CN103669821B - Detachable gantry installation frame and hanging basket - Google Patents
Detachable gantry installation frame and hanging basket Download PDFInfo
- Publication number
- CN103669821B CN103669821B CN201310674970.5A CN201310674970A CN103669821B CN 103669821 B CN103669821 B CN 103669821B CN 201310674970 A CN201310674970 A CN 201310674970A CN 103669821 B CN103669821 B CN 103669821B
- Authority
- CN
- China
- Prior art keywords
- installation frame
- tube
- gantry installation
- transverse tube
- fastener
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Types And Forms Of Lifts (AREA)
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
The present invention relates to a kind of Detachable gantry installation frame, vertical tube and transverse tube including both sides, each transverse tube two ends are connected on the vertical tube of both sides by U-shaped ferrum respectively, U-shaped ferrum is connected on two vertical tubes, is provided with land wheel bottom vertical tube, and riser upper portions is provided with fastener, Detachable gantry installation frame is connected with work platforms by fastener, load onto elevator, safety lock, steel wire rope, switch on power and achieve that cage lifting runs and workman's constructing operation.The present invention has simple in construction, conveniently moving, the bonding strength advantage such as detachably good, the most moderate, can meet the construction demand of various different special construction metope.
Description
Technical field
The present invention relates to a kind of portal frame, specifically a kind of Detachable gantry installation frame, belong to lowering or hoisting gear technical field.
Background technology
At present, high-lift operation hanging cradle is widely used to building trade in China, varied along with capital construction building style, common hanging basket installing rack can not fully meet the needs of construction, such as the chimney in some building, within doors square hole etc., end face can not install normal formula leverage, and also frame of sitting on the fence is installed in inconvenience, the width of metope, direction, position the most constantly change in construction progress, it is therefore desirable to be developed to adapt to the installing rack of special construction requirement.
Summary of the invention
The invention aims to overcome tradition gantry installation frame too high, mobile inconvenience, the shortcomings such as integral structure is complicated, it is provided that a kind of simple in construction, bonding strength flexible dismountable gantry installation frame good, small and exquisite.
The technical solution used in the present invention is as follows: a kind of Detachable gantry installation frame, including the vertical tube of both sides and the transverse tube that is connected between two montants, described transverse tube includes being positioned at the top horizontal pipe at top, superposed upper lateral tube, being positioned at the middle transverse tube at middle part and be positioned at the end transverse tube of bottom;Each transverse tube two ends are connected on the vertical tube of both sides by U-shaped ferrum respectively, and the lower end of two vertical tubes is equipped with land wheel, and the top of two vertical tubes is provided with the fixing fastener connecting work platforms.
Further, described U-shaped ferrum is connected on vertical tube, and described U-shaped ferrum is provided with two bolt through-holes.
Further, described fastener includes two piece of four orifice plate and four bolts.
Further, the fastener on described Detachable gantry installation frame top is connected with work platforms, loads onto elevator in the middle part of Detachable gantry installation frame, and safety lock is loaded onto on Detachable gantry installation frame top, and steel wire penetrating rope sheave is hanging on the main joint hinge on top.
The present invention has simple in construction, conveniently moving, the bonding strength advantage such as detachably good, the most moderate, can meet the construction demand of various different special construction metope.
Accompanying drawing explanation
Fig. 1 is the structural representation of Detachable gantry installation frame of the present invention.
Fig. 2 is the operating diagram of Detachable gantry installation frame of the present invention.
Fig. 3 is the partial enlarged drawing of the U-shaped ferrum of Detachable gantry installation frame of the present invention.
Reference: transverse tube, 6-land wheel, 7-fastener, 8-U sections, 9-work platforms, 10-platform upper lateral tube, 11-elevator, steel wire rope 12 at the bottom of transverse tube, 5-in 1-vertical tube, 2-top horizontal pipe, 3-upper lateral tube, 4-.
Detailed description of the invention
Below in conjunction with concrete accompanying drawing, the invention will be further described.
As shown in Figure 1-Figure 3, a kind of Detachable gantry installation frame, including the vertical tube 1 of both sides and the transverse tube that is connected between two vertical tubes, transverse tube includes being positioned at the top horizontal pipe 2 at top, superposed upper lateral tube 3, being positioned at the middle transverse tube 4 at middle part and be positioned at the end transverse tube 5 of bottom, two vertical tubes are provided with U-shaped ferrum (4mm is thick), U-shaped ferrum is provided with two bolt through-holes, and two circular holes at each transverse tube two ends are directed at two bolt through-holes on U-shaped ferrum, and M12 × 80, every hole bolt penetrates fastening.Vertical tube is provided with fastener 7, and fastener 7 includes two piece of four orifice plate and four bolt combination, on the position of the upper lateral tube 10 that vertical tube is fixed on platform by use fastener 7, can constantly be adjusted according to the position needing work platforms 9 of construction metope.All of transverse tube and vertical tube form a whole, i.e. rigidity gantry installation frame.
Hanging basket including described Detachable gantry installation frame, the fastener on Detachable gantry installation frame top is connected with work platforms, elevator 11 is loaded onto in the middle part of Detachable gantry installation frame, safety lock is loaded onto on Detachable gantry installation frame top, steel wire rope 12 is hanging on the main joint hinge on top through rope sheave, switches on power and achieves that cage lifting runs and workman's constructing operation.
First steel wire rope and elevator, safety lock is removed during dismounting;Unclamp the chain connecting bolt pulled down on each transverse tube, U-shaped ferrum, take off top horizontal pipe, upper lateral tube, middle transverse tube, end transverse tube respectively;Unclamping and pull down fastener 7, vertical tube 1 just disengages with work platforms 9, and whole portal frame is removed and resolved into pipe fitting.
Claims (2)
1. a Detachable gantry installation frame, including the vertical tube (1) of both sides and the transverse tube that is connected between two montants, it is characterised in that: described transverse tube include being positioned at the top horizontal pipe (2) at top, superposed upper lateral tube (3), be positioned at the middle transverse tube (4) at middle part and be positioned at bottom end transverse tube (5);Each transverse tube two ends are connected on the vertical tube of both sides by U-shaped ferrum (8) respectively, and the lower end of two vertical tubes is equipped with land wheel (6), and the top of two vertical tubes is provided with the fixing fastener (7) connecting work platforms (9);
Described U-shaped ferrum (8) is connected on vertical tube, and described U-shaped ferrum (8) is provided with two bolt through-holes;
Described fastener (7) includes two piece of four orifice plate and four bolts.
2. include the hanging basket of Detachable gantry installation frame described in claim 1, it is characterized in that: the fastener (7) on described Detachable gantry installation frame top is connected with work platforms, elevator (11) is loaded onto in the middle part of Detachable gantry installation frame, safety lock is loaded onto on Detachable gantry installation frame top, and steel wire rope (12) is hanging on the main joint hinge on top through rope sheave.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310674970.5A CN103669821B (en) | 2013-12-12 | 2013-12-12 | Detachable gantry installation frame and hanging basket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310674970.5A CN103669821B (en) | 2013-12-12 | 2013-12-12 | Detachable gantry installation frame and hanging basket |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103669821A CN103669821A (en) | 2014-03-26 |
CN103669821B true CN103669821B (en) | 2016-12-07 |
Family
ID=50308530
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310674970.5A Active CN103669821B (en) | 2013-12-12 | 2013-12-12 | Detachable gantry installation frame and hanging basket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103669821B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108979117A (en) * | 2018-09-10 | 2018-12-11 | 江苏叙然信息科技有限公司 | It is a kind of can automatic lifting building operating platform |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5069309A (en) * | 1989-09-28 | 1991-12-03 | Emerson Electric Co. | Rolling tower scaffold and method and tooling apparatus for manufacturing the same |
CN2150277Y (en) * | 1992-12-30 | 1993-12-22 | 安玉明 | Moveable scaffold |
CN2193401Y (en) * | 1993-05-17 | 1995-03-29 | 周魁刚 | Light elevating scaffold unit |
CN2487718Y (en) * | 2001-05-24 | 2002-04-24 | 杨克有 | Steel pipe gantry frame |
CN203654707U (en) * | 2013-12-12 | 2014-06-18 | 无锡华科机械设备有限公司 | Detachable gantry installation frame |
-
2013
- 2013-12-12 CN CN201310674970.5A patent/CN103669821B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN103669821A (en) | 2014-03-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN200999456Y (en) | Safety self-locking electric up-down scaffold | |
CN202706503U (en) | Electric lifting discharging platform for main building construction | |
CN101696598B (en) | Wholly lifted construction external frame | |
CN204112696U (en) | For the electric hoist elevator shaft platform of main building construction | |
CN102777030A (en) | Method for building up formwork construction platform of lift shaft | |
CN206707237U (en) | Cable-stayed type top layer construction platform for elevator installation | |
CN106150057B (en) | A kind of split blade type hydraulic pressure lift climbing frame | |
CN205773024U (en) | A kind of convenient pipeline lifting auxiliary device | |
CN103669821B (en) | Detachable gantry installation frame and hanging basket | |
CN203654707U (en) | Detachable gantry installation frame | |
CN107043072B (en) | Falling-beam-free integrated inner climbing tower crane supporting device and implementation method | |
CN113062584A (en) | Multipoint elevator shaft construction lifting platform and construction method | |
CN203867198U (en) | Slip equipment for high-rise steel structure transfer layer truss | |
CN202689498U (en) | Liftable scaffold for simple and easy building outer wall | |
CN203383516U (en) | Construction device for installing connecting beam on frame type steel structure | |
CN202729645U (en) | Tower crane with elevator | |
CN204983595U (en) | Attached type lifting scaffold | |
CN103195231A (en) | Integral outer frame | |
CN206032957U (en) | Novel improve companion ladder of structure | |
CN203878956U (en) | Automatic lifting protection screen and construction platform combined system | |
CN205531262U (en) | Steel construction construction platform can rise automatically | |
CN204823735U (en) | Crane girder structure | |
CN104695694A (en) | Worm and gear lead screw lifting type attached scaffold | |
KR101303148B1 (en) | Construction method for curtain wall | |
CN205076619U (en) | Single hoisting point double -deck elevator hanging flower basket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |