CN103507915A - Integral hoisting design method for wood ship upper layer building - Google Patents

Integral hoisting design method for wood ship upper layer building Download PDF

Info

Publication number
CN103507915A
CN103507915A CN201310414479.9A CN201310414479A CN103507915A CN 103507915 A CN103507915 A CN 103507915A CN 201310414479 A CN201310414479 A CN 201310414479A CN 103507915 A CN103507915 A CN 103507915A
Authority
CN
China
Prior art keywords
hanger
upper layer
integral hoisting
ship
layer building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310414479.9A
Other languages
Chinese (zh)
Inventor
黄永强
葛新培
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Mingde Heavy Industry Co Ltd
Original Assignee
Nantong Mingde Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Mingde Heavy Industry Co Ltd filed Critical Nantong Mingde Heavy Industry Co Ltd
Priority to CN201310414479.9A priority Critical patent/CN103507915A/en
Publication of CN103507915A publication Critical patent/CN103507915A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention relates to an integral hoisting design method for a wood ship upper layer building. The method comprises the first step of preparing a lifting lug, the second step of finishing room finish and installation of internal systems and equipment in the wood ship upper layer building and carrying out folding in the pre-assembled field, the third step of welding the lifting lug and the upper layer building into a whole and then carrying out integral hoisting, and the fourth step of cutting the lifting lug after hoisting. The integral hoisting design method has the advantages that the labor intensity of workers is improved, production efficiency is improved, the ship production cycle is shortened, and the ship manufacturing cost is reduced.

Description

Wood chip ship lifting and mounting complete superstructure method of designing
Technical field
The present invention relates to ship domain, refer in particular to a kind of wood chip ship lifting and mounting complete superstructure method of designing.
Background technology
What the hanger of current domestic shipyard lifting and mounting complete superstructure adopted mostly is split type standard hanger, is to be all welded on separately in superstructure structure to do and lift by crane use.Superstructure region, the lift-launch that segmentation is, pre outfitting rate is low, and after carrying, work capacity is huge, has a strong impact on the degree of utilization of dock and harbour, extends the production cycle of boats and ships.Also have and be designed to the hanger of combined and structure welding as lifting use, but its design too complicated and make require high, and lifting finish rear dismounting loaded down with trivial details, remove after the Reusability number of times of hanger low.This Project-developing be that hanger is directly designed in structure.After the project implementation completes, not only removing the welding job of hanger but also lifting, to finish rear dismounting hanger more convenient, improved greatly work efficiency.To improve greatly core competitiveness, in shipping industry, will maintain the leading position.
Summary of the invention
The object of the invention is in order to overcome above deficiency, provide a kind of by hanger design being added after calculating in superstructure with structure as one; After superstructure lifting finishes, only hanger partly need be cut off, not destroy application, reduce coating work; The structure hanger simplicity of design of superstructure, convenient making; The hanger of superstructure lifting still can Reusability wood chip ship lifting and mounting complete superstructure method of designing repeatedly after removing.
Object of the present invention is achieved through the following technical solutions: a kind of wood chip ship lifting and mounting complete superstructure method of designing, comprises the following steps:
A, preparation hanger;
B, the room finish in the superstructure of wood chip ship, built-in system, installations and facilities installation ,Yu Zu place are closed up;
C, hanger and superstructure are welded as a whole, and then carry out integral hoisting;
After D, lifting finish, hanger is cut again.
The present invention has the following advantages: as modern general assembly shipbuilding, improve speed, key is to improve the integraty of segmentation prepackage, accelerates freak oil finished products.On build as relatively independent construction module, guarantee its integraty and finished products, significant to shortening the harbour cycle.
According to the maximization of the existing load-carrying ability in our factory, carry out rational suspension centre arrangement analysis, Yu Zu place, whole Shang Jian region is closed up, room finish in superstructure, built-in system, installations and facilities are installed and are all completed, after integral hoisting, just can carry out in a short time harbour debugging, the test of clean ship check weighing, reach the object that region sealing is produced.
Improve labor strength, enhance productivity, shorten ship building period, reduce shipbuilding cost.
Accompanying drawing explanation:
Fig. 1 is structural representation of the present invention;
Number in the figure: 1-hanger.
The specific embodiment:
In order to deepen the understanding of the present invention, below in conjunction with embodiment and accompanying drawing, the invention will be further described, and this embodiment only, for explaining the present invention, does not form limiting the scope of the present invention.
As Fig. 1 shows a kind of wood chip ship of the present invention lifting and mounting complete superstructure method of designing, comprise the following steps:
A, preparation hanger 1, the part that structure hanger 1 is designed to structure can complete 1 in advance by production process in the parts of segmentation, not only enhances productivity, and has also shortened the dead work of follow-up integral hoisting, structure hanger 1 simplicity of design, does not need complicated processing and making;
B, the room finish in the superstructure of wood chip ship, built-in system, installations and facilities installation ,Yu Zu place are closed up;
C, hanger 1 and superstructure are welded as a whole, and then carry out integral hoisting, after integral hoisting, just can carry out in a short time harbour debugging, the test of clean ship check weighing, reach the object of region sealing production;
After D, lifting finish, hanger 1 is cut again, line of cut marks with dotted line in the drawings, after using, structure hanger 1 all needs to cut off, not only can not destroy structure and application and also reduce greatly repairing and polishing work, the structure hanger 1 after dismounting still can be used for more than 1 time as welding hanger repeatedly.

Claims (1)

1. a wood chip ship lifting and mounting complete superstructure method of designing, is characterized in that: comprise the following steps:
A, preparation hanger (1);
B, the room finish in the superstructure of wood chip ship, built-in system, installations and facilities installation ,Yu Zu place are closed up;
C, hanger (1) and superstructure are welded as a whole, and then carry out integral hoisting;
After D, lifting finish, hanger (1) is cut again.
CN201310414479.9A 2013-09-12 2013-09-12 Integral hoisting design method for wood ship upper layer building Pending CN103507915A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310414479.9A CN103507915A (en) 2013-09-12 2013-09-12 Integral hoisting design method for wood ship upper layer building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310414479.9A CN103507915A (en) 2013-09-12 2013-09-12 Integral hoisting design method for wood ship upper layer building

Publications (1)

Publication Number Publication Date
CN103507915A true CN103507915A (en) 2014-01-15

Family

ID=49891459

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310414479.9A Pending CN103507915A (en) 2013-09-12 2013-09-12 Integral hoisting design method for wood ship upper layer building

Country Status (1)

Country Link
CN (1) CN103507915A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107215431A (en) * 2017-06-29 2017-09-29 中船第九设计研究院工程有限公司 A kind of luxury liner block lifts eye thimble method for arranging
CN109911108A (en) * 2019-03-29 2019-06-21 广船国际有限公司 Block lifting hanging code design method is built on a kind of ship

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6080985A (en) * 1983-10-12 1985-05-08 Mitsubishi Heavy Ind Ltd Building method for ship superstructure
CN101224849A (en) * 2007-12-12 2008-07-23 大连理工大学 Hanging bracket for integral hoisting of ship superstructure and hoisting process
CN101850831A (en) * 2010-05-31 2010-10-06 南通中远船务工程有限公司 Hoisting method of living area block of large ocean maritime work platform
CN102490863A (en) * 2011-12-14 2012-06-13 扬州大洋造船有限公司 Overall lifting method for ship superstructure
CN202847968U (en) * 2012-09-21 2013-04-03 大连中远船务工程有限公司 Detachable lug structure for segmented lifting of T-shaped profiles
CN103057661A (en) * 2011-10-21 2013-04-24 上海江南长兴重工有限责任公司 Whole hoisting craft of ship superstructure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6080985A (en) * 1983-10-12 1985-05-08 Mitsubishi Heavy Ind Ltd Building method for ship superstructure
CN101224849A (en) * 2007-12-12 2008-07-23 大连理工大学 Hanging bracket for integral hoisting of ship superstructure and hoisting process
CN101850831A (en) * 2010-05-31 2010-10-06 南通中远船务工程有限公司 Hoisting method of living area block of large ocean maritime work platform
CN103057661A (en) * 2011-10-21 2013-04-24 上海江南长兴重工有限责任公司 Whole hoisting craft of ship superstructure
CN102490863A (en) * 2011-12-14 2012-06-13 扬州大洋造船有限公司 Overall lifting method for ship superstructure
CN202847968U (en) * 2012-09-21 2013-04-03 大连中远船务工程有限公司 Detachable lug structure for segmented lifting of T-shaped profiles

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107215431A (en) * 2017-06-29 2017-09-29 中船第九设计研究院工程有限公司 A kind of luxury liner block lifts eye thimble method for arranging
CN109911108A (en) * 2019-03-29 2019-06-21 广船国际有限公司 Block lifting hanging code design method is built on a kind of ship

Similar Documents

Publication Publication Date Title
CN102627139A (en) Final assembly method of ship shafting and rudder system
CN110562386A (en) Pre-assembling method for superstructure of large ship
CN101362505A (en) Production technology of hatch coaming and hatch cover
CN102756790B (en) Ten thousand tons of box ship hatch cover manufacturing process peculiar to vessel
CN101913409A (en) Method for improving shaft system centering process for ship building
CN102582784A (en) Process for sectionally putting up ship berths or docks
CN103010404B (en) Segmental general assembly method for aluminum alloy superstructure
CN103507915A (en) Integral hoisting design method for wood ship upper layer building
CN103507912B (en) The mounting process of one class chemical tanker cargo hold outfititem
CN104260828A (en) Method for lifting extra-large type bow portion total segment
CN105151225A (en) Segmentation building technology of top side tank
CN202175179U (en) Hatch coaming
CN103678796A (en) Method for optimizing nesting design in hull design
CN104071301A (en) Preassembling method for anchor mouth of bulk frighter in segmentation stage
CN104192264A (en) Ship curved surface planking mark making method
CN203638042U (en) Cone hanging tool for container ship guide rail mounting
CN103692684B (en) The method of quickly replacing mould
CN105667709A (en) Hull manufacturing method
CN111806653B (en) Pre-assembling method for side block of cruise ship
CN202295224U (en) Embedded bracket tool for positioning and mounting tail fin of ship
CN204036035U (en) A kind of gantry manipulator fixture
CN204432923U (en) A kind of sounding gear and boats and ships
CN210592364U (en) Novel composite suspended-horse type block for hull outer plate
CN203780740U (en) Auxiliary welding device for annular section of ship body
CN202295225U (en) Work fixture for closure of hulls

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140115

RJ01 Rejection of invention patent application after publication