CN103528560A - 一种高土石坝内部变形监测方法及装置 - Google Patents

一种高土石坝内部变形监测方法及装置 Download PDF

Info

Publication number
CN103528560A
CN103528560A CN201310453721.3A CN201310453721A CN103528560A CN 103528560 A CN103528560 A CN 103528560A CN 201310453721 A CN201310453721 A CN 201310453721A CN 103528560 A CN103528560 A CN 103528560A
Authority
CN
China
Prior art keywords
gallery
monitoring
high earth
dam
earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310453721.3A
Other languages
English (en)
Inventor
张宗亮
杨泽艳
谭志伟
张礼兵
吴毅谨
邹青
赵志勇
刘伟
蔡莹冰
王富强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Ltd Of Kunming Hydroelectric Investigation & Design Institute Of China Hydropower Consulting Group
Original Assignee
Co Ltd Of Kunming Hydroelectric Investigation & Design Institute Of China Hydropower Consulting Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Ltd Of Kunming Hydroelectric Investigation & Design Institute Of China Hydropower Consulting Group filed Critical Co Ltd Of Kunming Hydroelectric Investigation & Design Institute Of China Hydropower Consulting Group
Priority to CN201310453721.3A priority Critical patent/CN103528560A/zh
Publication of CN103528560A publication Critical patent/CN103528560A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

本发明是一种高土石坝内部变形监测方法及装置。所述的方法是在高土石坝内的不同断面、不同高程设置监测装置。所述的监测装置为预应力预制廊道,并在廊道内分段设置变形监测仪器。所述的预制廊道每段长度2.0m,每段预制廊道之间为填充柔性材料。本发明解决了长距离变形监测仪器的适应性和可靠性问题,同时监测廊道的设置还有效解决了土石坝内部监测仪器电缆过长和不易保护等问题,更方便了人工巡视检查。

Description

一种高土石坝内部变形监测方法及装置
技术领域
本发明涉及水电工程技术领域,具体说是一种高土石坝内部变形监测方法及装置。
背景技术
近年来国内水电技术发展迅速,以天生桥一级(坝高178m)、洪家渡(坝高179.5m)、三板溪(坝高185.5m)和水布垭(坝高233m)水电站等为代表的一批典型工程,将面板堆石坝高度逐步由100m级提升至200m级,使我国土石坝设计理论及施工技术达到国际先进水平。但是,面板堆石坝安全监测技术发展明显滞后于筑坝技术的发展,不少监测仪器适应性、耐久性、抗冲击等性能仍停留在100m级坝高的水平,对于300m级的高坝传统监测仪器已难以适应。
堆石体内部变形监测就是其中的难题之一,200m级堆石坝其监测管线长度400m~500m已是其材料和工艺极限,在实际使用过程中出现过诸多问题,对300m级面板坝700m~1000m左右的管线长度更是无能为力,因此急需寻找一种能解决300m级高土石坝内部变形监测的方法。
发明内容
本发明的目的是提供一种高土石坝内部变形监测方法及装置,以解决高土石坝内部变形监测的难题。
本发明的技术方案为:高土石坝内部变形监测方法是在高土石坝内的不同断面、不同高程设置监测装置,所述的监测装置为预应力预制廊道,并在廊道内分段设置变形监测仪器。
所述的预制廊道每段长度为2.0m左右,预制廊道之间采用土工膜或沥青等填充,以适应堆石坝不均匀沉降。
本发明在高土石坝内的不同断面、不同高程设置监测装置,能监测到高土石坝内不同位置和不同高度的内部变形情况。以解决高土石坝内部变形监测目前监测手段和仪器设备存在诸多局限的问题。在监测廊道内分段布设变形监测仪器,解决了长距离变形监测仪器的适应性和可靠性问题,同时监测廊道的设置还有效解决了土石坝内部监测仪器电缆过长和不易保护等问题,更方便了人工巡视检查。本发明从根本上改变我国高土石坝的安全监测设计和监测方法,在水电行业具有及其深远的意义。
附图说明
图1 是本发明的土石坝监测廊道布置示意图。
图2 是本发明的监测廊道结构示意图。
图3 是图2的A-A剖面图。
图4是本发明的监测廊道内监测仪器布置示意图。
图中:1―坝顶,2―土石坝,3―下游坝面,4、5―监测廊道,6―坝基,7―上游坝面,8―填充柔性材料,9、10―分段布置监测仪器。
具体实施方式
本发明的高土石坝内部变形监测方法是在高土石坝内的不同断面、不同高程设置监测装置,如图1所示中的监测廊道4、5。
所述的监测装置为预应力预制廊道,如图2~图3所示,并在廊道内分段设置变形监测仪器9、10(变形监测仪器为现有设备),如图4所示。
所述的预制廊道每段长度为2.0m左右,预制廊道之间采用填充柔性材料8(土工膜或沥青等)填充,以适应堆石坝不均匀沉降。
从监测廊道内打孔布设堆石体内部监测仪器,使得堆石体内部监测布置更具可操作性和合理性。堆石体内监测仪器电缆就近引入监测廊道,避免或减少了电缆长距离在堆石体内牵引有可能被损坏等问题。施工及运行期监测人员可通过监测廊道进行人工巡视检查。

Claims (3)

1.一种高土石坝内部变形监测方法,其特征在于所述的方法是在高土石坝内的不同断面、不同高程设置监测装置。
2.一种高土石坝内部变形监测装置,其特征在于所述的监测装置为预应力预制廊道,并在廊道内分段设置变形监测仪器。
3.根据权利要求2所述的高土石坝内部变形监测装置,其特征在于所述的预制廊道每段长度2.0m,每段预制廊道之间为填充柔性材料。
CN201310453721.3A 2013-09-29 2013-09-29 一种高土石坝内部变形监测方法及装置 Pending CN103528560A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310453721.3A CN103528560A (zh) 2013-09-29 2013-09-29 一种高土石坝内部变形监测方法及装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310453721.3A CN103528560A (zh) 2013-09-29 2013-09-29 一种高土石坝内部变形监测方法及装置

Publications (1)

Publication Number Publication Date
CN103528560A true CN103528560A (zh) 2014-01-22

Family

ID=49930764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310453721.3A Pending CN103528560A (zh) 2013-09-29 2013-09-29 一种高土石坝内部变形监测方法及装置

Country Status (1)

Country Link
CN (1) CN103528560A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108844516A (zh) * 2018-06-29 2018-11-20 深圳大学 一种堆石坝内部形变监测管道布设方法及***
CN110806192A (zh) * 2019-11-20 2020-02-18 武汉大学 一种高堆石坝内部变形的监测方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001082934A (ja) * 1999-09-16 2001-03-30 Sumitomo Electric Ind Ltd 破堤監視システム
JP2001304924A (ja) * 2000-04-27 2001-10-31 Reideikku:Kk 斜面崩壊測定装置及び歪分布測定方法
CN1940473A (zh) * 2004-01-17 2007-04-04 湖北清江水布垭工程建设公司 大坝面板挠度或坝体内部变形的监测管道
CN103196416A (zh) * 2013-03-17 2013-07-10 水利部交通运输部国家能源局南京水利科学研究院 大坝内部变形的机器人监测方法和监测***
CN103292762A (zh) * 2013-05-23 2013-09-11 青岛理工大学 判别大坝稳定性的位移监测方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001082934A (ja) * 1999-09-16 2001-03-30 Sumitomo Electric Ind Ltd 破堤監視システム
JP2001304924A (ja) * 2000-04-27 2001-10-31 Reideikku:Kk 斜面崩壊測定装置及び歪分布測定方法
CN1940473A (zh) * 2004-01-17 2007-04-04 湖北清江水布垭工程建设公司 大坝面板挠度或坝体内部变形的监测管道
CN103196416A (zh) * 2013-03-17 2013-07-10 水利部交通运输部国家能源局南京水利科学研究院 大坝内部变形的机器人监测方法和监测***
CN103292762A (zh) * 2013-05-23 2013-09-11 青岛理工大学 判别大坝稳定性的位移监测方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
何福江等: "高土石坝内部变形观测", 《四川水力发电》 *
彭虹: "300m级高混凝土面板堆石坝坝体内部变形监测新思路", 《水电自动化与大坝监测》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108844516A (zh) * 2018-06-29 2018-11-20 深圳大学 一种堆石坝内部形变监测管道布设方法及***
CN110806192A (zh) * 2019-11-20 2020-02-18 武汉大学 一种高堆石坝内部变形的监测方法
CN110806192B (zh) * 2019-11-20 2020-12-01 武汉大学 一种高堆石坝内部变形的监测方法

Similar Documents

Publication Publication Date Title
CN103487563B (zh) 一种模拟隔-降-灌联合作用下基坑三维渗流及地层变形机制的试验装置
CN106950070B (zh) 用于矩形顶管顶进施工全过程模拟的试验装置
CN104594911B (zh) 盾构始发阶段或接收阶段近距离下穿运营线路的施工方法
CN203177847U (zh) 沉降实时监测***
CN103953025A (zh) 测量深厚软土或覆盖层分层沉降的设备及其设置方法
CN203798629U (zh) 一种地下水分层采样装置
CN104569341A (zh) 真空预压联合电渗试验装置以及真空预压联合电渗试验的方法
CN203950414U (zh) 一种不稳定边坡自动报警装置
CN103471647A (zh) 一种盾构隧道远程自动化监测方法
CN103471648A (zh) 一种顶管隧道的扰动施工监测方法
CN104264719A (zh) 真空预压室内模型试验装置
Broch et al. The design of unlined hydropower tunnels and shafts: 100 years of Norwegian experience
CN103592904A (zh) 一种电力隧道远程监控***
CN103528560A (zh) 一种高土石坝内部变形监测方法及装置
CN204059120U (zh) 一种铁路路基塌陷实时监测装置
CN104533469A (zh) 一种解决地下洞室衬砌表面渗水漏水的方法及装置
CN203490361U (zh) 探地雷达检测辅助装置
CN202393377U (zh) 水电站基础建设工程的分层式沉降监测仪器
CN204402513U (zh) 一种解决地下洞室衬砌表面渗水漏水的装置
CN203835412U (zh) 一种水下巷道渗漏处理的结构
CN103195046A (zh) 一种一孔多孔隙水压力计埋设方法
CN203655210U (zh) 一种含水层水头监测用封孔器及监测仪
CN103512546A (zh) 一种土石坝内部变形非接触式监测方法
CN102926368B (zh) 一种道路路基不均匀沉降的监测装置及监测方法
CN104613858A (zh) 一种隧道围岩初期支护水平收敛位移监测仪器及方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140122