CN103514786A - 基于位移控制法的隧道施工对环境影响的模型试验方法 - Google Patents

基于位移控制法的隧道施工对环境影响的模型试验方法 Download PDF

Info

Publication number
CN103514786A
CN103514786A CN201310419785.1A CN201310419785A CN103514786A CN 103514786 A CN103514786 A CN 103514786A CN 201310419785 A CN201310419785 A CN 201310419785A CN 103514786 A CN103514786 A CN 103514786A
Authority
CN
China
Prior art keywords
tunnel
urceolus
model test
simulation
deformation device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310419785.1A
Other languages
English (en)
Other versions
CN103514786B (zh
Inventor
夏钒
叶冠林
卞荣
刘燕平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiaotong University
Original Assignee
Shanghai Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiaotong University filed Critical Shanghai Jiaotong University
Priority to CN201310419785.1A priority Critical patent/CN103514786B/zh
Publication of CN103514786A publication Critical patent/CN103514786A/zh
Application granted granted Critical
Publication of CN103514786B publication Critical patent/CN103514786B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明提供一种基于位移控制法的隧道施工对环境影响的模型试验方法,步骤如下:(1)针对模型试验采用的地层损失率,计算得到所需隧道变形装置长度和直径,隧道变形装置由内、外筒两部分组成,内筒模拟隧道设计尺寸,外筒模拟隧道开挖尺寸;(2)将内筒***外筒内部并封住它们之间空隙,然后将隧道变形装置固定安装到模型试验装置;(3)向模型试验装置中装填模型材料,安装模拟构筑物并最后安装测量仪器;(4)完成对测量仪器的校正和归零,抽出外筒进行试验,通过抽走外筒让模拟材料落入内外筒之间的空隙,模拟隧道施工造成的地层损失。该试验方法简单实用,成本低,易操作,适用于隧道施工对周边环境影响的试验研究。

Description

基于位移控制法的隧道施工对环境影响的模型试验方法
技术领域
本发明涉及一种隧道施工对环境影响的模型试验方法,具体地,涉及一种基于位移控制法的隧道施工模型试验方法。
背景技术
随着我国城市基础设施建设的飞速发展,隧道已经成为城市基础设施不可缺少的一部分,而且隧道线路越来越靠近各种构筑物,对周边环境产生不利影响的可能性越来越大。因此对隧道施工进行试验,尤其是模型试验的研究越来越多。
进行模型试验时,如果较好地反映由于隧道施工引起的沉降是一个关键点。由于隧道开挖施工方法的复杂性以及土体性质的不确定性等因素,直接复制实际隧道开挖过程的试验往往出现试验装置复杂、成本高、操作难,很难保证试验结果达到预期等问题。因此,在针对隧道施工的研究中引入了位移控制法(Displacement Control Method)。
位移控制法就是不考虑隧道施工的实际过程,直接在隧道边缘施加位移边界条件以模拟开挖过程的一种方法。由于隧道顶部收缩要大于隧道底部收缩,故位移控制法中的隧道收缩边界位移条件为非均匀收缩,顶部收缩最大,底部收缩为0,隧道开挖面以底部相切的“同底圆”方式收缩至设计尺寸,如图1所示,g代表最大地层位移损失,R代表隧道断面设计半径。
这种方法虽然不能模拟隧道各个施工环节,但意义明确且能够模拟任意给定的地层损失率,简单易行且容易控制,在研究隧道施工对环境影响中具有广泛的应用前景。但是隧道施工研究中对位移控制法的应用多见于有限元模拟等理论分析中,未见于应用于模型试验,对现有技术的文献检索尚未发现基于位移控制法的隧道施工模型试验的相关报道。
发明内容
针对现有技术中的空白,本发明的目的是提出了一种基于位移控制法的隧道施工对环境影响的室内模型试验方法,简单实用,大大提高隧道施工模型试验的效率和准确性。
本发明提出了一种基于位移控制法的隧道施工模型试验方法,具体步骤如下:
(1)针对模型试验采用的地层损失率,计算得到所需隧道变形装置长度和直径,隧道变形装置由内、外筒两部分组成,内筒模拟隧道设计尺寸,外筒模拟隧道开挖尺寸;
(2)将内筒***外筒内部并封住它们之间空隙,然后将隧道变形装置固定安装到模型试验装置上,同时准备好模型材料及模拟构筑物。
(3)向模型试验装置中装填模型材料,安装模拟构筑物并最后安装测量仪器。
(4)完成对测量仪器的校正和归零,抽出外筒进行试验,通过抽走外筒让模拟材料落入内外筒之间的空隙,模拟隧道施工造成的地层损失。
优选地,所述隧道变形装置由等长度的内筒和外筒两部分组成,内外筒的横截面形状包括但不限于圆形,内筒截面尺寸基于试验需要和工程实际直接确定,外筒截面尺寸由内筒截面尺寸和地层损失率确定,即外筒直径由下式算得:
D = d 1 + ϵ
式中D为外筒直径,d为内筒直径,ε为地层损失率。
优选地,所述隧道变形装置的内筒***外筒长度等于模拟隧道施工长度,筒口安装密封装置,组合后固定安装在模型试验装置上。
优选地,所述隧道变形装置依靠抽出外筒实现隧道施工的模拟。
与现有技术相比,本发明具有如下的有益效果:
1、本发明基于位移控制法原理,可根据试验需要根据给定的地层损失率大小进行隧道变形装置的设计,进行任何地层损失率情况下的隧道施工模拟。
2、本发明中的试验装置简单实用,成本低,易操作,适用于所有类型隧道施工的模型试验。
附图说明
通过阅读参照以下附图对非限制性实施例所作的详细描述,本发明的其它特征、目的和优点将会变得更明显:
图1为隧道开挖面以底部相切的“同底圆”方式收缩至设计尺寸示意图;
图2为本发明一实施例某隧道施工模型试验前隧道变形装置纵断面示意图;
图3为本发明一实施例某隧道施工模型试验中隧道变形装置纵断面示意图;
图4为本发明一实施例某隧道施工模型试验中隧道变形装置横截面变化图。
具体实施方式
下面结合具体实施例对本发明进行详细说明。以下实施例将有助于本领域的技术人员进一步理解本发明,但不以任何形式限制本发明。应当指出的是,对本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进。这些都属于本发明的保护范围。
本实施例提供一种基于位移控制法的顶管隧道施工模型试验,模拟施工长度1400mm,模拟隧道设计直径141mm,地层损失率5%。本实施例具体步骤如下:
(1)针对模型试验采用的地层损失率,计算得到所需隧道变形装置长度和直径,具体如下:
隧道变形装置由内、外筒两部分组成,内筒模拟隧道设计尺寸,外筒模拟隧道开挖尺寸。内筒和外筒采用相同长度,基于试验需要和工程实际确定为1400mm。内筒直径基于试验需要和工程实际直接确定为141mm,外筒直径由下式算得:
D = d 1 + ϵ
式中D为外筒直径,d为内筒直径,ε为地层损失率。解得外筒直径145mm。
(2)将内筒***外筒内部,并调整至内筒***长度等于模拟隧道施工长度,在筒口安装密封装置封住内、外筒之间的空隙,然后将组合好的内、外筒固定安装到模型试验装置(如模型箱)上,完成隧道变形装置的安装,如图2所示。同时准备好用于模拟地层的模型材料,并视试验需要制作模拟构筑物(如地面建筑物、土中桩基等)。
(3)向模型装置中装填模型材料,并视试验需要对模型材料进行后处理(如夯实、固结等)。视试验需要在模型材料装填中或装填后安装模拟构筑物,最后安装测量仪器。
(4)完成对测量仪器的校正和归零,抽出外筒进行试验。试验开始后,向一个方向抽动外筒,内、外筒之间原本的空隙暴露,模拟开挖后的地层损失。外筒外侧土层向此空隙收缩,进而对周边土层产生影响,模拟隧道开挖对周边环境的影响,如图3、图4。
本发明试验方法基于位移控制法原理,可根据试验需要根据给定的地层损失率大小进行隧道变形装置的设计,进行任何地层损失率情况下的隧道施工模拟。而且本发明中的试验装置简单实用,成本低,易操作,适用于所有类型隧道施工的模型试验。
以上对本发明的具体实施例进行了描述。需要理解的是,本发明并不局限于上述特定实施方式,本领域技术人员可以在权利要求的范围内做出各种变形或修改,这并不影响本发明的实质内容。

Claims (4)

1.一种基于位移控制法的隧道施工对环境影响的模型试验方法,其特征在于,所述方法具体步骤如下:
(1)针对模型试验采用的地层损失率,计算得到所需隧道变形装置长度和直径,隧道变形装置由内、外筒两部分组成,内筒模拟隧道设计尺寸,外筒模拟隧道开挖尺寸;
(2)将内筒***外筒内部并封住它们之间空隙,然后将隧道变形装置固定安装到模型试验装置上,同时准备好模型材料及模拟构筑物;
(3)向模型试验装置中装填模型材料,安装模拟构筑物并最后安装测量仪器;
(4)完成对测量仪器的校正和归零,抽出外筒进行试验,通过抽走外筒让模拟材料落入内外筒之间的空隙,模拟隧道施工造成的地层损失。
2.根据权利要求1所述的一种基于位移控制法的模型试验方法,其特征在于,所述隧道变形装置由等长度的内筒和外筒两部分组成,内筒截面尺寸基于试验需要和工程实际直接确定,外筒直径由内筒截面尺寸和地层损失率确定,即外筒直径由下式算得:
D = d 1 + ϵ
式中D为外筒直径,d为内筒直径,ε为地层损失率。
3.根据权利要求1所述的一种基于位移控制法的模型试验方法,其特征在于,所述隧道变形装置的内筒***外筒内部,并调整至内筒***长度等于模拟隧道施工长度,在筒口安装密封装置封住内、外筒之间的空隙,然后将组合好的内、外筒固定安装到模型试验装置上,完成隧道变形装置的安装。
4.根据权利要求1-3任一项所述的一种基于位移控制法的模型试验方法,其特征在于,所述隧道变形装置依靠抽出外筒实现模拟隧道施工造成的地层损失,即试验开始后,向一个方向抽动外筒,内、外筒之间原本的空隙暴露,模拟开挖后的地层损失;外筒外侧土层向此空隙收缩,进而对周边土层产生影响,模拟隧道开挖对周边环境的影响。
CN201310419785.1A 2013-09-13 2013-09-13 基于位移控制法的隧道施工对环境影响的模型试验方法 Active CN103514786B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310419785.1A CN103514786B (zh) 2013-09-13 2013-09-13 基于位移控制法的隧道施工对环境影响的模型试验方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310419785.1A CN103514786B (zh) 2013-09-13 2013-09-13 基于位移控制法的隧道施工对环境影响的模型试验方法

Publications (2)

Publication Number Publication Date
CN103514786A true CN103514786A (zh) 2014-01-15
CN103514786B CN103514786B (zh) 2015-10-14

Family

ID=49897445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310419785.1A Active CN103514786B (zh) 2013-09-13 2013-09-13 基于位移控制法的隧道施工对环境影响的模型试验方法

Country Status (1)

Country Link
CN (1) CN103514786B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107782248A (zh) * 2017-09-26 2018-03-09 重庆大学 一种隧道开挖变形可视化模型实验装置及方法
CN110320346A (zh) * 2019-07-24 2019-10-11 中国水利水电科学研究院 隧道挖掘离心模型试验方法
CN111119901A (zh) * 2019-12-12 2020-05-08 中电建生态环境集团有限公司 穿过既有构筑物沉降控制方法
CN112485125A (zh) * 2020-11-23 2021-03-12 山东建筑大学 一种可控土体损失率的隧道模型试验装置及试验方法
CN113643606A (zh) * 2021-09-15 2021-11-12 济南轨道交通集团有限公司 一种盾构下穿既有管线的施工模拟试验装置及方法
CN113804857A (zh) * 2021-08-27 2021-12-17 深圳大学 基于二维颗粒的多圆盾构隧道开挖模型试验装置及使用方法
CN114936401A (zh) * 2022-05-19 2022-08-23 广西交通设计集团有限公司 基于地层损失率的隧道开挖三维数值分析位移控制方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5168677A (en) * 1989-11-15 1992-12-08 Ernesto Daniel Gyurec Method of constructing flat building block modules from the union of two frustums by their congruent bases and slot connectors complement for a variety of constructive or amusing applications
CN202393607U (zh) * 2011-11-28 2012-08-22 同济大学 一种地下开挖模拟试验箱
CN103061774A (zh) * 2013-01-04 2013-04-24 西南交通大学 一种盾构隧道施工环境模拟装置
CN103117020A (zh) * 2013-02-20 2013-05-22 苏州科技学院 盾构隧道动态掘进诱发地层损失及地表沉陷试验装置

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5168677A (en) * 1989-11-15 1992-12-08 Ernesto Daniel Gyurec Method of constructing flat building block modules from the union of two frustums by their congruent bases and slot connectors complement for a variety of constructive or amusing applications
CN202393607U (zh) * 2011-11-28 2012-08-22 同济大学 一种地下开挖模拟试验箱
CN103061774A (zh) * 2013-01-04 2013-04-24 西南交通大学 一种盾构隧道施工环境模拟装置
CN103117020A (zh) * 2013-02-20 2013-05-22 苏州科技学院 盾构隧道动态掘进诱发地层损失及地表沉陷试验装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
马险峰、王俊淞等: "《盾构隧道引起地层损失和地表沉降的离心模型试验研究》", 《岩土工程学报》, 31 May 2012 (2012-05-31) *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107782248A (zh) * 2017-09-26 2018-03-09 重庆大学 一种隧道开挖变形可视化模型实验装置及方法
CN110320346A (zh) * 2019-07-24 2019-10-11 中国水利水电科学研究院 隧道挖掘离心模型试验方法
CN111119901A (zh) * 2019-12-12 2020-05-08 中电建生态环境集团有限公司 穿过既有构筑物沉降控制方法
CN112485125A (zh) * 2020-11-23 2021-03-12 山东建筑大学 一种可控土体损失率的隧道模型试验装置及试验方法
CN112485125B (zh) * 2020-11-23 2024-04-09 山东建筑大学 一种可控土体损失率的隧道模型试验装置及试验方法
CN113804857A (zh) * 2021-08-27 2021-12-17 深圳大学 基于二维颗粒的多圆盾构隧道开挖模型试验装置及使用方法
CN113804857B (zh) * 2021-08-27 2024-05-31 深圳大学 基于二维颗粒的多圆盾构隧道开挖模型试验装置及使用方法
CN113643606A (zh) * 2021-09-15 2021-11-12 济南轨道交通集团有限公司 一种盾构下穿既有管线的施工模拟试验装置及方法
CN114936401A (zh) * 2022-05-19 2022-08-23 广西交通设计集团有限公司 基于地层损失率的隧道开挖三维数值分析位移控制方法
CN114936401B (zh) * 2022-05-19 2024-04-12 广西交通设计集团有限公司 基于地层损失率的隧道开挖三维数值分析位移控制方法

Also Published As

Publication number Publication date
CN103514786B (zh) 2015-10-14

Similar Documents

Publication Publication Date Title
CN103514786B (zh) 基于位移控制法的隧道施工对环境影响的模型试验方法
CN103821183B (zh) 一种模拟土体突涌破坏现象及规律的试验装置
Chen et al. Shaking table test of utility tunnel under non-uniform earthquake wave excitation
Hsiung A case study on the behaviour of a deep excavation in sand
Saberi et al. On the mechanics and modeling of interfaces between granular soils and structural materials
CN103117020B (zh) 盾构隧道动态掘进诱发地层损失及地表沉陷试验装置
CN104792966B (zh) 一种模拟地铁盾构隧道施工引发地层空洞的试验装置及方法
CN105527404A (zh) 模拟盾构隧道纵断面内地层损失扩展的试验***及方法
CN205317774U (zh) 模拟盾构隧道纵断面内地层损失扩展的试验***
US11556680B1 (en) Test method based on test system for five-dimensional space effects of ground surface settlement caused by dual-mode shield construction
Liu et al. Longitudinal structural deformation mechanism of shield tunnel linings considering shearing dislocation of circumferential joints
Ng et al. Investigation of passive failure and deformation mechanisms due to tunnelling in clay
CN109975117B (zh) 顶管实验箱及实验方法
CN102425430B (zh) 软土地层盾构隧道结构抵抗纵向变形的保护控制方法
CN107179391B (zh) 一种用于超浅埋下穿隧道浅层注浆的试验装置
CN208818567U (zh) 一种模拟地铁盾构隧道管片初始应力的试验装置
Sun et al. Design of a displacement monitoring system based on optical grating and numerical verification in geomechanical model test of water leakage of tunnel
CN105257318B (zh) 一种衬砌局部渗漏引起隧道结构变形的安全保护方法
Beddelee et al. Validation on laboratory simulated optical fibre sensor instrumented bored pile defect using 3D Finite Element Method
Xu et al. Supporting behavior evolution of ultra-deep circular diaphragm walls during excavation: Monitoring and assessment methods comparison
CN203337473U (zh) 土压力传感器安装加载测试装置
CN103088847B (zh) 一种地基加固离心模型试验砂桩制作装置及制作方法
CN110095107B (zh) 用于模拟地层损失诱发的土体变形过程的装置及方法
He et al. Mechanical response of Gasketed bell‐and‐spigot joint of concrete pipeline under multifield coupling
Liu et al. Model test and 3 d numerical simulation study on excavation of double-arch tunnel.

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant