CN103438474B - The weary gas of boiler milling system part participates in pulverized coal carried by hot air utilization system - Google Patents

The weary gas of boiler milling system part participates in pulverized coal carried by hot air utilization system Download PDF

Info

Publication number
CN103438474B
CN103438474B CN201310414777.8A CN201310414777A CN103438474B CN 103438474 B CN103438474 B CN 103438474B CN 201310414777 A CN201310414777 A CN 201310414777A CN 103438474 B CN103438474 B CN 103438474B
Authority
CN
China
Prior art keywords
pipe
header
air
coal
recirculation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310414777.8A
Other languages
Chinese (zh)
Other versions
CN103438474A (en
Inventor
王学伟
王永金
郑勇
刘凤艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DATANG JIXI THERMOELECTRIC Co Ltd
Original Assignee
DATANG JIXI THERMOELECTRIC Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DATANG JIXI THERMOELECTRIC Co Ltd filed Critical DATANG JIXI THERMOELECTRIC Co Ltd
Priority to CN201310414777.8A priority Critical patent/CN103438474B/en
Publication of CN103438474A publication Critical patent/CN103438474A/en
Application granted granted Critical
Publication of CN103438474B publication Critical patent/CN103438474B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Solid Fuels And Fuel-Associated Substances (AREA)

Abstract

The weary gas of boiler milling system part participates in pulverized coal carried by hot air utilization system, its a kind of utilization system, is specifically related to the weary gas of a kind of boiler milling system part and participates in pulverized coal carried by hot air utilization system.The present invention in order to after solving intermediate storage-type pulverized coal preparation system blending coal slime at high proportion, the problem that ature of coal moisture is higher.The present invention includes warm-air pipe, coal, pulverulent fuel mixer, primary air piping, wear resistance ceramic tube, header, the liaison tube of recirculation and header and recirculation pipe, warm-air pipe is connected with coal, pulverulent fuel mixer air inlet, the air outlet of coal, pulverulent fuel mixer is connected with primary air piping, warm-air pipe is connected with header by wear resistance ceramic tube, and header is connected with recirculation pipe with the liaison tube of header by recirculation.The present invention is used for boiler powder process field.

