CN103236766B - Magnetic pole center positioning process used in process of assembling and disassembling magnetic pole of generator - Google Patents
Magnetic pole center positioning process used in process of assembling and disassembling magnetic pole of generator Download PDFInfo
- Publication number
- CN103236766B CN103236766B CN201310156817.3A CN201310156817A CN103236766B CN 103236766 B CN103236766 B CN 103236766B CN 201310156817 A CN201310156817 A CN 201310156817A CN 103236766 B CN103236766 B CN 103236766B
- Authority
- CN
- China
- Prior art keywords
- magnetic pole
- center
- strip board
- weight
- upper bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 14
- 238000002347 injection Methods 0.000 abstract 1
- 239000007924 injection Substances 0.000 abstract 1
- 230000001771 impaired effect Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Manufacture Of Motors, Generators (AREA)
Abstract
The invention discloses a magnetic pole center positioning process used in the process of assembling and disassembling a magnetic pole of a generator, which comprises the following steps of preparing a strip board, wherein the length of the strip board is greater than the width of 1,080mm between upper rack support arms; searching a midpoint position in the length of the strip board, arranging a positioning point at the midpoint position and hanging a weight at the positioning point by a perpendicular line; searching a support arm center position of the two upper rack support arms and horizontally erecting the strip board on which the weight is hung between the two upper rack support arms, so that the perpendicular line and the support arm center position are positioned on the same straight line, wherein the weight is positioned above a magnetic yoke and is at a distance of 4 to 5cm with the magnetic yoke; and manually turning to enable the center line of the magnetic pole, the perpendicular line and the center position of the upper rack support arms to be positioned on the same straight line. According to the invention, the problem that the center cannot be accurately aligned in the process of assembling and disassembling the magnetic pole is solved; the problem that the magnetic pole is slantingly pulled and hoisted when being lifted by an electric hoist can be avoided; times of turning can be greatly reduced; the operating time of a high pressure oil injection pump is reduced; and working efficiency is improved.
Description
Technical field
The present invention relates to the technique being applied to generator dismounting field, particularly pole center positioning process during generator magnetic pole dismounting.
Background technology
Present generator unit is when machine maintenance, pole center is determined by range estimation by service work personnel usually, easy like this pole center location of causing is inaccurate, service work personnel adjust the position of dismounting magnetic pole by artificial jiggering, or service work personnel think that dismounting magnetic pole puts in place, but in fact center also exists deviation, magnetic pole by oblique pull, easily can cause damage when lifting.
Summary of the invention
The object of the invention is to, pole center positioning process when a kind of generator magnetic pole dismounting is provided.It can avoid magnetic pole to be hung and impaired by askew skewing when dismantling, and reduces the number of times of jiggering, increases work efficiency, and reduces the labour intensity of workman.
Technical scheme of the present invention: pole center positioning process during generator magnetic pole dismounting, is characterized in that, comprise the steps:
A. prepare a strip board, the length of strip board is greater than the width 1080mm between upper bracket-arm;
B, find the midpoint of strip board length, one anchor point is set in this midpoint, mounts a weight at anchor point by vertical line;
C, find support arm center between two upper bracket-arms, the strip board level frame being mounted with weight is set between two upper bracket-arms, make vertical line and support arm center be positioned at same straight line, and weight is positioned at the top place of yoke, distance yoke is 4-5cm;
D, by artificial jiggering, the center line of magnetic pole and vertical line, upper bracket-arm is made to be centrally located at same straight line.
During aforesaid generator magnetic pole dismounting in pole center positioning process, strip board is plank, and its length is 1500-1550mm, and width is 85-95mm, and thickness is 20-30mm.
Compared with prior art, the strip board midpoint of the present invention between generator frame upper arm arranges anchor point, and at anchor point, place mounts weight by vertical line, finds pole center easily by artificial jiggering.The present invention is by above-mentioned technical scheme, magnetic pole is made to be parked in center between upper bracket-arm, solve the problem of magnetic pole center misalignment when dismounting, magnetic pole can be avoided by with occurring during electric hoist lifting askewly skewing the problem of hanging, the number of times reducing jiggering can also be greatly reduced, reduce high pressure oiling pump running time, reduce personnel labor intensity, increase work efficiency.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention.
Being labeled as in accompanying drawing: 1-upper bracket-arm, 2-magnetic pole, 3-strip board, 4-vertical line, 5-weight, 6-yoke, 7-support arm center.
Embodiment
Below in conjunction with drawings and Examples, the present invention is further illustrated, but not as the foundation limited the present invention.
Embodiment.Pole center positioning process during generator magnetic pole dismounting, comprises the steps: that A. prepares a strip board 3, and the length of strip board 3 is greater than the width 1080mm between upper bracket-arm 1;
B, find the midpoint of strip board 3 length, one anchor point is set in this midpoint, mounts a weight 5 at anchor point by vertical line 4;
C, find support arm center 7 between two upper bracket-arms 1, strip board 3 level frame being mounted with weight is set between two upper bracket-arms 1, make vertical line 4 and support arm center 7 be positioned at same straight line, and weight is positioned at the top place of yoke 6, distance yoke is 4-5cm;
D, by artificial jiggering, the center line of magnetic pole 2 and vertical line, upper bracket-arm is made to be centrally located at same straight line.
Strip board 3 can be plank, and its length is 1500-1550mm, and width is 85-95mm, and thickness is 20-30mm.Preferred size is length is 1520mm, and width is 90mm, and thickness is 25mm.Such size is more moderate, can stably be erected between upper bracket-arm, not waste material.
The dismounting process of generator magnetic pole: prepare a strip board 3, the length of strip board 3 is greater than the width 1080mm between upper bracket-arm 1; Find the midpoint of strip board 3 length, one anchor point is set in this midpoint, mount a weight 5 at anchor point by vertical line 4; Find the support arm center 7 between two upper bracket-arms 1, strip board 3 level frame being mounted with weight is set between two upper bracket-arms 1, make vertical line 4 and support arm center be positioned at same straight line, and weight is positioned at the top place of yoke 6, distance yoke is 4-5cm; By artificial jiggering, the center line of magnetic pole 2 and vertical line, upper bracket-arm is made to be centrally located at same straight line, now the center of magnetic pole between upper bracket-arm, namely between middle two screw rods of magnetic-pole connection wire pressing plate.Mark is carried out in the position of then placing strip board 3 on upper bracket-arm, when other magnetic poles of dismounting, strip board 3 is placed on same position, very simple and efficient.
After the center of magnetic pole is found accurately, with electric hoist or other boom hoistings by magnetic pole lifting dismounting, can avoid occurring because askew skewing is hung and situation about being damaged.
Claims (1)
1. pole center positioning process during generator magnetic pole dismounting, is characterized in that, comprise the steps:
A. prepare a strip board (3), described strip board (3) is plank, and its length is 1500-1550mm, and width is 85-95mm, and thickness is 20-30mm;
B, find the midpoint of strip board (3) length, one anchor point is set in this midpoint, mounts a weight (5) at anchor point by vertical line (4);
C, find support arm center (7) between two upper bracket-arms (1), strip board (3) level frame being mounted with weight is set between two upper bracket-arms (1), width between upper bracket-arm (1) is 1080mm, vertical line (4) and support arm center (7) is made to be positioned at same straight line, and weight is positioned at the top place of yoke (6), distance yoke is 4-5cm;
D, by artificial jiggering, the center line of magnetic pole (2) and vertical line, upper bracket-arm is made to be centrally located at same straight line.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310156817.3A CN103236766B (en) | 2013-04-28 | 2013-04-28 | Magnetic pole center positioning process used in process of assembling and disassembling magnetic pole of generator |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310156817.3A CN103236766B (en) | 2013-04-28 | 2013-04-28 | Magnetic pole center positioning process used in process of assembling and disassembling magnetic pole of generator |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103236766A CN103236766A (en) | 2013-08-07 |
CN103236766B true CN103236766B (en) | 2015-07-22 |
Family
ID=48884789
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310156817.3A Active CN103236766B (en) | 2013-04-28 | 2013-04-28 | Magnetic pole center positioning process used in process of assembling and disassembling magnetic pole of generator |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103236766B (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1337028A2 (en) * | 1995-05-02 | 2003-08-20 | Oppama Industry Co., Ltd. | A magneto electric generator rotor |
CN1937368A (en) * | 2006-10-16 | 2007-03-28 | 四川东风电机厂有限公司 | Water wheel generator polecore assembling process |
CN101404431A (en) * | 2008-07-24 | 2009-04-08 | 哈尔滨电机厂有限责任公司 | Pole core assembly technique for punching quadrant iron type through-flow generator |
CN101640457A (en) * | 2008-07-31 | 2010-02-03 | 上海电气集团上海电机厂有限公司 | Method for installing magnetic poles of AC/AC variable-frequency steel-rolling motor rotors |
CN102403864A (en) * | 2011-11-14 | 2012-04-04 | 株洲南车时代电气股份有限公司 | Permanent-magnet motor suitable for batch production and magnetic pole locating method thereof |
-
2013
- 2013-04-28 CN CN201310156817.3A patent/CN103236766B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1337028A2 (en) * | 1995-05-02 | 2003-08-20 | Oppama Industry Co., Ltd. | A magneto electric generator rotor |
CN1937368A (en) * | 2006-10-16 | 2007-03-28 | 四川东风电机厂有限公司 | Water wheel generator polecore assembling process |
CN101404431A (en) * | 2008-07-24 | 2009-04-08 | 哈尔滨电机厂有限责任公司 | Pole core assembly technique for punching quadrant iron type through-flow generator |
CN101640457A (en) * | 2008-07-31 | 2010-02-03 | 上海电气集团上海电机厂有限公司 | Method for installing magnetic poles of AC/AC variable-frequency steel-rolling motor rotors |
CN102403864A (en) * | 2011-11-14 | 2012-04-04 | 株洲南车时代电气股份有限公司 | Permanent-magnet motor suitable for batch production and magnetic pole locating method thereof |
Non-Patent Citations (3)
Title |
---|
刘云.转子磁极挂装.《水轮发电机故障处理与检修》.中国水利水电出版社,2002,211-216. * |
富丹华等.立式机组固定部件中心找正.《水轮发电机组及辅助设备运行与维修》.河海大学出版社,2005,128-130. * |
永磁三相同步电动机装配工艺;杨光等;《防爆电机》;20121231;第47卷(第6期);57-58 * |
Also Published As
Publication number | Publication date |
---|---|
CN103236766A (en) | 2013-08-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106703403A (en) | Pouring formwork and wall pouring equipment | |
CN103236766B (en) | Magnetic pole center positioning process used in process of assembling and disassembling magnetic pole of generator | |
CN203474231U (en) | Steel bar tower safety hoisting device | |
CN219885503U (en) | Automatic plugboard device for hoisting rotor of hydraulic generator | |
CN203463876U (en) | Hydraulic pump stand | |
CN215990502U (en) | Electric induction motor rotor drawing-penetrating device | |
CN203728448U (en) | Light mounting and dismounting frame for tower crane | |
CN201817243U (en) | Platform and device for replacing conductor rail | |
CN212712461U (en) | Special fan hoist device of wind-powered electricity generation construction | |
CN204772354U (en) | Frock is lifted to reducing | |
CN104153590A (en) | Quick positioning and adjusting device for prefabricated residence superimposed wallboard | |
CN203998724U (en) | A kind of tower machine attached wall assembling and disassembling stand | |
CN204342318U (en) | Single pulley type crane arm pull bar | |
CN202591916U (en) | A hydraulic cylinder hinge pin installation device | |
CN202657821U (en) | Impeller assembly-disassembly lifting device of no-split centrifugal compressor | |
CN206338546U (en) | A kind of hydraulic dynamometer base | |
CN205123512U (en) | Install dedicated dismouting device of motor perpendicularly | |
CN206328067U (en) | Movable draining platform | |
CN202309355U (en) | Novel oil pumping machine motor base | |
CN106698229A (en) | Hanging device of transformer | |
CN205398038U (en) | IGCT changes device | |
CN201536236U (en) | Bracket for hoisting heavy objects on object like an electrical pole | |
CN205170253U (en) | Detachable removal hoist device | |
CN203660740U (en) | Motor installation structure | |
CN104511876A (en) | Dismounting device for parts on shaft |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |