopted.But when steel truss girder bridge is disposed on horizontal curve, between adjacent axis, can have a drift angle, traditional free cantilever erection will make cantilever span in work progress, depart from its center line, can be with the problem of serving like this:
(1) need set up interim fulcrum at Dun Ding: due to adjacent, have angle between across axis, during cantilever erection, front end fulcrum and anchoring fulcrum all can off-design positions, must interim fulcrum be set in addition at each Dun Ding so.
(2) need carry out lateral pushing operation: after cantilever erection arrives interim fulcrum, need carry out the operation that lateral pushing is adjusted axis, make bridge span structure in place, so just must be equipped with corresponding lateral pushing equipment and device, bridge pier size will increase thereupon accordingly.
(3) affect loop wheel machine safety: during lateral pushing operation, loop wheel machine is still on bridge span structure, and its construction safety performance is affected.
For the longspan steel truss girder crane span structure on curved section, establish, also have at present some good tries, for example: before free cantilever erection, anchoring is adjusted to a suitable angle across beam-ends, reduce the lateral pushing shift value of structure after assembled completing; At N+1 Dun Ding, lay slide plate, reduce lateral pushing power etc.These methods can reduce the difficulty of construction to a certain extent, but cannot be from solving in fact the problem of bringing due to axis runout.
Summary of the invention
The object of the invention is for above-mentioned present situation, aim to provide a kind of cantilever bridge that can fundamentally solve across the problem of axis runout, construction speed is high, and easy construction, cost are low, can stablize, at curved section, set up greatly the method across freely-supported steel trussed beam cantilever efficiently.
The object of the invention is to be achieved through the following technical solutions, horizontal curve section is greatly across freely-supported steel trussed beam cantilever erection method, and concrete steps are as follows:
1) according to radius of horizontal curve, bridge span structure, the position on horizontal curve and main truss spacing utilize geometrical relationship to calculate cantilever span curve medial and lateral main truss rod member and anchoring across the length of curve medial and lateral main truss rod member, in the plane, outside cantilever span curve, the length of main truss rod member is greater than the length of the inner side of curve main truss rod member;
2) by cantilever span curve medial and lateral main truss member erection to the permanent support position of N Dun Ding, adopt the interim structure that connects that the permanent bearing of Dun Ding and anchoring are linked together across curve medial and lateral main truss rod member;
Interim connection is configured to the scab with knuckle, and knuckle equals cantilever span girder center line and anchoring across the drift angle between girder center line;
3) adjust the traveling speed in outside in loop wheel machine, loop wheel machine is turned over after corner α, run on cantilever span rod member, along bridge axis free cantilever erection steel truss girder;
Described corner α is that anchoring is across the angle between axis and cantilever span axis;
4) cantilever end fulcrum is dropped on the permanent bearing of N+1 Dun Ding, remove the interim structure that connects;
Rod member is assembled to N+1 Dun Ding, acts directly on permanent fulcrum; Remove N Dun Ding and connect temporarily, complete this construction of free cantilever erection across structure.
The present invention has successfully avoided the girder steel lateral pushing in work progress with regard to bit manipulation, can reduce pier top temporary construction facility and site work amount; After structure free cantilever erection is in place, each pier top position of the fulcrum, all without adjustment, has been simplified working procedure.
The invention enables greatly simplifying across the construction of freely-supported steel truss girder bridge cantilever erection greatly on curved section, stressed reliable, easy construction, simple to operate, accelerating construction progress, saves construction cost, remarkable in economical benefits.
Accompanying drawing explanation
Fig. 1 is free cantilever erection floor map,
Fig. 2 is that N pier pushes up local enlarged diagram,
Fig. 3 is the local enlarged diagram of novel interim splicing structure.
The specific embodiment
With reference to the accompanying drawings 1,2,3, the concrete steps in conjunction with horizontal curve section freely-supported steel trussed beam cantilever erection method, elaborate the present invention.
1) according to radius of horizontal curve, bridge span structure the position on horizontal curve and main truss distance computation cantilever span curve medial and lateral main truss rod member and anchoring across the length of curve medial and lateral main truss rod member.
Long+1/2 * sin α * main truss of main truss rod member length outside curve=internode spacing
Long-1/2 * sin α * main truss of the inner side of curve main truss rod member length=internode spacing
In the plane, the length of main truss rod member is greater than the length of the inner side of curve main truss rod member outside cantilever span curve, and its difference is sin α * main truss spacing;
2) main truss rod member 1, cantilever span the inner side of curve main truss rod member 3 outside cantilever span curve are lifted to the permanent bearing of N Dun Ding 6 positions, adopt the interim structure 5 that connects that the permanent bearing of Dun Ding and anchoring are linked together across the inner side of curve main truss rod member 4 across main truss rod member 2, anchoring outside curve;
The interim structure 5 that connects is the scab with knuckle, and knuckle equals cantilever span girder center line and anchoring across the drift angle between girder center line;
3) adjust the traveling speed in outside in loop wheel machine, loop wheel machine is turned over after corner α, run on cantilever span rod member, along bridge axis 7 free cantilever erection steel truss girders; In cantilever erection process, cantilever bridge axis is all the time along design axis direction.
Described corner α be anchoring across the angle between axis 9 and cantilever span axis 7, this corner is that the span distribution (i.e. " to roll over Dai Qu ") on curved section that is designed to straightway produces.The present invention has successfully overcome this corner, makes the free cantilever erection construction of cantilever span all the time along axis direction.Otherwise, after steel girder erection is in place, must eliminate corner α by lateral pushing.
4) cantilever end fulcrum is dropped on the permanent bearing 8 of N+1 Dun Ding, remove the interim structure that connects;
N+1 Dun Ding is equally without arranging interim fulcrum, and cantilever span rod member is assembled to N+1 Dun Ding, can act directly on permanent fulcrum.Remove N Dun Ding and connect temporarily, complete this construction of free cantilever erection across structure.
The present invention, in whole free cantilever erection process, does not arrange any interim fulcrum, and cantilever bridge all adopts permanent fulcrum across N, N+1 Dun Ding.Complete the spanning of free cantilever erection without carrying out any pushing tow and bearing adjusting operation, can as anchoring, across the cantilever erection that participates in next spanning, construct immediately.