Description

The weary gas of boiler milling system part participates in pulverized coal carried by hot air utilization system
Technical field
The present invention relates to a kind of utilization system, be specifically related to the weary gas of a kind of boiler milling system part and participate in pulverized coal carried by hot air utilization system.
Background technology
Existing intermediate storage-type pulverized coal preparation system is only suitable for bituminous coal and ature of coal total moisture is the coal of 5.2%, and when arriving 12% for ature of coal total moisture, drying capacity of pulverizer and ventilation are exerted oneself and occurred wretched insufficiency phenomenon; And existing pulverized coal preparation system tertiary air pressure is higher, causes tertiary-air velocity to strengthen, tertiary-air pipe wearing and tearing aggravation, high speed tertiary air will cause furnace flame center to move down, impact burning.
Summary of the invention
The present invention is after solving intermediate storage-type pulverized coal preparation system blending coal slime at high proportion, the problem that ature of coal moisture is higher, and then proposes boiler milling system part weary gas participation pulverized coal carried by hot air utilization system.
The present invention is the technical scheme taked that solves the problem: the present invention includes warm-air pipe, coal, pulverulent fuel mixer, primary air piping, wear resistance ceramic tube, header, the liaison tube of recirculation and header and recirculation pipe, warm-air pipe is connected with coal, pulverulent fuel mixer air inlet, the air outlet of coal, pulverulent fuel mixer is connected with primary air piping, warm-air pipe is connected with header by wear resistance ceramic tube, and header is connected with recirculation pipe with the liaison tube of header by recirculation.
The invention has the beneficial effects as follows: invention increases First air band powder amount, flame kernel improves, overheavy firing, reduce furnace outlet oxygen content, decrease chemical and that machinery is imperfect combustion heat loss, reduce unburned carbon in flue dust, reduce heating surface wear, reduce blower fan power consumption, improve boiler efficiency; The present invention reduces powder process tertiary air pressure, reduces the wearing and tearing of tertiary-air pipe and recirculating line, improves mill exhauster operating condition, improve coal pulverizer inlet negative pressure, increase the input of dry-heat air, avoid and regulate desiccant temperature with cold wind, powder process is leaked out few, improves Mill output; The present invention is owing to enhancing burning, furnace outlet gas temperature is greatly improved, water-cooling wall, front screen, rear screen, finishing superheater, reheater caloric receptivity increases, main reheater temperature is improved, simultaneously because evaporation capacity improves, the tube wall of front and back screen finishing superheater is cooled, is reduced the generation of overtemperature of tube wall; Due to the raising of steam initial temperature, steam efficiency is improved, reduce the corrosion to last stage vane of steam turbine.
Accompanying drawing explanation
Fig. 1 is overall structure schematic diagram of the present invention.
Detailed description of the invention
Detailed description of the invention one: composition graphs 1 illustrates present embodiment, the weary gas of boiler milling system part described in present embodiment participates in pulverized coal carried by hot air utilization system and comprises warm-air pipe 1, coal, pulverulent fuel mixer 2, primary air piping 3, wear resistance ceramic tube 4, header 6, the liaison tube 7 of recirculation and header and recirculation pipe 9, warm-air pipe 1 is connected with coal, pulverulent fuel mixer 2 air inlet, the air outlet of coal, pulverulent fuel mixer 2 is connected with primary air piping 3, warm-air pipe 1 is connected with header 6 by wear resistance ceramic tube 4, and header 6 is connected with recirculation pipe 9 with the liaison tube 7 of header by recirculation.
Detailed description of the invention two: composition graphs 1 illustrates present embodiment, the weary gas of boiler milling system part described in present embodiment participates in pulverized coal carried by hot air utilization system and also comprises the first Circular ventilation door 5 and the second Circular ventilation door 8, first Circular ventilation door 5 is arranged on wear resistance ceramic tube 4, and the second Circular ventilation door 8 is arranged on recirculation with on the liaison tube 7 of header.Other composition and annexation identical with detailed description of the invention one.
Detailed description of the invention three: composition graphs 1 illustrates present embodiment, the diameter that the weary gas of boiler milling system part described in present embodiment participates in the warm-air pipe 1 of pulverized coal carried by hot air utilization system is 480mm, the thickness of pipe wall of warm-air pipe 1 is 3mm, the diameter of primary air piping 3 is 450mm, the thickness of pipe wall of primary air piping 3 is 10mm, and the diameter of wear resistance ceramic tube 4 is 325mm, and the thickness of pipe wall of wear resistance ceramic tube 4 is 8mm, the diameter of recirculation pipe 9 is 720mm, and the thickness of pipe wall of recirculation pipe 9 is 5mm.Other composition and annexation identical with detailed description of the invention one.

Claims (1)

1. the weary gas of boiler milling system part participates in pulverized coal carried by hot air utilization system, it comprises warm-air pipe (1), coal, pulverulent fuel mixer (2), primary air piping (3), wear resistance ceramic tube (4), header (6), the liaison tube (7) of recirculation and header and recirculation pipe (9), warm-air pipe (1) is connected with coal, pulverulent fuel mixer (2) air inlet, the air outlet of coal, pulverulent fuel mixer (2) is connected with primary air piping (3), warm-air pipe (1) is connected with header (6) by wear resistance ceramic tube (4), header (6) is connected with recirculation pipe (9) with the liaison tube (7) of header by recirculation, described system also comprises the first Circular ventilation door (5) and the second Circular ventilation door (8), first Circular ventilation door (5) is arranged on wear resistance ceramic tube (4), second Circular ventilation door (8) is arranged on recirculation with on the liaison tube (7) of header, it is characterized in that: the diameter of warm-air pipe (1) is 480mm, the thickness of pipe wall of warm-air pipe (1) is 3mm, the diameter of primary air piping (3) is 450mm, the thickness of pipe wall of primary air piping (3) is 10mm, the diameter of wear resistance ceramic tube (4) is 325mm, the thickness of pipe wall of wear resistance ceramic tube (4) is 8mm, the diameter of recirculation pipe (9) is 720mm, the thickness of pipe wall of recirculation pipe (9) is 5mm.
CN201310414777.8A 2013-09-12 2013-09-12 The weary gas of boiler milling system part participates in pulverized coal carried by hot air utilization system Active CN103438474B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310414777.8A CN103438474B (en) 2013-09-12 2013-09-12 The weary gas of boiler milling system part participates in pulverized coal carried by hot air utilization system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310414777.8A CN103438474B (en) 2013-09-12 2013-09-12 The weary gas of boiler milling system part participates in pulverized coal carried by hot air utilization system

Publications (2)

Publication Number Publication Date
CN103438474A CN103438474A (en) 2013-12-11
CN103438474B true CN103438474B (en) 2016-01-20

Family

ID=49692173

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310414777.8A Active CN103438474B (en) 2013-09-12 2013-09-12 The weary gas of boiler milling system part participates in pulverized coal carried by hot air utilization system

Country Status (1)

Country Link
CN (1) CN103438474B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106556026B (en) * 2015-09-30 2019-10-11 邸生才 Air delivery pipe coal dust weight measurement instrument and multiple pipeline equilibrium powder supply control systems
CN111748395A (en) * 2020-07-02 2020-10-09 煤科院节能技术有限公司 Method for preparing coal powder by using coal slime
CN113154433B (en) * 2021-05-28 2023-02-21 西安热工研究院有限公司 Power station boiler negative pressure cooperative control method and system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0327914A2 (en) * 1988-02-08 1989-08-16 General Signal Corporation Calorimetry system
CN101596980A (en) * 2009-06-24 2009-12-09 哈尔滨工业大学 Hot blast and exhaust gas double-medium powder delivery method and weary gas and hot air mixer
CN201589289U (en) * 2010-02-05 2010-09-22 哈尔滨工业大学 Exhaust gas and hot air double-medium powder delivery system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0327914A2 (en) * 1988-02-08 1989-08-16 General Signal Corporation Calorimetry system
CN101596980A (en) * 2009-06-24 2009-12-09 哈尔滨工业大学 Hot blast and exhaust gas double-medium powder delivery method and weary gas and hot air mixer
CN201589289U (en) * 2010-02-05 2010-09-22 哈尔滨工业大学 Exhaust gas and hot air double-medium powder delivery system

Also Published As

Publication number Publication date
CN103438474A (en) 2013-12-11

Similar Documents

Publication Publication Date Title
CN203431902U (en) Smoke system reducing exhaust smoke temperature of secondary reheating boiler
CN102192639A (en) Method for reducing coal consumption of coal-fired power plant by adding fluidized bed drying system
CN201885213U (en) Primary air waste heat utilizing device of direct-blowing powder producing system of coal powder boiler
CN102252339A (en) System for reducing discharge smoke temperature of power station boiler
CN109681898B (en) Primary air heating temperature-regulating system of phase-change heat pipe type power plant
CN103925605A (en) High-moisture lignite medium-speed coal mill pulverizing system heating primary air through pulverized coal burning
CN206222288U (en) A kind of Steam Cooler System
CN103438474B (en) The weary gas of boiler milling system part participates in pulverized coal carried by hot air utilization system
CN106524127A (en) Steam cooler system and method for decreasing steam-extraction superheat degree of steam cooler system
CN203771439U (en) High-moisture lignite medium speed mill coal pulverizing system using pulverized coal combustion heating primary air
CN206682921U (en) A kind of station boiler multi-element heterogeneous afterheat utilizing system
CN203286582U (en) Boiler air preheating device
CN209706109U (en) Phase transformation heat pipe-type power plant's First air heats thermoregulating system
CN204421052U (en) A kind of waste heat recovery furnace
CN204901735U (en) Heat exchanger boiler waste heat utilization economizer
CN103939934A (en) Drying system for boiler pulverizing system
CN203797684U (en) Drying system used for boiler pulverizing system
CN203771438U (en) High-moisture lignite medium speed mill coal pulverizing system using coal gas combustion heating primary air
CN204240396U (en) Residual heat from boiler fume utilizes system
CN205988806U (en) The fan mill arrangement system of tower 350MW super critical boiler
CN202813757U (en) Rice hull burning air heating furnace
CN207035071U (en) Three points of storehouse air preheater gas bypass heat First airs and the system of feedwater
CN205155926U (en) Novel coal fired boiler residual heat from flue gas system
CN205979844U (en) Pi type 350MW supercritical boiler's fan grinds system of arranging
CN103925606A (en) High-moisture lignite medium-speed coal mill pulverizing system heating primary air through coal gas burning

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant