CN103410178B - A kind of pile bearing capacity detects Medium Exchange filling device - Google Patents
A kind of pile bearing capacity detects Medium Exchange filling device Download PDFInfo
- Publication number
- CN103410178B CN103410178B CN201310372652.3A CN201310372652A CN103410178B CN 103410178 B CN103410178 B CN 103410178B CN 201310372652 A CN201310372652 A CN 201310372652A CN 103410178 B CN103410178 B CN 103410178B
- Authority
- CN
- China
- Prior art keywords
- rebound
- lower shoe
- welded
- pressure chamber
- flexible wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The present invention relates to the pile detection medium exchange device measuring foundation pile supporting capacity in a kind of building foundation pile driving construction.It comprises rebound, flexible wall, inner cylinder body, outer cylinder body, lower shoe, feed tube, liquid back pipe, this device is arranged on the stage casing of foundation pile, rebound and foundation pile epimere reinforcing cage are welded as a whole, lower shoe and hypomere reinforcing cage are welded as a whole, top offset bar is welded on rebound, and leads directly to earth's surface by protecting pipe; Bottom offset bar is welded on lower shoe, and leads directly to earth's surface by protecting pipe; Centre is an annular pressure chamber, and this pressure chamber is made up of flexible wall, rebound, lower shoe, and flexible wall flange is arranged on rebound, lower shoe; The feed tube of pressure chamber is connected with ground loading system, and liquid back pipe leads directly to earth's surface.The present invention adopts annular pressure chamber, and lifting surface area is large, and flexible wall and rebound, lower shoe adopt Flange joint, good airproof performance, connects reliable, and does not need separately to fill sealing ring.The medium that the present invention adopts based on water, cement paste and other liquid, low price, and pollution-free.
Description
Technical field
The present invention relates to the pile detection medium exchange device measuring foundation pile supporting capacity in a kind of building foundation pile driving construction.
Background technology
The load box of the pile bearing capacity test now used, it is at the bottom of foundation pile stake or multiple hydraulic jack is settled in stake stage casing, loads foundation pile.In the program; enter each hydraulic cylinder from ground hydraulic station through an oil inlet pipe injection high pressure liquid force feed and carry out pile bearing capacity detection; separately to bury benefit slurry pipe for causing foundation pile space after detection and carry out benefit slurry; due to section when pile bearing capacity detects and rule useless; mend slurry weak effect, the workmanship of foundation pile can not be guaranteed.
Summary of the invention
In order to overcome above-mentioned defect, the object of the invention is to provide the pile detection medium exchange device that a kind of structure is simple, benefit slurry is effective, Transfer Medium substitutes water or other liquid based on cement paste.
In order to achieve the above object, the present invention adopts following technical scheme:
A kind of pile bearing capacity detects Medium Exchange filling device, it comprises rebound, flexible wall, inner cylinder body, outer cylinder body, lower shoe, feed tube, liquid back pipe, this device is arranged on the stage casing of foundation pile, rebound and foundation pile epimere reinforcing cage are welded as a whole, lower shoe and hypomere reinforcing cage are welded as a whole, top offset bar is welded on rebound, and leads directly to earth's surface by protecting pipe; Bottom offset bar is welded on lower shoe, and leads directly to earth's surface by protecting pipe; Centre is an annular pressure chamber, and this pressure chamber is made up of flexible wall, rebound, lower shoe, and flexible wall flange is arranged on rebound, lower shoe; The feed tube of pressure chamber is connected with ground loading system, and liquid back pipe leads directly to earth's surface.
Above-mentioned loading system is oil pump or water pump.
The invention has the beneficial effects as follows:
1. the present invention adopts annular pressure chamber, and lifting surface area is large, and flexible wall and rebound, lower shoe adopt Flange joint, good airproof performance, connects reliable, and does not need separately to fill sealing ring.
2. the medium of the present invention's employing is based on water, cement paste and other liquid, low price, and pollution-free.
3. the present invention adopts interior outer cylinder body to bear pressure, the frame mode that the upper-lower section reinforcing cage of rebound, lower shoe and foundation pile is welding as one, and structure is simple, and the process-cycle is short, easy for installation.