Claims (5)

1. horizontal curve section, greatly across freely-supported steel trussed beam cantilever erection method, is characterized in that concrete steps are as follows:
1) according to radius of horizontal curve, bridge span structure, the position on horizontal curve and main truss spacing utilize geometrical relationship to calculate cantilever span curve medial and lateral main truss rod member and anchoring across the length of curve medial and lateral main truss rod member, in the plane, outside cantilever span curve, the length of main truss rod member is greater than the length of cantilever span the inner side of curve main truss rod member;
2) by cantilever span curve medial and lateral main truss member erection to the permanent support position of N Dun Ding, adopt the interim structure that connects that the permanent bearing of Dun Ding and anchoring are linked together across curve medial and lateral main truss rod member;
Interim connection is configured to the scab with knuckle, and knuckle equals cantilever span girder center line and anchoring across the drift angle between girder center line;
3) adjust the traveling speed in outside in loop wheel machine, loop wheel machine is turned over after corner α, run on cantilever span rod member, along bridge axis free cantilever erection steel truss girder;
Described corner α is that anchoring is across the angle between axis and cantilever span axis;
4) cantilever end fulcrum is dropped on the permanent bearing of N+1 Dun Ding, remove the interim structure that connects;
Rod member is assembled to N+1 Dun Ding, acts directly on permanent fulcrum; Remove N Dun Ding and connect temporarily, complete this construction of free cantilever erection across structure.
2. horizontal curve section freely-supported steel trussed beam cantilever erection method according to claim 1, is characterized in that the length position on horizontal curve and design of main truss spacing according to bridge span structure of spanning end main truss rod member.
3. horizontal curve section freely-supported steel trussed beam cantilever erection method according to claim 1, it is characterized in that anchoring across and the axis of cantilever span between there is angle, adopt with the interim connection construction complete anchoring of knuckle across with cantilever span between the interim of main truss rod member be connected.
4. horizontal curve section freely-supported steel trussed beam cantilever erection method according to claim 1, is characterized in that, in whole free cantilever erection process, cantilever bridge all adopts permanent fulcrum across N, N+1 Dun Ding.
5. horizontal curve section freely-supported steel trussed beam cantilever erection method according to claim 1, is characterized in that in cantilever erection process, cantilever bridge axis across all the time along design axis direction.
CN201310726919.4A 2013-12-25 2013-12-25 Horizontal curve section is greatly across freely-supported steel trussed beam cantilever erection method Active CN103696374B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310726919.4A CN103696374B (en) 2013-12-25 2013-12-25 Horizontal curve section is greatly across freely-supported steel trussed beam cantilever erection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310726919.4A CN103696374B (en) 2013-12-25 2013-12-25 Horizontal curve section is greatly across freely-supported steel trussed beam cantilever erection method

Publications (2)

Publication Number Publication Date
CN103696374A true CN103696374A (en) 2014-04-02
CN103696374B CN103696374B (en) 2015-10-28

