CN103401257A - Multi-source coordinated control method including wind power grid for coping with steep power slope at peak - Google Patents
Multi-source coordinated control method including wind power grid for coping with steep power slope at peak Download PDFInfo
- Publication number
- CN103401257A CN103401257A CN2013103295310A CN201310329531A CN103401257A CN 103401257 A CN103401257 A CN 103401257A CN 2013103295310 A CN2013103295310 A CN 2013103295310A CN 201310329531 A CN201310329531 A CN 201310329531A CN 103401257 A CN103401257 A CN 103401257A
- Authority
- CN
- China
- Prior art keywords
- tau
- period
- blo
- load
- unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The invention provides a multi-source coordinated control method including a wind power grid for coping with a steep power slope at a peak. The method comprises the following steps: judging whether to start a control method or not according to front load and wind power prediction information; calculating the maximum adjustable margin of a BLR-AGC unit; calculating a steep slope rotation standby demand caused by a net load curve steep slope; establishing a load peak steep slope coordination strategy model to give different types of thermal power units and a resource scheduling power generation plan in different future time periods. The coordinated control method provided by the invention facilitates the power grid to go through peak dangerous time periods comprising steep slope events successfully, circuit overload, low frequency decreased load and even large-scale power failure accidents of the power grid, caused by poorer matching of a generator set, can be avoided effectively, and safe and stable running of the power grid is ensured.
Description
Technical field
The present invention relates to the dispatching of power netwoks solution formulation technology under large-scale wind power access background, be specifically related to a kind of multi-source coordination type control method that contains wind-powered electricity generation electrical network reply power abrupt slope, peak period.
Background technology
At present, large-scale wind power accesses the problem of bringing to electric power netting safe running and highlights all the more, some special operation is Japan-China, and wind power continues in peak period to reduce, and can make the relatively former load curve of peak period net load curve (load value checking electricity value) more precipitous.In case the peak period wind power falls suddenly, after with the rapid soaring effect of load, superposeing, larger variation will occur in interior net load in short-term, the abrupt slope of even breaking through the electrical network regulating power limit occur approaching.Abrupt slope is very big change of load curve shape not only, and also there is larger predicated error in itself.During generation abrupt slope, peak period event operating mode, electrical network must accurately calculate the abrupt slope spinning reserve demand that is caused by the abrupt slope predicated error.The abrupt slope prediction is the basis that meritorious coordination strategy is formulated in the electrical network peak period, and it predicts the outcome and has comparatively significantly time, amplitude and rate of change predicated error.Wherein, in certain period, except the amplitude prediction, itself there is certain error ME
1(magnitude error, ME) outward, the time prediction error also can produce extra amplitude predicated error ME
2.ME
1With ME
2Superposition value has formed amplitude predicated error ME that should the period jointly.ME is the principal element that affects electrical network spinning reserve demand, in the net load mathematics prediction under nominal situation, and ME
1With ME
2Amplitude all little, therefore the ME after both stacks is in BLR-AGC unit adjustable range, can all transfer to the BLR-AGC unit and dissolve, and also there is no need clearly to distinguish.Yet in the prediction of abrupt slope, ME
1With ME
2Amplitude may be larger, and the ME after stack probably exceeds BLR-AGC unit adjustable range, to electrical network, arranges spinning reserve to cause very big difficulty, also greatly increased electrical network simultaneously and formulated the difficulty of generating and alternative plan.If scheduling resource and control measures Shortcomings, electrical network probably can't be getted over abrupt slope smoothly, thereby produce power shortage, further bring out even major accident of low-frequency low-voltage load shedding.
Common high wind-powered electricity generation permeability dispatching of power netwoks scheme, lack the consideration to the abrupt slope spinning reserve demand that causes because of the abrupt slope predicated error at present, generally can only the adaptive peak operating mode that during phase, based model for load duration rises, wind-powered electricity generation continues slow decreasing.Under the background that installed capacity of wind-driven power constantly increases, by conventional method, formulate the dispatching of power netwoks scheme, in case wind power occurs in some special operation day, suddenly fall, follow generation net load curve to skyrocket, electrical network is emergent power vacancy event very easily, and safe operation is subject to serious threat.Therefore, under large-scale wind power access background, rationally utilize multiple scheduling resource, the accurate abrupt slope spinning reserve demand that is caused by abrupt slope time prediction error of calculating, and include these factors in novel meritorious scheduling strategy, to system reduce power shortage peak period, to get over dangerous working condition smoothly useful.
Summary of the invention
The object of the present invention is to provide a kind of multi-source coordination type control method that contains wind-powered electricity generation electrical network reply power abrupt slope, peak period.
The object of the present invention is achieved like this: method comprises the following steps:
Step 1: according to the place ahead load and wind-powered electricity generation prediction curve, judge whether control method starts; If the current on-line scheduling period is τ
0, and obtained the place ahead, peak period N
preIndividual pre-scheduling period, N altogether
OnIndividual on-line scheduling period net load predicted value.To the place ahead on-line scheduling period τ
q, the corresponding pre-scheduling period is t
p, the load value that the BLO-AGC unit is followed the trail of
For:
In formula:
For the whole basic point performance number of BLR-AGC unit, Peak climbing generally remains unchanged;
Be that i platform Non-AGC unit (comprising the Non-AGC unit that can participate in online scheduling time level adjusting) is at pre-scheduling period t
pThe power planning value.
Two Rule of judgment that start the abrupt slope control strategy are as follows.
Condition 1: adjacent two on-line scheduling period net load fluctuations have surpassed the peak response ability of BLO-AGC unit.
In formula: σ is the nargin coefficient; r
jIt is j platform BLO-AGC unit regulations speed; Δ τ is on-line scheduling time stage time width; G
BLOFor the set of BLO-AGC unit.
Condition 2: through q on-line scheduling after the period net load accumulation amplification surpassed the peak response ability of BLO-AGC unit.
If the place ahead on-line scheduling period τ
qMeet any one in formula (2) or formula (3) criterion, by τ
Q-1Period is to τ
qThe net load change of period is defined as abrupt slope, starts simultaneously the abrupt slope coordination strategy.
Step 2: calculate the maximum adjustable surplus amount of BLR-AGC unit; After the ultra-short Time level net load measured value of a plurality of operation day is added up with the deviation of on-line scheduling time stage net load predicted value, under high confidence level m, can obtain ultra-short Time level net load and predict that positive and negative deviation is respectively ε
Net, (+)With ε
Net, (-).In certain on-line scheduling period, if exerting oneself, all scheduling resource plans just with the net load predicted value, equate with BLR-AGC unit basic point performance number sum, meet the requirement of on-line scheduling time stage power-balance, the BLR-AGC unit exists and is just regulating surplus S in the period at an on-line scheduling
BLRFor:
Step 3: calculate abrupt slope positive rotation stand-by requirement; If n abrupt slope of net load curve occurs in τ
M-1Period is to τ
mPeriod, and amplitude is
τ
iPeriod (τ
i<τ
m) corresponding abrupt slope positive rotation stand-by requirement amount
For:
The physical meaning of formula (5) is: if τ
iPeriod when generation corresponding to n abrupt slope in window, and should the period corresponding net load change amount less than
This period will exist by n abrupt slope and may arrive in advance and the positive rotation stand-by requirement that produces; If net load change amount that should the period more than or equal to
Should the period by the positive rotation stand-by requirement that produces that arrives in advance of n abrupt slope, be zero.In addition, outside window online period when n abrupt slope occurred, the spinning reserve demand that this abrupt slope produces is also zero.
To the place ahead N
OnN in the individual on-line scheduling period
RAll calculate on individual abrupt slope
After, during due to the generation on these abrupt slopes, window may exist overlappingly, and certain online period may corresponding a plurality of positive rotation stand-by requirements like this.Should get the maximum in these positive rotation stand-by requirements this moment.Final like this place ahead τ that obtains
iThe abrupt slope positive rotation stand-by requirement of period is:
Step 4: set up abrupt slope, peak period control strategy model; The simulated target function is as follows:
In formula: N
OnHop count during for predictable all on-line schedulings of net load; N
preHop count during for predictable all pre-schedulings of net load;
For all BLO-AGC unit operation costs of τ period,
For τ period j platform BLO-AGC unit power output,
For positive rotation reserve level, k
BLO, j, u
BLO, jFor unit cost of electricity-generating and spinning reserve cost;
For τ period interruptible load cost,
For τ period interruptible load uses total amount, k
ILFor the interruptible load average unit cost;
For urgent peaking power source operating cost of τ period,
For urgent peaking power source of τ period uses total amount,
For positive rotation reserve level, k
eps, u
epsCorresponding unit cost of electricity-generating and unit spinning reserve cost;
For the adjustable surplus of τ period BLR-AGC unit in step 2 weakens cost,
For power shortage amount, k
LackFor the power shortage unit cost;
For τ period limited load cost, Δ L
τFor τ period limited load total amount, k
LSFor unit limited load average unit cost.
