CN103628363B - Construction method for filling and building subgrade by using silty-fine sand as filling materials - Google Patents

Construction method for filling and building subgrade by using silty-fine sand as filling materials Download PDF

Info

Publication number
CN103628363B
CN103628363B CN201310649563.9A CN201310649563A CN103628363B CN 103628363 B CN103628363 B CN 103628363B CN 201310649563 A CN201310649563 A CN 201310649563A CN 103628363 B CN103628363 B CN 103628363B
Authority
CN
China
Prior art keywords
construction
filler
fine sand
filling
powder fine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310649563.9A
Other languages
Chinese (zh)
Other versions
CN103628363A (en
Inventor
金发良
刘铁丰
郭俊清
王忠文
杨庆云
刘运泽
陈效星
陈必强
李伟
鲍雪银
谭军
周磊
孙闯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Railway Survey Design Consulting Co Ltd
Original Assignee
Shenyang Railway Survey Design Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Railway Survey Design Consulting Co Ltd filed Critical Shenyang Railway Survey Design Consulting Co Ltd
Priority to CN201310649563.9A priority Critical patent/CN103628363B/en
Publication of CN103628363A publication Critical patent/CN103628363A/en
Application granted granted Critical
Publication of CN103628363B publication Critical patent/CN103628363B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention relates to a construction method for filling and building a subgrade by using silty-fine sand as filling materials. The construction method comprises the following steps that (1) a railway subgrade bed is subjected to edge covering by adopting filling materials in groups A and B, concretely, the filling materials in groups A and B with the horizontal width being 2.0m are adopted for filling and building at the two sides of the subgrade body under the subgrade bed, the silty-fine sand is adopted for filling and building in the middle, and a crawler type bulldozer is adopted for compact compression; (2) the subgrade bed is filled and built by adopting modified soil or qualified filling materials in groups A and B. The construction method has the advantages that the silty-fine sand is reasonably utilized, the engineering manufacturing cost is reduced, the defect caused by the subgrade filling and building by the silty-fine sand is overcome, the construction operability is high, the large-area construction is convenient, and the construction progress requirements can be ensured.

Description

A kind of powder fine sand that utilizes is as the filling roadbed construction method of filler
Technical field
The present invention relates to a kind of civil engineering construction method.Particularly a kind of powder fine sand roadbed filling construction technology and method.
Background technology
In railway engineering, highway engineering, municipal engineering, all to carry out a large amount of earth materials (or) gravel embankment.The filling construction of earth and stone material proportion in the engineering of these industries is very large, and the construction method of native stone reclamation work and quality, directly affect quality and the cost of corresponding engineering, construction technology theory and the method for therefore grasping earth rock placement engineering are extremely important.
Roadbed filling construction adopts qualified general filler (piece stone, rubble, gravel class filler in A, B group filler) conventionally, adopts layering, the construction technology process such as pave smooth, watering or airing, cal rolling (road roller), check visa, road surface and side slope shaping constructs.
Shen Xi Industrial Corridor flint hilllock is to Bohai Sea railway engineering, limited because investing, must employing fetch earth nearby (most of is nearby powder fine sand).Powder fine sand is C group filler, its fine particle content seldom, disproportionately graded.Adopt conventional roadbed filling construction, can not meet compacting criteria.
Summary of the invention
The object of this invention is to provide a kind of powder fine sand that utilizes as filler construction method for filling roadbed, the method strong operability, be convenient to large-area construction.
The object of the invention is to be achieved through the following technical solutions: a kind of powder fine sand that utilizes, as the filling roadbed construction method of filler, is characterized in that: construction sequence is as follows:
(1) railway bed bedding adopts A, B group filler bound edge below, and A, the B group filler that is specially the wide 2.0m of the following roadbed body of bedding both sides employing level fills, and the middle powder fine sand that adopts fills, and adopts crawler dozer to carry out compacting;
Concrete steps are as follows:
(a) filling property analysis:
In construction soil field, sample soil carries out indoor particle analysis, determines that sample great soil group does not belong to A group filler, B group filler or powder fine sand, measures natural moisture content, grain density, minimax dry density;
(b) engineer testing: get a bid section (distance) as engineer testing section on construction line, engineer testing idiographic flow is: preparation of construction → base treatment → placement in layers → paving and leveling → turn airing → grinding compacting → check visa → roadbed to rebuild;
(b1) preparation of construction:
Powder fine sand fetches earth nearby, after a native sand adopts an excavator to dig out, stacks to the field of fetching earth and controls water, and after powder fine sand control water extremely flows out without open fire, with excavator loading, tipping truck is transported to test section job location; A, B are organized to filler to job location simultaneously;
(b2) base treatment:
Before test section construction, cleaning original ground foreign material, detect the natural bearing capacity of original ground, and bearing capacity will meet the parameter of construction requirement: static sounding specific penetration resistance P svalue: I level railway is less than 1.2MPa, II level railway is less than 1.0MPa; Or natural ground Basic bearing ability σ 0: I level railway is less than 0.15MPa, and II level railway is less than 0.12MPa;
If bearing capacity does not meet the parameter of above-mentioned construction requirement, after original ground fills one deck A, B group filler, original ground bearing capacity is strengthened, and strengthened substrate is detected, until meet requirement for bearing capacity;
(b3) placement in layers:
Bound edge carries out with filling simultaneously: during bound edge, be to guarantee side slope width and compaction quality, emit the inside and outside sideline of bound edge every side widen 50cm and fill according to cross section; While filling out powder fine sand, for controlling the accuracy of loose laying depth, before back-up sand, on roadbed, with lime, draw grid, control loose laying depth;
(b4) paving and leveling:
Using bulldozer to coordinate manually paves to banketing, when in paving process, basis is determined loose laying depth in advance, plug in mark post height is grasped actual loose laying depth, after having paved, adopt level gauge to measure the filler elevation after paving, with pave before compare with ground level, calculate accurate loose laying depth;
(b5) turn airing:
According to test, while tentatively determining that powder fine sand moisture content is between 8~12%, detect coefficient of subgrade reaction K30 up to standard, therefore detect in time the moisture content of powder fine sand filler before paving and in paving process, when moisture content is greater than 12%, employing is revolved the crotch that ploughing or bulldozer carry and is turned airing, to control filler moisture content 8~12%;
(b6) roll:
Powder fine sand filler adopts SD22 type bulldozer to roll, and while rolling, the mode of taking vertical, horizontal to replace combination rolls, and after first pass longitudinal rolling, next laterally rolls all over adopting, and so hockets; Compacting order is according to first both sides, and roll rear centre; Bulldozer travel speed is no more than 4km/h; In construction paragraph junction, overlapping the rolling of palpus, longitudinal lap joint length is not less than 2m, the overlapping 10cm that is not less than of compacting bulldozer wheelmark between row and row; A, B group filler adopts road roller compacting;
(b7) compaction quality detects:
Powder fine sand filler adopts SD22 bulldozer vertical, horizontal in conjunction with rolling, and rolls the 6th time beginning, and often roll one time and detect relative density, coefficient of subgrade reaction, porosity and a moisture content, and record, technological parameter reference standard during as full bid section construction; When relative density, coefficient of subgrade reaction, porosity and moisture content reach construction reference, detect qualified after, complete this layer and roll, every layer is detected after qualified and repeats aforesaid operations again, carries out lower one deck construction;
(c) all fronts filling construction
By aforementioned (b) engineer testing step, obtain and fill device combination mode, number of rolling and roller compaction processes, the parameter of laying depth, water content and the powder fine sand filler of A, B group filler filler, in construction, carrying out filling construction completely: the construction method that adopts placement in layers, layered rolling during construction, it is to banket according to subgrade cross section overall with is longitudinal layered that horizontal slice is filled, every layer of both sides take A, B group filler to carry out bound edge, adopt bulldozer longitudinally to nappe and fill earth material, every layer of loose laying depth is no more than 40cm, adopts bulldozer and road roller to roll;
(d) check and accept
At every layer of placement grinding, reach after the definite number of rolling of scheme, for the following roadbed body of bedding powder fine sand filler, adopt relative density and coefficient of subgrade reaction K30 as compaction quality judgment criteria; For bound edge A, B group filler, adopt porosity and coefficient of subgrade reaction K30 as compaction quality judgment criteria;
(2) roadbed bottom, adopts conditioned soil or qualified A, B group filler to fill;
(3) subgrade bed top layer, adopts conditioned soil or qualified A, B group filler to fill.
Wherein in (b) engineer testing step, adopt crisscross the rolling of SD22 bulldozer to be generally 7 ~ 9 times, below loose laying depth 40cm.
Adopt this kind of debulking methods, for powder fine sand filler roadbed, can meet design and relevant acceptance criteria requirement.
Beneficial effect of the present invention: the present invention adopts such scheme, compares with construction method in the past, and tool has the following advantages:
1), overcome powder fine sand and directly filled out, compaction quality is difficult to the defect guaranteeing;
2), construct workablely, be convenient to large-area construction, can guarantee construction speed requirement;
3), engineering construction quality is guaranteed, and can meet the requirement of design and technical specification;
4), rationally utilize powder fine sand, reduce construction costs.
Accompanying drawing explanation
Fig. 1 is the roadbed section figure that adopts construction method of the present invention.
The specific embodiment
Note: the technical term relating in the application, as: A group, B group filler, conditioned soil, coefficient of subgrade reaction K30 etc. all come from the industry standard < < of People's Republic of China (PRC) railway bed design specifications > > (TB 10001-2005/J 447-2005), and whole construction and acceptance criteria are also with reference to this standard and relevant industries standard implementation.
1), subgrade bed part, adopt conditioned soil routinely dam filling construction fill.
2), bedding adopts A, B group filler bound edge below, A, the B group filler that is specially the wide 2.0m of roadbed body both sides employing level fills, the middle powder fine sand that adopts fills, emphasis is that powder fine sand roadbed adopts crawler dozer to carry out compacting.
In the present invention, emphasis is the following powder fine sand of bedding filling construction, introduces powder fine sand direct filling construction method below, carries out according to the following steps:
A), filling property analysis
In construction soil field, sample soil carries out indoor particle analysis, determine that sample great soil group does not belong to A group filler, B group filler or powder fine sand, measure natural moisture content, grain density, minimax dry density, when A group filler, B group filler or powder fine sand indices meet construction requirement, can carry out lower step operation.
B) engineer testing: get a bid section (distance) as engineer testing section on construction line, construction technology process is: preparation of construction → base treatment → placement in layers → paving and leveling → turn airing → grinding compacting → check visa → roadbed to rebuild.
B1), preparation of construction
Powder fine sand fetches earth nearby, considers that under soil site, water level is high, and the sand moisture content just having taken out is large, after a native sand adopts an excavator to dig out, stack to the field of fetching earth and control water, after powder fine sand control water extremely flows out without open fire, with excavator loading, tipping truck is transported to test section job location; A, B group fill source is far away, is transported to job location simultaneously.
B2), base treatment
Before test section construction, cleaning original ground crops root system weeds etc., detect the natural bearing capacity of original ground, and bearing capacity will meet the parameter of construction requirement: static sounding specific penetration resistance P svalue: I level railway is less than 1.2MPa, II level railway is less than 1.0MPa; Or natural ground Basic bearing ability σ 0: I level railway is less than 0.15MPa, and II level railway is less than 0.12MPa;
If bearing capacity does not meet the parameter of above-mentioned construction requirement, after original ground fills one deck A, B group filler, original ground bearing capacity is strengthened, and strengthened substrate is detected, until meet requirement for bearing capacity.
B3), placement in layers
Bound edge carries out with filling simultaneously.During bound edge, be to guarantee side slope width and compaction quality, according to cross section, emit the inside and outside sideline of bound edge every side and widen 50cm and fill; While filling out powder fine sand, for controlling the accuracy of loose laying depth, before back-up sand, on roadbed, with lime, draw grid, control loose laying depth.
B4), paving and leveling
Using bulldozer to coordinate manually paves to banketing, when in paving process, basis is determined loose laying depth in advance, plug in mark post height is grasped actual loose laying depth, after having paved, adopt level gauge to measure the filler elevation after paving, with pave before compare with ground elevation, to calculate accurate loose laying depth.
B5), turn airing
According to test, while tentatively determining that powder fine sand moisture content is between 8~12%, detect coefficient of subgrade reaction K30 higher, meet construction reference, therefore detect in time the moisture content of powder fine sand filler before paving and in paving process, when moisture content is greater than 12%, adopts and to revolve the crotch that ploughing or bulldozer carry and turn airing, to control filler moisture content 8~12%.
B6), roll
Because fine sand cohesion is little, road roller is difficulty in walking in sand, and rolls in process and easily sand large area is thrown, and makes sand water loss, does not have compaction.Consider above factor, powder fine sand roadbed adopts SD22 type bulldozer to roll, and when this equipment rolls, crawler belt indentation is darker, and applicable sand rolls.Bound edge soil adopts road roller to roll according to a conventional method.
While adopting SD22 type bulldozer to roll, take the mode of vertical, horizontal combination to roll, after first pass longitudinal rolling, next laterally rolls all over adopting, and so hockets.Compacting order is according to first both sides, and roll rear centre.Bulldozer travel speed is no more than 4km/h.Each paragraph junction of constructing, overlapping the rolling of palpus, longitudinal lap joint length is not less than 2m, the overlapping 10cm that is not less than of compacting bulldozer wheelmark between row and row.
B7), compaction quality detects
Powder fine sand filler adopts SD22 bulldozer vertical, horizontal in conjunction with rolling, and rolls the 6th time beginning, and often roll one time and detect relative density, coefficient of subgrade reaction, porosity and a moisture content, and record, technological parameter reference standard during as full bid section construction; When relative density, coefficient of subgrade reaction, porosity and moisture content reach construction reference, in practical operation, conventionally adopt crisscross the rolling of SD22 bulldozer to be generally 7 ~ 9 times, detect each parameter and can reach standard, below loose laying depth 40cm.Detect qualified after, complete this layer and roll, every layer is detected after qualified and repeats aforesaid operations again, carries out lower one deck construction.
C), all fronts filling construction
By aforementioned b) engineer testing step, obtain the device combination mode of filling, number of rolling and roller compaction processes, A, the laying depth of B group filler filler, the parameter of water content and powder fine sand filler, in construction, carrying out filling construction completely: during construction, adopt placement in layers, the construction method of layered rolling, it is to banket according to subgrade cross section overall with is longitudinal layered that horizontal slice is filled, A is taked in every layer of both sides, B group filler carries out bound edge, adopt bulldozer longitudinally to nappe and fill earth material, every layer of loose laying depth is no more than 40cm, adopt bulldozer and road roller to roll according to the definite construction parameter of engineer testing.
D), check and accept
At every layer of placement grinding, reach after the definite number of rolling of scheme, for the following roadbed body of bedding powder fine sand filler, adopt relative density and coefficient of subgrade reaction K30 as compaction quality judgment criteria; For bound edge A, B group filler, adopt porosity and coefficient of subgrade reaction K30 as compaction quality judgment criteria.
The technological principle of this construction method:
Because sand grain content in powder fine sand soil earth is large, clay content is minimum, 85% particle mainly concentrates between particle diameter 0.25mm~0.075mm, caking property and moulding very little, adopts traditional road roller compacting, and its contact surface is less, road roller is difficulty in walking in sand, and roll in process and easily sand large area is thrown, make sand water loss, do not have compaction.Adopt SD22 type bulldozer to roll, this equipment self-weight is large and contact area is larger, can easily on sand, walk, and while rolling, crawler belt indentation is darker, and applicable sand rolls.Another emphasis is to control powder fine sand moisture content, controls rationally (between 8~12%) and can reach designing requirement.
Concrete application example: Shen Xi Industrial Corridor flint hilllock is to the construction of railways of the Bohai Sea, for guaranteeing Subgrade Construction Quality, solution roadbed filling fetches earth, and material source is far away, cost is high, powder fine sand constructional difficulties, be difficult to compacting, quality is difficult to many unfavorable construction problems such as assurance, incorporation engineering is actual, to the filling roadbed construction method of taking bound edge protection against erosion, adopting bulldozer to roll of powder fine sand, and tentatively by audit, the evaluation of these railway construction headquarter.Parallel testing result through self check and supervisor, fills quality and can reach design and demand of technical standard.This constructure scheme reduces fortune far away material for public use 7,100,000 sides, saves 31,950 ten thousand yuan of construction investments.Facts have proved, it is feasible adopting A, B group filler bag powder fine sand, adopting the construction method of bulldozer compacting.
Main construction equipment table in this constructure scheme is as follows:
Machinery title Model and specification Unit Quantity Remarks
Excavator CAT320B Platform 1 ?
Bulldozer SD22 Platform 2 ?
Land leveller PY160 Platform 1 ?
Road roller YZ20C Platform 1 Original ground processing and bound edge soil pressure are real
Tipping truck 18m 3 ? 6 ?
Rotary plow ? Platform 1 ?
Sprinkling truck 8t Platform 1 ?

Claims (2)

1. utilize powder fine sand as the filling roadbed construction method of filler, it is characterized in that: construction sequence is as follows:
(1) railway bed bedding adopts A, B group filler bound edge below, and A, the B group filler that is specially the wide 2.0m of the following roadbed body of bedding both sides employing level fills, and the middle powder fine sand that adopts fills, and adopts crawler dozer to carry out compacting;
Concrete steps are as follows:
(a) filling property analysis:
In construction soil field, sample soil carries out indoor particle analysis, determines that sample great soil group does not belong to A group filler, B group filler or powder fine sand, measures natural moisture content, grain density, minimax dry density;
(b) engineer testing: get a bid section as engineer testing section on construction line, engineer testing idiographic flow is: preparation of construction → base treatment → placement in layers → paving and leveling → turn airing → grinding compacting → check visa → roadbed to rebuild;
(b1) preparation of construction:
Powder fine sand fetches earth nearby, after a native sand adopts an excavator to dig out, stacks to the field of fetching earth and controls water, and after powder fine sand control water extremely flows out without open fire, with excavator loading, tipping truck is transported to test section job location; A, B are organized to filler to job location simultaneously;
(b2) base treatment:
Before test section construction, cleaning original ground foreign material, detect the natural bearing capacity of original ground, and bearing capacity will meet the parameter of construction requirement: static sounding specific penetration resistance P svalue: I level railway is less than 1.2MPa, II level railway is less than 1.0MPa; Or natural ground Basic bearing ability σ 0: I level railway is less than 0.15MPa, and II level railway is less than 0.12MPa;
If bearing capacity does not meet the parameter of above-mentioned construction requirement, after original ground fills one deck A, B group filler, original ground bearing capacity is strengthened, and strengthened substrate is detected, until meet requirement for bearing capacity;
(b3) placement in layers:
Bound edge carries out with filling simultaneously: during bound edge, be to guarantee side slope width and compaction quality, emit the inside and outside sideline of bound edge every side widen 50cm and fill according to cross section; While filling out powder fine sand, for controlling the accuracy of loose laying depth, before back-up sand, on roadbed, with lime, draw grid, control loose laying depth;
(b4) paving and leveling:
Using bulldozer to coordinate manually paves to banketing, when in paving process, basis is determined loose laying depth in advance, plug in mark post height is grasped actual loose laying depth, after having paved, adopt level gauge to measure the filler elevation after paving, with pave before compare with ground level, calculate accurate loose laying depth;
(b5) turn airing:
According to test, while tentatively determining that powder fine sand moisture content is between 8~12%, detect coefficient of subgrade reaction K30 up to standard, therefore detect in time the moisture content of powder fine sand filler before paving and in paving process, when moisture content is greater than 12%, employing is revolved the crotch that ploughing or bulldozer carry and is turned airing, to control filler moisture content 8~12%;
(b6) roll:
Powder fine sand filler adopts SD22 type bulldozer to roll, and while rolling, the mode of taking vertical, horizontal to replace combination rolls, and after first pass longitudinal rolling, next laterally rolls all over adopting, and so hockets; Compacting order is according to first both sides, and roll rear centre; Bulldozer travel speed is no more than 4km/h; In construction paragraph junction, overlapping the rolling of palpus, longitudinal lap joint length is not less than 2m, the overlapping 10cm that is not less than of compacting bulldozer wheelmark between row and row; A, B group filler adopts road roller compacting;
(b7) compaction quality detects:
Powder fine sand filler adopts SD22 bulldozer vertical, horizontal in conjunction with rolling, and rolls the 6th time beginning, and often roll one time and detect relative density, coefficient of subgrade reaction, porosity and a moisture content, and record, technological parameter reference standard during as full bid section construction; When relative density, coefficient of subgrade reaction, porosity and moisture content reach construction reference, detect qualified after, complete this layer and roll, every layer is detected after qualified and repeats aforesaid operations again, carries out lower one deck construction;
(c) all fronts filling construction
By aforementioned (b) engineer testing step, obtain and fill device combination mode, number of rolling and roller compaction processes, the parameter of laying depth, water content and the powder fine sand filler of A, B group filler filler, in construction, carrying out filling construction completely: the construction method that adopts placement in layers, layered rolling during construction, it is to banket according to subgrade cross section overall with is longitudinal layered that horizontal slice is filled, every layer of both sides take A, B group filler to carry out bound edge, adopt bulldozer longitudinally to nappe and fill earth material, every layer of loose laying depth is no more than 40cm, adopts bulldozer and road roller to roll;
(d) check and accept
At every layer of placement grinding, reach after the definite number of rolling of scheme, for the following roadbed body of bedding powder fine sand filler, adopt relative density and coefficient of subgrade reaction K30 as compaction quality judgment criteria; For bound edge A, B group filler, adopt porosity and coefficient of subgrade reaction K30 as compaction quality judgment criteria;
(2) roadbed bottom, adopts conditioned soil or qualified A, B group filler to fill;
(3) subgrade bed top layer, adopts conditioned soil or qualified A, B group filler to fill.
2. a kind of powder fine sand that utilizes according to claim 1, as the filling roadbed construction method of filler, is characterized in that: in described (b) engineer testing step, adopt that SD22 bulldozer is crisscross to roll 7 ~ 9 times, below pine paving 40cm.
CN201310649563.9A 2013-12-06 2013-12-06 Construction method for filling and building subgrade by using silty-fine sand as filling materials Active CN103628363B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310649563.9A CN103628363B (en) 2013-12-06 2013-12-06 Construction method for filling and building subgrade by using silty-fine sand as filling materials

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310649563.9A CN103628363B (en) 2013-12-06 2013-12-06 Construction method for filling and building subgrade by using silty-fine sand as filling materials

Publications (2)

Publication Number Publication Date
CN103628363A CN103628363A (en) 2014-03-12
CN103628363B true CN103628363B (en) 2014-11-26

Family

ID=50209794

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310649563.9A Active CN103628363B (en) 2013-12-06 2013-12-06 Construction method for filling and building subgrade by using silty-fine sand as filling materials

Country Status (1)

Country Link
CN (1) CN103628363B (en)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047210B (en) * 2014-06-26 2016-06-22 李社军 Rail track roadbed
CN106087627A (en) * 2016-06-16 2016-11-09 中交四公局第二工程有限公司 Red sandstone roadbed filling construction technique
CN106638545B (en) * 2017-01-23 2019-06-18 中铁第四勘察设计院集团有限公司 The Treatment of Expansive Soil Embankment structure and construction method that the improvement of cored method is reinforced
CN107119505A (en) * 2017-05-22 2017-09-01 锦州铁道勘察设计院有限公司 The general fast railway bed filling construction method of desert area
CN107503256A (en) * 2017-07-12 2017-12-22 河海大学 A kind of sandy soil improves filling roadbed construction method
CN107338686A (en) * 2017-07-13 2017-11-10 高军 A kind of Subgrade Filled Soil in High Speed Railway construction method
CN107653758A (en) * 2017-08-18 2018-02-02 中交第四公路工程局有限公司 Laterite bound edge wind-blown sand fill subgrade construction method
CN108532380A (en) * 2018-05-09 2018-09-14 新疆铁道勘察设计院有限公司 A kind of railway bed bedding cored structure of windy and sandy area
CN108570909B (en) * 2018-05-15 2020-03-13 西南交通大学 Filling and compacting method for fine sand roadbed
CN108867226B (en) * 2018-07-20 2021-03-26 四川锦城智信建设工程有限公司 Roadbed filling construction method for physically improving fine sand
CN109183541A (en) * 2018-10-09 2019-01-11 中铁六局集团广州工程有限公司 A kind of roadbed construction method and application using gravelly sand group material
CN109610244A (en) * 2018-12-25 2019-04-12 四川天鑫达建筑工程有限公司 The physically improved roadbed filling method of fine silt
CN110273428A (en) * 2019-07-03 2019-09-24 中电建十一局工程有限公司 It is a kind of using building waste as the construction method for filling materials
CN111021173B (en) * 2019-12-31 2021-07-27 郑州一建集团有限公司 Construction method of municipal road sand-filled roadbed
CN111188234A (en) * 2020-01-10 2020-05-22 中国十七冶集团有限公司 Method for enhancing construction quality of red sandstone roadbed
CN114508012A (en) * 2022-01-24 2022-05-17 浙江交工集团股份有限公司港航工程分公司 Fine sand soil in-situ solidified roadbed and construction method thereof
CN116289375B (en) * 2023-03-22 2023-09-19 黑龙江农垦建工路桥有限公司 Construction method suitable for alternately filling wind-driven materials and river sand into roadbed

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1496161A1 (en) * 2003-07-11 2005-01-12 Ooms Avenhorn Holding B.V. Method to stabilise the traffic route
CN103061225A (en) * 2011-10-21 2013-04-24 中铁二十一局集团有限公司 Rock salt railroad bed structure of section parallel to existing line and construction method of structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1496161A1 (en) * 2003-07-11 2005-01-12 Ooms Avenhorn Holding B.V. Method to stabilise the traffic route
CN103061225A (en) * 2011-10-21 2013-04-24 中铁二十一局集团有限公司 Rock salt railroad bed structure of section parallel to existing line and construction method of structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李世勇.铁路路基填筑施工技术及质量控制研究.《广西质量监督导报》.2009,(第4期),36-37. *
铁路路基填筑施工技术及质量控制研究;李世勇;《广西质量监督导报》;20090426(第4期);34-37 *

Also Published As

Publication number Publication date
CN103628363A (en) 2014-03-12

Similar Documents

Publication Publication Date Title
CN103628363B (en) Construction method for filling and building subgrade by using silty-fine sand as filling materials
CN108611932B (en) A kind of construction method for passing through pool, fish pond location multiply road railway high-fill roadbed
CN104358188B (en) Filling construction method for collapsible loess subgrade
CN104631253A (en) Improvement and filling method of red clay subgrades at zone 94 and zone 96 of highway
CN106522074A (en) Construction technology for gravel-pebble-soil roadbed of expressway
CN105696426B (en) It is a kind of to handle the construction method and its road structure for closing on both wired soft soil foundations
CN107338686A (en) A kind of Subgrade Filled Soil in High Speed Railway construction method
CN102747662A (en) Construction method for sand-filling subgrade
CN106245503A (en) A kind of for rendzinas control debulking methods in roadbed filling
CN107761495A (en) A kind of pre-buried expanding bag compensation subgrade settlement construction method
CN107675577B (en) Road subgrade closed cushion structure in soft soil area and construction method thereof
CN103276649B (en) Side is had to limit layering many thickness Stone Filled Embankment construction method
CN104452507A (en) Construction method for filling roadbed by using wind deposited sand
CN105297571A (en) Mudstone filled roadbed structure and construction method thereof
CN107653758A (en) Laterite bound edge wind-blown sand fill subgrade construction method
CN107489137A (en) A kind of method that collapsible loess foundation is handled using cement soil padding
CN109183541A (en) A kind of roadbed construction method and application using gravelly sand group material
CN110761137B (en) Non-damage layered rolling construction method using cement-modified fine silt as roadbed filler
CN203908552U (en) Surface subsidence leveling measuring and monitoring device
CN104652180A (en) Roadbed filling construction method
CN114232649A (en) Construction method for filling earthwork of ballastless track roadbed
CN103243624B (en) Construction method for salty soil district railway roadbed with water content lower than liquid limit
CN103276716B (en) A kind of changeover portion CFG stake and mattress layer composite foundation stabilization construction method
CN104762859B (en) Mountain skin stone processes soft soil roadbed method
CN111827033A (en) Construction method for widening and filling solidified soil of expressway intercommunicating ramp roadbed

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant