CN103424055B - Totally-enclosed non-pedestrian tunnel caving angle observation procedure - Google Patents

Totally-enclosed non-pedestrian tunnel caving angle observation procedure Download PDF

Info

Publication number
CN103424055B
CN103424055B CN201310326674.6A CN201310326674A CN103424055B CN 103424055 B CN103424055 B CN 103424055B CN 201310326674 A CN201310326674 A CN 201310326674A CN 103424055 B CN103424055 B CN 103424055B
Authority
CN
China
Prior art keywords
survey line
tunnel
caving
totally
pedestrian
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310326674.6A
Other languages
Chinese (zh)
Other versions
CN103424055A (en
Inventor
李树刚
林海飞
王红刚
潘红宇
赵鹏翔
成连华
魏宗勇
王红胜
李莉
丁洋
张天军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Science and Technology
Original Assignee
Xian University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Science and Technology filed Critical Xian University of Science and Technology
Priority to CN201310326674.6A priority Critical patent/CN103424055B/en
Publication of CN103424055A publication Critical patent/CN103424055A/en
Application granted granted Critical
Publication of CN103424055B publication Critical patent/CN103424055B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Aerodynamic Tests, Hydrodynamic Tests, Wind Tunnels, And Water Tanks (AREA)

Abstract

The present invention relates to coal and gas power phenomenon field, specifically a kind of totally-enclosed non-pedestrian back caving angle observation procedure.Comprise survey line straightening device and survey line collapsing length self-recording unit, by cooperatively interacting between the two, realize the test to totally-enclosed non-pedestrian tunnel caving angle.The present invention can observe with the caving angle of the advance of the face and back deflection closed roadway tunnel fire dam is outer, and the effective relation disclosed between totally-enclosed non-pedestrian tunnel and workplace water component.Observed result is clear directly perceived, and implementation process is safe and reliable.The invention solves totally-enclosed non-pedestrian tunnel caving angle and test this difficult problem, (inclining) is walked to further test roof and provides method to the caving angle in high-order gas pumping lane, foundation is provided to the layer position determining that roof is walked (inclining) to high-order gas drainage lane, has important meaning to raising gas pumping efficiency.

Description

Totally-enclosed non-pedestrian tunnel caving angle observation procedure
Technical field
The present invention relates to coal and gas power phenomenon field, specifically a kind of method of testing totally-enclosed non-pedestrian back caving angle.The method is applicable in coal production process, observation is carried out with the caving angle of the advance of the face in the totally-enclosed non-pedestrian tunnel arranged for mash gas extraction, clearly this tunnel is caving the relation between workplace periodic weighting step pitch further, for the determination of totally-enclosed non-pedestrian tunnel correlation parameter and maintenance mode thereof provide theoretical direction.
Background technology
Current mine gas disaster is still one of accident of restriction China's coal-mine safety in production, simultaneously gas still cause greenhouse effect, the source of the air environmental pollution such as to damage the ozone layer.In addition, the inflammable gas of gas or a kind of economy is high heat, cleaning, the easily energy.Coal-bed gas integrates profit and evil; it is the distinctive precious resources in colliery; effective, the safety that realize coal and non-coal two spike-type cultivars are adopted altogether; the triple effects such as mine safety production, environmental protection and new forms of energy supply can be realized; obtain significant economic and social benefit, control of coalmine gas has utilized and has listed " 863 " state key brainstorm project in by current country.
Colliery arranges high-order gas pumping tunnel mainly to arrange that above roof totally-enclosed non-pedestrian gas pumping tunnel is main extraction means, wherein arrange trend or be inclined to high-order gas pumping lane to be one of important means of comprehensive regulation gas in current pit mining process along roof, and layout layer position, high-order gas pumping lane is whether reasonable, decide again the quality of gas pumping effect and the complexity of roadway maintenance.Wherein high-order extraction lane is again one of key factor of impact layer position, high-order gas pumping lane selection with the caving angle during advance of the face.At present, the mine of all employings of China high-order gas pumping lane mash gas extraction, because high-order gas pumping lane is that two ends seal during use, almost cannot test the caving angle of this tunnel with the advance of the face, be difficult to determine the relation between the high-order extraction tunnel of gas and coal face advance distance, make gas extraction concentration be difficult to all the time reach satisfied effect.
Summary of the invention
In order to determine the relation between this tunnel and workplace water component, thus solve the caving angle how determining high-order gas pumping lane, be the key issue improving gas extraction concentration, the invention provides a kind of totally-enclosed non-pedestrian tunnel caving angle observation procedure.
Technical solution of the present invention is: a kind of totally-enclosed non-pedestrian tunnel caving angle observation procedure, comprise survey line straightening device and survey line collapsing length self-recording unit, survey line straightening device is made up of weight (6), pulley (2) and survey line (3), survey line collapsing length self-recording unit is made up of survey line collapsing length auto testing instrument (1) and survey line (3), comprise the steps: to arrange some measuring points along back in high-order gas pumping tunnel, each measuring point being arranged in internal heads place, tunnel all connects a weight (6), and binding firmly; In inside, tunnel, a ceramic pulley (2) is set every 5 ~ 10m, is used for ensureing the straight of interim survey line; The other end of survey line (3) utilizes PE to manage (5) as reducing, by the fire dam (7) of survey line (3) pull-out suction road, is connected with survey line collapsing length self-recording device (1); Calculate being caving highly of its superincumbent stratum according to working seam thickness, outside the fire dam of high-order extraction tunnel, reserve the survey line of possibility length accordingly in advance, guarantee that survey line has enough tensile elongations; Work as the advance of the face, through high-order gas pumping lane, due to this tunnel of effect bending subsidence and even be caving suddenly gradually of rock pressure [in mine, in whole process, in tunnel, the weight (6) of survey line end declines along with the motion of suction road under gravity, thus make fire dam (7) outer survey line (3) free end produce corresponding displacement, thus realize the measurement it being caving to degree and caving angle.
Described survey line (3) arrangement is as follows: at the scene in work progress, according to tunnel developed width, presets 4 ~ 5 surveys line (3), can be arranged in 1/3 scope of the totally-enclosed non-pedestrian tunnel total length carrying out testing respectively; A weight is arranged in each survey line (3) one end, and with smooth insulated copper silk rope by weight (6) fixation in roadway floor; The ceramic pulley (2) of survey line (3) through arranging every 5 ~ 10 meters is pulled near fire dam (7), (5) are managed as reducing again by PE, survey line (3) is caused test tunnel fire dam (7) outside, be connected with survey line collapsing length self-recording device (1).
The present invention can airtightly in tunnel to observe with the caving angle of the advance of the face and back deflection closed roadway outward, and the effective relation disclosed between totally-enclosed non-pedestrian tunnel and workplace water component.Observed result is clear directly perceived, and implementation process is safe and reliable.This method of testing solves totally-enclosed non-pedestrian tunnel caving angle and tests this difficult problem, (inclining) is walked to further test roof and provides method to the caving angle in high-order gas pumping lane, foundation is provided to the layer position determining that roof is walked (inclining) to high-order gas drainage lane, has important meaning to raising gas pumping efficiency.
Accompanying drawing explanation
Fig. 1 is survey line straightening device of the present invention and survey line collapsing length self-recording unit structural representation;
Fig. 2 is the vertical view of Fig. 1.
Fig. 3 is each survey line daily progression rate result schematic diagram.
Embodiment
