CN103225346B - Assembly method for easily assembled or disassembled plastic-wood pavilion - Google Patents

Assembly method for easily assembled or disassembled plastic-wood pavilion Download PDF

Info

Publication number
CN103225346B
CN103225346B CN201310158118.2A CN201310158118A CN103225346B CN 103225346 B CN103225346 B CN 103225346B CN 201310158118 A CN201310158118 A CN 201310158118A CN 103225346 B CN103225346 B CN 103225346B
Authority
CN
China
Prior art keywords
ridgepole
fixed
column
lower transverse
transverse beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310158118.2A
Other languages
Chinese (zh)
Other versions
CN103225346A (en
Inventor
刘子叔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Space Kandak Plastic Co ltd
Original Assignee
HUNAN LVGUANG LANDSCAPE NEW MATERIAL CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN LVGUANG LANDSCAPE NEW MATERIAL CO Ltd filed Critical HUNAN LVGUANG LANDSCAPE NEW MATERIAL CO Ltd
Priority to CN201310158118.2A priority Critical patent/CN103225346B/en
Publication of CN103225346A publication Critical patent/CN103225346A/en
Application granted granted Critical
Publication of CN103225346B publication Critical patent/CN103225346B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses an assembly method for an easily assembled or disassembled plastic-wood pavilion. The assembly method comprises the steps as follows: (1) connecting columns with lower beams; (2) connecting the columns with upper beams and girders through column beam ridge three-way connection pieces; (3) fixing the upper ends of the girders by top connection pieces; (4) connecting and fixing joists with the girders by eave ridge three-way connection pieces; (5) fixing slope purlins with the joists and the girders respectively; and (6) fixing pavilion tile boards. According to the assembly method, the parts of the pavilion are connected and fixed by the connection pieces and can be conveniently assembled or disassembled, the pavilion is compact in structure, high in firmness and accurate in size, the problem of difficulty for connection in plastic-wood technology is solved, and the appearance of the pavilion is not influenced as the connection pieces are hidden after the parts of the pavilion are connected.

Description

The assemble method of wooden wayside pavilion is moulded in easy assembling and dismantling
Technical field
The present invention relates to the assemble method of wayside pavilion, the assemble method moulding wooden wayside pavilion of particularly a kind of easy assembling and dismantling.
Background technology
In prior art, wayside pavilion normally at the scene limit making limit to install and carry out constructing, there is following drawback like this: in-site installation long work consuming consuming time is many, and cost is higher; Field fabrication equipment is limited, occurs relatively large deviation unavoidably in manufacturing process; The wayside pavilion that general connected mode makes, can not dismounting arbitrarily, is also not easy to transport, is difficult to recycling or reuses loss large; Layman can not install, and is not convenient for remote customer and purchases use.
Summary of the invention
The object of the present invention is to provide a kind of assembling and dismantling convenient, make wayside pavilion close structure, firmness is high, and the assemble method of wooden wayside pavilion is moulded in accurate in size easy assembling and dismantling.
For achieving the above object, technical scheme provided by the invention is: the assemble method of wooden wayside pavilion is moulded in a kind of easy assembling and dismantling, comprises the following steps: 1. column is connected with lower transverse beam; 2. column is connected by post beam ridge three-dimensional connector with top rail, ridgepole, described post beam ridge three-dimensional connector comprises loaded plate, the column implant that centre, the loaded plate back side is fixedly installed, the ridgepole fixed head be fixedly connected with hinge type with one jiao, the front of loaded plate, the described ridgepole fixed head other end is fixed on loaded plate by adjusting screw; Also comprise at least two crossbeam positioning screws and at least two ridgepole positioning screws, described crossbeam positioning screw is vertically fixed on loaded plate, lay respectively at the both sides of ridgepole fixed head, described ridgepole positioning screw is vertically fixed on ridgepole fixed head, described crossbeam positioning screw is respectively arranged with the first junction plate, is connected by the second junction plate between described ridgepole positioning screw; 3. ridgepole upper end roof connecting is fixed; 4. eaves purlin and ridgepole are connected and fixed by eaves ridge three-dimensional connector, described eaves ridge three-dimensional connector comprises U-shaped mouth link slot, tube connector, described U-shaped mouth link slot is made up of angled two grooves, and one end of described tube connector is fixed on the interior angle place of U-shaped mouth link slot by junction plate; 5. domatic purlin is fixed with eaves purlin, ridgepole respectively; 6. a wayside pavilion watt plate is fixed.
Preferably, the mode that described column is connected with lower transverse beam is specific as follows: the corresponding position hole milling 1. will installing lower transverse beam at column, then on the lined steel pipe of aperture welded steel pipe as implant; 2. column implant is inserted in the lined steel pipe of lower transverse beam; 3. lower transverse beam, implant are holed respectively, with screw rod, nut, lower transverse beam and implant are locked; 4. after the lower transverse beam of all directions being connected and fixed, then column is fixed on the ground.
Preferably, described adjusting screw is vertically fixed on loaded plate.
Preferably, the center line projection of described ridgepole fixed head overlaps with the diagonal of loaded plate.
Preferably, the direction at described tube connector place and the plane at described two groove places be not in same plane.
A technical scheme tool in technique scheme has the following advantages or beneficial effect: the assemble method that wooden wayside pavilion is moulded in these easy assembling and dismantling is connected and fixed by connector, assembling and dismantling are convenient, make wayside pavilion close structure, firmness is high, size is accurate, solve the problem of moulding wood technology and connecting difficulty, and connect rear connectors and be hidden, do not affect wayside pavilion outward appearance.
Accompanying drawing explanation
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, simple introduction is done below by the accompanying drawing used required in embodiment or description of the prior art, apparently, accompanying drawing in the following describes is some embodiments of the present invention, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Accompanying drawing 1 is the structural representation that embodiment of the present invention column is connected with lower transverse beam;
Accompanying drawing 2 is the structural representation of embodiment of the present invention post beam ridge three-dimensional connector;
Using state figure when accompanying drawing 3 is the connection of embodiment of the present invention post beam ridge three-dimensional connector;
Accompanying drawing 4 is the structural representation of embodiment of the present invention roof connecting;
Accompanying drawing 5 is the structural representation of embodiment of the present invention eaves ridge three-dimensional connector.
Detailed description of the invention
Below by specific embodiment, the present invention is further illustrated.
Build all parts machine-shaping all in advance that wooden wayside pavilion is moulded in easy assembling and dismantling, all come by screw rod or connector during assembling and dismantling.The installation steps of embodiment are as follows:
1, column 1 is connected with lower transverse beam 11, as shown in Figure 1:
1. the corresponding position hole milling of lower transverse beam 11 will be installed at column 1, pore size is as the criterion can insert lower transverse beam 11, the aperture degree of depth is all to remove plastic wood layer, expose column lined steel pipe 2 to be as the criterion, then on aperture column lined steel pipe 2, welded steel pipe is as implant 3, and implant 3 size is as the criterion can be inserted in lower transverse beam lined steel pipe 4; 2. implant 3 is inserted in lower transverse beam lined steel pipe 4; 3. lower transverse beam 11, implant 3 are holed respectively, with screw rod 5, nut, lower transverse beam 11 and implant 3 are locked; 4. after the lower transverse beam 11 of all directions being connected and fixed, then column 1 is fixed on the ground.
2, column 1 is connected by post beam ridge three-dimensional connector with top rail 12, ridgepole 13:
As shown in Figure 2, post beam ridge three-dimensional connector comprises the first loaded plate 6, the column implant 7 that first centre, loaded plate 6 back side is fixedly installed, the ridgepole fixed head 8 be fixedly connected with hinge type with one jiao, the front of the first loaded plate 6, ridgepole fixed head 8 other end is fixed on the first loaded plate 6 by adjusting screw 9, adjusting screw 9 is vertically fixed on the first loaded plate 6, and the center line projection of ridgepole fixed head 8 overlaps with the diagonal of the first loaded plate 6; Also comprise two crossbeam positioning screws 10 and two ridgepole positioning screws 20, crossbeam positioning screw 10 is vertically fixed on the first loaded plate 6, lay respectively at the both sides of ridgepole fixed head 8, crossbeam positioning screw 10 is respectively arranged with the first junction plate 21, ridgepole positioning screw 20 is vertically fixed on ridgepole fixed head 8, is connected between ridgepole positioning screw 20 by the second junction plate 22.
Concrete connected mode is as shown in Figure 3:
1. be directly inserted in the cavity of column lined steel pipe 2 by the column implant 7 of post beam ridge three-dimensional connector, the size of column implant 7 is as the criterion just can intert to enter in column lined steel pipe 2, and insertion depth can not be less than 500mm; Then with screw, column lined steel pipe 2 and column implant 7 are fixed together; 2. by the boring of each position to top rail 12, the corresponding crossbeam positioning screw 10 of ridgepole 13, ridgepole positioning screw 20; 3. being interted by top rail 12 is placed in crossbeam positioning screw 10, and ridgepole 13 is interspersed to be placed in ridgepole positioning screw 20, puts the first junction plate 21 and the second junction plate 22 respectively well, clamp nut.
3, ridgepole 13 upper end roof connecting is fixed:
As shown in Figure 4, roof connecting comprises support and connection pipe 23, ridgepole tube connector 24 and the second loaded plate 25, four ridgepole tube connectors 24 be arranged on respectively support and connection pipe 23 surrounding and with its at an angle, angle between the lower end of ridgepole tube connector 24 and support and connection pipe 23 is acute angle, and the size of ridgepole tube connector 24 is as the criterion to be just inserted in ridgepole lined steel pipe.Second loaded plate 25 is arranged on support and connection pipe 23 lower end and vertical with support and connection pipe.During fixing ridgepole 13 upper end, the ridgepole tube connector 24 of roof connecting is inserted in ridgepole lined steel pipe.
4, eaves purlin 14 and ridgepole 13 are connected and fixed by eaves ridge three-dimensional connector:
As shown in Figure 5, eaves ridge three-dimensional connector comprises U-shaped mouth link slot 27, tube connector 28, and U-shaped mouth link slot 27 is made up of angled two grooves 26, and the angle between two grooves 26 is equal to the Plane Angle at wayside pavilion eaves angle; One end of tube connector 28 is fixed on the interior angle place of U-shaped mouth link slot 27 by junction plate, the direction at tube connector 28 place and the plane at two groove 26 places be not in same plane.On U-shaped mouth link slot 27, tube connector 28, drill two holes is as screw rod locating hole 29 at least respectively, and size to be as the criterion into screw rod interting.Be installed in U-shaped mouth link slot 27 by eaves purlin 14 during connection, ridgepole 13 is inserted in tube connector 28, and interts into positioning screw in screw rod locating hole 29 respectively, then fixes with nut check.
5, domatic purlin is fixed with eaves purlin, ridgepole respectively:
Namely domatic purlin is positioned on the slope of corridor top, is used for carrying the purlin of corridor watt plate.Domatic purlin connects ridgepole, and lower even eaves purlin, is connected and fixed with screw and corner brace.
6, a wayside pavilion watt plate is fixed:
Utilization is moulded fillet and is done skeleton, will mould shide plate spelling and become prefabricated chunk, and overlapped by prefabricated chunk and be fixed on the domatic purlin on wayside pavilion top during installation.
Below the assembling that wooden wayside pavilion is moulded in easy assembling and dismantling is namely completed.
Apply specific embodiment herein to set forth principle of the present invention and embodiment, the explanation of above embodiment just understands method of the present invention and core concept thereof for helping.The above is only the preferred embodiment of the present invention, should be understood that, due to the finiteness of literal expression, and objectively there is unlimited concrete structure, for those skilled in the art, under the premise without departing from the principles of the invention, some improvement, retouching or change can also be made, also above-mentioned technical characteristic can be combined by rights; These improve retouching, change or combination, or the design of invention and technical scheme are directly applied to other occasion without improving, and all should be considered as protection scope of the present invention.

Claims (5)

1. an assemble method for wooden wayside pavilion is moulded in easy assembling and dismantling, it is characterized in that, comprises the following steps: 1. column is connected with lower transverse beam; 2. column is connected by post beam ridge three-dimensional connector with top rail, ridgepole, described post beam ridge three-dimensional connector comprises loaded plate, the column implant that centre, the loaded plate back side is fixedly installed, the ridgepole fixed head be fixedly connected with hinge type with one jiao, the front of loaded plate, the described ridgepole fixed head other end is fixed on loaded plate by adjusting screw; Also comprise at least two crossbeam positioning screws and at least two ridgepole positioning screws, described crossbeam positioning screw is vertically fixed on loaded plate, lay respectively at the both sides of ridgepole fixed head, described ridgepole positioning screw is vertically fixed on ridgepole fixed head, described crossbeam positioning screw is respectively arranged with the first junction plate, is connected by the second junction plate between described ridgepole positioning screw; 3. ridgepole upper end roof connecting is fixed; 4. eaves purlin and ridgepole are connected and fixed by eaves ridge three-dimensional connector, described eaves ridge three-dimensional connector comprises U-shaped mouth link slot, tube connector, described U-shaped mouth link slot is made up of angled two grooves, and one end of described tube connector is fixed on the interior angle place of U-shaped mouth link slot by junction plate; 5. domatic purlin is fixed with eaves purlin, ridgepole respectively; 6. a wayside pavilion watt plate is fixed.
2. the assemble method of wooden wayside pavilion is moulded in easy assembling and dismantling according to claim 1, it is characterized in that, the mode that described column is connected with lower transverse beam is specific as follows: the corresponding position hole milling 1. will installing lower transverse beam at column, then on the lined steel pipe of aperture welded steel pipe as implant; 2. column implant is inserted in the lined steel pipe of lower transverse beam; 3. lower transverse beam, implant are holed respectively, with screw rod, nut, lower transverse beam and implant are locked; 4. after the lower transverse beam of all directions being connected and fixed, then column is fixed on the ground.
3. the assemble method of wooden wayside pavilion is moulded in easy assembling and dismantling according to claim 1, and it is characterized in that, described adjusting screw is vertically fixed on loaded plate.
4. the assemble method of wooden wayside pavilion is moulded in easy assembling and dismantling according to claim 1, it is characterized in that, the center line projection of described ridgepole fixed head overlaps with the diagonal of loaded plate.
5. the assemble method of wooden wayside pavilion is moulded in easy assembling and dismantling according to claim 1, it is characterized in that, the direction at described tube connector place and the plane at described two groove places be not in same plane.
CN201310158118.2A 2013-05-02 2013-05-02 Assembly method for easily assembled or disassembled plastic-wood pavilion Expired - Fee Related CN103225346B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310158118.2A CN103225346B (en) 2013-05-02 2013-05-02 Assembly method for easily assembled or disassembled plastic-wood pavilion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310158118.2A CN103225346B (en) 2013-05-02 2013-05-02 Assembly method for easily assembled or disassembled plastic-wood pavilion

Publications (2)

Publication Number Publication Date
CN103225346A CN103225346A (en) 2013-07-31
CN103225346B true CN103225346B (en) 2015-05-27

Family

ID=48835968

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310158118.2A Expired - Fee Related CN103225346B (en) 2013-05-02 2013-05-02 Assembly method for easily assembled or disassembled plastic-wood pavilion

Country Status (1)

Country Link
CN (1) CN103225346B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110629880A (en) * 2019-08-22 2019-12-31 广东玖米空间科技有限公司 Assembled building structure system and three-way connecting device of top column thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN87102968A (en) * 1987-04-20 1988-11-02 李殿钧 Assembled type imitation antique building
JPH11315610A (en) * 1998-05-01 1999-11-16 Yamahisa:Kk Roof truss construction method in wooden architecture
CN1616254A (en) * 2003-11-14 2005-05-18 孟繁华 Micro antique pavilion, terrace and tower structure system
CN200992814Y (en) * 2006-12-20 2007-12-19 赵迎辉 Spliced combined type archaized building

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN87102968A (en) * 1987-04-20 1988-11-02 李殿钧 Assembled type imitation antique building
JPH11315610A (en) * 1998-05-01 1999-11-16 Yamahisa:Kk Roof truss construction method in wooden architecture
CN1616254A (en) * 2003-11-14 2005-05-18 孟繁华 Micro antique pavilion, terrace and tower structure system
CN200992814Y (en) * 2006-12-20 2007-12-19 赵迎辉 Spliced combined type archaized building

Also Published As

Publication number Publication date
CN103225346A (en) 2013-07-31

Similar Documents

Publication Publication Date Title
CN105544738A (en) Self-locking mortise and tenon type module building connecting joint
CN104405155A (en) Substation room
CN106193402B (en) Girder truss integrated form flooring module and its installation method
KR101760775B1 (en) Concrete form assembly for forming wall and construction method thereof
CN210597866U (en) Steel construction assembled wallboard
CN210104967U (en) Assembled house structure
CN205329865U (en) Auto -lock mortise type module building connected node
CN205057364U (en) Truss assemble bed -jig
CN200946328Y (en) Connecting joint of movable house rack and vertical column
CN103225346B (en) Assembly method for easily assembled or disassembled plastic-wood pavilion
CN204385916U (en) A kind of beam-to-column joint structure of movable plank house
CN103216110B (en) The assemble method of timber building is moulded in easy assembling and dismantling
CN105369890A (en) Earthquake-proof folk house steel framework and installation method thereof
CN206337651U (en) Assembled architecture wall column connector and attachment structure
CN214220746U (en) Assembled tool room
CN211816922U (en) Steel construction assembled house frame construction
CN103233583B (en) The assemble method of wooden corridor is moulded in easy assembling and dismantling
CN216109355U (en) Precast concrete post suitable for draw-in groove formula precast beam
CN207392740U (en) A kind of assemble type concrete slab support system
CN211007050U (en) Assembled light steel assembly house
CN203403576U (en) Assembly-type parking lot floor plate of full steel structure
CN205348384U (en) Antidetonation local -style dwelling houses steel framework
CN214574657U (en) Steel structure room easy to disassemble
CN220538883U (en) Connection structure between green wall, roof beam and post
CN202831620U (en) European style hollow-out plate pinnacle modeling structure template system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170504

Address after: Three road 410000 in Hunan Province, Yuelu District City, Changsha Fenglin No. 1068 Hunan East Red Shoes Co. Ltd. factory

Patentee after: HUNAN SPACE KANDAK PLASTIC CO.,LTD.

Address before: 410002, 1206, building 9, 38 West Sunshine Road, California Valley, Changsha hi tech Development Zone, Hunan, China

Patentee before: HUNAN LVGUANG LANDSCAPE NEW MATERIAL Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150527