CN103641343A - Method for grinding preprocessing steel slag - Google Patents

Method for grinding preprocessing steel slag Download PDF

Info

Publication number
CN103641343A
CN103641343A CN201310632025.9A CN201310632025A CN103641343A CN 103641343 A CN103641343 A CN 103641343A CN 201310632025 A CN201310632025 A CN 201310632025A CN 103641343 A CN103641343 A CN 103641343A
Authority
CN
China
Prior art keywords
grinding
slag
steel slag
mill
phase
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310632025.9A
Other languages
Chinese (zh)
Inventor
李福洲
黄凯
颜波
刘明亮
李贵超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
Original Assignee
Wuhan University of Technology WUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT filed Critical Wuhan University of Technology WUT
Priority to CN201310632025.9A priority Critical patent/CN103641343A/en
Publication of CN103641343A publication Critical patent/CN103641343A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P40/00Technologies relating to the processing of minerals
    • Y02P40/10Production of cement, e.g. improving or optimising the production methods; Cement grinding

Abstract

The invention discloses a method for grinding preprocessing steel slag. The method is characterized in that RO-phase particles in the steel slag are removed before the steel slag is ground. The method comprises the steps of (1) adding a preprocessing system on the basis of the existing grinding system, wherein the preprocessing system comprises an ultrashort mill, an RO-phase processing device, a screen and a magnetic separation device; (2) crushing the steel slag into the granularity of 1mm through the ultrashort mill; (3) removing the RO-phase particles in the steel-slag powder through the RO-phase processing device; (4) sending the steel slag powder to the magnetic separation device to be magnetically separated so as to obtain the equivalent iron ore concentrate through the screen; (5) further grinding the steel slag powder processed in step (4) through the grinding system. By adopting the method, the RO phase in the steel slag is eliminated within the appropriate granularity range, so that the steel slag grinding system can continuously and high-efficiently operate. The RO-phase particles are difficult to crush and can continuously abrade the mill if being accumulated on a grinding disc, and the yield and service life of the mill can be influenced.

Description

A kind of pretreated method of steel slag grinding
Technical field:
The present invention relates to technology of producing cement field, particularly relate to a kind of pretreated method of steel slag grinding, make continuous, the efficient operation of steel slag grinding system become possibility.
Background technology:
Slag is in steelmaking process, and the impurity that the oxide compound of the oxidized rear generation of each element, the furnace lining being etched and fettling material, metal charge are brought in metal charge is as silt particle and the slag making materials that specially adds, and wherein slag making materials is the main source of slag.Slag is the material that contains silicate, ferro-aluminate ore deposit phase through high-temperature calcination, can be used as dross slag cement raw material, the raw material of cement additive, calcining cement clinker and building product etc.Yet, because the component of slag is various, cause the grindability of the contained mineral of slag to exist very large difference.Wherein, molten to have FeO, MgO be the popularity sosoloid RO phase that the metal oxide of other divalence such as main and MnO forms, and its vickers hardness number reaches 330HV/MPa, and its hydration reaction activity is very low.In existing slag use procedure, steel slag grinding system typically uses Vertical Mill or ball milling carries out grinding.But, in actual production process, always have the sosoloid RO phase particle of some large particle diameters to be difficult to fragmentation.While using vertical mill grinding, because these difficult abrasive particle quality are larger, selection by winnowing is difficult to screen out these particles, accumulates on mill, constantly wear and tear mill and grinding roller, affects vertical mill system output and mill, grinding roller life-span.While using ball mill grinding, these particles can stop up bin isolation board, have reduced output and the continuous operating time of ball mill.So how processing these particles that are difficult to grinding is the key issues that solve steel slag grinding technology.
Summary of the invention:
The problem existing in order to solve above-mentioned prior art, the object of this invention is to provide simple, the lower-cost steel slag grinding pretreatment process of a kind of technique, to realize the failure rate that reduces grinding system and the object that improves its mill efficiency.
The pretreated method of steel slag grinding, is characterized in that: before grinding, weed out the RO phase particle in slag.
The pretreated method of a kind of steel slag grinding of the present invention, it is characterized in that comprising following concrete steps: (1) increases a pretreatment system on the basis of existing grinding system, described pretreatment system comprises a ultrashort mill, a RO phase treatment unit, a sieve and a concentration equipment; (2) slag passes through ultrashort mill by slag crushing to millimeter; (3) by RO phase treatment unit, reject RO phase particle in slag powder again; (4) by sifting out, be sent to concentration equipment and carry out the smart iron ore that magnetic separation obtains respective amount; (5) the slag powder of processing through step (4) is sent into grinding system and carry out further grinding.
Ultrashort mill in described pretreatment system, RO phase treatment unit, sieve and concentration equipment are existing structure, directly from market, buy and obtain.
Compared with prior art, the invention has the beneficial effects as follows:
1, solved the problem that slag can not be used in batches in cement production process.
2, grinding system life-span and efficiency have been improved.
3, in preprocessing process, can obtain the smart iron ore of respective amount.
4, this traditional industry waste material of slag is turned waste into wealth, introduce the production process of cement clinker, ensureing under the prerequisite of finished cement quality, effectively reduce production costs, played the effect of protection of the environment simultaneously.
Accompanying drawing explanation:
Fig. 1 is process flow sheet of the present invention.
Concrete embodiment:
Below in conjunction with accompanying drawing, the embodiment of a kind of pretreated method of steel slag grinding proposing according to the present invention is explained, be described in detail as follows.
Technological process of the present invention:
A kind of pretreated method of steel slag grinding, before grinding, weed out the RO phase particle in slag, comprise following concrete steps: (1) increases a pretreatment system on the basis of existing grinding system, described pretreatment system comprises a ultrashort mill, a RO phase treatment unit, a sieve and a concentration equipment; (2) slag passes through ultrashort mill by slag crushing to millimeter; (3) by RO phase treatment unit, reject RO phase particle in slag powder again; (4) by sifting out, be sent to concentration equipment and carry out the smart iron ore that magnetic separation obtains respective amount; (5) the slag powder of processing through step (4) is sent into grinding system and carry out further grinding.
Ultrashort mill in described pretreatment system, RO phase treatment unit, sieve and concentration equipment are existing structure, directly from market, buy and obtain.
Technological process of the present invention:
Slag is sent into ultrashort mill by travelling belt, after fragmentation, obtain a millimeter slag powder, by RO phase treatment unit, reject RO phase particle in slag powder again, easily wearing into minute as tricalcium silicate and Dicalcium Phosphate (Feed Grade) are sent to concentration equipment through sifting out in slag carried out magnetic separation and obtained respective amount essence iron ore, finally by sending into grinding system through the slag powder of magnetic separation, carry out further grinding, can obtain having the slag powder of certain hydration activity.

