CN103510712A - 多层h钢柱“┕┑”形空中对接施工工法 - Google Patents

多层h钢柱“┕┑”形空中对接施工工法 Download PDF

Info

Publication number
CN103510712A
CN103510712A CN201210221123.9A CN201210221123A CN103510712A CN 103510712 A CN103510712 A CN 103510712A CN 201210221123 A CN201210221123 A CN 201210221123A CN 103510712 A CN103510712 A CN 103510712A
Authority
CN
China
Prior art keywords
shaped steel
shaped
layer
welding
angled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210221123.9A
Other languages
English (en)
Inventor
倪廷玉
赵利杰
陈玲风
门长根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA SIXTH METALLURGICAL CONSTRUCTION Co Ltd
Original Assignee
CHINA SIXTH METALLURGICAL CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA SIXTH METALLURGICAL CONSTRUCTION Co Ltd filed Critical CHINA SIXTH METALLURGICAL CONSTRUCTION Co Ltd
Priority to CN201210221123.9A priority Critical patent/CN103510712A/zh
Publication of CN103510712A publication Critical patent/CN103510712A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

一种多层H钢柱“┕┑”形空中对接施工工法,本施工工法打破了原使用地面胎架焊接工艺,在第一节H型柱吊装就位标高、定位测量完成后,立即使地脚螺栓固定好钢柱,后进行二次灌浆,当混凝土强度达到80%后进行二节柱的吊装,当安装好脚踏板、安全绳、安全护栏后使用50T吊车进行二节柱的吊装和焊接工作,吊装和焊接工作完成后可继续使用此工法完成后节钢柱的空中对接。使用本施工工法进行二节柱对焊施工,大大简化了地面胎架焊接复杂的工艺过程,降低了吊车台班费、人工费约35%以上,施工进度提高45%,满足设计和规范要求,达到降低成本,缩短工期的目的。

Description

多层H钢柱“┕┑”形空中对接施工工法
技术领域
本发明涉及房屋建筑过程中钢结构的施工领域,尤其是多层H钢柱“┕┑”形空中对接施工工法。
背景技术
近年来,随着工业经济的快速发展,为缩短建设周期,工业厂房多采用钢结构H钢,因为工艺要求有些车间使用的多层H钢柱超长(长30多米,重近20吨),制作安装质量难于保证,并且由于受构件制作、运输、施工方法和现场条件的制约而导致多层H型钢柱问题影响了施工进度,延长了工期,提高了工程成本并且安装质量也降低了。
发明内容
为了克服传统施工方法中受构件制作、运输、施工方法和现场条件的制约而导致多层H型钢柱问题影响了施工进度进而工期延长、成本增加和安装质量低等不足,本发明提供一种多层H形钢柱“┕┑”形空中对接施工工法,该工法不受场地限制,在控制好焊接变形质量的前提下,能够快速安装好多层H型钢柱,质量可靠,且有利于吊装设备的多途选择。
本发明解决其技术问题所采取的技术方案是:该施工工法打破了原使用地面胎架焊接工艺,在第一节H型柱吊装就位标高、定位测量完成后,立即使地脚螺栓固定好钢柱,后进行二次灌浆,当混凝土强度达到80%后进行二节柱的吊装,当安装好脚踏板、安全绳、安全护栏后使用50T吊车进行二节柱的吊装和焊接工作,吊装和焊接工作完成后可继续使用此工法完成后节钢柱的空中对接。使用本施工工法进行二节柱对焊施工,大大简化了地面胎架焊接复杂的工艺过程,降低了吊车台班费、人工费约35%以上,施工进度提高45%,满足设计和规范要求,达到降低成本,缩短工期的目的。
本发明的有益效果是:经济效益体现突出,不需制作胎架,现场空中焊接完成施工,技术先进,施工速度快,节省工期,为后期设备安装赢得了充足时间,并且有利于在狭窄作业区多层H型钢柱对接的推广和应用。
附图说明
下面结合附图对本发明作进一步说明。
图1是焊接过程中是焊接技术参数。
图2是垂直吊装焊接时H钢柱的侧视图。
图3是垂直吊装焊接时H钢的主视图。
图2和图3中的2处表示焊接处的焊缝。
具体实施方式
本工程采用的测量设备为经纬仪DJ2-1、水准仪SZ3、钢卷尺30m/50m,运输及起吊设备QY50吨汽车吊,焊接设备有交流焊机BX-300、烘干箱ZKN-100,探伤设备为超声波探伤仪。施工主要步骤如下。
(1)基础交接检验,做好检验记录,根据控制定位轴线把纵横轴线引到H型钢柱基础上,定位轴线必须重合封闭。再根据定位线的尺寸误差不得超过探测线,定位轴线必须重合或平行,定位轴线应有业主、监理、安装联合检查验收,并做好中交记录,根据吊装顺序,安装一节柱,标高及偏移找正后,土建方立即进行二次浇注,砼强度超过80%后,进行二节柱吊装。
(2)安装脚踏板、安全绳、安全护栏,安装完后,用QY50吨汽车吊垂直起吊钢柱至安装位置与下节柱对正就位先调标高,在对正上下接头错位、扭转,再用经纬仪DJ2-1校正柱子垂直度,偏差到规范允许范围内,拉紧缆风绳,焊接,成型,摘吊钩支撑***连接。工程主构件材质为Q345B,钢柱连接采用坡口全熔透焊接,在焊接工艺评定的基础上,确定焊接的电焊条为Φ4~Φ6碳钢焊条J422型焊条,焊接技术参数如图1所示。
(3)焊条使用前应根据质量证明书的规定用烘干箱ZKN-100进行烘焙和保温,烘焙次数不超过两次。
(4)施焊前应将焊条边缘30-50mm范围内的铁锈、毛刺、油污等清理干净,以减少产生焊接气孔的缺陷因素。外层施焊应连续施焊,一层焊缝完成后应及时清理,焊缝出现裂纹时,焊工不应擅自处理,应申报技术负责人,查清原因,提出修补措施后方可处理。
(5)接头坡口处理,图2和图3中(2)处所示焊缝处,坡口角度为30度,在吊装之前进行检查对坡口的角度和平直度进行检查,对受损和达不到要求的部位进行打磨和修补处理,合格后,在对接头部位的坡口和附近2CM范围内打磨处理,直至露出金属光泽,焊接时两焊工在相对位置等速施焊,减少焊接变形和焊接应力。
(6)第二遍离第一遍起弧点50—100mm,拐角放慢焊条移动速度,圆滑过渡,一个接头连续不中断焊完,焊工焊完每个节点将自己钢印打在焊接部位。所有对接点,焊缝完成外观检查后进行100%超声波无损探伤,检测执行标准《钢结构焊缝和超声波探伤方法和结果分析》(GB11345—89)。
(7)焊接过程中如有发现焊缝存有缺陷,立即终止焊接,进行碳弧气刨清除缺陷,待缺陷完全清理后再进行焊接。
焊工施焊完成后,应及时清理焊渣,进行外观检查,要求焊缝金属表面焊接均匀,不得有裂纹夹渣、焊瘤、烧孔、弧坑、针状气孔等缺陷,并清除焊接区的飞溅物,使焊缝质量达到设计和规范要求。
(8)对不合格的焊缝,根据其缺陷位置、深度,采用碳弧气刨切除,超声波探伤检查存在缺陷的焊缝,从缺陷两端各加50mm作为清除部位,用焊缝相同的焊接工艺进行补焊,同样的方法和标准进行检验,同一部位返修不得超过两次。
(9)焊接完成并检查合格后该H形钢柱空中对接即完成,然后即可按照此工法继续下节柱的空中对接。
上述方案本行业技术人员通过行业技术手段可以实现。

Claims (1)

1.一种多层H钢柱“┕┑”形空中对接施工工法,其特征是:该工法不使用传统工法中使用地面胎架焊接工艺,在第一节H型柱吊装就位标高、定位测量完成后,立即使地脚螺栓固定好钢柱,后进行二次灌浆,当混凝土强度达到80%后进行二节柱的吊装,当安装好脚踏板、安全绳、安全护栏后使用50T吊车进行二节柱的吊装和焊接工作,吊装和焊接完成后可继续按此工法安装下节钢柱。
CN201210221123.9A 2012-06-29 2012-06-29 多层h钢柱“┕┑”形空中对接施工工法 Pending CN103510712A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210221123.9A CN103510712A (zh) 2012-06-29 2012-06-29 多层h钢柱“┕┑”形空中对接施工工法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210221123.9A CN103510712A (zh) 2012-06-29 2012-06-29 多层h钢柱“┕┑”形空中对接施工工法

Publications (1)

Publication Number Publication Date
CN103510712A true CN103510712A (zh) 2014-01-15

Family

ID=49894086

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210221123.9A Pending CN103510712A (zh) 2012-06-29 2012-06-29 多层h钢柱“┕┑”形空中对接施工工法

Country Status (1)

Country Link
CN (1) CN103510712A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652829A (zh) * 2015-01-23 2015-05-27 中铁四局集团钢结构有限公司 自提升折叠定位操作***施工方法
CN109991311A (zh) * 2019-04-09 2019-07-09 中国十七冶集团有限公司 一种厂房柱加固方法及其焊缝检测装置

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02161043A (ja) * 1988-12-14 1990-06-20 Shimizu Corp 綱管コンクリート柱の継手構造、綱管コンクリート柱及びその施工方法
JPH06257226A (ja) * 1993-03-09 1994-09-13 Kajima Corp 角形鋼管柱或いは角形鋼管コンクリート柱と梁の仕口構造
CN201351310Y (zh) * 2009-01-15 2009-11-25 西安建筑科技大学 配槽钢空腹骨架的混凝土异形柱——型钢混凝土梁框架节点
CN201351313Y (zh) * 2009-01-15 2009-11-25 西安建筑科技大学 配槽钢空腹骨架的混凝土异形柱——钢筋混凝土梁框架节点

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02161043A (ja) * 1988-12-14 1990-06-20 Shimizu Corp 綱管コンクリート柱の継手構造、綱管コンクリート柱及びその施工方法
JPH06257226A (ja) * 1993-03-09 1994-09-13 Kajima Corp 角形鋼管柱或いは角形鋼管コンクリート柱と梁の仕口構造
CN201351310Y (zh) * 2009-01-15 2009-11-25 西安建筑科技大学 配槽钢空腹骨架的混凝土异形柱——型钢混凝土梁框架节点
CN201351313Y (zh) * 2009-01-15 2009-11-25 西安建筑科技大学 配槽钢空腹骨架的混凝土异形柱——钢筋混凝土梁框架节点

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
耿云峰: "论钢结构工业厂房的设计与施工", 《今日科苑》, 23 October 2008 (2008-10-23) *
邵鹍等: "钢结构重型工业厂房安装技术研究", 《科技致富向导》, no. 23, 10 August 2010 (2010-08-10) *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652829A (zh) * 2015-01-23 2015-05-27 中铁四局集团钢结构有限公司 自提升折叠定位操作***施工方法
CN109991311A (zh) * 2019-04-09 2019-07-09 中国十七冶集团有限公司 一种厂房柱加固方法及其焊缝检测装置
CN109991311B (zh) * 2019-04-09 2021-06-11 中国十七冶集团有限公司 一种厂房柱加固方法及其焊缝检测装置

Similar Documents

Publication Publication Date Title
CN101967886B (zh) 核电站钢制安全壳的组装和安装方法
CN101890583B (zh) 大型储罐液压顶升自动焊倒装施工方法
CN107100309B (zh) 一种用于整体吊装大型多棱角悬挑桁架的施工方法
CN101691787B (zh) 中高层钢结构建筑逆向施工工艺
CN101956457B (zh) 一种矩形钢管混凝土柱施工工法
CN103806669A (zh) 十字形断面h型钢劲性柱施工方法
CN111561048A (zh) 一种高空吊装型钢梁、梁柱节点的安装方法
CN101804501A (zh) 汽化冷却烟道地面组对焊接整体安装施工工艺
CN112342922B (zh) 异形截面箱式钢结构流线型钢拱制造方法
CN114439249B (zh) 一种大跨三角桁架空中转体提升施工方法
CN111250833A (zh) 一种用于钢箱梁节段拼装的桥位焊接方法
CN103157955A (zh) 大直径钢圆筒的制造方法
CN112211103A (zh) 输煤栈桥钢桁架组合安装安全专项施工工艺
CN104195948A (zh) 桥梁悬吊管道顶推安装施工方法
CN115162182B (zh) 一种悬臂式钢箱梁高精度缆索吊装施工方法
CN105537848A (zh) 四梁双小车起重机副主梁冲撞变形的在线修复方法
CN114955887B (zh) 一种船舶上门座起重机安装方法
CN116100182A (zh) 一种c型船用lng储罐止移块的装焊方法
WO2003095142A1 (fr) Dispositif de travail pour surface de paroi interieure de tour reservoir et procede utilisant ce dispositif
CN103495793A (zh) 改进的大吨位铸钢构件复杂节点吊装焊接施工方法
CN104590487B (zh) 一种工程船用大型艉滚筒法兰盘高精度装焊工艺
CN103510712A (zh) 多层h钢柱“┕┑”形空中对接施工工法
CN106400675A (zh) 一种钢锚箱及其安装方法
CN106120664B (zh) 升船机下闸首工作闸门施工方法
CN103243928A (zh) 双向倾斜v型柱施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140115