CN103321239B - A kind of rig basis - Google Patents
A kind of rig basis Download PDFInfo
- Publication number
- CN103321239B CN103321239B CN201310260067.4A CN201310260067A CN103321239B CN 103321239 B CN103321239 B CN 103321239B CN 201310260067 A CN201310260067 A CN 201310260067A CN 103321239 B CN103321239 B CN 103321239B
- Authority
- CN
- China
- Prior art keywords
- elongated slot
- steel plate
- rig
- basis
- foot
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Earth Drilling (AREA)
Abstract
The present invention relates to a kind of rig basis.At the oriented underground elongated slot of freezing hole periphery, the left and right sidewall of elongated slot there is masonry walls, the ground of described elongated slot periphery is covered with foot-operated steel plate.Its basis is steady, drilling quality is high, and use cost is low.
Description
Technical field
The present invention relates to a kind of rig basis, the particularly basis of inclined shaft freezing boring drill.
Background technology
Freezing borehole construction is the important working procedure freezing Refrigeration Engineering construction early stage, and the quality of freezing borehole construction quality directly affects quality and the economic benefit of whole freezing engineering.The rig used in freezing borehole construction must lay rig basis, in the special sinking shaft construction freezing method that eighties of last century the fifties is introduced by the former Soviet Union, freezing borehole is constructed, rig basis for 37 lime earth rammed levelling after, lay pillow rail, be rig basis, rig can slide above again.After the eighties, be improved to 37 lime earth add concrete foundation.Both defects are that cost is high, the engineering time long, remove difficulty greatly, time-consuming.Particularly in inclined shaft freezing drilling construction, the boring of construction is more shallow, and the 37 lime earth of rig adds concrete foundation horizontal range speciality.
Summary of the invention
In order to overcome the shortcoming of prior art, the invention provides a kind of rig basis, its basis is steady, drilling quality is high, and use cost is low.
The present invention solves the technical scheme that its technical problem takes: at the oriented underground elongated slot of freezing hole periphery, the left and right sidewall of elongated slot has masonry walls, the ground of described elongated slot periphery is covered with foot-operated steel plate.
The present invention has following advantages: 1), rig constructs steadily on steel plate basis; 2), occur that drilling slurry retaining wall is bad and step on sky phenomenon after, because the globality of steel plate is fine, there will not be rig crooked, improve drilling construction quality; 3), drilling-machine shifter time, resistance is little, and speed is fast; 4), civilized construction environment is good; 5) environment pollution and waste discharge, is decreased; 6), foot-operated steel plate can recycle, and greatly reduces use cost.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, this present invention is further illustrated.
Fig. 1 is front view of the present invention;
Fig. 2 is top view of the present invention.
Detailed description of the invention
As shown in Figure 1, 2, at the oriented underground elongated slot 4 of freezing hole 5 periphery, the left and right sidewall of elongated slot 4 there is masonry walls 3, the ground of described elongated slot 4 periphery is covered with foot-operated steel plate 2.
The ground on the limit, top of described elongated slot 4 is covered with auxiliary steel plate 6.
Described foot-operated steel plate 2 is of a size of long 12m, wide 2m, thick 25mm.
The size of described auxiliary steel plate 6 is identical with foot-operated steel plate 2.
Claims (3)
1. a rig basis, it is characterized in that: the oriented underground elongated slot (4) of freezing hole (5) periphery, the left and right sidewall of elongated slot (4) there is masonry walls (3), the ground of described elongated slot (4) periphery is covered with foot-operated steel plate (2); The ground on the limit, top of described elongated slot (4) is covered with auxiliary steel plate (6).
2. rig basis according to claim 1, is characterized in that: described foot-operated steel plate (2) is of a size of long 12m, wide 2m, thick 25mm.
3. rig basis according to claim 1, is characterized in that: the size of described auxiliary steel plate (6) is identical with foot-operated steel plate (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310260067.4A CN103321239B (en) | 2013-06-26 | 2013-06-26 | A kind of rig basis |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310260067.4A CN103321239B (en) | 2013-06-26 | 2013-06-26 | A kind of rig basis |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103321239A CN103321239A (en) | 2013-09-25 |
CN103321239B true CN103321239B (en) | 2015-09-30 |
Family
ID=49190262
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310260067.4A Active CN103321239B (en) | 2013-06-26 | 2013-06-26 | A kind of rig basis |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103321239B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112813763A (en) * | 2021-01-05 | 2021-05-18 | 中国十七冶集团有限公司 | Bored pile formed hole peripheral bearing steel base plate and using method thereof |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5526304A (en) * | 1978-08-09 | 1980-02-25 | Ohbayashigumi Ltd | Vibration-proof machine foundation |
CN101225740A (en) * | 2008-01-29 | 2008-07-23 | 中煤第一建设公司特殊凿井处 | Annular filling method for space between freezing pipe and surrounding rock |
CN101487261A (en) * | 2009-01-21 | 2009-07-22 | 浙江中成建工集团有限公司 | Profiled bar freezing wall foundation ditch combined enclosure method and its structure |
CN101696578A (en) * | 2009-09-28 | 2010-04-21 | 中铁八局集团第一工程有限公司 | Construction method for pouring foundations of main pylon piers of bridge on deep water inclined runway |
CN201459755U (en) * | 2009-08-07 | 2010-05-12 | 北京首钢建设集团有限公司 | Bolt sleeve for construction of equipment foundation |
CN102268871A (en) * | 2010-06-03 | 2011-12-07 | 中国建筑第七工程局有限公司 | Construction method of turnover platform for underwater pile foundation of bridge |
CN102619522A (en) * | 2012-03-20 | 2012-08-01 | 天津城建隧道股份有限公司 | Construction method for subway contact passage |
CN102777185A (en) * | 2012-05-15 | 2012-11-14 | 张晓岩 | Inclined well shaft construction technology |
CN202830966U (en) * | 2012-03-26 | 2013-03-27 | 秦大春 | Foundation for ground composite module type drilling machine |
-
2013
- 2013-06-26 CN CN201310260067.4A patent/CN103321239B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5526304A (en) * | 1978-08-09 | 1980-02-25 | Ohbayashigumi Ltd | Vibration-proof machine foundation |
CN101225740A (en) * | 2008-01-29 | 2008-07-23 | 中煤第一建设公司特殊凿井处 | Annular filling method for space between freezing pipe and surrounding rock |
CN101487261A (en) * | 2009-01-21 | 2009-07-22 | 浙江中成建工集团有限公司 | Profiled bar freezing wall foundation ditch combined enclosure method and its structure |
CN201459755U (en) * | 2009-08-07 | 2010-05-12 | 北京首钢建设集团有限公司 | Bolt sleeve for construction of equipment foundation |
CN101696578A (en) * | 2009-09-28 | 2010-04-21 | 中铁八局集团第一工程有限公司 | Construction method for pouring foundations of main pylon piers of bridge on deep water inclined runway |
CN102268871A (en) * | 2010-06-03 | 2011-12-07 | 中国建筑第七工程局有限公司 | Construction method of turnover platform for underwater pile foundation of bridge |
CN102619522A (en) * | 2012-03-20 | 2012-08-01 | 天津城建隧道股份有限公司 | Construction method for subway contact passage |
CN202830966U (en) * | 2012-03-26 | 2013-03-27 | 秦大春 | Foundation for ground composite module type drilling machine |
CN102777185A (en) * | 2012-05-15 | 2012-11-14 | 张晓岩 | Inclined well shaft construction technology |
Also Published As
Publication number | Publication date |
---|---|
CN103321239A (en) | 2013-09-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103195365B (en) | A kind of rotary drilling rig ground consisting of hard rock classification drilling construction technique | |
CN102041807B (en) | Dense hole preliminary loosening hard plagioclase construction technique | |
CN105178970A (en) | Horizontal oriented spiral drilling machine | |
CN106381865B (en) | A kind of brill milling combination engineering method applied to hard rock grooving | |
CN104047543B (en) | A kind of construction method of large diameter drill hole pile pore-forming in high intensity lithostratigraphy | |
CN106759282B (en) | A kind of mechanical hole building method of super-large diameter hard rock bored concrete pile half | |
CN112664159A (en) | Horizontal directional leaking stoppage method for small-sized cracks of coal seam roof | |
CN102777185A (en) | Inclined well shaft construction technology | |
CN103834372B (en) | A kind of deep gurmy roadway surrounding rock pre grouting from the surface of km modified boring work mud | |
CN103321239B (en) | A kind of rig basis | |
CN102817361B (en) | Double bushing top cover for broken rock curtain grouting and construction method of double bushing top cover | |
CN104947664A (en) | Thick stone sea-filling layer prestressing force high-strength concrete square pile construction method | |
CN108396759B (en) | Deviation rectifying construction method for inclined open caisson under different soil conditions | |
CN204212150U (en) | The cross type pile of bottom prism-shaped | |
CN103628814A (en) | Dual-purpose concentric pipe-along drilling tool | |
CN101701459A (en) | Method for processing soft soil foundation of intertidal belt to form construction working face | |
CN103628500B (en) | Continuous wall trench underground construction method in Fu Shui circle gravel stratum | |
CN202659174U (en) | Single-cone single-screw twist drill | |
CN204252131U (en) | The casing device of pore-forming in a kind of building lot | |
CN204252120U (en) | The construction equipment of concrete pile | |
CN102644285B (en) | Anchor cable is holed anti-collapse hole construction method | |
CN203334951U (en) | Down hole hammer | |
CN202659153U (en) | Push plate type cylindrical drill | |
CN104032736A (en) | Construction method of cement-soil mixed pile in coral-reef limestone stratum | |
CN204530700U (en) | A kind of civil engineering roofbolt construction arrangement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |