CN103507915A - Integral hoisting design method for wood ship upper layer building - Google Patents
Integral hoisting design method for wood ship upper layer building Download PDFInfo
- Publication number
- CN103507915A CN103507915A CN201310414479.9A CN201310414479A CN103507915A CN 103507915 A CN103507915 A CN 103507915A CN 201310414479 A CN201310414479 A CN 201310414479A CN 103507915 A CN103507915 A CN 103507915A
- Authority
- CN
- China
- Prior art keywords
- hanger
- upper layer
- integral hoisting
- ship
- layer building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
The invention relates to an integral hoisting design method for a wood ship upper layer building. The method comprises the first step of preparing a lifting lug, the second step of finishing room finish and installation of internal systems and equipment in the wood ship upper layer building and carrying out folding in the pre-assembled field, the third step of welding the lifting lug and the upper layer building into a whole and then carrying out integral hoisting, and the fourth step of cutting the lifting lug after hoisting. The integral hoisting design method has the advantages that the labor intensity of workers is improved, production efficiency is improved, the ship production cycle is shortened, and the ship manufacturing cost is reduced.
Description
Technical field
The present invention relates to ship domain, refer in particular to a kind of wood chip ship lifting and mounting complete superstructure method of designing.
Background technology
What the hanger of current domestic shipyard lifting and mounting complete superstructure adopted mostly is split type standard hanger, is to be all welded on separately in superstructure structure to do and lift by crane use.Superstructure region, the lift-launch that segmentation is, pre outfitting rate is low, and after carrying, work capacity is huge, has a strong impact on the degree of utilization of dock and harbour, extends the production cycle of boats and ships.Also have and be designed to the hanger of combined and structure welding as lifting use, but its design too complicated and make require high, and lifting finish rear dismounting loaded down with trivial details, remove after the Reusability number of times of hanger low.This Project-developing be that hanger is directly designed in structure.After the project implementation completes, not only removing the welding job of hanger but also lifting, to finish rear dismounting hanger more convenient, improved greatly work efficiency.To improve greatly core competitiveness, in shipping industry, will maintain the leading position.
Summary of the invention
The object of the invention is in order to overcome above deficiency, provide a kind of by hanger design being added after calculating in superstructure with structure as one; After superstructure lifting finishes, only hanger partly need be cut off, not destroy application, reduce coating work; The structure hanger simplicity of design of superstructure, convenient making; The hanger of superstructure lifting still can Reusability wood chip ship lifting and mounting complete superstructure method of designing repeatedly after removing.
Object of the present invention is achieved through the following technical solutions: a kind of wood chip ship lifting and mounting complete superstructure method of designing, comprises the following steps:
A, preparation hanger;
B, the room finish in the superstructure of wood chip ship, built-in system, installations and facilities installation ,Yu Zu place are closed up;
C, hanger and superstructure are welded as a whole, and then carry out integral hoisting;
After D, lifting finish, hanger is cut again.
The present invention has the following advantages: as modern general assembly shipbuilding, improve speed, key is to improve the integraty of segmentation prepackage, accelerates freak oil finished products.On build as relatively independent construction module, guarantee its integraty and finished products, significant to shortening the harbour cycle.
According to the maximization of the existing load-carrying ability in our factory, carry out rational suspension centre arrangement analysis, Yu Zu place, whole Shang Jian region is closed up, room finish in superstructure, built-in system, installations and facilities are installed and are all completed, after integral hoisting, just can carry out in a short time harbour debugging, the test of clean ship check weighing, reach the object that region sealing is produced.
Improve labor strength, enhance productivity, shorten ship building period, reduce shipbuilding cost.
Accompanying drawing explanation:
Fig. 1 is structural representation of the present invention;
Number in the figure: 1-hanger.
The specific embodiment:
In order to deepen the understanding of the present invention, below in conjunction with embodiment and accompanying drawing, the invention will be further described, and this embodiment only, for explaining the present invention, does not form limiting the scope of the present invention.
As Fig. 1 shows a kind of wood chip ship of the present invention lifting and mounting complete superstructure method of designing, comprise the following steps:
A, preparation hanger 1, the part that structure hanger 1 is designed to structure can complete 1 in advance by production process in the parts of segmentation, not only enhances productivity, and has also shortened the dead work of follow-up integral hoisting, structure hanger 1 simplicity of design, does not need complicated processing and making;
B, the room finish in the superstructure of wood chip ship, built-in system, installations and facilities installation ,Yu Zu place are closed up;
C, hanger 1 and superstructure are welded as a whole, and then carry out integral hoisting, after integral hoisting, just can carry out in a short time harbour debugging, the test of clean ship check weighing, reach the object of region sealing production;
After D, lifting finish, hanger 1 is cut again, line of cut marks with dotted line in the drawings, after using, structure hanger 1 all needs to cut off, not only can not destroy structure and application and also reduce greatly repairing and polishing work, the structure hanger 1 after dismounting still can be used for more than 1 time as welding hanger repeatedly.
Claims (1)
1. a wood chip ship lifting and mounting complete superstructure method of designing, is characterized in that: comprise the following steps:
A, preparation hanger (1);
B, the room finish in the superstructure of wood chip ship, built-in system, installations and facilities installation ,Yu Zu place are closed up;
C, hanger (1) and superstructure are welded as a whole, and then carry out integral hoisting;
After D, lifting finish, hanger (1) is cut again.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310414479.9A CN103507915A (en) | 2013-09-12 | 2013-09-12 | Integral hoisting design method for wood ship upper layer building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310414479.9A CN103507915A (en) | 2013-09-12 | 2013-09-12 | Integral hoisting design method for wood ship upper layer building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103507915A true CN103507915A (en) | 2014-01-15 |
Family
ID=49891459
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310414479.9A Pending CN103507915A (en) | 2013-09-12 | 2013-09-12 | Integral hoisting design method for wood ship upper layer building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103507915A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107215431A (en) * | 2017-06-29 | 2017-09-29 | 中船第九设计研究院工程有限公司 | A kind of luxury liner block lifts eye thimble method for arranging |
CN109911108A (en) * | 2019-03-29 | 2019-06-21 | 广船国际有限公司 | Block lifting hanging code design method is built on a kind of ship |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6080985A (en) * | 1983-10-12 | 1985-05-08 | Mitsubishi Heavy Ind Ltd | Building method for ship superstructure |
CN101224849A (en) * | 2007-12-12 | 2008-07-23 | 大连理工大学 | Hanging bracket for integral hoisting of ship superstructure and hoisting process |
CN101850831A (en) * | 2010-05-31 | 2010-10-06 | 南通中远船务工程有限公司 | Hoisting method of living area block of large ocean maritime work platform |
CN102490863A (en) * | 2011-12-14 | 2012-06-13 | 扬州大洋造船有限公司 | Overall lifting method for ship superstructure |
CN202847968U (en) * | 2012-09-21 | 2013-04-03 | 大连中远船务工程有限公司 | Detachable lug structure for segmented lifting of T-shaped profiles |
CN103057661A (en) * | 2011-10-21 | 2013-04-24 | 上海江南长兴重工有限责任公司 | Whole hoisting craft of ship superstructure |
-
2013
- 2013-09-12 CN CN201310414479.9A patent/CN103507915A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6080985A (en) * | 1983-10-12 | 1985-05-08 | Mitsubishi Heavy Ind Ltd | Building method for ship superstructure |
CN101224849A (en) * | 2007-12-12 | 2008-07-23 | 大连理工大学 | Hanging bracket for integral hoisting of ship superstructure and hoisting process |
CN101850831A (en) * | 2010-05-31 | 2010-10-06 | 南通中远船务工程有限公司 | Hoisting method of living area block of large ocean maritime work platform |
CN103057661A (en) * | 2011-10-21 | 2013-04-24 | 上海江南长兴重工有限责任公司 | Whole hoisting craft of ship superstructure |
CN102490863A (en) * | 2011-12-14 | 2012-06-13 | 扬州大洋造船有限公司 | Overall lifting method for ship superstructure |
CN202847968U (en) * | 2012-09-21 | 2013-04-03 | 大连中远船务工程有限公司 | Detachable lug structure for segmented lifting of T-shaped profiles |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107215431A (en) * | 2017-06-29 | 2017-09-29 | 中船第九设计研究院工程有限公司 | A kind of luxury liner block lifts eye thimble method for arranging |
CN109911108A (en) * | 2019-03-29 | 2019-06-21 | 广船国际有限公司 | Block lifting hanging code design method is built on a kind of ship |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102627139A (en) | Final assembly method of ship shafting and rudder system | |
CN110562386A (en) | Pre-assembling method for superstructure of large ship | |
CN101362505A (en) | Production technology of hatch coaming and hatch cover | |
CN102756790B (en) | Ten thousand tons of box ship hatch cover manufacturing process peculiar to vessel | |
CN101913409A (en) | Method for improving shaft system centering process for ship building | |
CN102582784A (en) | Process for sectionally putting up ship berths or docks | |
CN103010404B (en) | Segmental general assembly method for aluminum alloy superstructure | |
CN103507915A (en) | Integral hoisting design method for wood ship upper layer building | |
CN103507912B (en) | The mounting process of one class chemical tanker cargo hold outfititem | |
CN104260828A (en) | Method for lifting extra-large type bow portion total segment | |
CN105151225A (en) | Segmentation building technology of top side tank | |
CN202175179U (en) | Hatch coaming | |
CN103678796A (en) | Method for optimizing nesting design in hull design | |
CN104071301A (en) | Preassembling method for anchor mouth of bulk frighter in segmentation stage | |
CN104192264A (en) | Ship curved surface planking mark making method | |
CN203638042U (en) | Cone hanging tool for container ship guide rail mounting | |
CN103692684B (en) | The method of quickly replacing mould | |
CN105667709A (en) | Hull manufacturing method | |
CN111806653B (en) | Pre-assembling method for side block of cruise ship | |
CN202295224U (en) | Embedded bracket tool for positioning and mounting tail fin of ship | |
CN204036035U (en) | A kind of gantry manipulator fixture | |
CN204432923U (en) | A kind of sounding gear and boats and ships | |
CN210592364U (en) | Novel composite suspended-horse type block for hull outer plate | |
CN203780740U (en) | Auxiliary welding device for annular section of ship body | |
CN202295225U (en) | Work fixture for closure of hulls |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20140115 |
|