CN103614149A - Carbonization chamber bottom brick integral-replacement hot-repair structure and method - Google Patents

Carbonization chamber bottom brick integral-replacement hot-repair structure and method Download PDF

Info

Publication number
CN103614149A
CN103614149A CN201310639856.9A CN201310639856A CN103614149A CN 103614149 A CN103614149 A CN 103614149A CN 201310639856 A CN201310639856 A CN 201310639856A CN 103614149 A CN103614149 A CN 103614149A
Authority
CN
China
Prior art keywords
brick
carbonization chamber
car body
send
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310639856.9A
Other languages
Chinese (zh)
Other versions
CN103614149B (en
Inventor
陈振炜
黄刚
王又魁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pangang Group Panzhihua Steel and Vanadium Co Ltd
Original Assignee
Pangang Group Panzhihua Steel and Vanadium Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pangang Group Panzhihua Steel and Vanadium Co Ltd filed Critical Pangang Group Panzhihua Steel and Vanadium Co Ltd
Priority to CN201310639856.9A priority Critical patent/CN103614149B/en
Publication of CN103614149A publication Critical patent/CN103614149A/en
Application granted granted Critical
Publication of CN103614149B publication Critical patent/CN103614149B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The invention discloses a maintenance structure, particularly a carbonization chamber bottom brick integral-replacement hot-repair structure. The invention provides a carbonization chamber bottom brick integral-replacement hot-repair structure capable of thermal insulation for the carbonization chamber, which comprises a carbonization chamber main body composed of a top, a bottom and side walls, and a thermal insulation door and a brick delivery device, wherein the thermal insulation door is arranged at the inlet of the carbonization chamber main body; and a brick delivery space for the brick delivery device to pass through is left between the bottom side of the thermal insulation door and the bottom of the carbonization chamber main body. In the carbonization chamber maintenance process, the thermal insulation door is used for implementing thermal insulation for the carbonization chamber, thereby preventing the heat of the carbonization chamber from being quick emission, and implementing thermal insulation for the carbonization chamber; and thus, the great temperature difference of the carbonization chamber is avoided, thereby effectively prolonging the service life of the carbonization chamber. When mounting new high-alumina bricks, the special brick delivery device can be adopted, so that the brick mounting distance can be increased, so that all the bottom bricks can be replaced.

Description

Bottom brick of carbonization chamber integral replacing hot repair structure and method
Technical field
The present invention relates to a kind of maintaining structure, especially a kind of bottom brick of carbonization chamber integral replacing hot repair structure.In addition, the invention still further relates to a kind of method for maintaining, especially a kind of bottom brick of carbonization chamber integral replacing hot repair method.
Background technology
In current coking chamber maintenance, bottom brick of carbonization chamber of coke oven hot repair is local replacing, the longest less than 9m.Because coking chamber is longer, under hot repair state there is larger difficulty in integral replacing bottom brick of carbonization chamber, and workload is large, and temperature is high, adds that coking chamber is longer, send brick distance, and heap brick amount is large, is easy to faulting of slab ends.
In the maintenance process of coking chamber, must open the door of coking chamber, because the replacing time of bottom brick is longer, this stove overlong time that makes to have leisure, the temperature of coking chamber declines very fast; It is too fast that the overlong time of opening wide fire door causes temperature of furnace wall to reduce, and furnace wall rapid heat cycle causes silica brick damage efflorescence to degrade, and affects coke oven work-ing life.
Summary of the invention
It can be the bottom brick of carbonization chamber integral replacing hot repair structure of coking chamber insulation that technical problem to be solved by this invention is to provide a kind of.
The present invention solves the bottom brick of carbonization chamber integral replacing hot repair structure that its technical problem adopts, comprise the coking chamber main body being formed by top, bottom and sidewall, also comprise heat insulation door and send brick equipment, described heat insulation door is arranged on the ingress of coking chamber main body, and that between the base of described heat insulation door and the bottom of coking chamber main body, leaves that feed brick equipment passes through send brick space.
Be further, describedly send brick equipment to comprise car body, wheel, send brick handle, brick pushing plate and push away brick handle, described wheel is arranged on the bottom of car body, the described brick handle that send is connected on car body, described brick pushing plate is arranged on car body and can moves along car body surface, described in push away brick handle and be connected with described brick pushing plate.
Further, described heat insulation door comprises door frame and thermal insulation layer, and described heat insulation door is arranged on the ingress of coking chamber main body, and described thermal insulation layer covers on door frame.
Further, described thermal insulation layer is ceramic fiber blanket.
In addition, another technical problem that will solve of the present invention is to provide a kind of bottom brick of carbonization chamber integral replacing hot repair method that can be coking chamber insulation.
The present invention also provides a kind of bottom brick of carbonization chamber integral replacing hot repair method, comprises the following steps:
A, in the ingress of coking chamber main body, set up heat insulation door, that between the bottom of heat insulation door and the bottom of coking chamber main body, leaves that feed brick equipment passes through send brick space;
B, processing high alumina brick preheating, configure refractory clay;
C, use rail steel are removed second-hand brick, cleaning bottom of carbonization chamber;
D, utilization are sent brick equipment the high alumina brick after preheating to be fed through to the bottom of coking chamber main body, and high alumina brick are laid on to the bottom of coking chamber main body;
E, to utilize refractory clay be that the high alumina brick grouting laying is plastered;
F, dismounting heat insulation door.
Be further, in D step, describedly send brick equipment to comprise car body, wheel, send brick handle, brick pushing plate and push away brick handle, described wheel is arranged on the bottom of car body, the described brick handle that send is connected on car body, described brick pushing plate is arranged on car body and can moves along car body surface, described in push away brick handle and be connected with described brick pushing plate; When carrying high alumina brick, utilize and send brick handle to control car body, make car body carry high alumina brick to the position of setting, then utilize to push away brick handle and control brick pushing plate motion, make high alumina brick slide and drop into the position of setting from car body.
Further, in C step, the direction of removing second-hand brick is: from cokery side to centre.
Further, in C step, after removing second-hand brick, the position that need build new brick at the bottom of coking chamber is purged totally with pressurized air, do not stay the grit that is greater than 5mm.
The invention has the beneficial effects as follows: when carrying out coking chamber maintenance, utilize heat insulation door to be incubated for coking chamber, thereby avoid the heat Quick diffusing of coking chamber, thereby be effectively coking chamber insulation, avoid coking chamber to occur the larger temperature difference, thereby effectively extend the work-ing life of coking chamber.When new high alumina brick is installed, can adopt the special-purpose brick equipment that send, the raising that this distance that makes to lay brick is strengthened, thus can change all bottom bricks.This send brick device fabrication material simple, light easy to use, bottom brick can be fixed, especially in hot situation, bottom brick directly fast can be delivered to coking chamber depths, deliver to behind predetermined position, touch and send brick device push rod, bottom brick steadily can be placed and be formulated position, avoided using conventional instrument to send easily causing in brick process bottom brick to topple over or crooked need send the brick could success repeatedly back and forth several times, cause bottom not steady, brickwork joint faulting of slab ends, even causes operation unsuccessfully to need repair for 2nd time.
Accompanying drawing explanation
Fig. 1 is schematic diagram of the present invention;
Fig. 2 is the schematic diagram of heat insulation door;
Component, position and numbering in figure: coking chamber main body 1, heat insulation door 2, send brick equipment 3, send brick space 4, car body 5, wheel 6, send brick handle 7, brick pushing plate 8, push away brick handle 9, door frame 10, thermal insulation layer 11, high alumina brick 12.
Embodiment
Below in conjunction with accompanying drawing, the invention will be further described.
As depicted in figs. 1 and 2, the present invention includes the coking chamber main body 1 being formed by top, bottom and sidewall, also comprise heat insulation door 2 and send brick equipment 3, described heat insulation door 2 is arranged on the ingress of coking chamber main body 1, and that between the base of described heat insulation door 2 and the bottom of coking chamber main body 1, leaves that feed brick equipment 3 passes through send brick space 4.When keeping in repair, heat insulation door 2 is installed to the ingress of coking chamber main body 1, make heat insulation door 2 play the effect of heat-insulation and heat-preservation, prevent the heat loss of coking chamber main body 1.Between heat insulation door 2 and bottom, leave and send brick space 4, this makes to send the brick equipment 3 can be by the inwall that send brick space 4 to enter into coking chamber main body 1, thereby completes the installation of new high alumina brick 12.
Concrete, as shown in Figure 1, describedly send brick equipment 3 to comprise car body 5, wheel 6, send brick handle 7, brick pushing plate 8 and push away brick handle 9, described wheel 6 is arranged on the bottom of car body 5, the described brick handle 7 that send is connected on car body 5, described brick pushing plate 8 is arranged on car body 5 and can be along car body 5 apparent motion, described in push away brick handle 9 and be connected with described brick pushing plate 8.Brick pushing plate 8 can be by guide rails assembling the surface at car body 5, thereby realize motion.Sending brick handle 7 and push away the length of brick handle 9 should be enough, so that car body 5 can reach the degree of depth that coking chamber main body 1 is inner enough.In use, high alumina brick 12 is placed on car body 6 and with brick pushing plate 8 and is coordinated, then utilize and send brick handle 7 to promote car body 5 from sending brick space 4 to enter into coking chamber main body 1 inside, when arriving the placement location of high alumina brick 12, promotion pushes away brick handle 9, thereby make brick pushing plate 8 motion, and then promote high alumina brick 12 and be slipped to the bottom of coking chamber main body 1 from car body 6.So just, completed the installation of high alumina brick 12.
Concrete, as shown in Figure 2, described heat insulation door 2 comprises door frame 10 and thermal insulation layer 11, and described heat insulation door 2 is arranged on the ingress of coking chamber main body 1, and described thermal insulation layer 11 covers on door frame 10.Door frame 10 adopts steel construction, is arranged on the ingress of coking chamber main body 1, then on door frame 10, lays thermal insulation layer, and thermal insulation layer 11 adopts ceramic fiber blanket.
Embodiment
When the hot repair of bottom brick of carbonization chamber integral replacing, adopt following steps:
A, in the ingress of coking chamber main body 1, set up heat insulation door 2, that between the bottom of heat insulation door 2 and the bottom of coking chamber main body 1, leaves that feed brick equipment passes through send brick space 4;
B, processing high alumina brick 12 preheating, configure refractory clay;
C, use rail steel are removed second-hand brick, cleaning bottom of carbonization chamber; The direction of removing second-hand brick is: from cokery side to centre; After removing second-hand brick, the position that need build new brick at the bottom of coking chamber is purged totally with pressurized air, do not stay the grit that is greater than 5mm.
D, the length of again measuring, confirm dismounting place and the degree of depth, to confirm whether new high alumina brick 12 meets dimensional requirement, otherwise process new high alumina brick 12; Utilization send brick equipment 3 high alumina brick after preheating 12 to be fed through to the bottom of coking chamber main body 1, and high alumina brick 12 is laid on to the bottom of coking chamber main body 1; From centre to cokery side two by 12 1 one of high alumina brick with sending brick equipment to send " dry pendulum " to, until cokery side coking chamber mouth, high alumina brick 12 is built by laying bricks or stones and is required smoothly, must not become stepped appearance, align with both sides furnace wall, and keep whole coking chamber main body 1 bottom level basically identical; When new high alumina brick 12 is built to stove frame place, last piece high alumina brick 12 is processed according to size; Send brick equipment 3 preferably to adopt aforesaid equipment, when carrying high alumina brick 12, utilize and send brick handle 7 to control car body 5, make 5 years high alumina bricks 12 of car body to the position of setting, then utilize to push away brick handle 9 and control brick pushing plates 8 motions, make high alumina brick 12 slide and drop into the position of setting from car body 5.
E, new block high alumina brick 12 surface cleanings are clean, utilizing refractory clay is that high alumina brick 12 grouting that lay are plastered;
F, finally remove heat insulation door 2.
In whole maintenance process, coking chamber main body 1 has all been subject to heat insulation door 2 effects, thereby effectively keep temperature, send brick equipment 3 in hot situation, bottom high alumina brick 12 directly fast can be delivered to coking chamber main body 1 depths, bottom high alumina brick 12 steadily can be placed and formulated position, avoided using conventional instrument to send easily causing in brick process bottom brick to topple over or crooked need send the brick could success repeatedly back and forth several times, cause bottom not steady, brickwork joint faulting of slab ends, even causes operation unsuccessfully to need repair for 2nd time.

Claims (8)

1. bottom brick of carbonization chamber integral replacing hot repair structure, comprise the coking chamber main body (1) being formed by top, bottom and sidewall, it is characterized in that: also comprise heat insulation door (2) and send brick equipment (3), described heat insulation door (2) is arranged on the ingress of coking chamber main body (1), and that between the base of described heat insulation door (2) and the bottom of coking chamber main body (1), leaves that feed brick equipment (3) passes through send brick space (4).
2. bottom brick of carbonization chamber integral replacing hot repair structure as claimed in claim 1, it is characterized in that: described in send brick equipment (3) to comprise car body (5), wheel (6), send brick handle (7), brick pushing plate (8) and push away brick handle (9), described wheel (6) is arranged on the bottom of car body (5), the described brick handle (7) that send is connected on car body (5), it is upper and can be along car body (5) apparent motion that described brick pushing plate (8) is arranged on car body (5), described in push away brick handle (9) and be connected with described brick pushing plate (8).
3. bottom brick of carbonization chamber integral replacing hot repair structure as claimed in claim 1 or 2, it is characterized in that: described heat insulation door (2) comprises door frame (10) and thermal insulation layer (11), described heat insulation door (2) is arranged on the ingress of coking chamber main body (1), and described thermal insulation layer (11) covers on door frame (10).
4. bottom brick of carbonization chamber integral replacing hot repair structure as claimed in claim 3, is characterized in that: described thermal insulation layer (11) is ceramic fiber blanket.
5. the bottom brick of carbonization chamber integral replacing hot repair method that adopts hot repair structure as described in claim as arbitrary in claim 1 to 4, is characterized in that: comprise the following steps:
A, in the ingress of coking chamber main body (1), set up heat insulation door (2), that between the bottom of heat insulation door (2) and the bottom of coking chamber main body (1), leaves that feed brick equipment (3) passes through send brick space (4);
B, processing high alumina brick (12) preheating, configure refractory clay;
C, use rail steel are removed second-hand brick, cleaning bottom of carbonization chamber;
D, utilization are sent brick equipment (3) high alumina brick after preheating (12) to be fed through to the bottom of coking chamber main body (1), and high alumina brick (12) are laid on to the bottom of coking chamber main body (1);
E, to utilize refractory clay be that high alumina brick (12) grouting laying is plastered;
F, dismounting heat insulation door (2).
6. bottom brick of carbonization chamber integral replacing hot repair method as claimed in claim 5, it is characterized in that: in D step, describedly send brick equipment (3) to comprise car body (5), wheel (6), send brick handle (7), brick pushing plate (8) and push away brick handle (9), described wheel (6) is arranged on the bottom of car body (5), the described brick handle (7) that send is connected on car body (5), it is upper and can be along car body (5) apparent motion that described brick pushing plate (8) is arranged on car body (5), described in push away brick handle (9) and be connected with described brick pushing plate (8); When carrying high alumina brick (12), utilization send brick handle (7) to control car body (5), make car body (5) carry high alumina brick (12) to the position of setting, then utilize to push away brick handle (9) and control brick pushing plate (8) motion, make high alumina brick (12) slide and drop into the position of setting from car body (5).
7. bottom brick of carbonization chamber integral replacing hot repair method as claimed in claim 5, is characterized in that: in C step, the direction of removing second-hand brick is: from cokery side to centre.
8. bottom brick of carbonization chamber integral replacing hot repair method as claimed in claim 5, is characterized in that: in C step, after removing second-hand brick, the position that need build new brick at the bottom of coking chamber is purged totally with pressurized air, do not stay the grit that is greater than 5mm.
CN201310639856.9A 2013-12-02 2013-12-02 Carbonization chamber bottom brick integral-replacement hot-repair structure and method Active CN103614149B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310639856.9A CN103614149B (en) 2013-12-02 2013-12-02 Carbonization chamber bottom brick integral-replacement hot-repair structure and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310639856.9A CN103614149B (en) 2013-12-02 2013-12-02 Carbonization chamber bottom brick integral-replacement hot-repair structure and method

Publications (2)

Publication Number Publication Date
CN103614149A true CN103614149A (en) 2014-03-05
CN103614149B CN103614149B (en) 2015-05-20

Family

ID=50164870

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310639856.9A Active CN103614149B (en) 2013-12-02 2013-12-02 Carbonization chamber bottom brick integral-replacement hot-repair structure and method

Country Status (1)

Country Link
CN (1) CN103614149B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109294601A (en) * 2017-07-25 2019-02-01 广东韶钢松山股份有限公司 A kind of carbonizing chamber of coke oven bottom fast repairing method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1613967A (en) * 2003-11-07 2005-05-11 酒泉钢铁(集团)有限责任公司 Process for heat maintaining whole walls of coke carbonating chamber
CN101907298A (en) * 2010-07-31 2010-12-08 中国洛阳浮法玻璃集团有限责任公司 Hot repair method of port tongue arch of coal-burning glass furnace

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1613967A (en) * 2003-11-07 2005-05-11 酒泉钢铁(集团)有限责任公司 Process for heat maintaining whole walls of coke carbonating chamber
CN101907298A (en) * 2010-07-31 2010-12-08 中国洛阳浮法玻璃集团有限责任公司 Hot repair method of port tongue arch of coal-burning glass furnace

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109294601A (en) * 2017-07-25 2019-02-01 广东韶钢松山股份有限公司 A kind of carbonizing chamber of coke oven bottom fast repairing method
CN109294601B (en) * 2017-07-25 2021-04-30 广东韶钢松山股份有限公司 Rapid repairing method for bottom of carbonization chamber of coke oven

Also Published As

Publication number Publication date
CN103614149B (en) 2015-05-20

Similar Documents

Publication Publication Date Title
JP2020521841A (en) System and method for repairing a coke oven
CN105419821A (en) Thermal-state non-stop production replacement method of lattice bricks in regenerative chamber of coke oven
JP2010280809A (en) Installation method of oven top equipment in coke oven construction
CN103614149B (en) Carbonization chamber bottom brick integral-replacement hot-repair structure and method
CN114181719A (en) Large coke oven building and building process
CN107782065B (en) Yellow phosphorus electric furnace electrode baking method capable of avoiding damaging furnace bottom
CN103788966A (en) High-temperature resistant expansion joint for dry quenching
CN2848853Y (en) Fire brick building device of coke oven carbonation chamber bottom
CN102373063B (en) Bricklaying loading method of coke oven
CN204718409U (en) A kind of can the anode furnace of hot replacing redox mouth brick
CN102887621B (en) Molding device produced by glass rolling method
CN201442956U (en) Main iron runner with air cooling channel for blast furnace
CN104073269A (en) Deep maintenance method on coke-oven charcoal bottom bricks
CN111575026A (en) Novel heat insulation structure of coke oven foundation roof
CN210916195U (en) Energy-saving metal wire annealing furnace
CN201553699U (en) Thermal insulation device for maintaining bottom of coke oven
CN206768167U (en) A kind of masonry construction of RH refining furnaces lower channel
CN212504700U (en) Novel heat insulation structure of coke oven foundation roof
CN110849147A (en) Heat accumulating type steel pushing heating furnace bottom structure
CN203866243U (en) High-temperature-resistant expansion joint for dry quenching
CN219572671U (en) Composite prefabricated brick for cement kiln lining
CN220728892U (en) Easy-to-replace silicon nitride push plate
CN203653480U (en) Construction structure of bracket supporting bricks in inclined flue region of dry-quenching coke oven
CN202902861U (en) Masonry type sintering machine trolley breast board
CN204824578U (en) Glass melting furnace flue bottom plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant