CN103321212A - 一柱一桩后插法施工工艺 - Google Patents

一柱一桩后插法施工工艺 Download PDF

Info

Publication number
CN103321212A
CN103321212A CN2013101989416A CN201310198941A CN103321212A CN 103321212 A CN103321212 A CN 103321212A CN 2013101989416 A CN2013101989416 A CN 2013101989416A CN 201310198941 A CN201310198941 A CN 201310198941A CN 103321212 A CN103321212 A CN 103321212A
Authority
CN
China
Prior art keywords
steel pipe
pipe column
correcting device
verticality
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101989416A
Other languages
English (en)
Inventor
刘加峰
吴洁妹
李耀良
郭宏斌
张国磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI FOUNDATION ENGINEERING Co Ltd
Original Assignee
SHANGHAI FOUNDATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI FOUNDATION ENGINEERING Co Ltd filed Critical SHANGHAI FOUNDATION ENGINEERING Co Ltd
Priority to CN2013101989416A priority Critical patent/CN103321212A/zh
Publication of CN103321212A publication Critical patent/CN103321212A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

本发明涉及一种一柱一桩后插法施工工艺,其步骤是:1)移走钻机,清理孔口;2)在护筒内安装导向纠偏装置;3)安装液压调直设备;4)吊运钢管柱,于调直架孔口位置对中;5)通过导向纠偏装置限位,利用两层抱箍将钢管柱下放至下部砼面;6)调整钢管柱垂直度;7)将钢管柱下放至设计深度;8)再次测量钢管柱垂直度;9)钢管柱孔口固定,移走调直架;10)割除工具管、下导管、浇灌砼至设计高度;11)桩孔回填、注浆。本发明可以有效地降低操作难度,提高调直精度及效率;下部支承桩和上部钢管柱同步施工,能有效地节省时间,提高施工的效率,避免了置换钢管柱底部及埋深部位低标号混凝土而浪费的高标号混凝土,从而有效地节约混凝土成本。

Description

一柱一桩后插法施工工艺
技术领域
本发明涉及一种通过插管调直机对一柱一桩施工中上部钢管柱***、调垂的施工工艺。
背景技术
随着城市的不断发展,土地资源紧张的情况日渐显著。为保障施工用地利用率最大化,往往以逆做盖挖法为施工措施,即将地下室顶板作为挖土机械作业平台及材料堆放场地。在盖挖逆作法基坑施工中为节省造价,将支护体系立柱桩与结构柱合二为一使用,即立柱桩上部的钢立柱不割除,结构回筑时在钢立柱外包裹钢筋混凝土做永久性结构柱使用。
一柱一桩的施工垂直度要求比一般的支护体系立柱桩高出许多,尤其是基坑开挖深度近30m的超深、超大基坑,设计一般要求钢立柱的垂直度控制在1/500-1/600,如何确保钢立柱的***垂直度,减小由于后期钢立柱的垂直偏差造成的必须通过结构柱直径超标扩大来满足竖向承载力要求。目前尚缺乏一种合理高效的施工方法,既能高效的***钢立柱到下部支撑桩中一定深度,又能确保钢立柱的垂直度达到设计要求,且达标率比较低。常规的地面调直架调垂方法费时、费力、垂直度控制效果不佳且钢立柱偏位普遍。
发明内容
本发明是要解决现有一柱一桩钢管柱施工精度低、施工效率低下、材料损耗较大的技术问题,而提供一种一柱一桩后插法施工工艺。
为实现上述目的,本发明是通过以下技术方案实现的:
一种一柱一桩后插法施工工艺,其步骤是:
1)移走钻机,清理孔口
在下部支承桩浇灌完成之后,移走钻机,清理孔口,并在孔口周边铺设钢板;
2)在护筒内安装导向纠偏装置
在6m长钢护筒内安装四副导向纠偏装置,导向纠偏装置成垂直布置并固定牢固;
3)安装液压调直设备
  在安装好导向纠偏装置之后,安装液压调直设备,将液压调直设备的底座和上部主机分两次吊装,分别定位之后对整个液压调直设备进行调平、对中;
    4)吊运钢管柱,于调直架孔口位置对中
     用吊机对钢管柱进行吊运,在调直架上方,待钢管柱平稳后缓缓下放至调直架孔口位置并调整钢管柱对中;
    5)通过导向纠偏装置限位,利用两层抱箍将钢管柱下放至下部砼面
钢管柱调整好位置对中下放后,移动钢护筒上的液压纠偏装置,使液压纠偏装置抱紧钢管柱,固定好以对钢管柱的行程进行限位,移动上下两层抱箍将钢管柱下放至下部砼面;钢管柱下放过程中,在钢管柱柱身不同位置安设二部吸附式测斜仪;
    6)调整钢管柱垂直度
钢管柱下放至砼面以后,利用测斜仪和抱箍、导向纠偏装置纠正钢管柱偏位,从而调整钢管柱至设计垂直度;
    7)将钢管柱下放至设计深度;
     在钢管柱调整至设计垂直度后固定好导向纠偏装置从而对钢管柱行程进行限位,利用抱箍按照既有路线将钢管柱下放至设计深度;
8)再次测量钢管柱垂直度;
在钢管柱下放到设计深度后,通过测斜仪再次测量钢管柱垂直度,确保钢管柱垂直度符合设计要求;若垂直度过大,则通过导向纠偏装置及抱箍继续调整至符合要求;
    9)钢管柱孔口固定,移走调直架
     在桩位中心、钢管柱垂直度、钢管柱下放深度均符合设计及规范要求后,将钢管柱孔口进行固定,然后移走调直架;
    10)割除工具管、下导管、浇灌砼至设计高度
     从钢管柱内下放相应管径的导管,将设计标号的砼通过对应管径的导管利用干浇法浇灌至设计高度;
    11)桩孔回填、注浆
     待钢管柱内混凝土初凝后,在钢管柱两侧通过人工在不对钢管柱产生扰动的情况下均匀回填沙石至孔口,回填密实之后对周边回填部分进行注浆。
本发明的有益效果是:本发明通过对原有一柱一桩调直设备及施工流程的改进和优化,有效地提高了设备对钢管柱的限位、导向、调直效果,使整个钢管柱调直流程简捷、方便,且可以与一柱一桩支承桩同步施工,弱化了一柱一桩施工的局限条件,提高了设备的利用效率,从而大大的提高了一柱一桩钢管柱施工的效率和精度,节约了施工成本。
附图说明
图1是孔口清理、铺设钢板示意图;
图2是安装导向纠偏装置示意图;
图3是调直架底座及上部主机吊放及对中调平示意图;
其中:(a)是调直架底座吊放及对中调平示意图,(b)是上部主机吊放拼接示意图,(c)液压调直设备调平、对中示意图;
图4是钢管柱吊放对中示意图;
图5是利用纠偏装置限位,将钢管柱下放至砼面示意图;
图6是调整钢管柱垂直度示意图;
图7是钢管柱***至设计深度调垂示意图;
图8是钢管柱孔口固定、移走调直架示意图;
图9是混凝土浇灌完毕示意图;
图10是桩孔回填示意图。
具体实施方式
下面结合附图与实施例对本发明作进一步说明。
如图1至图10所示,本发明的一柱一桩后插法施工工艺,其施工步骤是:
1)移走钻机,清理孔口
在下部支承桩浇灌完成之后,移走钻机,清理孔口,并在孔口周边铺设钢板1,见图1;
2)在护筒内安装导向纠偏装置
在6m长钢护筒内安装四副导向纠偏装置2,导向纠偏装置成垂直布置并固定牢固,见图2;
    3)安设HDC液压调直设备,定位、调平、对中
     如图3所示,在安装好导向纠偏装置之后,安设HDC液压调直设备,HDC液压调直设备将底座3(图3a)及上部主机4分两次吊装(图3b),分别定位之后对整个设备进行调平、对中(图3c);
    4)吊运钢管柱,于调直架孔口位置对中
     合理选择吊机对钢管柱5进行吊运,在调直架上方,待钢管柱平稳后缓缓下放至调直架孔口位置并调整钢管柱对中,见图4;
    5)通过导向纠偏装置限位,利用两层抱箍将钢管柱下放至下部砼面;
钢管柱5调整好位置对中下放后,移动钢护筒上的液压纠偏装置2,使液压纠偏装置2抱紧钢管柱5。固定好以对钢管柱5的行程进行限位,移动上下两层抱箍将钢管柱5下放至下部砼面;钢管柱5下放过程中,在钢管柱柱身不同位置安设二部吸附式测斜仪6,见图5;
    6)调整钢管柱垂直度
钢管柱5下放至砼面以后,利用测斜仪6和抱箍7、导向纠偏装置2纠正钢管柱5偏位,从而调整钢管柱5至设计垂直度,见图6;
    7)将钢管柱下放至设计深度
     在钢管柱5调整至设计垂直度后固定好导向纠偏装置2从而对钢管柱5行程进行限位,利用抱箍按照既有路线将钢管柱5下放至设计深度,见图7;
8)再次测量钢管柱垂直度
在钢管柱下放到设计深度后,通过测斜仪6再次测量钢管柱垂直度,确保钢管柱垂直度符合设计要求;若垂直度过大,则通过导向纠偏装置2及抱箍7继续调整至符合要求;
    9)钢管柱孔口固定,移走调直架
     在桩位中心、钢管柱垂直度、钢管柱下放深度均符合设计及规范要求后,将钢管柱孔口进行固定,然后移走调直架,见图8;
    10)割除工具管、下导管、浇灌砼至设计高度
     从钢管柱内下放相应管径的导管,将设计标号的砼通过对应管径的导管利用干浇法浇灌至设计高度,见图9;
    11)桩孔回填、注浆;
     待钢管柱内混凝土初凝后,在钢管柱两侧通过人工在不对钢管柱产生扰动的情况下均匀回填沙石至孔口,回填密实之后对周边回填部分进行注浆,见图10。

Claims (1)

1.一种一柱一桩后插法施工工艺,其特征在于,其步骤是:
1)移走钻机,清理孔口
在下部支承桩浇灌完成之后,移走钻机,清理孔口,并在孔口周边铺设钢板;
2)在护筒内安装导向纠偏装置
在6m长钢护筒内安装四副导向纠偏装置,导向纠偏装置成垂直布置并固定牢固;
3)安装液压调直设备
  在安装好导向纠偏装置之后,安装液压调直设备,将液压调直设备的底座和上部主机分两次吊装,分别定位之后对整个液压调直设备进行调平、对中;
    4)吊运钢管柱,于调直架孔口位置对中
     用吊机对钢管柱进行吊运,在调直架上方,待钢管柱平稳后缓缓下放至调直架孔口位置并调整钢管柱对中;
    5)通过导向纠偏装置限位,利用两层抱箍将钢管柱下放至下部砼面
钢管柱调整好位置对中下放后,移动钢护筒上的液压纠偏装置,使液压纠偏装置抱紧钢管柱,固定好以对钢管柱的行程进行限位,移动上下两层抱箍将钢管柱下放至下部砼面;钢管柱下放过程中,在钢管柱柱身不同位置安设二部吸附式测斜仪;
    6)调整钢管柱垂直度;
钢管柱下放至砼面以后,利用测斜仪和抱箍、导向纠偏装置纠正钢管柱偏位,从而调整钢管柱至设计垂直度;
    7)将钢管柱下放至设计深度;
     在钢管柱调整至设计垂直度后固定好导向纠偏装置从而对钢管柱行程进行限位,利用抱箍按照既有路线将钢管柱下放至设计深度;
8)再次测量钢管柱垂直度;
在钢管柱下放到设计深度后,通过测斜仪再次测量钢管柱垂直度,确保钢管柱垂直度符合设计要求;若垂直度过大,则通过导向纠偏装置及抱箍继续调整至符合要求;
    9)钢管柱孔口固定,移走调直架
     在桩位中心、钢管柱垂直度、钢管柱下放深度均符合设计及规范要求后,将钢管柱孔口进行固定,然后移走调直架;
    10)割除工具管、下导管、浇灌砼至设计高度
     从钢管柱内下放相应管径的导管,将设计标号的砼通过对应管径的导管利用干浇法浇灌至设计高度;
    11)桩孔回填、注浆
     待钢管柱内混凝土初凝后,在钢管柱两侧通过人工在不对钢管柱产生扰动的情况下均匀回填沙石至孔口,回填密实之后对周边回填部分进行注浆。
CN2013101989416A 2013-05-27 2013-05-27 一柱一桩后插法施工工艺 Pending CN103321212A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101989416A CN103321212A (zh) 2013-05-27 2013-05-27 一柱一桩后插法施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101989416A CN103321212A (zh) 2013-05-27 2013-05-27 一柱一桩后插法施工工艺

Publications (1)

Publication Number Publication Date
CN103321212A true CN103321212A (zh) 2013-09-25

Family

ID=49190236

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101989416A Pending CN103321212A (zh) 2013-05-27 2013-05-27 一柱一桩后插法施工工艺

Country Status (1)

Country Link
CN (1) CN103321212A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967058A (zh) * 2014-04-24 2014-08-06 上海市基础工程集团有限公司 基于一柱一桩后插法的孔内导向纠偏和钢管柱调直的方法
CN109930603A (zh) * 2019-03-27 2019-06-25 中国建筑第四工程局有限公司 一种超深逆作钢管柱垂直度控制装置及其使用方法
CN110629744A (zh) * 2019-09-16 2019-12-31 中铁广州工程局集团深圳工程有限公司 一种地铁车站钢管混凝土桩施工工艺
CN112814277A (zh) * 2020-12-31 2021-05-18 开普天(上海)岩土科技有限公司 一柱一桩施工中的立柱施工方法
CN112832458A (zh) * 2020-12-31 2021-05-25 开普天(上海)岩土科技有限公司 一柱一桩施工中的立柱施工方法
CN113293869A (zh) * 2021-04-21 2021-08-24 北京城建集团有限责任公司 钢立柱后插法施工工法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002061198A (ja) * 2000-08-21 2002-02-28 Railway Technical Res Inst 鋼管柱の建て込み工法及びそのための場所打ち杭の杭頭処理工法
CN1391010A (zh) * 2002-07-25 2003-01-15 上海隧道工程股份有限公司 ***法立柱桩施工工艺
JP2006322179A (ja) * 2005-05-18 2006-11-30 Okumura Corp 杭と柱の一体化施工方法
CN101240534A (zh) * 2007-12-31 2008-08-13 浙江省一建建设集团有限公司 逆作法一柱一桩的施工工艺及其校正装置

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002061198A (ja) * 2000-08-21 2002-02-28 Railway Technical Res Inst 鋼管柱の建て込み工法及びそのための場所打ち杭の杭頭処理工法
CN1391010A (zh) * 2002-07-25 2003-01-15 上海隧道工程股份有限公司 ***法立柱桩施工工艺
JP2006322179A (ja) * 2005-05-18 2006-11-30 Okumura Corp 杭と柱の一体化施工方法
CN101240534A (zh) * 2007-12-31 2008-08-13 浙江省一建建设集团有限公司 逆作法一柱一桩的施工工艺及其校正装置

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
广联丁红波: "HDC高精度钢立柱安装施工方法介绍.pdf(网址:http://wenku.***.com/link?url=WJ8TymOgvQjEFM_jdBKKB4ma7q-E6yTxF4NASxpt0QEPdqU-LoKue1KFSeOUHBt9zp2qQFJn_7aP4NoaBWuA9_upMKAkqjM3hIEjo6k0bCy)", 《百度文库》, 18 December 2012 (2012-12-18) *
陈新华: "逆作法施工中一柱一桩垂直度的有效控制", 《建筑施工》, vol. 34, no. 8, 31 December 2012 (2012-12-31), pages 792 - 794 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967058A (zh) * 2014-04-24 2014-08-06 上海市基础工程集团有限公司 基于一柱一桩后插法的孔内导向纠偏和钢管柱调直的方法
CN109930603A (zh) * 2019-03-27 2019-06-25 中国建筑第四工程局有限公司 一种超深逆作钢管柱垂直度控制装置及其使用方法
CN110629744A (zh) * 2019-09-16 2019-12-31 中铁广州工程局集团深圳工程有限公司 一种地铁车站钢管混凝土桩施工工艺
CN110629744B (zh) * 2019-09-16 2021-08-13 中铁广州工程局集团深圳工程有限公司 一种地铁车站钢管混凝土桩施工工艺
CN112814277A (zh) * 2020-12-31 2021-05-18 开普天(上海)岩土科技有限公司 一柱一桩施工中的立柱施工方法
CN112832458A (zh) * 2020-12-31 2021-05-25 开普天(上海)岩土科技有限公司 一柱一桩施工中的立柱施工方法
CN113293869A (zh) * 2021-04-21 2021-08-24 北京城建集团有限责任公司 钢立柱后插法施工工法

Similar Documents

Publication Publication Date Title
CN103321212A (zh) 一柱一桩后插法施工工艺
CN107653884B (zh) 砂土地基灌注桩钻孔用钢护筒设置装置及其施工方法
CN109487822B (zh) 逆作法施工钢管柱安装调整方法及控制装置
CN106013053B (zh) 一种用于建造地下车库沉井的钢板桩支护施工方法
CN105672314B (zh) 一种半逆作法钢管立柱桩施工方法
CN103967058A (zh) 基于一柱一桩后插法的孔内导向纠偏和钢管柱调直的方法
CN103195076A (zh) 淤泥质深基坑塔吊基础施工方法
CN103132537A (zh) 钢格构柱回字型混凝土承台组合式塔吊基础结构及施工方法
CN104294819A (zh) 一种灌注桩的施工方法
CN107620311A (zh) 一种泥浆护壁成孔灌注桩防止孔口护筒下沉的方法
CN105064381A (zh) 一种高低刃脚双壁钢围堰钢筋混凝土一次封底施工方法
CN204608753U (zh) 一种组合钢板桩
CN205296219U (zh) 钢管柱液压抱紧和垂直***工法机
CN104032767A (zh) 一种深基坑内塔吊基础及其施工方法
CN103669383B (zh) 一种在海底地面上安装和调平沉箱的方法
CN104074234B (zh) 电厂循环水***的内河水取水口结构及其施工方法
CN204059460U (zh) 电厂循环水***的内河水取水口结构
CN211646415U (zh) 一种狭小深基坑预制围护结构
CN105714851B (zh) 装配式地连墙或预制桩与现浇地下车站一体化施工装置及采用其的施工方法
CN104975734A (zh) 铸造机井套管安装方法
CN203034476U (zh) 钢格构柱回字型混凝土承台组合式塔吊基础结构
CN202626989U (zh) 大直径钢护筒步进式导向架
CN204715364U (zh) 一种基坑支护装置
CN203049588U (zh) 坑中坑筒模
CN204298830U (zh) 基于地下基坑内格构柱平面及高程调控装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130925