4. the present invention adopts feed tube to inject high-intensity cement paste, and liquid back pipe discharges the method for former medium and air, mends slurry reliable, guarantees the workmanship of foundation pile.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the structural representation of depression angle of the present invention;
Fig. 3 is the structural representation of cross section of the present invention angle.
Detailed description of the invention
The present invention is described in detail for lower denomination accompanying drawing 1,2,3:
A kind of pile bearing capacity detects Medium Exchange filling device, it comprises rebound 7, flexible wall 6, inner cylinder body 10, outer cylinder body 4, lower shoe 5, feed tube 2, liquid back pipe 9, this device is arranged on the stage casing of foundation pile, rebound 7 and foundation pile epimere reinforcing cage are welded as a whole, lower shoe 5 and hypomere reinforcing cage are welded as a whole, top offset bar 1 is welded on rebound 7, and leads directly to earth's surface by protecting pipe; Bottom offset bar 8 is welded on lower shoe 5, and leads directly to earth's surface by protecting pipe; Centre is an annular pressure chamber, and this pressure chamber is made up of flexible wall 6, rebound 7, lower shoe 5, and flexible wall 6 flange 3 is arranged on rebound 7, lower shoe 5; The feed tube 2 of pressure chamber is connected with ground loading system, and liquid back pipe 9 leads directly to earth's surface.
Above-mentioned loading system is oil pump or water pump.
Displacement bar is for after measuring foundation pile bearing load, and whether qualified the plunger panel of side seal type load box and the displacement of lower shoe, the namely displacement of foundation pile, carry out judgement basis pile bearing capacity according to the displacement of foundation pile.
Liquid back pipe is for completing the slurry of the benefit after loading process, and injected from feed tube by cement paste, liquid medium is discharged from liquid back pipe; when there being cement paste to discharge from liquid back pipe; close liquid back pipe pressurize, now guarantee that foundation pile hypomere cavity fills cement paste, guarantee the workmanship of foundation pile.
Claims (2)
1. a pile bearing capacity detects Medium Exchange filling device, it comprises rebound (7), flexible wall (6), inner cylinder body (10), outer cylinder body (4), lower shoe (5), feed tube (2), liquid back pipe (9), this device is arranged on the stage casing of foundation pile, it is characterized in that: rebound (7) and foundation pile epimere reinforcing cage are welded as a whole, lower shoe (5) and hypomere reinforcing cage are welded as a whole, top offset bar (1) is welded on rebound (7), and leads directly to earth's surface by protecting pipe; Bottom offset bar (8) is welded on lower shoe (5), and leads directly to earth's surface by protecting pipe; Centre is an annular pressure chamber, and this pressure chamber is made up of flexible wall (6), rebound (7), lower shoe (5), and flexible wall (6) flange (3) is arranged on rebound (7), lower shoe (5); The feed tube (2) of pressure chamber is connected with ground loading system, and liquid back pipe (9) leads directly to earth's surface.
2. pile bearing capacity according to claim 1 detects Medium Exchange filling device, it is characterized in that: above-mentioned loading system is oil pump or water pump.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310372652.3A CN103410178B (en) | 2013-08-23 | 2013-08-23 | A kind of pile bearing capacity detects Medium Exchange filling device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310372652.3A CN103410178B (en) | 2013-08-23 | 2013-08-23 | A kind of pile bearing capacity detects Medium Exchange filling device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103410178A CN103410178A (en) | 2013-11-27 |
CN103410178B true CN103410178B (en) | 2016-01-06 |
Family
ID=49603216
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310372652.3A Active CN103410178B (en) | 2013-08-23 | 2013-08-23 | A kind of pile bearing capacity detects Medium Exchange filling device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103410178B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638730B (en) * | 2017-02-09 | 2019-02-26 | 南昌永祺科技发展有限公司 | Load box is used in the extrudable pile foundation self-balancing test resetted of piston mode |
CN110331745A (en) * | 2019-07-12 | 2019-10-15 | 浙江欧感机械制造有限公司 | The method of plane of disruption engineering media filler is synchronously completed in the detection of self-balancing load box |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4634316A (en) * | 1983-12-27 | 1987-01-06 | Vyzkumny ustav inzenierskych stavieb | Compacted deep foundation structure, method of and apparatus for building the same |
CN2422636Y (en) * | 2000-03-31 | 2001-03-07 | 龚维明 | Loading box for measuring pile bearing capacity |
CN101435206A (en) * | 2008-12-19 | 2009-05-20 | 钱崑 | Pile body self-rebound force balance loading case |
CN203129192U (en) * | 2012-12-22 | 2013-08-14 | 哈尔滨商业大学 | Annular embedded box device for pile foundation test |
CN203403448U (en) * | 2013-08-23 | 2014-01-22 | 南昌永祺科技发展有限公司 | Foundation pile bearing capacity detecting medium exchanging and filling device |
-
2013
- 2013-08-23 CN CN201310372652.3A patent/CN103410178B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4634316A (en) * | 1983-12-27 | 1987-01-06 | Vyzkumny ustav inzenierskych stavieb | Compacted deep foundation structure, method of and apparatus for building the same |
CN2422636Y (en) * | 2000-03-31 | 2001-03-07 | 龚维明 | Loading box for measuring pile bearing capacity |
CN101435206A (en) * | 2008-12-19 | 2009-05-20 | 钱崑 | Pile body self-rebound force balance loading case |
CN203129192U (en) * | 2012-12-22 | 2013-08-14 | 哈尔滨商业大学 | Annular embedded box device for pile foundation test |
CN203403448U (en) * | 2013-08-23 | 2014-01-22 | 南昌永祺科技发展有限公司 | Foundation pile bearing capacity detecting medium exchanging and filling device |
Also Published As
Publication number | Publication date |
---|---|
CN103410178A (en) | 2013-11-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104763436B (en) | A kind of push-bench method of reseptance under high hydraulic pressure complex geological condition and device | |
CN104749081B (en) | Hypotonic soil body hydraulic pressure transfer law test device and its method of testing | |
CN202970602U (en) | Plugging structure of high-rise building deep foundation pit large water volume tube well | |
CN201865113U (en) | Automatic check valve type pressure grouting device | |
CN103556644A (en) | Basement bottom plate dewatering well mouth plugging casing and construction method | |
CN103869054B (en) | Grouting test device with pressure and test method for rock sample | |
CN203514333U (en) | Basement soleplate precipitation well mouth blocking sleeve | |
CN203403448U (en) | Foundation pile bearing capacity detecting medium exchanging and filling device | |
CN103410178B (en) | A kind of pile bearing capacity detects Medium Exchange filling device | |
CN206710037U (en) | Portable cement culvert pipe air-tightness detection device | |
CN104234217B (en) | Light-duty pressure grouting device for overall and grout construction method thereof | |
CN209673308U (en) | The pressure-resistant seal performance test device of submerged tunnel structure | |
CN206289678U (en) | A kind of foundation pile autobalanced detection device with internal slip casting | |
CN205192863U (en) | Turbocharging system integrated form steel pipe hydrostatic test machine fills wetting system | |
CN104833463A (en) | Plastic inspection well leakage test device and detection method | |
CN208040445U (en) | A kind of underground mine use paste body filling bag | |
CN209603160U (en) | A kind of civil air defense constructions and installations pipe well plugging structure | |
CN208701774U (en) | The novel squeezed uplift pile conical hole forming of falling umbrella frame device | |
CN112554238A (en) | Method for plugging and repairing deformation joint of underground structure | |
CN201714128U (en) | Anti-leakage bag component of agricultural field water storage cistern | |
CN206591524U (en) | Load-compensating support meanss and system | |
CN105002910A (en) | Cement mortar grouting tank for prestress long anchor rope grouting and application method | |
CN204630699U (en) | A kind of plastic inspection well leak tightness test device | |
CN203382447U (en) | Tire pressure force application device with annular inner container | |
CN109827724A (en) | A kind of Test on Bridge Loading load vehicle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 330200 No. 6, Fuqi Road, Jinsha Fourth Road, Xiaolan Economic Development Zone, Nanchang City, Jiangxi Province Patentee after: Yongqi Technology Testing Co.,Ltd. Address before: 330200 No. 6, Fuqi Road, Jinsha Fourth Road, Xiaolan Economic Development Zone, Nanchang City, Jiangxi Province Patentee before: NANCHANG YONGQI TECHNOLOGY DEVELOPMENT Co.,Ltd. |