During for pre-scheduling period t, only participate in the Non-AGC unit (G of pre-scheduling time stage regulation and control
Non1Set) total adjustment cost,
For G
Non1Set aggregate capacity adjustment amount, k
Non1For G
Non1The set unit destroys the average adjusted cost of the original plan.Formula (7) model meets following constraint:
The pre-scheduling period is t
p, the on-line scheduling period is τ
qThe time power-balance be constrained to:
The constraint of on-line scheduling time stage power bound:
In formula:
For the upper and lower limit of BLO-AGC unit power output;
Be respectively the upper and lower limit of Emergency Power power output.
On-line scheduling time stage unit ramping rate constraints:
In formula: r
jFor BLO-AGC unit regulations speed.
The BLR-AGC unit is regulated the nargin constraint:
The positive rotation Reserve Constraint:
Time dimension and the optimized variable of above model are all few, can adopt classical linear programming algorithm to solve, and the rolling that is applicable to control strategy is upgraded.In optimized variable, the interruptible load use amount
Limited load amount Δ L
τWith Non-AGC unit overall adjustment amount
All with the total amount form, provide.If obtain
With Δ L
τUntrivialo solution, by the load significance level of each interruptible load use cost from different nodes, provide interruptible load operational version and each node plan limited load amount.
Give G
Non1In set, the Non-AGC unit output is optimized submodel.
G
Non1The set unit output is optimized submodel:
In formula:
For G
Non1In set, i platform Non-AGC unit is at the power adjustment of pre-scheduling period t, k
Non1, iFor corresponding unit adjustment cost; H is G
Non1The physical constraint of set unit and network congestion constraint.Attention is solving G
Non1Network congestion when constraint of set unit, should using by BLO-AGC power of the assembling unit planned value, Emergency Power power planning value and each node plan limited load amount in the multi-period multi-source Coordination Model in abrupt slope as network known power input source.
Beneficial effect of the present invention is as follows:
(1) while being applicable to high wind-powered electricity generation permeability electrical network net load prediction curve and abrupt slope occurs, the formulation of electric network active scheduling strategy, this coordination strategy has accurately calculated the abrupt slope spinning reserve demand that is caused by abrupt slope time prediction error, rationally utilized number of different types scheduling resource in electrical network, be of value to when electrical network abrupt slope occurs in the net load peak period and get over dangerous periods.
(2) it is in service that the generation schedule that relies on this control strategy to formulate is put into the electrical network actual schedule, can effectively avoid because generating set coordinates poor electrical network generation circuit overload, the even massive blackout accident of UFLS of causing, favourable to guaranteeing power network safety operation.
(3) the cutting load amount that provides according to control strategy, dispatching of power netwoks department can hold in advance climbs the dangerous situation in peak, informs that in advance non-important load user carries out the restriction load and prepares, and reduces the loss.
The accompanying drawing explanation
Fig. 1 is time, amplitude and the rate of change predicated error schematic diagram of abrupt slope prediction;
Fig. 2 is control flow chart of the present invention;
Fig. 3 is net load predicted value figure.
Embodiment
The invention will be further described for example below in conjunction with accompanying drawing.
Embodiment 1: get certain province's actual electric network year load data this paper control strategy is analyzed.The Non-AGC unit that this electrical network has 4 BLR-AGC units, 15 can only participate in the pre-scheduling time stage to regulate, 1 can participate in online scheduling time level Non-AGC unit (being numbered G1), 3 identical BLO-AGC units of physical characteristic (equivalence is to be numbered G2 after 1 unit) and 1 urgent peaking power source (being numbered G3) of regulating; The wind-powered electricity generation total installation of generating capacity is 1260MW; The unit partial parameters is in Table 1, and the parameters such as operation of power networks situation are in Table 2.Following 2 pre-scheduling periods, totally 6 on-line scheduling period net load predicted values are shown in Pat1 curve in Fig. 3.Current being in of electrical network climbed the peak later stage, and fired power generating unit integral body is exerted oneself and is in a high position.
Table 1 unit parameter
? | G1 | G2 | G3 | Interruptible load |
Maximum size (MW) | 800 | 600 | 40 | 10 |
Lower bound of capacity (MW) | 460 | 300 | 10 | 0 |
Power initial value (MW) | 490 | 480 | -- | -- |
Regulations speed (MW/min) | 6 | 16 | -- | -- |
K (unit/MW) | 1400 | 300 | 3000 | 100 |
U (unit/MW) | 1000 | 150 | 1600 | -- |
Table 2 electrical network parameter
Parameter | Numerical value | Parameter | Numerical value |
k lack1(unit/MW/5min) | 6000 | S BLR(MW) | 20 |
k LS(unit/MW/5min) | 30000 | |
2 |
β(MW/Hz) | -1200 | ? | ? |
According to the place ahead period net load prediction case, find that period 0-1, period 1-2, period 2-3, the fluctuation of period 5-6 net load meet the entry condition 1 of abrupt slope control strategy, period 3-4 and the fluctuation of period 4-5 net load meet the entry condition 2 of control strategy, net load change is violent, the abrupt slope control strategy starts immediately, obtains unit generation plan and alternative plan in Table 3.
Unit generation and the alternative plan of table 3Pat1
Visible by table 3 result, G1 and G2 have reached the regulations speed limit or the unit capacity upper limit in a plurality of periods.Abrupt slope spinning reserve demand reached maximum 2 o'clock periods, was 68MW.This is mainly that time prediction error by period 2-3 causes, period 2-3 net load change reaches maximum 153MW.When the pre-scheduling period started, the Non-AGC unit was by changing former generation schedule, reduced G1 and G2 in the period 1 force level that goes out with the period 4, make G1 and G2 can be in getting over the abrupt slope process all one's effort Pan Feng.At the most violent period 2-3 of net load change, when G3 reached peak power output 40MW, the BLR-AGC unit had used the adjusting surplus of 13MW, had avoided the cutting load risk and had getted over smoothly all abrupt slopes.
Embodiment 2: identical with all parameters of electrical network in embodiment 1, only net load change is more violent, in 2-3 period and 3-4 period, has increased 10MW in respectively than embodiment 1, sees Pat2 curve in Fig. 3.The Pat2 generation schedule is in Table 4.
Unit generation and the alternative plan of table 4Pat2
With Pat1, compare, Pat2 is affected by more violent net load change, 2 o'clock periods, will meet the abrupt slope spinning reserve demand up to 78MW, and this forces G2 to compare Pat1 in the period 2 will prepare more spinning reserve.In addition, the period 3, after the adjusting surplus of using up urgent peaking power source and BLR-AGC unit, must just can get over this period by limited load 3MW smoothly.Visible from the Pat2 result, rely on multiple scheduling resource and control measures cooperation, although electrical network has been transferred multiple expensive scheduling resource, and sacrificed the adjusting surplus of BLR-AGC unit, but at utmost reduced electrical network limited load amount, at utmost reduce overall loss guaranteeing that electrical network is under the safety operation level prerequisite, had obvious economic benefit.
Claims (1)
1. contain the multi-source coordination type control method on wind-powered electricity generation electrical network reply power abrupt slope, peak period, it is characterized in that, method is as follows:
Step 1: according to the place ahead load and wind-powered electricity generation prediction curve, judge whether control method starts; The current on-line scheduling period is τ
0, and obtained the place ahead, peak period N
preIndividual pre-scheduling period, N altogether
OnIndividual on-line scheduling period net load predicted value, to the place ahead on-line scheduling period τ
q, the corresponding pre-scheduling period is t
p, the load value that the BLO-AGC unit is followed the trail of
For:
In formula:
For the whole basic point performance number of BLR-AGC unit, Peak climbing remains unchanged;
Be that i platform Non-AGC unit is at pre-scheduling period t
pThe power planning value;
Two Rule of judgment that start the abrupt slope control method are as follows:
Condition 1: adjacent two on-line scheduling period net load fluctuations have surpassed the peak response ability of BLO-AGC unit,
In formula: σ is the nargin coefficient; r
jIt is j platform BLO-AGC unit regulations speed; Δ τ is on-line scheduling time stage time width; G
BLOFor the set of BLO-AGC unit;
Condition 2: through q on-line scheduling after the period net load accumulation amplification surpassed the peak response ability of BLO-AGC unit,
The place ahead on-line scheduling period τ
qMeet any one in formula (2) or formula (3) criterion, by τ
Q-1Period is to τ
qThe net load change of period is defined as abrupt slope, starts simultaneously control method;
Step 2: calculate the maximum adjustable surplus amount of BLR-AGC unit; After the ultra-short Time level net load measured value of a plurality of operation day is added up with the deviation of on-line scheduling time stage net load predicted value, under high confidence level m, obtain ultra-short Time level net load and predict that positive and negative deviation is respectively ε
Net, (+)With ε
Net, (-)In certain on-line scheduling period, all scheduling resource plans are exerted oneself and just with the net load predicted value, are equated with BLR-AGC unit basic point performance number sum, meet the requirement of on-line scheduling time stage power-balance, the BLR-AGC unit exists and is just regulating surplus S in the period at an on-line scheduling
BLRFor:
Step 3: calculate abrupt slope positive rotation stand-by requirement; N abrupt slope of net load curve occurs in τ
M-1Period is to τ
mPeriod, and amplitude is
τ
iPeriod (τ
i<τ
m) corresponding abrupt slope positive rotation stand-by requirement amount
For:
The physical meaning of formula (5) is: if τ
iPeriod when generation corresponding to n abrupt slope in window, and should the period corresponding net load change amount less than
This period will exist by n abrupt slope and may arrive in advance and the positive rotation stand-by requirement that produces; If net load change amount that should the period more than or equal to
Should the period by the positive rotation stand-by requirement that produces that arrives in advance of n abrupt slope, be zero; In addition, outside window online period when n abrupt slope occurred, the spinning reserve demand that this abrupt slope produces is also zero;
To the place ahead N
OnN in the individual on-line scheduling period
RAll calculate on individual abrupt slope
After, should get the maximum in these positive rotation stand-by requirements, final like this place ahead τ that obtains this moment
iThe abrupt slope positive rotation stand-by requirement of period is:
Step 4: set up abrupt slope, peak period control strategy model; The simulated target function is as follows:
In formula: N
OnHop count during for predictable all on-line schedulings of net load; N
preHop count during for predictable all pre-schedulings of net load;
For all BLO-AGC unit operation costs of τ period,
For τ period j platform BLO-AGC unit power output,
For positive rotation reserve level, k
BLO, j, u
BLO, jFor unit cost of electricity-generating and spinning reserve cost;
For τ period interruptible load cost,
For τ period interruptible load uses total amount, k
ILFor the interruptible load average unit cost;
For urgent peaking power source operating cost of τ period,
For urgent peaking power source of τ period uses total amount,
For positive rotation reserve level, k
eps, u
epsCorresponding unit cost of electricity-generating and unit spinning reserve cost;
For the adjustable surplus of τ period BLR-AGC unit in step 2 weakens cost,
For power shortage amount, k
LackFor the power shortage unit cost;
For τ period limited load cost, Δ L
τFor τ period limited load total amount, k
LSFor unit limited load average unit cost.
During for pre-scheduling period t, only participate in the Non-AGC unit (G of pre-scheduling time stage regulation and control
Non1Set) total adjustment cost,
For G
Non1Set aggregate capacity adjustment amount, k
Non1For G
Non1The set unit destroys the average adjusted cost of the original plan; Formula (7) model meets following constraint:
The pre-scheduling period is t
p, the on-line scheduling period is τ
qThe time power-balance be constrained to:
In formula:
For t
pPeriod G
Non1In set, unit is worth in the original plan, is known quantity;
The constraint of on-line scheduling time stage power bound:
In formula:
For the upper and lower limit of BLO-AGC unit power output;
Be respectively the upper and lower limit of Emergency Power power output;
On-line scheduling time stage unit ramping rate constraints:
In formula: r
jFor BLO-AGC unit regulations speed;
The BLR-AGC unit is regulated the nargin constraint:
The positive rotation Reserve Constraint:
The time dimension of above model and optimized variable adopt classical linear programming algorithm to solve, in optimized variable, and the interruptible load use amount
Limited load amount Δ L
τWith Non-AGC unit overall adjustment amount
All with the total amount form, provide; If obtain
With Δ L
τUntrivialo solution, by the load significance level of each interruptible load use cost from different nodes, provide interruptible load operational version and each node plan limited load amount;
Give G
Non1In set, the Non-AGC unit output is optimized submodel;
G
Non1The set unit output is optimized submodel:
In formula:
For G
Non1In set, i platform Non-AGC unit is at the power adjustment of pre-scheduling period t, k
Non1, iFor corresponding unit adjustment cost; H is G
Non1The physical constraint of set unit and network congestion constraint; Solving G
Non1Network congestion when constraint of set unit, should using by BLO-AGC power of the assembling unit planned value, Emergency Power power planning value and each node plan limited load amount in the multi-period multi-source Coordination Model in abrupt slope as network known power input source.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310329531.0A CN103401257B (en) | 2013-08-01 | 2013-08-01 | Multi-source coordinated control method including wind power grid for coping with steep power slope at peak |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310329531.0A CN103401257B (en) | 2013-08-01 | 2013-08-01 | Multi-source coordinated control method including wind power grid for coping with steep power slope at peak |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103401257A true CN103401257A (en) | 2013-11-20 |
CN103401257B CN103401257B (en) | 2015-06-17 |
Family
ID=49564830
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310329531.0A Expired - Fee Related CN103401257B (en) | 2013-08-01 | 2013-08-01 | Multi-source coordinated control method including wind power grid for coping with steep power slope at peak |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103401257B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103618340A (en) * | 2013-11-27 | 2014-03-05 | 哈尔滨工业大学 | Reserve optimized decision-making method coping with rapid ramping event |
CN104537428A (en) * | 2014-12-05 | 2015-04-22 | 天津大学 | Method for evaluating economic operation considering wind power integration uncertainty |
CN104810850A (en) * | 2015-04-15 | 2015-07-29 | 哈尔滨工业大学 | Non-critical load continuously adjustable DC (direct current) micro-grid off-grid and on-grid unified and coordinated control method |
CN108110806A (en) * | 2018-01-26 | 2018-06-01 | 国网辽宁省电力有限公司 | A kind of dispatching method of New-energy power system under the method for operation of Abnormal regulation domain |
CN112288130A (en) * | 2020-09-24 | 2021-01-29 | 国网内蒙古东部电力有限公司 | New energy consumption calculation method based on two-stage multi-objective optimization |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101453187A (en) * | 2008-12-29 | 2009-06-10 | 浙江大学 | Wind turbine control reference signal detection method for unsymmetrical failure of electric grid |
WO2011136204A1 (en) * | 2010-04-28 | 2011-11-03 | 通研電気工業株式会社 | Power grid control system, and power grid control method |
US20120139576A1 (en) * | 2010-12-03 | 2012-06-07 | Thomas Dreyer | Arrangement and method for testing an electric power generation system |
CN102709926A (en) * | 2012-06-28 | 2012-10-03 | 哈尔滨工业大学 | Rotary hot spare dispatching method in construction of intelligent power grid on basis of relevance vector machine |
CN103151803A (en) * | 2013-03-14 | 2013-06-12 | 吉林省电力有限公司电力科学研究院 | Method for optimizing wind power system-contained unit and backup configuration |
-
2013
- 2013-08-01 CN CN201310329531.0A patent/CN103401257B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101453187A (en) * | 2008-12-29 | 2009-06-10 | 浙江大学 | Wind turbine control reference signal detection method for unsymmetrical failure of electric grid |
WO2011136204A1 (en) * | 2010-04-28 | 2011-11-03 | 通研電気工業株式会社 | Power grid control system, and power grid control method |
US20120139576A1 (en) * | 2010-12-03 | 2012-06-07 | Thomas Dreyer | Arrangement and method for testing an electric power generation system |
CN102709926A (en) * | 2012-06-28 | 2012-10-03 | 哈尔滨工业大学 | Rotary hot spare dispatching method in construction of intelligent power grid on basis of relevance vector machine |
CN103151803A (en) * | 2013-03-14 | 2013-06-12 | 吉林省电力有限公司电力科学研究院 | Method for optimizing wind power system-contained unit and backup configuration |
Non-Patent Citations (2)
Title |
---|
张娜等: "含风电***的多级机组组合协调制定策略", 《电力***自动化》, vol. 37, no. 11, 10 June 2013 (2013-06-10) * |
苏鹏等: "含风电的***最优旋转备用的确定", 《电网技术》, vol. 34, no. 12, 31 December 2010 (2010-12-31) * |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103618340A (en) * | 2013-11-27 | 2014-03-05 | 哈尔滨工业大学 | Reserve optimized decision-making method coping with rapid ramping event |
CN103618340B (en) * | 2013-11-27 | 2015-06-17 | 哈尔滨工业大学 | Reserve optimized decision-making method coping with rapid ramping event |
CN104537428A (en) * | 2014-12-05 | 2015-04-22 | 天津大学 | Method for evaluating economic operation considering wind power integration uncertainty |
CN104537428B (en) * | 2014-12-05 | 2017-12-15 | 天津大学 | One kind meter and the probabilistic economical operation appraisal procedure of wind power integration |
CN104810850A (en) * | 2015-04-15 | 2015-07-29 | 哈尔滨工业大学 | Non-critical load continuously adjustable DC (direct current) micro-grid off-grid and on-grid unified and coordinated control method |
CN108110806A (en) * | 2018-01-26 | 2018-06-01 | 国网辽宁省电力有限公司 | A kind of dispatching method of New-energy power system under the method for operation of Abnormal regulation domain |
CN108110806B (en) * | 2018-01-26 | 2022-06-21 | 国网辽宁省电力有限公司 | Scheduling method of new energy power system in abnormal regulation and control domain operation mode |
CN112288130A (en) * | 2020-09-24 | 2021-01-29 | 国网内蒙古东部电力有限公司 | New energy consumption calculation method based on two-stage multi-objective optimization |
CN112288130B (en) * | 2020-09-24 | 2023-09-05 | 国网内蒙古东部电力有限公司 | New energy consumption calculation method based on two-stage multi-objective optimization |
Also Published As
Publication number | Publication date |
---|---|
CN103401257B (en) | 2015-06-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101931241B (en) | Wind farm grid-connected coordination control method | |
US9124138B2 (en) | Power grid operation control system, device, and method | |
CN103023074B (en) | Active real-time scheduling method for large power grid based on model predictive control | |
CN103219751B (en) | Control method of active power of clustered wind power plants | |
CN104882905B (en) | A kind of new energy for considering transient security constraint receives capability assessment method | |
CN102545268B (en) | Large grid active power real-time control method in restricted wind power state | |
CN109687530A (en) | A kind of power grid mixing rolling scheduling method considering obstruction and energy storage tou power price | |
CN103401257B (en) | Multi-source coordinated control method including wind power grid for coping with steep power slope at peak | |
CN104795846A (en) | Optimized operation method of pumped-storage power station and wind power combined system | |
CN104167730A (en) | Real-time cascade hydropower stations dispatching optimizing method under complex restrictions | |
CN102075014A (en) | Large grid real-time scheduling method for accepting access of wind power | |
CN103762617B (en) | Wind power plant optimal operation method with wind generation set operation health degree taken into consideration | |
CN104037805B (en) | A kind of photovoltaic plant taking into account power system security constraints can power generation margin distribution method | |
CN105162149A (en) | Fuzzy adaptive control based method for tracking output of power generation plan of light storage system | |
CN102184472A (en) | Wind, water and fire united dispatching method based on power grid dispatching side demand | |
CN109245184B (en) | Multi-source cooperative active control method suitable for multi-type constraint and multi-control interval | |
CN107404127A (en) | Consider the wind-powered electricity generation Robust Interval trace scheduling method that Multiple Time Scales are coordinated | |
CN103050998B (en) | Thermal power system dynamic scheduling method of wind power integration | |
CN104810863A (en) | Generator set active power real-time dispatching method considering wind power prediction error | |
CN108054790A (en) | The active method for real-time optimization control of wind light generation cluster based on prediction output Approach by inchmeal | |
CN107528348A (en) | One kind is based on the probabilistic step power station load adjustment method of water | |
CN103812112A (en) | Regional power grid automatic voltage control (AVC) method | |
CN103326394B (en) | Multi-scene probability optimal scheduling method for calculating wind electricity volatility | |
CN104239966A (en) | Active power distribution network operating method based on electricity cost differentiation | |
CN105826946A (en) | Power distribution network dynamic reactive power optimization method for large-scale photovoltaic access |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150617 |