CN103469798A - Pit support structure and construction method thereof - Google Patents

Pit support structure and construction method thereof Download PDF

Info

Publication number
CN103469798A
CN103469798A CN201310380666XA CN201310380666A CN103469798A CN 103469798 A CN103469798 A CN 103469798A CN 201310380666X A CN201310380666X A CN 201310380666XA CN 201310380666 A CN201310380666 A CN 201310380666A CN 103469798 A CN103469798 A CN 103469798A
Authority
CN
China
Prior art keywords
foundation pit
construction
pit supporting
pile
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310380666XA
Other languages
Chinese (zh)
Other versions
CN103469798B (en
Inventor
张中善
张鹏
焦安亮
侯振国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201310380666.XA priority Critical patent/CN103469798B/en
Publication of CN103469798A publication Critical patent/CN103469798A/en
Application granted granted Critical
Publication of CN103469798B publication Critical patent/CN103469798B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a pit support structure and a construction method thereof. The pit support structure comprises a pit support pile, a water-stopping curtain, an earth berm and a horizontal lattice steel support. The pit support pile is a cast-in-place reinforced concrete bored pile. The water stopping curtain is a row of meshed cement mixing piles and disposed on one side, corresponding to the periphery of a pit, of the pit support pile. The horizontal lattice steel support is disposed between a cap beam and a reinforced concrete bracket.

Description

A kind of foundation pit supporting construction and job practices thereof
Technical field
Patent of the present invention relates to a kind of foundation pit supporting construction and job practices thereof, belongs to the Geotechnical Engineering field.
Technical background
Along with developing rapidly of highrise building increased, foundation ditch is by increasing, darker, and the construction of the supporting and protection structure of foundation ditch is also by more and more difficult.In building construction process, for the construction that guarantees underground structure and safety and the easy construction of surrounding deep foundation pit environment, must take to deep-foundation side wall and surrounding enviroment the measure of supporting and reinforcing.
At present, to the super large foundation ditch, the common employing bored pile of pattern foundation pit supporting structure, arrange the horizontal reinforcement concrete support in hole, improved rigidity and the stability of foundation pit enclosure structure, controlled preferably foundation pit deformation, and the foundation ditch accident greatly reduces.Weak point is that construction, maintenance and support replacement thereof and the dismounting of reinforced concrete support extended the foundation pit construction duration, has improved construction costs, also to basement construction, makes troubles.
Summary of the invention
The deficiency existed for prior art, the object of the present invention is to provide a kind of foundation pit supporting construction and job practices thereof that facilitates basement structure construction, saving engineering cost, shortens the foundation pit construction duration.
The present invention is achieved by the following technical solutions:
A kind of foundation pit supporting construction, comprise foundation pit supporting pile, water-stop curtain, back-pressure soil and horizontal lattice steel support, described foundation pit supporting pile is set to the cast-in-situ steel reinforced concrete bored pile, described water-stop curtain is set to the engaged cement mixing method of a row, and described water-stop curtain is arranged on the corresponding foundation ditch periphery of foundation pit supporting pile one side, and described horizontal lattice steel supports and is arranged between cap and Reinforced Concrete Corbels.
Be provided with reinforcing cage in described existing bar pouring concrete drilling bored concrete pile, the longitudinal rib of corresponding water-stop curtain one side of described reinforcing cage distributes close in opposite side.
Described cast-in-situ concrete bored pile top is provided with the steel concrete cap, and a side of cap leans on cement mixing method.
Be inserted with many bar dowels in described back-pressure soil, and at domatic sprayed mortar.
Advantage of the present invention is:
Base pit stand construction described in the present invention, incorporation engineering actual conditions and surrounding enviroment have adopted multiple support system, the pattern foundation pit supporting structure mode that adopts reserved back-pressure soil and horizontal lattice steel to support a kind of cost-effective support pattern of can yet be regarded as, especially be applicable to the supporting of large-scale excavation.
(1) support by cement mixing method, bored pile and horizontal lattice steel the foundation pit supporting system formed, given full play to characteristics separately, can guarantee sealing and the displacement control of foundation ditch, and significantly shorten the construction period.
(2) adopt " benzvalene form " shoveling mode, insert bar dowel in the interior reserved back-pressure soil of foundation ditch and form earth structure, domatic sprayed mortar, its internal stability and the stable problem of external overall during with solution foundation pit supporting construction the first operating mode.
(3) horizontal lattice steel is supported on prefabrication, after dismounting, can have enough to meet the need use, has not only reduced construction costs but also shortened the construction period.
The accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the A-A sectional view of Fig. 1;
Reference numeral: 1-foundation pit supporting pile, 2-water-stop curtain, 3-horizontal lattice steel support, 4-back-pressure soil, 5-steel concrete cap, 6-Reinforced Concrete Corbels, 7-steel concrete cap, 8-bar dowel, 9-sprayed mortar, 10-foundation ditch central area sole plate, 11-foundation ditch central area agent structure, 12-foundation ditch perimeter zone sole plate, 13-foundation ditch perimeter zone agent structure.
The specific embodiment
Embodiment: as shown in Figure 1 and Figure 2, a kind of foundation pit supporting construction comprises foundation pit supporting pile 1, water-stop curtain 2, horizontal lattice steel support 3, back-pressure soil 4, steel concrete cap 5, Reinforced Concrete Corbels 6, steel concrete cap 7, bar dowel 8, sprayed mortar 9, foundation ditch central area sole plate 10, foundation ditch central area agent structure 11, foundation ditch perimeter zone sole plate 12, foundation ditch perimeter zone agent structure 13.Described water-stop curtain 2 is set to the engaged cement mixing method of a row, described water-stop curtain is arranged on the corresponding foundation ditch periphery of foundation pit supporting pile one side, described bored pile 1 is close to water-stop curtain 2, and described horizontal lattice steel supports 3 and is arranged between Reinforced Concrete Corbels 5 and steel concrete cap 7.
A kind of job practices of foundation pit supporting construction is characterized in that: comprise the following steps:
The first step: according to site condition and computational analysis, determine that the stake of bored pile 1 is long, stake footpath, spacing and arrangement of reinforcement, determine that the stake of cement mixing method is long, stake footpath, spacing;
Second step: cross section, the arrangement of reinforcement of determining bored pile top steel concrete cap 5;
The 3rd step: construction water-stop curtain 2;
The 4th step: construction drill castinplace pile 1;
The 5th step: construction reinforced bar concrete cap 5;
The 6th step: the earthwork of excavation pit central area, reserved back-pressure soil 4;
Be inserted with many bar dowels 8 in described reserved back-pressure soil 4, and at domatic sprayed mortar 9, its internal stability and the stable problem of external overall during with solution foundation pit supporting construction the first operating mode.
The 7th step: at the bottom of hole, foundation ditch central area, being cleared up, flatten, build bed course, construction central area sole plate 10 and agent structure 11;
The 8th step: horizontal lattice steel is installed and is supported 3;
The 9th step: excavation pit periphery back-pressure soil 4;
The tenth step: at the bottom of hole, foundation ditch perimeter zone, being cleared up, flatten, build bed course, construction foundation pit periphery sole plate 12 and agent structure 13;
The 11 step: remove horizontal lattice steel support 4, Reinforced Concrete Corbels 6.
Certainly, the invention is not limited to above-mentioned embodiment, those of ordinary skill in the art also can make equivalent variations or replacement under the prerequisite without prejudice to spirit of the present invention, and the modification that these are equal to or replacement all are included in the application's claim limited range.

Claims (5)

1. a foundation pit supporting construction, it is characterized in that: comprise that foundation pit supporting pile, water-stop curtain, back-pressure soil and horizontal lattice steel support, described foundation pit supporting pile is set to the cast-in-situ steel reinforced concrete bored pile, described water-stop curtain is set to the engaged cement mixing method of a row, described water-stop curtain is arranged on the corresponding foundation ditch periphery of foundation pit supporting pile one side, and described horizontal lattice steel supports and is arranged between cap and Reinforced Concrete Corbels.
2. foundation pit supporting construction according to claim 1 is characterized in that: be provided with reinforcing cage in described cast-in-situ steel reinforced concrete bored pile, the longitudinal rib of corresponding water-stop curtain one side of described reinforcing cage distributes close in opposite side.
3. foundation pit supporting construction according to claim 1 is characterized in that: described cast-in-situ concrete bored pile top is provided with the steel concrete cap, and a side of cap leans on cement mixing method.
4. foundation pit supporting construction according to claim 1 is characterized in that: be inserted with many bar dowels in described back-pressure soil, and at the jet surface concrete.
5. the job practices of foundation pit supporting construction as claimed in claim 1 is characterized in that: comprise the following steps:
The first step: according to site condition and computational analysis, determine that the stake of bored pile is long, stake footpath, spacing and arrangement of reinforcement, determine that the stake of cement mixing method is long, stake footpath, spacing;
Second step: cross section, the arrangement of reinforcement of determining bored pile top steel concrete cap;
The 3rd step: construction water-stop curtain;
The 4th step: construction drill castinplace pile;
The 5th step: construction reinforced bar concrete cap;
The 6th step: the earthwork of excavation pit central area, reserved back-pressure soil;
The 7th step: at the bottom of hole, foundation ditch central area, being cleared up, flatten, build bed course, construction central area sole plate and agent structure;
The 8th step: horizontal lattice steel is installed and is supported;
The 9th step: excavation pit periphery back-pressure soil;
The tenth step: at the bottom of hole, foundation ditch perimeter zone, being cleared up, flatten, build bed course, construction foundation pit periphery sole plate and agent structure;
The 11 step: remove horizontal lattice steel support, Reinforced Concrete Corbels.
CN201310380666.XA 2013-08-28 2013-08-28 A kind of foundation pit supporting construction and construction method thereof Active CN103469798B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310380666.XA CN103469798B (en) 2013-08-28 2013-08-28 A kind of foundation pit supporting construction and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310380666.XA CN103469798B (en) 2013-08-28 2013-08-28 A kind of foundation pit supporting construction and construction method thereof

Publications (2)

Publication Number Publication Date
CN103469798A true CN103469798A (en) 2013-12-25
CN103469798B CN103469798B (en) 2016-01-20

Family

ID=49794827

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310380666.XA Active CN103469798B (en) 2013-08-28 2013-08-28 A kind of foundation pit supporting construction and construction method thereof

Country Status (1)

Country Link
CN (1) CN103469798B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032763A (en) * 2014-06-25 2014-09-10 上海市建工设计研究院有限公司 Combined-type anti-seepage waterstop curtain structure and construction method thereof
CN105040728A (en) * 2015-06-05 2015-11-11 朱奎 Three-layer basement supporting structure
CN105178326A (en) * 2015-06-03 2015-12-23 福建工程学院 Water stop method for upper-soft and lower-hard water-rich stratum foundation pit engineering retaining structure
CN105887889A (en) * 2016-04-20 2016-08-24 中铁上海工程局集团有限公司 Excavation construction method for super-wide low-permeability silty deep foundation pit
CN106120805A (en) * 2016-06-23 2016-11-16 程华清 The construction method of the ultra-deep foundation pit supporting under dilapidated house environment
CN107503355A (en) * 2017-07-20 2017-12-22 广东省建筑工程集团有限公司 Shaped steel formula double-row pile foundation pit supporting system and its construction method are inserted after outer row
CN108316316A (en) * 2018-04-18 2018-07-24 南京工业大学 Support system suitable for island type support and application thereof
CN109403339A (en) * 2018-10-16 2019-03-01 中建局集团建设发展有限公司 The deep basal pit composite supporting construction and its method for protecting support of double-row pile combination method of center island
CN113668550A (en) * 2021-08-04 2021-11-19 深圳宏业基岩土科技股份有限公司 Construction method for supporting foundation pit under geological condition of silt

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0892959A (en) * 1994-09-28 1996-04-09 Kajima Corp Head-section structure of earth retaining wall
CN2647920Y (en) * 2003-07-23 2004-10-13 顺德市永基建筑基础有限公司 Diagonal post supporting ground hole for construction
CN101892667A (en) * 2010-07-23 2010-11-24 中国建筑第二工程局有限公司 Foundation pit supporting device and construction method
CN102011404A (en) * 2010-11-24 2011-04-13 温州中城建设集团有限公司 Pit supporting structure and construction method thereof
CN102425172A (en) * 2011-12-05 2012-04-25 中冶天工集团有限公司 Support method for excavating deep foundation pit closely adjacent to high-rise building
CN103243720A (en) * 2013-05-20 2013-08-14 中冶天工集团有限公司 Soft foundation ultra-deep foundation pit supporting method
CN103255772A (en) * 2013-05-27 2013-08-21 天津三建建筑工程有限公司 Construction method optimizing deep foundation pit changing supporting construction sequences

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0892959A (en) * 1994-09-28 1996-04-09 Kajima Corp Head-section structure of earth retaining wall
CN2647920Y (en) * 2003-07-23 2004-10-13 顺德市永基建筑基础有限公司 Diagonal post supporting ground hole for construction
CN101892667A (en) * 2010-07-23 2010-11-24 中国建筑第二工程局有限公司 Foundation pit supporting device and construction method
CN102011404A (en) * 2010-11-24 2011-04-13 温州中城建设集团有限公司 Pit supporting structure and construction method thereof
CN102425172A (en) * 2011-12-05 2012-04-25 中冶天工集团有限公司 Support method for excavating deep foundation pit closely adjacent to high-rise building
CN103243720A (en) * 2013-05-20 2013-08-14 中冶天工集团有限公司 Soft foundation ultra-deep foundation pit supporting method
CN103255772A (en) * 2013-05-27 2013-08-21 天津三建建筑工程有限公司 Construction method optimizing deep foundation pit changing supporting construction sequences

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张晓鹏等: ""盆式开挖+中心岛支撑"基坑工程实例分析", 《矿产勘察》 *
解裕荣等: ""昆明西坝路改扩建工程地道坞式段‘中心岛’法基坑支护技术"", 《铁道建筑》 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032763A (en) * 2014-06-25 2014-09-10 上海市建工设计研究院有限公司 Combined-type anti-seepage waterstop curtain structure and construction method thereof
CN105178326A (en) * 2015-06-03 2015-12-23 福建工程学院 Water stop method for upper-soft and lower-hard water-rich stratum foundation pit engineering retaining structure
CN105178326B (en) * 2015-06-03 2017-05-31 福建工程学院 Upper soft lower hard water rich strata base pit engineering building enclosure water-stopping method
CN105040728A (en) * 2015-06-05 2015-11-11 朱奎 Three-layer basement supporting structure
CN105887889A (en) * 2016-04-20 2016-08-24 中铁上海工程局集团有限公司 Excavation construction method for super-wide low-permeability silty deep foundation pit
CN105887889B (en) * 2016-04-20 2018-04-24 中铁上海工程局集团有限公司 A kind of ultra-wide hyposmosis mud method of excavation of deep foundation pit
CN106120805B (en) * 2016-06-23 2019-09-13 程华清 The construction method of ultra-deep foundation pit supporting under dilapidated house environment
CN106120805A (en) * 2016-06-23 2016-11-16 程华清 The construction method of the ultra-deep foundation pit supporting under dilapidated house environment
CN107503355A (en) * 2017-07-20 2017-12-22 广东省建筑工程集团有限公司 Shaped steel formula double-row pile foundation pit supporting system and its construction method are inserted after outer row
CN107503355B (en) * 2017-07-20 2023-10-13 广东省建筑工程集团有限公司 Externally-arranged rear-inserted steel type double-row pile foundation pit supporting system and construction method thereof
CN108316316A (en) * 2018-04-18 2018-07-24 南京工业大学 Support system suitable for island type support and application thereof
CN109403339A (en) * 2018-10-16 2019-03-01 中建局集团建设发展有限公司 The deep basal pit composite supporting construction and its method for protecting support of double-row pile combination method of center island
CN109403339B (en) * 2018-10-16 2024-01-23 中建一局集团建设发展有限公司 Deep foundation pit composite supporting structure combining double-row piles with center island method and supporting method thereof
CN113668550A (en) * 2021-08-04 2021-11-19 深圳宏业基岩土科技股份有限公司 Construction method for supporting foundation pit under geological condition of silt
CN113668550B (en) * 2021-08-04 2023-03-07 深圳宏业基岩土科技股份有限公司 Construction method for supporting foundation pit under geological condition of silt

Also Published As

Publication number Publication date
CN103469798B (en) 2016-01-20

Similar Documents

Publication Publication Date Title
CN103469798B (en) A kind of foundation pit supporting construction and construction method thereof
CN205742213U (en) Foundation pit supporting construction
CN101250886B (en) Method for reinforcing masonry structure building base
CN101560770B (en) Novel deep building foundation pit supporting system
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN204418187U (en) Subway protection region soil nail wall is in conjunction with double-row pile deep foundation ditch composite supporting construction
CN103114595A (en) Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch
CN201873997U (en) Support structure of foundation pit
CN205024712U (en) Combined tower crane foundation
CN109024609A (en) A kind of foundation pit supporting construction and its construction method based on old campshed
CN105064711A (en) Method for constructing underground garage between residential buildings
CN106894424A (en) A kind of short branch supporting system of basin excavation and its construction technology
CN201991013U (en) High-piled tower footing structure of tower crane concrete-filled steel tube
CN102220764B (en) Construction method of deep foundation pit bracing system
CN204282399U (en) A kind of subway space enclosing structure
CN210263073U (en) Supporting construction that adjacent foundation ditch synchronous excavation was asynchronously backfilled
CN201416177Y (en) T-shaped pile combined plank sinking pit bracing construction
CN203821399U (en) Deep foundation pit supporting structure
CN204059341U (en) Bamboo joint type mortar pile
CN207003470U (en) A kind of pin-connected panel ecological anchor rod retaining wall structure
CN103711123B (en) The construction method of bamboo joint type mortar pile
CN216339582U (en) Combined inclined support for foundation pit support
CN206562618U (en) A kind of basin excavation steel structure horizontal bracing unit
CN211816394U (en) Retaining wall structure without drainage in bedrock area
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant