CN103243740B - 旋挖、长螺旋组合钻孔压灌混凝土咬合桩连续墙施工方法 - Google Patents
旋挖、长螺旋组合钻孔压灌混凝土咬合桩连续墙施工方法 Download PDFInfo
- Publication number
- CN103243740B CN103243740B CN201310186897.7A CN201310186897A CN103243740B CN 103243740 B CN103243740 B CN 103243740B CN 201310186897 A CN201310186897 A CN 201310186897A CN 103243740 B CN103243740 B CN 103243740B
- Authority
- CN
- China
- Prior art keywords
- pile
- construction
- construction method
- stake
- drilling pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 55
- 238000005553 drilling Methods 0.000 claims abstract description 57
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 22
- 230000000694 effects Effects 0.000 claims description 12
- 230000002441 reversible effect Effects 0.000 claims description 8
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical group [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 6
- 208000028804 PERCHING syndrome Diseases 0.000 claims description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract 4
- 238000000034 method Methods 0.000 description 4
- 238000005086 pumping Methods 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 210000000481 breast Anatomy 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 238000012407 engineering method Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000009916 joint effect Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Earth Drilling (AREA)
Abstract
Description
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310186897.7A CN103243740B (zh) | 2013-05-20 | 2013-05-20 | 旋挖、长螺旋组合钻孔压灌混凝土咬合桩连续墙施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310186897.7A CN103243740B (zh) | 2013-05-20 | 2013-05-20 | 旋挖、长螺旋组合钻孔压灌混凝土咬合桩连续墙施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103243740A CN103243740A (zh) | 2013-08-14 |
CN103243740B true CN103243740B (zh) | 2015-02-04 |
Family
ID=48923592
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310186897.7A Active CN103243740B (zh) | 2013-05-20 | 2013-05-20 | 旋挖、长螺旋组合钻孔压灌混凝土咬合桩连续墙施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103243740B (zh) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104631437B (zh) * | 2014-12-19 | 2016-05-04 | 国家电网公司 | 送电线路工程应用旋挖钻机进行挖孔桩基础成孔的方法 |
CN107489158A (zh) * | 2017-09-23 | 2017-12-19 | 北京建材地质工程有限公司 | 一种旋挖成孔搅喷水泥土咬合帷幕桩的施工方法 |
CN107587502B (zh) * | 2017-09-23 | 2020-10-23 | 北京建材地质工程有限公司 | 一种旋挖成孔压灌水泥土咬合帷幕桩的施工方法 |
CN107653889B (zh) * | 2017-09-23 | 2020-05-19 | 北京建材地质工程有限公司 | 一种型钢压灌水泥土帷幕支护桩的施工方法 |
CN110016920B (zh) * | 2019-04-26 | 2021-07-02 | 深圳市工勘岩土集团有限公司 | 荤素搭配的咬合桩施工方法 |
CN115354673B (zh) * | 2022-08-19 | 2023-09-05 | 四川省公路规划勘察设计研究院有限公司 | 红层软岩区抗滑桩成孔方法及吊装式人工辅助装置 |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1137313C (zh) * | 2000-12-27 | 2004-02-04 | 柯刚 | 长螺旋干成孔压灌混凝土桩施工工艺及其钢筋笼振动送笼器 |
CN2716484Y (zh) * | 2004-06-26 | 2005-08-10 | 山东鸿泰建设集团有限公司 | 一种压灌钻头 |
CN101560765A (zh) * | 2008-04-18 | 2009-10-21 | 万勇 | 多轴长螺旋钻杆咬合桩地下连续墙施工技术 |
CN201363086Y (zh) * | 2009-01-20 | 2009-12-16 | 颜廷想 | 旋挖钻机用旋挖钻 |
CN102286981A (zh) * | 2011-07-15 | 2011-12-21 | 深圳市鸿荣轩建设工程有限公司 | 一种止水帷幕及其施工方法 |
CN102628267A (zh) * | 2012-04-20 | 2012-08-08 | 吴传清 | 无套管长螺旋混凝土咬合桩施工方法 |
CN202924606U (zh) * | 2012-11-28 | 2013-05-08 | 烟台海州机械有限公司 | 钢筋笼专用振动器 |
CN102966094B (zh) * | 2012-12-15 | 2014-08-27 | 马春根 | 一种旋挖压灌混凝土桩施工方法 |
-
2013
- 2013-05-20 CN CN201310186897.7A patent/CN103243740B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN103243740A (zh) | 2013-08-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103243740B (zh) | 旋挖、长螺旋组合钻孔压灌混凝土咬合桩连续墙施工方法 | |
CN101638891B (zh) | 全套管旋进隔离桩施工方法 | |
CN105780763B (zh) | 中孔振动套管护壁长螺旋钻孔压灌桩的施工方法 | |
CN107524142A (zh) | 一种泥浆护壁钻孔灌注桩施工方法 | |
CN102383431B (zh) | 中掘预应力离心管桩沉桩装置及其沉桩法 | |
CN102286984A (zh) | 一种止水帷幕及其施工方法 | |
CN106759288A (zh) | 一种建筑钻孔灌注桩施工方法 | |
CN103147442A (zh) | 超深基坑压灌桩与预应力锚杆联合支护施工方法 | |
CN105464074B (zh) | 一种人工挖孔桩高聚物注浆防护结构及其施工方法 | |
CN102635113A (zh) | 一种液压振动沉管灌注桩施工方法 | |
US20160340851A1 (en) | Method for installing metal piles in permafrost soil | |
CN105714772A (zh) | 岩溶地区嵌岩桩成孔复钻砼护壁方法 | |
CN102864781A (zh) | 一种斜桩基坑支护方法 | |
CN105672307A (zh) | 一种扩底组合端承桩基础 | |
CN202519694U (zh) | 饱和水条件下地质为淤泥层的沉井基础结构 | |
CN202194149U (zh) | 一种止水帷幕 | |
CN206721870U (zh) | 一种长螺旋钻孔压灌桩用钢筋笼 | |
CN105089023A (zh) | 一种水电站厂房混凝土底板改进方法及其结构 | |
CN103485347A (zh) | 一种建筑基坑支护用斜桩及其施工方法 | |
CN107100164A (zh) | 一种长螺旋钻孔压灌桩施工方法 | |
CN104563104B (zh) | 桩工钻机用联动式护壁装置及使用其的施工方法 | |
CN204608773U (zh) | 桩工钻机用联动式护壁装置 | |
CN106480878A (zh) | 一种上、下部扩大型水泥土复合管桩 | |
CN108086307A (zh) | 钢管混凝土挖孔灌注复合微型桩 | |
CN207794067U (zh) | 钢管混凝土挖孔灌注复合微型桩 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20130814 Assignee: JIANGXI ZHONGHENG GEOTECHNICAL ENGINEERING TECHNOLOGY CO., LTD. Assignor: Ma Chungen Contract record no.: 2015360000044 Denomination of invention: Construction method of rotary excavating and long spiral combination bored concrete pressure grouting secant pile continuous wall Granted publication date: 20150204 License type: Exclusive License Record date: 20150519 |
|
LICC | Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model | ||
C41 | Transfer of patent application or patent right or utility model | ||
EM01 | Change of recordation of patent licensing contract |
Change date: 20161031 Contract record no.: 2015360000044 Assignee after: JIANGXI ZHONGHENG UNDERGROUND SPACE TECHNOLOGY CO., LTD. Assignee before: JIANGXI ZHONGHENG GEOTECHNICAL ENGINEERING TECHNOLOGY CO., LTD. |
|
LICC | Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20161111 Address after: 333000 Jiangxi Province, Jingdezhen City Changjiang district fish Li Industrial Park, No. fifteenth Patentee after: Jiangxi Huanqiu geotechnical Technology Co., Ltd. Address before: 333000 Jiangxi Province, Jingdezhen city Zhushan District pear garden in Shangri-La 27 Patentee before: Ma Chungen |