Family

ID=50358024

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310726919.4A Active CN103696374B (en) 2013-12-25 2013-12-25 Horizontal curve section is greatly across freely-supported steel trussed beam cantilever erection method

Country Status (1)

Country Link
CN (1) CN103696374B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107974917A (en) * 2017-11-15 2018-05-01 中铁大桥勘测设计院集团有限公司 One kind bending node, curve continuous steel girder bridge and its design method
CN108265632A (en) * 2018-03-27 2018-07-10 洛阳理工学院 Curved bridge fitting layout stracture and its distribution method based on orthogonal precast beam
CN108755384A (en) * 2018-07-27 2018-11-06 山东大学 A kind of belt track free cantilever erection steel girder bridge and its construction method
CN109537800A (en) * 2018-11-30 2019-03-29 中国建筑第八工程局有限公司 Super-span overhangs prestressed arc-shape steel beam structure and its construction method
CN111501564A (en) * 2020-04-22 2020-08-07 中交第三航务工程局有限公司 Corner arc track arrangement process
CN111764300A (en) * 2020-07-21 2020-10-13 安徽省交通建设股份有限公司 Curved steel beam pushing system and construction method
CN112144401A (en) * 2020-06-28 2020-12-29 中交第二航务工程局有限公司 Bridge girder erection machine over-span method based on curve track and large longitudinal slope environment
CN112411343A (en) * 2020-11-30 2021-02-26 中交路桥建设有限公司 Mountain area ultrahigh traffic-guaranteeing curve cast-in-place box girder combined support and erection method
CN114626137A (en) * 2022-04-15 2022-06-14 中铁大桥局集团有限公司 Method for acquiring curve section steel truss girder of large-span steel-concrete combined continuous beam bridge

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2297491C2 (en) * 2005-06-03 2007-04-20 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Device for bridge span structure protrusion
KR100909839B1 (en) * 2008-05-21 2009-07-28 우경건설 주식회사 Curve type preflexion steel beam frame using preflexion for installing reinforcing material at curved steel material of a curved steel frame and method for manufacturing the same
CN102041782A (en) * 2010-12-10 2011-05-04 合肥中铁钢结构有限公司 Multi-point pushing system of large-span steel truss girders and pushing process thereof
CN102409616A (en) * 2011-09-09 2012-04-11 中交第四公路工程局有限公司第五工程处 Construction method of bridge girder with ultra-small radius and bridge erecting machine used in same
CN102433840A (en) * 2011-12-28 2012-05-02 中铁大桥局股份有限公司 Incremental launching construction method for large-tonnage steel truss girder and sliding block switching system
CN102747691A (en) * 2012-08-02 2012-10-24 中铁二十三局集团有限公司 Integral pushing erection method for truss girders
CN103205935A (en) * 2013-03-11 2013-07-17 中交武汉港湾工程设计研究院有限公司 Automatic pushing system for modular steel truss and construction technology for automatic pushing system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2297491C2 (en) * 2005-06-03 2007-04-20 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Device for bridge span structure protrusion
KR100909839B1 (en) * 2008-05-21 2009-07-28 우경건설 주식회사 Curve type preflexion steel beam frame using preflexion for installing reinforcing material at curved steel material of a curved steel frame and method for manufacturing the same
CN102041782A (en) * 2010-12-10 2011-05-04 合肥中铁钢结构有限公司 Multi-point pushing system of large-span steel truss girders and pushing process thereof
CN102409616A (en) * 2011-09-09 2012-04-11 中交第四公路工程局有限公司第五工程处 Construction method of bridge girder with ultra-small radius and bridge erecting machine used in same
CN102433840A (en) * 2011-12-28 2012-05-02 中铁大桥局股份有限公司 Incremental launching construction method for large-tonnage steel truss girder and sliding block switching system
CN102747691A (en) * 2012-08-02 2012-10-24 中铁二十三局集团有限公司 Integral pushing erection method for truss girders
CN103205935A (en) * 2013-03-11 2013-07-17 中交武汉港湾工程设计研究院有限公司 Automatic pushing system for modular steel truss and construction technology for automatic pushing system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
程慧林: "曲线桥顶推施工技术", 《铁道建筑技术》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107974917B (en) * 2017-11-15 2019-04-16 中铁大桥勘测设计院集团有限公司 A kind of bending node, curve continuous steel girder bridge and its design method
CN107974917A (en) * 2017-11-15 2018-05-01 中铁大桥勘测设计院集团有限公司 One kind bending node, curve continuous steel girder bridge and its design method
CN108265632A (en) * 2018-03-27 2018-07-10 洛阳理工学院 Curved bridge fitting layout stracture and its distribution method based on orthogonal precast beam
CN108265632B (en) * 2018-03-27 2023-12-26 洛阳理工学院 Curve bridge fitting layout structure based on orthogonal precast beam plates and layout method thereof
CN108755384B (en) * 2018-07-27 2023-06-02 山东大学 Cantilever assembled steel truss bridge with track and construction method thereof
CN108755384A (en) * 2018-07-27 2018-11-06 山东大学 A kind of belt track free cantilever erection steel girder bridge and its construction method
CN109537800A (en) * 2018-11-30 2019-03-29 中国建筑第八工程局有限公司 Super-span overhangs prestressed arc-shape steel beam structure and its construction method
CN111501564A (en) * 2020-04-22 2020-08-07 中交第三航务工程局有限公司 Corner arc track arrangement process
CN112144401A (en) * 2020-06-28 2020-12-29 中交第二航务工程局有限公司 Bridge girder erection machine over-span method based on curve track and large longitudinal slope environment
CN111764300A (en) * 2020-07-21 2020-10-13 安徽省交通建设股份有限公司 Curved steel beam pushing system and construction method
CN111764300B (en) * 2020-07-21 2022-03-25 安徽省交通建设股份有限公司 Curved steel beam pushing system and construction method
CN112411343A (en) * 2020-11-30 2021-02-26 中交路桥建设有限公司 Mountain area ultrahigh traffic-guaranteeing curve cast-in-place box girder combined support and erection method
CN114626137A (en) * 2022-04-15 2022-06-14 中铁大桥局集团有限公司 Method for acquiring curve section steel truss girder of large-span steel-concrete combined continuous beam bridge
CN114626137B (en) * 2022-04-15 2024-04-19 中铁大桥局集团有限公司 Method for obtaining large-span steel-concrete combined continuous beam bridge curve section steel truss girder

Also Published As

Publication number Publication date
CN103696374B (en) 2015-10-28

Similar Documents

Publication Publication Date Title
CN103696374B (en) Horizontal curve section is greatly across freely-supported steel trussed beam cantilever erection method
CN102182147B (en) Steel box girder erection method
CN104328745B (en) Across the rotary body device of the little bridge beam of high ferro and construction method thereof on a kind of low-angle
CN103215894B (en) Portable interim prestressed stretch-draw anchor block
CN207079483U (en) Guiding and deviation correcting device available for Large-span Steel Box Beam construction
CN103643640A (en) Jacking-first and line-reinforcement-second jacking construction method for frame bridge
CN103046476A (en) Railway long-span rotator T-shaped bridge construction method
CN106702909A (en) Integral swiveling structure for double-body steel box girder and construction method thereof
CN102134832B (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN104947604A (en) Rapid beam-replacing construction method for high speed railway 900 t concrete box beam
CN104018426A (en) Steel truss installation method
CN203559354U (en) Stay cable anchoring structure applied to prestressed concrete partially cable-stayed bridge
CN102518034B (en) Bidirectional pre-bent multi-steel-girder and concrete bridge deck combined small box girder bridge structure
CN103924528A (en) Overall long-distance pushing slippage construction method for large-span bridge box girder structure of large-span bridge
CN103774543A (en) Deck bridge with cable-arch combination structure
CN201560397U (en) Whole support for steel box girder precise location installation
CN103184721B (en) Method for performing block-by-block suspension, glue splicing and linear control on precast segments to assemble polycarbonate (PC) continuous box girder
CN108978485B (en) Method for on-site installation of anchor plate of steel structure cable-stayed bridge
CN204112239U (en) Across the rotary body device of the little bridge beam of high ferro on a kind of low-angle
CN104314009A (en) Large segment lifting mechanism and use method thereof
CN103628421A (en) Horizontal swivel construction system and method for simply supported steel trussed beam
CN104110002A (en) Method for replacing bridge deck slabs of steel truss girder bridge
CN203716044U (en) Low bearing or middle bearing cable arch combined structural bridge
CN111794109A (en) Large-span bridge fabrication machine and continuous hole passing process method for large-span combined beam
CN202298438U (en) Bidirectional pre-bent multi-beam type structure of small steel-concrete box girder bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20151221

Address after: 430050 Hanyang Road, Hubei, Wuhan, No. 34

Patentee after: China Zhongtie Major Bridge Reconnaissance & Design Institute Co., Ltd.

Patentee after: CHINA RAILWAY CORPORATION

Address before: 430050 Hanyang Road, Hubei, Wuhan, No. 34

Patentee before: China Zhongtie Major Bridge Reconnaissance & Design Institute Co., Ltd.