CN103437731B - A kind of movement erecting device of drillng operation blowout preventer set - Google Patents

A kind of movement erecting device of drillng operation blowout preventer set Download PDF

Info

Publication number
CN103437731B
CN103437731B CN201310343350.3A CN201310343350A CN103437731B CN 103437731 B CN103437731 B CN 103437731B CN 201310343350 A CN201310343350 A CN 201310343350A CN 103437731 B CN103437731 B CN 103437731B
Authority
CN
China
Prior art keywords
bracket
hydraulic cylinder
track
welded
rotating turret
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310343350.3A
Other languages
Chinese (zh)
Other versions
CN103437731A (en
Inventor
常玉连
樊岩松
郑永谭
张有锋
冯志鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CNPC Bohai Equipment Manufacturing Co Ltd
Northeast Petroleum University
Original Assignee
CNPC Bohai Equipment Manufacturing Co Ltd
Northeast Petroleum University
China Petroleum Liaohe Equipment Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNPC Bohai Equipment Manufacturing Co Ltd, Northeast Petroleum University, China Petroleum Liaohe Equipment Co filed Critical CNPC Bohai Equipment Manufacturing Co Ltd
Priority to CN201310343350.3A priority Critical patent/CN103437731B/en
Publication of CN103437731A publication Critical patent/CN103437731A/en
Application granted granted Critical
Publication of CN103437731B publication Critical patent/CN103437731B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The present invention relates to petroleum drilling technology field, particularly a kind of movement erecting device of drillng operation blowout preventer set.The slip of this device fixedly comprises slip fixed head, and slip fixed head two ends are all connected with the little deck of track and the large deck of track, slip fixed head are welded with horizontal hydraulic cylinder bearing, and ratchet is arranged on slip fixed head; Translating trolleys comprises translating trolleys base plate, and translating trolleys base plate two ends are connected with the large deck of track, translating trolleys base plate is welded with horizontal hydraulic cylinder bearing, support bracket support and lifting hydraulic cylinder bearing.Present invention achieves can fast, movement efficiently and accurately and install blowout preventer set, increase work efficiency, reduce labour intensity, improve processing safety.Overcome existing installation blowout preventer set to waste time and energy, operating difficulties, the deficiency of poor stability.

Description

A kind of movement erecting device of drillng operation blowout preventer set
Technical field:
The present invention relates to petroleum drilling technology field, particularly a kind of movement erecting device of drillng operation blowout preventer set.
Background technology:
Current well site of oil field present situation, for the installation work of blowout preventer set, especially large-scale blowout preventer set, not only consuming time but also heavy, it can only move along a direction in horizontal plane, make preventer installation position and well head installation position be difficult to centering, operating difficulties, lifting operation makes personal safety can not get ensureing.
Summary of the invention:
The technical problem to be solved in the present invention is to provide a kind of movement erecting device of drillng operation blowout preventer set, the arrangement achieves can fast, movement efficiently and accurately and install blowout preventer set, increase work efficiency, reduce labour intensity, improve processing safety.Overcome existing installation blowout preventer set to waste time and energy, operating difficulties, the deficiency of poor stability.
The technical solution used in the present invention is: a kind of movement erecting device of drillng operation blowout preventer set, comprises two fixing, two tracks of sliding, two translating trolleys, bracket, rotating turret and two leading screw platforms, slide and fixedly comprise slip fixed head, slip fixed head two ends are all connected with the little deck of track and the large deck of track, slip fixed head are welded with horizontal hydraulic cylinder bearing, and ratchet is arranged on slip fixed head, translating trolleys comprises translating trolleys base plate, and translating trolleys base plate two ends are connected with the large deck of track, translating trolleys base plate is welded with horizontal hydraulic cylinder bearing, support bracket support and lifting hydraulic cylinder bearing, bracket comprises bracket i iron and two bracket slide blocks, and bracket i iron two ends are all welded with bracket slide block, and upper and lower hydraulic cylinder bearing is welded on bracket i iron, bracket slide block is welded with bracket welding bearing, rotating turret comprises and rotates frame plate and two rotating turret slide blocks, and upper and lower hydraulic cylinder bearing is welded on and rotates on frame plate, rotates frame plate two ends and is all welded with rotating turret slide block, rotates to be welded with rotating turret gusset between frame plate and rotating turret slide block and rotating turret strengthens gusset, leading screw platform comprises leading screw pedestal, and leading screw pedestal two ends are all connected with the little deck of track and the large deck of track, is installed on leading screw pedestal, leading screw pedestal is provided with ratchet together with leading screw and screw slider otch connect also, slide fixing, translating trolleys and leading screw platform are installed in orbit, track has equally distributed notch, the notch that ratchet can be stuck in track is locked, slide to fix and be connected by horizontal hydraulic cylinder with between translating trolleys, bracket and support bracket support pass through pinned connection, upper and lower hydraulic cylinder is connected with between rotating turret and bracket, rotating turret and bracket join the upper and lower hydraulic cylinder of merga pass by groove port can make rotating turret move up and down along bracket, lifting hydraulic cylinder lower end connects lifting hydraulic cylinder bearing, lifting hydraulic cylinder upper end connects bracket welding bearing, the bearing that screw slider welds and support bar pass through pinned connection, the support bar other end is connected with bracket by bearing pin.
The invention has the beneficial effects as follows: the present invention can fast, movement efficiently and accurately and install blowout preventer set, increase work efficiency, reduce labour intensity, improve processing safety.
Accompanying drawing illustrates:
Below in conjunction with the drawings and specific embodiments, the present invention will be further described in detail.
Fig. 1 is structural representation of the present invention.
Fig. 2 is the fixing structural representation that slides.
Fig. 3 is the structural representation of translating trolleys.
Fig. 4 is the structural representation of bracket.
Fig. 5 is the structural representation of rotating turret.
Fig. 6 is the structural representation of leading screw platform.
Fig. 7 is the structural representation of ratchet.
Detailed description of the invention:
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, a kind of movement erecting device of drillng operation blowout preventer set, comprises two slips and fixes 1, two tracks, 2, two translating trolleys 3, bracket 4, rotating turret 5 and two leading screw platforms 7, slip is fixed 1 and is comprised slip fixed head 12, and slip fixed head 12 two ends are all connected with the little deck of track 11 and the large deck 13 of track, and slip fixed head 12 is welded with horizontal hydraulic cylinder bearing 14, ratchet 29 is arranged on slip fixed head 12, translating trolleys 3 comprises translating trolleys base plate 15, and translating trolleys base plate 15 two ends are connected with the large deck 13 of track, translating trolleys base plate 15 are welded with horizontal hydraulic cylinder bearing 14, support bracket support 16 and lifting hydraulic cylinder bearing 17, bracket 4 comprises bracket i iron 18 and two bracket slide blocks 19, and bracket i iron 18 two ends are all welded with bracket slide block 19, and upper and lower hydraulic cylinder bearing 21 is welded on bracket i iron 18, bracket slide block 19 is welded with bracket welding bearing 20, rotating turret 5 comprises rotation frame plate 22 and two rotating turret slide blocks 25, upper and lower hydraulic cylinder bearing 21 is welded on and rotates on frame plate 22, rotate frame plate 22 two ends and be all welded with rotating turret slide block 25, rotate and be welded with rotating turret gusset 23 between frame plate 22 and rotating turret slide block 25 and rotating turret strengthens gusset 24, leading screw platform 7 comprises leading screw pedestal 28, and leading screw pedestal 28 two ends are all connected with the little deck of track 11 and the large deck 13 of track, is installed on leading screw pedestal 28, leading screw pedestal 28 is provided with ratchet 29 together with leading screw 26 and screw slider 27 otch connect also, slip fixes 1, translating trolleys 3 and leading screw platform 7 are arranged on track 2, track 2 has equally distributed notch, the notch that ratchet 29 can be stuck in track 2 is locked, slip is fixed between 1 with translating trolleys 3 and is connected by horizontal hydraulic cylinder 10, bracket 4 and support bracket support 16 pass through pinned connection, upper and lower hydraulic cylinder 6 is connected with between rotating turret 5 and bracket 4, rotating turret 5 and bracket 4 join the upper and lower hydraulic cylinder 6 of merga pass by groove port can make rotating turret 5 move up and down along bracket 4, lifting hydraulic cylinder 9 lower end connects lifting hydraulic cylinder bearing 17, lifting hydraulic cylinder 9 upper end connects bracket welding bearing 20, bearing and the support bar 8 of welding on screw slider 27 pass through pinned connection, support bar 8 other end is connected with bracket 4 by bearing pin.
Be understandable that, above about specific descriptions of the present invention, the technical scheme described by the embodiment of the present invention is only not limited to for illustration of the present invention, those of ordinary skill in the art is to be understood that, still can modify to the present invention or equivalent replacement, to reach identical technique effect; Needs are used, all within protection scope of the present invention as long as meet.

Claims (1)

1. a movement erecting device for drillng operation blowout preventer set, comprises two slide fixing (1), two tracks (2), two translating trolleys (3), bracket (4), rotating turret (5) and two leading screw platforms (7), it is characterized in that: slide fixing (1) comprises slip fixed head (12), slip fixed head (12) two ends are all connected with the little deck of track (11) and the large deck of track (13), slip fixed head (12) is welded with horizontal hydraulic cylinder bearing (14), ratchet (29) is arranged on slip fixed head (12), translating trolleys (3) comprises translating trolleys base plate (15), translating trolleys base plate (15) two ends are connected with the large deck of track (13), translating trolleys base plate (15) are welded with horizontal hydraulic cylinder bearing (14), support bracket support (16) and lifting hydraulic cylinder bearing (17), bracket (4) comprises bracket i iron (18) and two bracket slide blocks (19), bracket i iron (18) two ends are all welded with bracket slide block (19), upper and lower hydraulic cylinder bearing (21) is welded on bracket i iron (18), bracket slide block (19) is welded with bracket welding bearing (20), rotating turret (5) comprises rotation frame plate (22) and two rotating turret slide blocks (25), upper and lower hydraulic cylinder bearing (21) is welded on to be rotated on frame plate (22), rotate frame plate (22) two ends and be all welded with rotating turret slide block (25), rotate between frame plate (22) and rotating turret slide block (25) and be welded with rotating turret gusset (23) and rotating turret strengthens gusset (24), leading screw platform (7) comprises leading screw pedestal (28), leading screw pedestal (28) two ends are all connected with the little deck of track (11) and the large deck of track (13), leading screw (26) and screw slider (27) otch are installed on leading screw pedestal (28) together with connecting also, leading screw pedestal (28) are provided with ratchet (29), slide fixing (1), translating trolleys (3) and leading screw platform (7) are arranged on track (2), (2) have equally distributed notch to track, the notch that ratchet (29) can be stuck in track (2) is locked, the fixing horizontal hydraulic cylinder (10) that passes through between (1) with translating trolleys (3) that slides is connected, bracket (4) and support bracket support (16) pass through pinned connection, upper and lower hydraulic cylinder (6) is connected with between rotating turret (5) and bracket (4), rotating turret (5) and bracket (4) join the upper and lower hydraulic cylinder of merga pass (6) by groove port can make rotating turret (5) move up and down along bracket (4), lifting hydraulic cylinder (9) lower end connects lifting hydraulic cylinder bearing (17), lifting hydraulic cylinder (9) upper end connects bracket welding bearing (20), bearing and the support bar (8) of the upper welding of screw slider (27) pass through pinned connection, support bar (8) other end is connected with bracket (4) by bearing pin.
CN201310343350.3A 2013-08-07 2013-08-07 A kind of movement erecting device of drillng operation blowout preventer set Expired - Fee Related CN103437731B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310343350.3A CN103437731B (en) 2013-08-07 2013-08-07 A kind of movement erecting device of drillng operation blowout preventer set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310343350.3A CN103437731B (en) 2013-08-07 2013-08-07 A kind of movement erecting device of drillng operation blowout preventer set

Publications (2)

Publication Number Publication Date
CN103437731A CN103437731A (en) 2013-12-11
CN103437731B true CN103437731B (en) 2016-01-20

Family

ID=49691437

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310343350.3A Expired - Fee Related CN103437731B (en) 2013-08-07 2013-08-07 A kind of movement erecting device of drillng operation blowout preventer set

Country Status (1)

Country Link
CN (1) CN103437731B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103924939A (en) * 2014-05-08 2014-07-16 喻书华 Quick connection device for blowout preventer in drilling tool
CN105651531A (en) * 2016-02-23 2016-06-08 上海振华重工(集团)股份有限公司 Moon pool vehicle testing platform
CN108394841B (en) * 2018-02-02 2019-12-31 宝鸡石油机械有限责任公司 Blowout preventer stack transportation pressure testing function integrated device
CN108928356A (en) * 2018-08-27 2018-12-04 江苏诚创智能装备有限公司 A kind of position-limit mechanism and its preventer transfer device using the position-limit mechanism

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1709068A1 (en) * 1990-02-14 1992-01-30 Предприятие Производственного Объединения "Баррикады" Preventer control device
CN2658374Y (en) * 2003-09-29 2004-11-24 兰州兰石国民油井石油工程有限公司 Mounting device of oil-gas well blowout preventer
CN200964809Y (en) * 2006-06-07 2007-10-24 成都美加石油机械工程有限责任公司 Blowout prevention device mounting device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7784546B2 (en) * 2005-10-21 2010-08-31 Schlumberger Technology Corporation Tension lift frame used as a jacking frame

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1709068A1 (en) * 1990-02-14 1992-01-30 Предприятие Производственного Объединения "Баррикады" Preventer control device
CN2658374Y (en) * 2003-09-29 2004-11-24 兰州兰石国民油井石油工程有限公司 Mounting device of oil-gas well blowout preventer
CN200964809Y (en) * 2006-06-07 2007-10-24 成都美加石油机械工程有限责任公司 Blowout prevention device mounting device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《新型防喷器移送装置的研究与应用》;朱奇,侯勇俊;《石油机械》;20111101;第39卷;第28-30页 *
《石油钻机用防喷器装卸***研制及应用》;马永刚等;《石油矿场机械》;20101225;第39卷(第12期);第64-67页 *

Also Published As

Publication number Publication date
CN103437731A (en) 2013-12-11

Similar Documents

Publication Publication Date Title
CN103437731B (en) A kind of movement erecting device of drillng operation blowout preventer set
US10329849B2 (en) Multi-functional drilling experiment platform
CN104314480B (en) A kind of pipe tool erection device
CN103590763B (en) A kind of oil drilling platform preventer transport erecting device
CN204609762U (en) Outstanding rail rock drilling machine
CN107965281B (en) Offshore module drilling rig blowout preventer moving device and moving method
CN202370430U (en) Mine rig
CN203531747U (en) Frame-column-type emulsified liquid drilling machine for fully-mechanized face fault passing
CN103277046B (en) Wheel type truck-mounted drilling rig
CN204186306U (en) A kind of pipe erection device
CN204344020U (en) A kind of borer drill rod clamper
CN104533279A (en) Full-hydraulic dual-power combined type myriametre drilling machine
CN203592972U (en) Novel fast self-lifting and self-locking chassis
CN203769665U (en) Detachable folding type vertical sleeving derrick
CN103395691B (en) Hydraulic lifting mechanism
CN203905871U (en) Device for rapid replacement of BOP (blowout preventer)
CN203050697U (en) Onboard detection drilling machine
CN205823149U (en) A kind of portable all-hydraulic engineering investigation rig
CN205012942U (en) Derrick formula coiled tubing centering structure
WO2015169737A1 (en) System for well operation
CN203626649U (en) Blowout preventer transportation and installation device for oil drilling platform
CN201539213U (en) Movable long-hole drilling machine platform
CN203925282U (en) Crawler type deep foundation ditch anchoring rig
CN203891800U (en) Normally-closed hydraulic chuck with quick-change slip
CN203626636U (en) Sheathing telescopic K type derrick casing centralizing hydraulic ascending and descending device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180928

Address after: 300457 Tianjin Binhai New Area Binhai Service Outsourcing Industrial Park 3 Building

Co-patentee after: NORTHEAST PETROLEUM University

Patentee after: CNPC BOHAI EQUIPMENT MANUFACTURING Co.,Ltd.

Address before: 300457 Tianjin Binhai New Area Binhai Service Outsourcing Industrial Park 3 Building

Co-patentee before: CHINA PETROLEUM LIAOHE EQUIPMENT Co.

Patentee before: CNPC BOHAI EQUIPMENT MANUFACTURING Co.,Ltd.

Co-patentee before: NORTHEAST PETROLEUM University

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160120