Claims (2)

1. the pretreated method of steel slag grinding, is characterized in that: before grinding system, weed out the RO phase particle in slag.
2. the pretreated method of steel slag grinding according to claim 1, it is characterized in that comprising following concrete steps: (1) increases a pretreatment system on the basis of existing grinding system, described pretreatment system comprises a ultrashort mill, a RO phase treatment unit, a sieve and a concentration equipment; (2) slag passes through ultrashort mill by slag crushing to millimeter; (3) by RO phase treatment unit, reject RO phase particle in slag powder again; (4) by sifting out, be sent to concentration equipment and carry out the smart iron ore that magnetic separation obtains respective amount; (5) the slag powder of processing through step (4) is sent into grinding system and carry out further grinding.
CN201310632025.9A 2013-12-02 2013-12-02 Method for grinding preprocessing steel slag Pending CN103641343A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310632025.9A CN103641343A (en) 2013-12-02 2013-12-02 Method for grinding preprocessing steel slag

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310632025.9A CN103641343A (en) 2013-12-02 2013-12-02 Method for grinding preprocessing steel slag

Publications (1)

Publication Number Publication Date
CN103641343A true CN103641343A (en) 2014-03-19

Family

ID=50246679

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310632025.9A Pending CN103641343A (en) 2013-12-02 2013-12-02 Method for grinding preprocessing steel slag

Country Status (1)

Country Link
CN (1) CN103641343A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103992049A (en) * 2014-04-28 2014-08-20 武汉钢铁(集团)公司 Cement clinker preparation method using converter steel slag to correct iron quality
CN104446022A (en) * 2014-12-18 2015-03-25 长沙紫宸科技开发有限公司 Method for preparing steel slag sand, activated slag powder and RO phase from steel slag
CN104841554A (en) * 2015-06-04 2015-08-19 山东省建筑材料工业设计研究院 Special RO-phase magnetic separator for steel slag micro powder
CN107473612A (en) * 2017-09-21 2017-12-15 西南科技大学 A kind of method for reducing slag ore grinding energy consumption
CN110340007A (en) * 2019-07-25 2019-10-18 衢州柯城幕布电子有限公司 A kind of multiple sieving optimization processing device based on steel slag
CN113233807A (en) * 2020-09-08 2021-08-10 山东埃尔派粉体科技有限公司 Method for high-activity superfine treatment of RO phase in steel slag

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1899731A (en) * 2006-07-18 2007-01-24 浙江海穆钢铁服务有限公司 Method for producing super fine steel slag powder

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1899731A (en) * 2006-07-18 2007-01-24 浙江海穆钢铁服务有限公司 Method for producing super fine steel slag powder

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
侯新凯 等: "钢渣中二价金属氧化物固溶体的选别性研究", 《硅酸盐学报》, vol. 41, no. 8, 18 August 2013 (2013-08-18), pages 1142 - 1150 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103992049A (en) * 2014-04-28 2014-08-20 武汉钢铁(集团)公司 Cement clinker preparation method using converter steel slag to correct iron quality
CN103992049B (en) * 2014-04-28 2016-04-27 武汉钢铁(集团)公司 Bessemer furnace slag is utilized to correct the cement clinker preparation method of irony
CN104446022A (en) * 2014-12-18 2015-03-25 长沙紫宸科技开发有限公司 Method for preparing steel slag sand, activated slag powder and RO phase from steel slag
CN104446022B (en) * 2014-12-18 2016-06-08 长沙紫宸科技开发有限公司 A kind of prepared from steel slag is for the method for Steel-slag Sand, activation ground-slag and RO phase
CN104841554A (en) * 2015-06-04 2015-08-19 山东省建筑材料工业设计研究院 Special RO-phase magnetic separator for steel slag micro powder
CN104841554B (en) * 2015-06-04 2017-03-01 山东省建筑材料工业设计研究院 A kind of special RO phase magnetic separator of slag micro powder
CN107473612A (en) * 2017-09-21 2017-12-15 西南科技大学 A kind of method for reducing slag ore grinding energy consumption
CN110340007A (en) * 2019-07-25 2019-10-18 衢州柯城幕布电子有限公司 A kind of multiple sieving optimization processing device based on steel slag
CN110340007B (en) * 2019-07-25 2020-03-31 山东路友再生资源设备有限公司 Multiple sieving optimization treatment device based on steel slag
CN113233807A (en) * 2020-09-08 2021-08-10 山东埃尔派粉体科技有限公司 Method for high-activity superfine treatment of RO phase in steel slag
CN113233807B (en) * 2020-09-08 2021-11-19 山东埃尔派粉体科技有限公司 Method for high-activity superfine treatment of RO phase in steel slag

Similar Documents

Publication Publication Date Title
CN102240588B (en) Dry-grinding and dry-separation method of magnetite
CN103641343A (en) Method for grinding preprocessing steel slag
CN102228865B (en) Novel wet-type strong-magnetic pre-separation process of weak-magnetic low-grade iron mineral roller mill
CN102247925B (en) Flotation method of nonferrous metal ores
CN103290153B (en) Steel slag treating technology
CN110694789B (en) Ore dressing method for magnetite
CN101579654A (en) Iron ore powder mineral dressing process
CN107309081B (en) A kind of processing barren rocks iron selection technique
CN102240587A (en) Wet-type magnetic separation method of magnetite
CN104888947A (en) Magnetic separation-centrifuge separation technology of micro-fine particle dissemination magnet-hematite mixed ore
CN105032610A (en) High-pressure roller selective comminuting and magnetic separating method for lean magnetite ore
CN104004867A (en) High-efficiency economic secondary treatment process for steel slag
CN107159426A (en) A kind of slag is secondary to select iron method
DK162484B (en) PROCEDURE AND EQUIPMENT FOR JOINT PAINTING OF TWO OR MORE IN DIFFERENT GRADE FORMAL SHOE MATERIALS
CN111747669A (en) Steel slag multistage crushing and grinding ultrafine powder preparation device and method
CN108043578A (en) A kind of processing barren rocks iron selection technique
CN102641782A (en) Beneficiation method
CN101880736B (en) Preparation technology of superfine steel slag micropowder and production process
CN103143438A (en) Production technique of magnetite refined powdered iron by dry process
CN102489373B (en) Mineral processing technology for processing iron ore
JP2011236115A (en) Treatment method of steel slag
CN107470016A (en) A kind of method that chemical industry iron powder is prepared using zinc kiln slag as raw material
CN101362116A (en) Large-sized energy-saving ore processing equipment and technique
CN103041905A (en) Method and system for crumbling and grinding carbide slag
CN103693875A (en) Production process for recycling premixed concrete solid waste residues

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140319