The present invention includes survey line straightening device and survey line collapsing length self-recording unit, by cooperatively interacting between the two, realize the test to totally-enclosed non-pedestrian tunnel caving angle.Wherein survey line straightening device is made up of weight 6, pulley 2 and survey line 3; Survey line collapsing length self-recording unit is made up of survey line collapsing length auto testing instrument 1 and survey line 3.In high-order gas pumping tunnel, arrange some measuring points along back, each measuring point being arranged in internal heads place, tunnel all connects a survey line straightening device, and binding firmly.In inside, tunnel, a ceramic pulley is set every 5 ~ 10m, is used for ensureing the straight of interim survey line.Survey line 3, as reducing, is pulled out the fire dam 7 of suction road, is connected with survey line collapsing length self-recording device 1 by the PE pipe 5 that the other end of survey line 3 utilizes diameter to be 2.5cm.Calculate being caving highly of its superincumbent stratum according to working seam thickness, outside the fire dam of high-order extraction tunnel, reserve the survey line of possibility length accordingly in advance, guarantee that survey line has enough tensile elongations.Work as the advance of the face, through high-order gas pumping lane, due to this tunnel of effect bending subsidence and even be caving suddenly gradually of rock pressure [in mine, in whole process, in tunnel, the survey line straightening device of survey line end declines along with the motion of suction road under gravity, thus make the outer survey line free end of fire dam produce corresponding displacement, thus realize the measurement it being caving to degree and caving angle.
Survey line 3 arrangement: in observation program site operation process, due to the restriction of span length, in order to ensure the lateral separation between each measuring point, can according to tunnel developed width, preset 4 ~ 5 surveys line 3, can be arranged in respectively in 1/3 scope of the totally-enclosed non-pedestrian tunnel total length carrying out testing.A survey line straightening device is arranged in each survey line 3 one end, and with the smooth insulation copper rope of diameter 3mm by this device fixation in roadway floor.The ceramic pulley 2 of survey line 3 through arranging every 5 ~ 10 meters is pulled near fire dam, then by the PE pipe 5 of diameter 2.5cm as reducing, is caused by survey line 3 outside test tunnel fire dam 7, be connected with survey line shift-in amount auto testing instrument 1.
Embodiment:
The present invention select certain high methane colliery at its main mining coal seam top board along the totally-enclosed non-pedestrian gas pumping tunnel that bearing is arranged as site test district.Calculate according to working seam thickness, its superincumbent stratum is caving height can not more than 10m, and therefore, outside the fire dam of test tunnel, 10 ~ 15m reserved by every bar survey line 3.When workplace pushes through suction road, due to the effect of rock pressure [in mine, the top board bending subsidence and even be caving suddenly gradually in test tunnel, the survey line testing fire dam inside, tunnel in whole process along with back sinking and be caving and move down, thus make the survey line free end outside fire dam produce corresponding displacement, thus test the caving angle in this tunnel.
Observation station arrangement: in observation program field conduct process, due to the restriction of span length, in order to ensure the lateral separation between each measuring point, according to on-the-spot tunnel developed width, final decision arranges 4 surveys line 3 along back: wherein 2 are positioned in the middle part of tunnel, and other 2 are positioned at roadway's sides.By being distributed in each pulley 2 inside tunnel fire dam 7 and survey line 3,4 surveys line 3 are drawn to distance fire dam 130m, 110m, 90m and 70m place, tunnel, a weight 6 is arranged at the end of each measuring point, and with the smooth insulation copper rope of diameter 3mm by this weight 6 and survey line 3 fixation, ensure that survey line 3 moment is in straight condition.Caused tunnel fire dam 7 outside by the PE pipe 5 of diameter 2.5cm as reducing at the other end of survey line 3, in order to ensure that test macro can be measured accurately to tunnel caving angle and deflection thereof, the survey line 3 of reserved 10 ~ 15m length outside the fire dam of tunnel, and its free termination is connected with survey line collapsing length auto testing instrument 1.
In advance of the face process, originally tunnel form maintains the original state substantially, and after the advance of the face one segment distance, under the effect of rock pressure [in mine, distortion appears sinking in tunnel, and workplace continues to advance, and being caving finally appears in tunnel.After this along with the continuation of workplace advances, tunnel presents the periodicity polyisomenism of above-mentioned three kinds of distortion, in the process, survey line 3 along with the sinking in tunnel and can be caving the corresponding movement of generation, survey line 3 free end through survey line collapsing length auto testing instrument 1 outside tunnel fire dam 7 then can move forward thereupon, survey line collapsing length auto testing instrument 1 can be monitored in real time to the shift-in amount of survey line 3, thus ensure that survey line 3 pairs of tunnels are caving the continuity of overall process test, make test result can reflect caving angle and the shift-in amount thereof in tunnel more accurately, simultaneously also find out observation back when deflection by the size of survey line 3 shift-in amount, when be caving.
The method has carried out type approval test at certain high methane coal master mining face, observes with roadway deformation deflection and caving angle thereof in advance of the face process its totally-enclosed non-pedestrian tunnel.According to on-site actual situations, before this coal master's mining face top board moves towards totally-enclosed non-pedestrian roadway linking, the length of 4 measuring points in this tunnel of arranging along its dynamic version is respectively: about the length 160m of 1# survey line in this tunnel, about the length 135m of 2# survey line in this tunnel, about the length 110m of 3# survey line in this tunnel, about the length 80m of 4# survey line in this tunnel.
To arranging in tunnel that each measuring point deflection is measured, draw the test result as Fig. 3.Along with workplace constantly advances, superincumbent stratum sinks, thus each measuring point is sunk thereupon, is finally caving.As can be seen from the figure, at 1# survey line shortening on June 16 ~ 17 3cm, June 22 ~ 23,2# survey line shortened 3.5cm, and June 27 ~ 28,3# survey line shortened 10.9cm, and July 2 ~ 3,4# survey line shortened 18.6cm.By survey line above reduce the distance can judge 1# ~ 4# measuring point be caving the time and be respectively: June 16 ~ 17, June 22 ~ 23, June 27 ~ 28, July 2 ~ 3.In conjunction with on-the-spot actual Roof Span, test point distance workplace distance and workplace day push-in stroke and test result be analyzed and can find, June 16 ~ 17, June 22 ~ 23, June 27 ~ 28, July 2 ~ 3 p-wire there occurs respectively and shorten largely, illustrate that now this top board moves towards totally-enclosed non-pedestrian tunnel and is caving, thus determine that the caving angle that this coal master's mining face top board moves towards totally-enclosed non-pedestrian tunnel is 24m, 26m and 20m, average 23.3m.

Claims (2)

1. a totally-enclosed non-pedestrian tunnel caving angle observation procedure, comprise survey line straightening device and survey line collapsing length self-recording unit, survey line straightening device is by weight (6), pulley (2) and survey line (3) composition, survey line collapsing length self-recording unit is made up of survey line collapsing length auto testing instrument (1) and survey line (3), it is characterized in that: comprise the steps: to arrange some measuring points along back in high-order gas pumping tunnel, each measuring point being arranged in internal heads place, tunnel all connects a weight (6), and binding firmly, in inside, tunnel, a pulley (2) is set every 5 ~ 10m, is used for ensureing the straight of interim survey line, the other end of survey line (3) utilizes PE to manage (5) as reducing, by the fire dam (7) of survey line (3) pull-out suction road, is connected with survey line collapsing length self-recording device (1), calculate being caving highly of its superincumbent stratum according to working seam thickness, outside the fire dam of high-order extraction tunnel, reserve the survey line of possibility length accordingly in advance, guarantee that survey line has enough tensile elongations, work as the advance of the face, through high-order gas pumping lane, due to this tunnel of effect bending subsidence and even be caving suddenly gradually of rock pressure [in mine, in whole process, in tunnel, the weight (6) of survey line end declines along with the motion of suction road under gravity, thus make fire dam (7) outer survey line (3) free end produce corresponding displacement, thus realize the measurement it being caving to degree and caving angle.
2. totally-enclosed non-pedestrian tunnel as claimed in claim 1 caving angle observation procedure, it is characterized in that: described survey line (3) arrangement is as follows: at the scene in work progress, according to tunnel developed width, preset 4 ~ 5 surveys line (3), can be arranged in 1/3 scope of the totally-enclosed non-pedestrian tunnel total length carrying out testing respectively; A weight (6) is arranged in each survey line (3) one end, and with insulation copper rope smooth by weight (6) fixation in roadway floor; The pulley (2) of survey line (3) through arranging every 5 ~ 10 meters is pulled near fire dam (7), (5) are managed as reducing again by PE, survey line (3) is caused test tunnel fire dam (7) outside, be connected with survey line collapsing length self-recording device (1).
CN201310326674.6A 2013-07-30 2013-07-30 Totally-enclosed non-pedestrian tunnel caving angle observation procedure Expired - Fee Related CN103424055B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310326674.6A CN103424055B (en) 2013-07-30 2013-07-30 Totally-enclosed non-pedestrian tunnel caving angle observation procedure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310326674.6A CN103424055B (en) 2013-07-30 2013-07-30 Totally-enclosed non-pedestrian tunnel caving angle observation procedure

Publications (2)

Publication Number Publication Date
CN103424055A CN103424055A (en) 2013-12-04
CN103424055B true CN103424055B (en) 2015-10-21

Family

ID=49649164

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310326674.6A Expired - Fee Related CN103424055B (en) 2013-07-30 2013-07-30 Totally-enclosed non-pedestrian tunnel caving angle observation procedure

Country Status (1)

Country Link
CN (1) CN103424055B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111102009B (en) * 2019-12-17 2021-03-16 西安科技大学 Method for calculating pressure step distance of thin-bedrock shallow coal seam
CN112182841B (en) * 2020-08-31 2022-06-17 太原理工大学 Safety assessment method for caving step of underground rock roof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4573531A (en) * 1980-02-21 1986-03-04 Vsesojuznoe Nauchno-Proizvod-Stvennoe Obiedinenie "Sojuzpromgaz" Method of underground gasification of coal seam
RU2382879C1 (en) * 2008-09-16 2010-02-27 "Государственное образовательное учреждение высшего профессионального образования Дальневосточный государственный технический университет (ДВПИ им. В.В. Куйбышева)" (ГОУ ВПО ДВГТУ) Underground gasification method
CN102155226A (en) * 2010-11-30 2011-08-17 淄博市王庄煤矿 Roadway backfill mining method for coal seams with medium-high thickness
CN103089305A (en) * 2013-01-14 2013-05-08 中国矿业大学(北京) Risk assessment method for coal and gas outburst of coal beds

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8262167B2 (en) * 2009-08-20 2012-09-11 George Anthony Aulisio Apparatus and method for mining coal

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4573531A (en) * 1980-02-21 1986-03-04 Vsesojuznoe Nauchno-Proizvod-Stvennoe Obiedinenie "Sojuzpromgaz" Method of underground gasification of coal seam
RU2382879C1 (en) * 2008-09-16 2010-02-27 "Государственное образовательное учреждение высшего профессионального образования Дальневосточный государственный технический университет (ДВПИ им. В.В. Куйбышева)" (ГОУ ВПО ДВГТУ) Underground gasification method
CN102155226A (en) * 2010-11-30 2011-08-17 淄博市王庄煤矿 Roadway backfill mining method for coal seams with medium-high thickness
CN103089305A (en) * 2013-01-14 2013-05-08 中国矿业大学(北京) Risk assessment method for coal and gas outburst of coal beds

Also Published As

Publication number Publication date
CN103424055A (en) 2013-12-04

Similar Documents

Publication Publication Date Title
Wang et al. Debrining prediction of a salt cavern used for compressed air energy storage
CN103528731B (en) A kind of coal mine paste filling on-line monitoring system based on optical fiber grating sensing
CN104142187A (en) Gob-side entry retaining pasty filler on-line detection method
CN101660410A (en) Long wall alternate type coal mining method
CN105021662B (en) Adopt workplace regimen real-time dynamic monitoring test unit and test method
CN104848891A (en) Dynamic monitoring system and monitoring method for connection structure of concrete dam and earth and rockfill dam
Ma et al. Distance effects of the fault on the surrounding rock mass stability of the main powerhouse at the Huanggou pumped-storage power station
CN109446602B (en) Numerical test method for extracting gas from ultra-thick coal seam through ground vertical drilling
Li et al. The integrated drainage technique of directional high-level borehole of super large diameter on roof replacing roof extraction roadway: A case study of the underground Zhaozhuang Coal Mine
CN103471648A (en) Disturbance construction monitoring method of top pipe tunnel
CN103424055B (en) Totally-enclosed non-pedestrian tunnel caving angle observation procedure
Wang et al. Optimization of construction scheme and supporting technology for HJS soft rock tunnel
CN104089595B (en) Stope base object model ruptures determination of distance method in advance
CN201892527U (en) Pipe section joint opening monitoring device for electric power tunnels
CN105401973A (en) Method for performing extraction treatment on corner gas on work faces of adjacent roadways
CN204514373U (en) The dynamic monitoring system of the syndeton of a kind of concrete dam and earth and rockfill dam
CN103061322A (en) Method and system for remote intelligent monitoring and three-dimensional digital comprehensive warning of deep foundation pit stability
CN204479065U (en) A kind of High Precision Traverses formula tunneling boring stability of slope monitor and early warning system
CN207351793U (en) Glass curtain wall 3 D deformation on-site detecting device
Gomes et al. Conceptual framework of the Snowy 2.0 Pumped Storage Project (PSP) Geotechnical Baseline Report (GBR) for underground works
Lin et al. Tunnel Monitoring and measurement case study in Qiyueshan Tunnel
CN203164732U (en) Remote monitoring system of power tunnel comprehensive data
CN210091544U (en) Reaction frame of pipe jacking experimental box
Liu et al. 3D Numerical Modelling of Stability of Underground Pumped Storage Hydropower (UPSH)
Yang et al. Prediction and Prevention of High Intensity Mining Water Burst under Reservoirs in Western Mining Areas

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151021

Termination date: 20160730

CF01 Termination of patent right due to non-payment of annual fee