CN103246283A - 一种电厂侧自动电压控制***闭环测试方法 - Google Patents
一种电厂侧自动电压控制***闭环测试方法 Download PDFInfo
- Publication number
- CN103246283A CN103246283A CN2013101818323A CN201310181832A CN103246283A CN 103246283 A CN103246283 A CN 103246283A CN 2013101818323 A CN2013101818323 A CN 2013101818323A CN 201310181832 A CN201310181832 A CN 201310181832A CN 103246283 A CN103246283 A CN 103246283A
- Authority
- CN
- China
- Prior art keywords
- power plant
- model
- plant side
- real
- avc
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
本发明涉及一种电厂侧自动电压控制***闭环测试方法,建立电厂侧AVC***的闭环测试***:包括实时数字仿真***、电厂侧AVC***、远动终端RTU,实时数字仿真***建模仿真电厂实际电力***,并模拟发电***进入相应的运行状态;实时数字仿真***输出控制信号到通过远动终端RTU处理转换数据发送至电厂侧AVC***,电厂侧AVC***将实际控制信号再回传到实时数字仿真***中的***平台模型相应模拟元件上,再通过中央控制***模型模拟运行后输出控制信号,形成闭环运行实现闭环测试。实现对电厂侧AVC***功能进行离线实时测试。对建立统一的电厂侧AVC***的各项指标有重要的指导作用,为电厂侧AVC***入网测试提供了很好的解决方案。
Description
技术领域
本发明涉及一种电力测试技术,特别涉及一种电厂侧自动电压控制***闭环测试方法。
背景技术
电力***无功功率优化和补偿是电力***安全经济运行的重要组成部分。通过对无功电源的合理配置和对无功负荷的补偿,不仅可以维持电压水平、提高电力***运行的稳定性,还可以降低网损,使电力***安全经济运行。在传统的电压控制管理模式下,发电厂的发电机无功功率、高压母线电压主要由各电厂值班人员根据***调度的要求人工调节。这种调节方式仅能保证部分时段、部分节点的电压合格,但与电力***的经济运行、可靠供电的目标相去甚远。电厂自动电压控制***(AVC)是利用先进的电子、网络通讯与自动控制技术,在线接收省电力调度中心下发的母线电压指令,自动对发电机无功出力或高压侧母线电压进行实时跟踪调控。该***可有效地控制区域电网无功的合理流动,增强***运行的稳定性和安全性,保证电压质量,改善电网整体供电水平,减少电网有功网损,充分发挥电网的经济效益,同时降低运行人员的劳动强度。
发明内容
本发明是针对电厂侧电力调度不经济合理的问题,提出了一种电厂侧自动电压控制***闭环测试方法,利用实时数字仿真***的实时模拟和闭环运行的特性,构建电厂侧AVC***的闭环测试试验平台,并在此平台上提出电厂侧AVC***的测试方法,实现对电厂侧AVC***功能进行离线实时测试。
本发明的技术方案为:一种电厂侧自动电压控制***闭环测试方法,具体包括如下步骤:
1)建立电厂侧AVC***的闭环测试***:包括实时数字仿真***、电厂侧AVC***、远动终端RTU,
实时数字仿真***建模包括***平台模型和中央控制***模型,***平台模型由模拟电力***元件构建完成,该模型仿真电厂实际电力***,中央控制***模型由模拟运行***元件构建完成,通过用户输入数据和/或指令对***平台模型进行模拟控制,模拟发电***进入相应的运行状态;
2)实时数字仿真***中的中央控制***模型输出控制信号,通过远动终端RTU处理转换数据后发送至电厂侧AVC***,电厂侧AVC***将实际控制信号再回传到实时数字仿真***中的***平台模型相应模拟元件上,再通过中央控制***模型模拟运行后输出控制信号,形成闭环运行;
3)按照电厂侧AVC***的基本功能进行参数设定试验、基本功能试验、安全特性试验三部分试验;
4)查看测试结果。
所述步骤1)中***平台模型建模选择实际电力***接线方式,在实时数字仿真***中搭建一次***模型,一次***模型中包含发电机模型、两绕组变压器模型、等值负荷模型、等值电源模型、断路器模型、电压互感器模型、电流互感器模型。
所述步骤2)中远动终端RTU中的监控单元实时采集实时数字仿真***来的控制模拟量,远动终端RTU中的通信管理机对控制模拟量进行处理转换,转换成IEC101规约数据发送至电厂侧AVC***。
本发明的有益效果在于:本发明电厂侧自动电压控制***闭环测试方法,构建电厂侧AVC***的闭环测试试验平台,并在此平台上实现对电厂侧AVC***功能进行离线实时测试。对建立统一的电厂侧AVC***的技术原则、结构要求、功能及性能指标有重要的指导作用,为电厂侧AVC***入网测试提供了很好的解决方案。
附图说明
图1为本发明实施例提供的电厂侧AVC***的闭环测试原理图;
图2为本发明实施例提供的电厂侧AVC***的闭环测试硬件连接示意图;
图3为本发明实施例电力***一次***模型结构示意图。
具体实施方式
如图1、图2实施例提供的电厂侧AVC***的闭环测试原理图和硬件连接示意图,基于实时数字仿真***的电厂侧AVC***功能测试试验平台,包括硬件架构和软件建模;所述硬件架构包括实时数字仿真***、电厂侧AVC***、远动终端RTU。
实时数字仿真***的软件建模包括***平台模型和中央控制***模型,***平台模型由模拟电力***元件构建完成,该模型仿真电厂实际电力***,中央控制***模型由模拟运行***元件构建完成,通过用户输入数据和/或指令对***平台模型进行模拟控制,使其发电***进入相应的模拟运行状态。
所述电厂侧AVC***闭环测试试验平台,在硬件构架中,实时数字仿真***输出机端电压、机端电流和母线电压模拟量,通过远动终端RTU的测控单元实时采集,然后在远动终端RTU的通信管理机中处理转换成IEC101规约数据发送至电厂侧AVC***的上位机,同时,电厂侧AVC***的省调AVC主站给AVC子站下发调控目标,由AVC子站装置执行调控,得到机组增减磁控制信号,然后将控制信号再回传到实时数字仿真***中,形成闭环运行。
***平台模型选择某发电厂电力***接线方式,如图3所示电力***一次***模型结构示意图,具体包含发电机、两绕组变压器、等值线路、等值电源、等值负荷和二次测量***。模拟***中建立了正一母Bus1和正二母Bus2,分别接入两台发电机和两台变压器,黑色实心的断路器为闭合,空心的断路器为打开的状态,电厂的出线用两条等值线路表示,每条出线用一等值电源来模拟***运行。二次测量***包含测点和被测量。在实时数字仿真***中建立发电机模型、变压器模型、线路模型、电源模型、负荷模型、电压互感器模型、电流互感器模型。发电机模型主要设置发电机容量、各种电抗参数、时间常数、电压等级等。变压器模型主要设置变压器各侧的电压等级和容量、基准频率、漏抗、空载损耗等;负荷模型设为一个可变的恒功率负荷,根据试验中的要求动态变化。
***平台模型建立步骤:
1、新建***模型文件并保存;
2、搭建发电机模型、汽轮机模型、变压器模型、断路器模型、负荷模型并按照电气关系连接起来;
3、完成各种模型的参数设置,设置断路器开关信号;
4、构建各台发电机励磁控制模型;
5、构建机组AVC***的增减磁控制模型;
6、构建动态负荷的控制模型;
7、完成***平台模型的搭建。
中央控制***模型包含对发电机的励磁***和机组AVC增减磁控制***进行控制。发电机励磁***的控制,包括发电机增磁和减磁信号的接受和控制逻辑,一方面可通过手动调节增减磁信号实现控制,另一方面可通过接受外部的AVC下发的增减磁指令来实现控制;控制***还可以对发电机的有功出力和无功出力进行控制,由中央控制***的用户输入指令实现控制。完成上述***平台模型和相应的子模型及参数配置之后,即可编译模型,仿真电厂的***运行。机组AVC增减磁控制***,由于AVC***的增减磁控制信号同时送入AVR,设置控制回路判断增减磁信号。
中央控制***模型是模拟电厂的集控中心,由实时数字仿真***的运行元件建设完成。中央控制***模型可实时显示***运行数据,包含显示各母线电压、各发电机的有功/无功功率、各变压器各绕组有功/无功功率、各台发电机的增减磁信号状态等。此外,还可以手动调节各台发电机的相角,实现对各台发电机有功出力和无功出力的控制,从而改变发电***的运行状态,还可以手动触发发电机的增减磁信号,检测励磁控制***模型的有效性。
中央控制***模型建立步骤:
1)、新建中央控制***文件并保存;
2)、搭建电厂一次***网架结构;
3)、将***平台模型的母线电压、发电机有功/无功出力、断路器开关状态、负荷投切状态并以仪表或指示灯的方式显示;
4)、将各断路器开关进行建模;
5)、将动态负荷开关进行建模;
6)、完成中央控制***模型的搭建;
7)、进行***调试,完成闭环测试***的软件部分的整体建模。
所述的电厂侧AVC***的闭环测试步骤如下:
1)完成***闭环测试平台的建设,包含硬件架构和软件建模两部分;
2)按照电厂侧AVC***的基本功能进行参数设定试验、基本功能试验、安全特性试验三部分试验;
3)查看测试结果。
通过以下实施例可知,一种电厂侧AVC***的闭环测试方法可对待测的电厂侧AVC***进行各项功能测试,具体包含参数设定试验、基本功能试验、安全特性试验三部分试验。
实施例一、机组无功调节装置脉冲宽度整定试验:此试验为参数设定试验之一。该试验通过调节AVC子站输出脉冲宽度来设定“无功输出设置”中机组信号输出间隔、信号最大宽度、信号最小宽度和斜率等重要参数,为现场试验和参数整定积累经验。
实施例二、机组间无功分配调节性能试验:此试验为基本功能试验之一。设置AVC***的“母线电压调控”方式,测试AVC子站在调节过程中各机组无功分配的合理性,即测试四种分配方法,如:等功率因素无功分配、等裕度无功分配、等容量无功分配、无功平均分配,查看各种无功分配方法的分配效果。
实施例三、机组无功反调试验:此试验为基本功能试验之一。测试AVC***调节过程中无功越限反调并合理分配无功的能力。首先设定“母线电压调控”方式,主站下发指令减磁至机组无功越下限,查看AVC子站装置的无功反调过程。或者,主站下发指令增磁至机组无功越上限,查看AVC子站装置的无功反调过程。
实施例四、机组电压反调试验:此试验为基本功能试验之一。测试AVC子站装置调节过程中机端电压越限反调并合理分配无功的能力。首先设定“母线电压调控”方式,主站下发指令减磁至机组机端电压越下限,查看AVC子站装置的电压反调过程。或者,主站下发指令减磁至机组机端电压越上限,查看AVC子站装置的电压反调过程。
实施例五、AVC主站与AVC子站通信中断试验:此试验为安全特性试验之一。测试AVC主站与子站通信中断时,AVC子站装置的动作情况。方法是断开AVC主站与子站装置之间的接线,然后查看AVC子站装置的动作。
实施例六、AVC子站与RTU通信中断试验:此试验为安全特性试验之一。测试AVC子站装置与RTU通信完全中断时,查看AVC子站装置的动作情况。方法是断开AVC子站的上位机与RTU通信管理机间的接线,然后查看AVC子站装置的动作。
实施例七、闭锁试验:此试验为安全特性试验之一。测试AVC子站装置在检测到遥测数据超出闭锁限制时的动作情况。主要包含母线电压机组有功/无功、机端电压、机端电流、厂用电等遥测数据闭锁。
Claims (3)
1.一种电厂侧自动电压控制***闭环测试方法,其特征在于,具体包括如下步骤:
1)建立电厂侧AVC***的闭环测试***:包括实时数字仿真***、电厂侧AVC***、远动终端RTU,
实时数字仿真***建模包括***平台模型和中央控制***模型,***平台模型由模拟电力***元件构建完成,该模型仿真电厂实际电力***,中央控制***模型由模拟运行***元件构建完成,通过用户输入数据和/或指令对***平台模型进行模拟控制,模拟发电***进入相应的运行状态;
2)实时数字仿真***中的中央控制***模型输出控制信号,通过远动终端RTU处理转换数据后发送至电厂侧AVC***,电厂侧AVC***将实际控制信号再回传到实时数字仿真***中的***平台模型相应模拟元件上,再通过中央控制***模型模拟运行后输出控制信号,形成闭环运行;
3)按照电厂侧AVC***的基本功能进行参数设定试验、基本功能试验、安全特性试验三部分试验;
4)查看测试结果。
2.根据权利要求1所述电厂侧自动电压控制***闭环测试方法,其特征在于,所述步骤1)中***平台模型建模选择实际电力***接线方式,在实时数字仿真***中搭建一次***模型,一次***模型中包含发电机模型、两绕组变压器模型、等值负荷模型、等值电源模型、断路器模型、电压互感器模型、电流互感器模型。
3.根据权利要求1所述电厂侧自动电压控制***闭环测试方法,其特征在于,所述步骤2)中远动终端RTU中的监控单元实时采集实时数字仿真***来的控制模拟量,远动终端RTU中的通信管理机对控制模拟量进行处理转换,转换成IEC101规约数据发送至电厂侧AVC***。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013101818323A CN103246283A (zh) | 2013-05-16 | 2013-05-16 | 一种电厂侧自动电压控制***闭环测试方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013101818323A CN103246283A (zh) | 2013-05-16 | 2013-05-16 | 一种电厂侧自动电压控制***闭环测试方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103246283A true CN103246283A (zh) | 2013-08-14 |
Family
ID=48925861
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2013101818323A Pending CN103246283A (zh) | 2013-05-16 | 2013-05-16 | 一种电厂侧自动电压控制***闭环测试方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103246283A (zh) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104283215A (zh) * | 2014-10-29 | 2015-01-14 | 上海电力学院 | 一种智能分布式配电终端的检测试验方法及装置 |
CN105974819A (zh) * | 2016-04-29 | 2016-09-28 | 广东电网有限责任公司电力调度控制中心 | 电力实时数字仿真***的故障点控制方法和*** |
CN110262455A (zh) * | 2019-06-26 | 2019-09-20 | 南方电网科学研究院有限责任公司 | 电站自动发电控制***控制特性的测试方法、装置及设备 |
CN110632410A (zh) * | 2019-08-19 | 2019-12-31 | 国网湖南省电力有限公司 | 一种智能变电站自动化设备智能调试***及其应用方法 |
CN110765616A (zh) * | 2019-10-24 | 2020-02-07 | 南方电网科学研究院有限责任公司 | 一种发电厂计算机监控***的仿真闭环测试***及方法 |
CN112015162A (zh) * | 2020-08-03 | 2020-12-01 | 国网山东省电力公司电力科学研究院 | 新能源场站无功电压控制***硬件在环测试***及方法 |
CN113708492A (zh) * | 2021-08-24 | 2021-11-26 | 华能重庆两江燃机发电有限责任公司 | 检测自动电压控制***的方法、***及装置 |
CN114123321A (zh) * | 2021-11-19 | 2022-03-01 | 广东电网有限责任公司 | 一种新能源并网测试*** |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202798014U (zh) * | 2012-08-21 | 2013-03-13 | 广东明阳风电产业集团有限公司 | 一种风电场并网控制的拓扑结构 |
CN102981500A (zh) * | 2012-11-27 | 2013-03-20 | 四川电力科学研究院 | 基于rtds的地区电网avc***功能试验检测平台及其构建方法 |
-
2013
- 2013-05-16 CN CN2013101818323A patent/CN103246283A/zh active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202798014U (zh) * | 2012-08-21 | 2013-03-13 | 广东明阳风电产业集团有限公司 | 一种风电场并网控制的拓扑结构 |
CN102981500A (zh) * | 2012-11-27 | 2013-03-20 | 四川电力科学研究院 | 基于rtds的地区电网avc***功能试验检测平台及其构建方法 |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104283215A (zh) * | 2014-10-29 | 2015-01-14 | 上海电力学院 | 一种智能分布式配电终端的检测试验方法及装置 |
CN105974819A (zh) * | 2016-04-29 | 2016-09-28 | 广东电网有限责任公司电力调度控制中心 | 电力实时数字仿真***的故障点控制方法和*** |
CN105974819B (zh) * | 2016-04-29 | 2018-11-09 | 广东电网有限责任公司电力调度控制中心 | 电力实时数字仿真***的故障点控制方法和*** |
CN110262455A (zh) * | 2019-06-26 | 2019-09-20 | 南方电网科学研究院有限责任公司 | 电站自动发电控制***控制特性的测试方法、装置及设备 |
CN110632410A (zh) * | 2019-08-19 | 2019-12-31 | 国网湖南省电力有限公司 | 一种智能变电站自动化设备智能调试***及其应用方法 |
CN110632410B (zh) * | 2019-08-19 | 2021-10-01 | 国网湖南省电力有限公司 | 一种智能变电站自动化设备智能调试***及其应用方法 |
CN110765616A (zh) * | 2019-10-24 | 2020-02-07 | 南方电网科学研究院有限责任公司 | 一种发电厂计算机监控***的仿真闭环测试***及方法 |
CN112015162A (zh) * | 2020-08-03 | 2020-12-01 | 国网山东省电力公司电力科学研究院 | 新能源场站无功电压控制***硬件在环测试***及方法 |
CN112015162B (zh) * | 2020-08-03 | 2021-11-09 | 国网山东省电力公司电力科学研究院 | 新能源场站无功电压控制***硬件在环测试***及方法 |
CN113708492A (zh) * | 2021-08-24 | 2021-11-26 | 华能重庆两江燃机发电有限责任公司 | 检测自动电压控制***的方法、***及装置 |
CN113708492B (zh) * | 2021-08-24 | 2024-05-31 | 华能重庆两江燃机发电有限责任公司 | 检测自动电压控制***的方法、***及装置 |
CN114123321A (zh) * | 2021-11-19 | 2022-03-01 | 广东电网有限责任公司 | 一种新能源并网测试*** |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103246283A (zh) | 一种电厂侧自动电压控制***闭环测试方法 | |
Meng et al. | Flexible system integration and advanced hierarchical control architectures in the microgrid research laboratory of Aalborg University | |
CN107359617B (zh) | 一种包含微网群的主动配电网源-网-荷协调控制*** | |
Vijay et al. | Real-time testing approaches for microgrids | |
Salehi et al. | Laboratory-based smart power system, part II: Control, monitoring, and protection | |
Wang et al. | Development of a universal platform for hardware in-the-loop testing of microgrids | |
WO2018014450A1 (zh) | 基于rt-lab的真实微电网运行动态仿真测试平台 | |
JP5960985B2 (ja) | 電力変換システムを制御するための方法及びシステム | |
Yang et al. | Development of converter based reconfigurable power grid emulator | |
CN103248127B (zh) | 多时空导航式电力***恢复决策支持***及恢复决策方法 | |
CN103245855A (zh) | 基于数字仿真的智能变电站继电保护测试方法及*** | |
CN202159106U (zh) | 一种智能电网自愈控制技术的智能测试仪 | |
Rakhshani et al. | Modeling and sensitivity analyses of VSP based virtual inertia controller in HVDC links of interconnected power systems | |
CN106814263A (zh) | 一种半实物仿真并网检测***及方法 | |
Berizzi et al. | Architecture and functionalities of a smart Distribution Management System | |
CN105896550A (zh) | 一种智能无功补偿***的监控方法 | |
CN104049543A (zh) | 一种直流孤岛运行机网协调特性研究实时仿真平台 | |
Genić et al. | Multi-layer hardware-in-the-loop testbed for microgrids | |
CN103837776A (zh) | 一种交直流并联电网电压稳定性测试的实验*** | |
CN202563004U (zh) | 一种用于发电机端***的信号测量装置 | |
CN105355122A (zh) | 一种虚负荷模拟组网发生装置及发生方法 | |
Gueissaz et al. | Fair control of distributed pv plants in low voltage grids | |
CN108539749A (zh) | 利用公共信息模型进行数据交互的电厂电压控制仿真方法 | |
Save et al. | Pmu-based power system analysis of a MV distribution grid | |
Govindaraj et al. | A wide area monitoring system using neuro control technique for load restoration |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20130814 |