CN103618250A CN201310617038.9A CN201310617038A CN103618250A CN 103618250 A CN103618250 A CN 103618250A CN 201310617038 A CN201310617038 A CN 201310617038A CN 103618250 A CN103618250 A CN 103618250A
Authority
CN
China
Prior art keywords
insulator
arm
insulator string
high voltage
machete card
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310617038.9A
Other languages
Chinese (zh)
Inventor
闫旭东
胡志鹏
李明
胡振
张珣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Maintenance Branch of State Grid Hubei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Maintenance Branch of State Grid Hubei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Maintenance Branch of State Grid Hubei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201310617038.9A priority Critical patent/CN103618250A/en
Publication of CN103618250A publication Critical patent/CN103618250A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)
  • Insulators (AREA)

Abstract

The invention provides an operating method for electrified replacement of double-V double-L insulator chains of an extra-high voltage circuit. The operating method comprises the following steps that a tower cross arm fixture is mounted through a preformed construction hole or a main material at an insulator chain hanging point, and a large tool fixture is mounted through a wire side two-gang plate; a wire lifting device, an insulating pull rod and the tower cross arm fixture are connected to form a mechanical load transfer system of the insulator chains; the contact point of the back of the large tool fixture and the two-gang plate is used as a fulcrum, the wire lifting device is operated to carry out small-distance wire lifting position changing, a large tool fixture operating arm is driven to rotate to drive an action arm to transfer loads on the insulator chains, and the mechanical loads of the insulator chains to be maintained are transferred to the wire lifting device; the insulator chains to be maintained are dismantled. Through the lever principle, the wire lifting device is operated to carry out small-distance wire lifting position changing, so that the large tool fixture operating arm is driven to rotate to drive the action arm to transfer the loads on the insulator chains, the insulator chains can be conveniently and quickly replaced, and the requirement for electrified maintenance of the extra-high voltage circuit is met.

Description

The operational method of the two V of super, extra high voltage line charged for replacement, two L insulator strings
[technical field]
The present invention relates to surpass, extra-high voltage electric transmission and transformation field, relate in particular to the operational method of a kind of super, two V of extra high voltage line charged for replacement, two L insulator strings.
[background technology]
Transmission line operation maintenance service work is the important means of grasping operation of power networks situation, discovery in time and treatment facility defect, is also the element task of guaranteeing line security stable operation.Because super extra-high voltage grid is in service in core status at whole national grid, therefore the operating maintenance work of super extra-high voltage grid is of great significance for safe, stable, the reliability service tool that guarantee super extra-high voltage grid and even whole national grid.
At first extra-high voltage direct-current, make progress in engineering design and first common-tower double-return DC line Ge Nan line (woods maple line) engineering design, the tangent tower of circuit adopts two " V " insulator strings and hard capstan head to adopt the assembling mode of two " L " insulator strings conventionally.When there is defect in insulator string parts, the general mechanical load that adopts " just carrying line " mode to shift insulator string, maintenance and replacing insulator string.
Refer to Fig. 1, so-called " just carrying line " mode mainly refers to, with locating to reserve construction hole (or main material) directly over wire yoke plate, do fulcrum on the tower of instrument, cross arm of tower special mould clamp (or fastening means) is installed, being connected is connected with wire, the mechanical load transfer system of composition insulator string by connection, to carry line apparatus (mechanical screw mandrel or hydraulic screw rod), high-strength insulating pull bar, quadripartion line lifter (six division line lifters).By operate machine screw mandrel or hydraulic screw rod, load transfer system is tightened up stressed, slowly wire is mentioned, make the load transfer of Awaiting Overhaul insulator string machinery to carrying line apparatus, realize the maintenance of insulator string.
Yet, the mechanical load of carrying lineman's utensil of the operating type of this " just carrying line " is large, may cause maintenance side insulator string horizontal direction force to diminish, thereby wire is offset round about, when and in maintenance during defective insulator string, insulator string also will adopt the wire lateral displacement measure that prevents while resetting, reset difficult with exemption from inspection insulator string.
[summary of the invention]
In view of this, for overcoming the deficiencies in the prior art, be necessary to provide a kind of and be applicable to surpass, the two V of charged for replacement of extra high voltage line, the operational method of two L insulator strings.
An operational method for the two V of super, extra high voltage line charged for replacement, two L insulator strings, described operational method comprises the following steps: by tangent tower, enter equipotential; Utilize reserved construction hole, insulator string hanging point place or the main material in hanging point place, as fulcrum on the tower of instrument, cross arm of tower jig is installed, utilize side of wire was duplex plate at the fulcrum of side of wire was, machete card to be installed as instrument; By carrying line apparatus, high-strength insulating pull bar is connected with cross-arm jig on tower, forms the mechanical load transfer system of insulator string; Utilize the card of machete card to carry on the back with duplex plate contact position as fulcrum, and machete card is divided into actuation arm and motion arm, the linear deflection of proposing that line apparatus carries out small distance is proposed in operation, drive machete card motion arm to rotate, induced effect arm shifts load on insulator string, makes the load transfer of Awaiting Overhaul insulator string machinery to carrying line apparatus; Pull down Awaiting Overhaul insulator string.
Therein at least one embodiment, the described step of utilizing side of wire was duplex plate at the fulcrum of side of wire was, machete card to be installed as instrument comprises: the bottom that the bayonet socket of machete card is installed on to Awaiting Overhaul insulator string one side on duplex plate, the hook of machete card is caught on to the core through screw rod at duplex plate center, the flat surface of the bayonet socket root of machete card holds up Awaiting Overhaul insulator string one side of duplex plate.
Therein at least one embodiment, described in the load transfer of Awaiting Overhaul insulator string machinery is comprised to the step of carrying line apparatus: at the external line apparatus of carrying of openend of machete card, by adjusting, carry line apparatus the openend of machete card applied to power.
Therein at least one embodiment, described in carry traditional thread binding mechanical screw mandrel or the hydraulic screw rod of being set to.
The operational method of the two V of charged for replacement super, extra high voltage line of the present invention, two L insulator strings has been utilized lever principle, by operation, propose the linear deflection of proposing that line apparatus carries out small distance, can drive machete card motion arm to rotate, induced effect arm shifts load on insulator string, can change quickly and easily two " V " insulator strings of straight line, firmly turn two " L " insulator strings, meet requirement super, UHVDC Transmission Lines hotline maintenance.
[accompanying drawing explanation]
Fig. 1 is the schematic diagram that existing " just carrying line " method is changed insulator string.
Fig. 2 A, 2B are respectively front view and the vertical view that the machete card adopting in the operational method of tangent tower, hard capstan head insulator string is changed in preferred embodiment of the present invention.
Fig. 3 is for adopting the operation chart of the machete card replacement insulator string in Fig. 2.
[embodiment]
For understanding better the present invention, below with reference to accompanying drawing and instantiation, invention is described in detail.
According to design feature super, UHV transmission line design, the invention provides two " V " insulator strings of a kind of replacing straight line, firmly turn two " L " insulator string operations employing machete cards and utilize " the micro-line working system of carrying of lever principle " to shift the mechanical load of insulator string.
Incorporated by reference to consulting Fig. 2 A, 2B, the structure of machete card is as shown in Fig. 2 A, 2B.Machete card comprises hook 10, opening 30 and the waist 20 that connects described hook 10 and described opening 30.In hook 10, be provided with bayonet socket 12, the root of bayonet socket 12 is flat surface 14 by the face of a side of waist 20.
Incorporated by reference to consulting Fig. 3, the hook 10 that the hook 10 of one end of machete card and the core through screw rod 42 of inverted triangle duplex plate 40 match, the opening 30 of the other end is for external screw mandrel 50, and the flat surface 14 of its waist 20 contacts with the bottom side of inverted triangle duplex plate 40.During use, the bayonet socket 12 of linking up with 10 ends is contained in inverted triangle duplex plate 40 both sides by machete cutting ferrule, links up with 10 and hooks and close mutually with the core through screw rod 42 of inverted triangle duplex plate 40, and the root flat surface 14 of bayonet socket 12 contacts with the bottom side of inverted triangle duplex plate 40.
If need to safeguard in advance and overhaul by the gold utensil on a certain side on respect to inverted triangle duplex plate 40, when first the bayonet socket of machete card 12 being installed on to inverted triangle duplex plate 40 this side bottom, hook 10 core through screw rod 42 that catch in inverted triangle duplex plate 40 centers, the root flat surface 14 of bayonet socket 12 holds up the pre-maintenance of inverted triangle duplex plate 40 and one end of maintenance, so form and take the lever that the other end of inverted triangle duplex plate 40 upper sides is fulcrum, opening 30 ends are lever end.And then at the external screw mandrel 50 of opening 30 end, by manual adjustment screw mandrel 50, opening 30 ends are applied to power, lever end is that opening 30 places only need apply less strength and just the heavier load on one end of the pre-maintenance of triangle duplex plate 40 and maintenance can be laid down like this.Last staff just can easily safeguard and maintenance transmission facility under high-altitude and charged operating mode.
Below by employing machete card of the present invention and utilize " the micro-line working system of carrying of lever principle " to change two " V " insulator strings of straight line, the operational method that firmly turns two " L " insulator strings describes, its concrete operation step is as follows:
(1) by tangent tower, enter equipotential;
(2) utilize reserved construction hole, insulator string hanging point place (or the main material in hanging point place), as fulcrum on the tower of instrument, cross arm of tower jig is installed, utilize side of wire was duplex plate at the fulcrum of side of wire was, machete card to be installed as instrument;
(3) by carrying line apparatus (mechanical screw mandrel or hydraulic screw rod), high-strength insulating pull bar is connected with cross-arm jig on tower, forms the mechanical load transfer system of insulator string;
(4) utilize the card of machete card to carry on the back with duplex plate contact position as fulcrum, and machete card is divided into actuation arm and motion arm, the linear deflection of proposing that line apparatus carries out small distance is proposed in operation, drive machete card motion arm to rotate, induced effect arm shifts load on insulator string, makes the load transfer of Awaiting Overhaul insulator string machinery to carrying line apparatus;
(5) pull down Awaiting Overhaul insulator string.
In above-mentioned technique, two " V " insulator string, the live load that firmly turns two " L " insulator string machete cards are 50KN.Above-mentioned technique is owing to having utilized lever principle, the linear deflection of proposing that line apparatus carries out small distance is proposed in operation, can drive machete card motion arm to rotate, induced effect arm shifts load on insulator string, can change quickly and easily two " V " insulator strings, firmly turn two " L " insulator strings, meet requirement super, UHVDC Transmission Lines hotline maintenance.
The above embodiment has only expressed several execution mode of the present invention, and it describes comparatively concrete and detailed, but can not therefore be interpreted as the restriction to the scope of the claims of the present invention.It should be pointed out that for the person of ordinary skill of the art, without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.Therefore, the protection range of patent of the present invention should be as the criterion with claims.

Claims (4)

1. an operational method for the two V of super, extra high voltage line charged for replacement, two L insulator strings, described operational method comprises the following steps:
By tangent tower, enter equipotential;
Utilize reserved construction hole, insulator string hanging point place or the main material in hanging point place, as fulcrum on the tower of instrument, cross arm of tower jig is installed, utilize side of wire was duplex plate at the fulcrum of side of wire was, machete card to be installed as instrument;
By carrying line apparatus, high-strength insulating pull bar is connected with cross-arm jig on tower, forms the mechanical load transfer system of insulator string;
Utilize the card of machete card to carry on the back with duplex plate contact position as fulcrum, and machete card is divided into actuation arm and motion arm, the linear deflection of proposing that line apparatus carries out small distance is proposed in operation, drive machete card motion arm to rotate, induced effect arm shifts load on insulator string, makes the load transfer of Awaiting Overhaul insulator string machinery to carrying line apparatus;
Pull down Awaiting Overhaul insulator string.
2. the operational method of super, two V of extra high voltage line charged for replacement according to claim 1, two L insulator strings, it is characterized in that, the described step of utilizing side of wire was duplex plate at the fulcrum of side of wire was, machete card to be installed as instrument comprises: the bottom that the bayonet socket of machete card is installed on to Awaiting Overhaul insulator string one side on duplex plate, the hook of machete card is caught on to the core through screw rod at duplex plate center, the flat surface of the bayonet socket root of machete card holds up Awaiting Overhaul insulator string one side of duplex plate.
3. the operational method of super, two V of extra high voltage line charged for replacement according to claim 1, two L insulator strings, it is characterized in that, described the load transfer of Awaiting Overhaul insulator string machinery is comprised to the step of carrying line apparatus: at the external line apparatus of carrying of openend of machete card, by adjusting, carry line apparatus the openend of machete card is applied to power.
4. the operational method of super, two V of extra high voltage line charged for replacement according to claim 3, two L insulator strings, is characterized in that: described in carry traditional thread binding mechanical screw mandrel or the hydraulic screw rod of being set to.
CN201310617038.9A 2013-11-27 2013-11-27 Operating method for electrified replacement of double-V double-L insulator chains of extra-high voltage circuit Pending CN103618250A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310617038.9A CN103618250A (en) 2013-11-27 2013-11-27 Operating method for electrified replacement of double-V double-L insulator chains of extra-high voltage circuit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310617038.9A CN103618250A (en) 2013-11-27 2013-11-27 Operating method for electrified replacement of double-V double-L insulator chains of extra-high voltage circuit

Publications (1)

Publication Number Publication Date
CN103618250A true CN103618250A (en) 2014-03-05

Family

ID=50168953

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310617038.9A Pending CN103618250A (en) 2013-11-27 2013-11-27 Operating method for electrified replacement of double-V double-L insulator chains of extra-high voltage circuit

Country Status (1)

Country Link
CN (1) CN103618250A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104242153A (en) * 2014-09-29 2014-12-24 国家电网公司 Construction technology for replacing monolithic 550kN glass insulators of strain towers of extra-high voltage direct-current transmission lines
CN106992466A (en) * 2017-05-18 2017-07-28 国家电网公司 The strain insulator string electrification replacing tool of extra-high voltage six and replacing options
CN111725737A (en) * 2020-07-07 2020-09-29 国网湖南省电力有限公司 Device and method for live replacement of extra-high voltage direct current v-type duplex composite insulator

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000059936A (en) * 1998-08-10 2000-02-25 Chubu Electric Power Co Inc Insulator replacing device for two-string strain- insulator apparatus
KR20040037868A (en) * 2002-10-30 2004-05-08 한국전력공사 An insulator exchanger of power line
CN202014055U (en) * 2010-12-28 2011-10-19 河北省电力公司超高压输变电分公司 Overhauling device of V-shaped double-string insulator for +-660KV direct current transmission line

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000059936A (en) * 1998-08-10 2000-02-25 Chubu Electric Power Co Inc Insulator replacing device for two-string strain- insulator apparatus
KR20040037868A (en) * 2002-10-30 2004-05-08 한국전력공사 An insulator exchanger of power line
CN202014055U (en) * 2010-12-28 2011-10-19 河北省电力公司超高压输变电分公司 Overhauling device of V-shaped double-string insulator for +-660KV direct current transmission line

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王星超等: "带电作业工器具研制及带电作业实用化研究", 《湖北电力》 *
胡川等: "±800kV特高压直流输电线路带电作业工器具研制及应用", 《湖北电力》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104242153A (en) * 2014-09-29 2014-12-24 国家电网公司 Construction technology for replacing monolithic 550kN glass insulators of strain towers of extra-high voltage direct-current transmission lines
CN104242153B (en) * 2014-09-29 2017-06-13 国家电网公司 Change UHVDC Transmission Lines anchor support monolithic 550kN glass insulator construction technologies
CN106992466A (en) * 2017-05-18 2017-07-28 国家电网公司 The strain insulator string electrification replacing tool of extra-high voltage six and replacing options
CN111725737A (en) * 2020-07-07 2020-09-29 国网湖南省电力有限公司 Device and method for live replacement of extra-high voltage direct current v-type duplex composite insulator

Similar Documents

Publication Publication Date Title
WO2015078279A1 (en) Live overhaul process for ±800 kv ultra-high voltage dc power transmission line
WO2012088987A1 (en) Maintenance tool for insulator of direct current transmission line
CN205429581U (en) A locking lever structure for electron field
CN101820144B (en) Special tool of live line work for replacing rectilinear insulator string of large-section double multiple wire
CN103618249A (en) technology for electrified overhaul of +-500kV double-circuit direct-current power transmission lines on same tower
CN102185265B (en) Construction method for replacing cross arm of 35kV line linear rod
CN205092507U (en) Multi -functional insulating drainage line support frame
CN103606853A (en) Operating method for replacing linear V insulator string on super and ultra-high voltage direct current transmission line in electrified mode
CN104821517A (en) Double-pull-rod wing-shaped lead lifting device
CN104143782A (en) Electrified replacement tool and method for +/-800 kV circuit strain insulator string
CN102290743B (en) Electrified linkage pin-pulling device for replacing 220kV linear insulator string
CN103618250A (en) Operating method for electrified replacement of double-V double-L insulator chains of extra-high voltage circuit
CN101814707B (en) Tool for live replacement of 220kV line 'V' string insulator and method
CN204885990U (en) Transmission line yoke plate hoisting device
CN104143786A (en) Multi-purpose 10 kV drainage wire insulation fixer and work method with same
CN102820629B (en) The method of charged for replacement drainage thread parallel groove clamp
CN202602171U (en) A tool for power-on replacing multi-loop double split conductor insulator of 220kV line
CN203787855U (en) Power transmission line linear charged wire lifting device
CN102208776B (en) Working tool for live-line replacement of insulator chain of triangle link plate hanging point type and working method thereof
CN205159908U (en) Backup protection fixing -line device
CN102916372B (en) 10kV multi-circuit lines on the same pole mesophase spherule wire lifting instrument
CN102623927B (en) Charged for replacement 220kV circuit multiloop double bundle conductor insulator tool and method
CN204793844U (en) Change promotion instrument of single wire insulator of 110kV with electricity
CN204333858U (en) Core-bunched strain clamp
CN102163824B (en) Operating tool and operation method for electrically replacing T-type mounting point suspending insulator in 110kV line steel pipe rod

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140305

RJ01 Rejection of invention patent application after publication