CN103217622B - Based on the distribution network fault line selection method of multiterminal voltage traveling wave - Google Patents

Based on the distribution network fault line selection method of multiterminal voltage traveling wave Download PDF

Info

Publication number
CN103217622B
CN103217622B CN201310031702.1A CN201310031702A CN103217622B CN 103217622 B CN103217622 B CN 103217622B CN 201310031702 A CN201310031702 A CN 201310031702A CN 103217622 B CN103217622 B CN 103217622B
Authority
CN
China
Prior art keywords
fault
traveling wave
line
time
distribution network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310031702.1A
Other languages
Chinese (zh)
Other versions
CN103217622A (en
Inventor
曾祥君
钱庆林
陈晓红
徐斌
颜彦
张海波
李靖强
喻锟
柳芊芊
王阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha Jingke Electric Technology Co Ltd
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN201310031702.1A priority Critical patent/CN103217622B/en
Publication of CN103217622A publication Critical patent/CN103217622A/en
Application granted granted Critical
Publication of CN103217622B publication Critical patent/CN103217622B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Locating Faults (AREA)

Abstract

The invention discloses a kind of distribution network fault line selection method based on multiterminal voltage traveling wave, belong to Relay Protection Technology in Power System field.The steps include: the transformer station in power distribution network and each basic routing line branches end installed rows ripple harvester; Utilize transformer station's bus connection switch divide-shut brake to produce travelling wave signal, the mistiming of the initial time that on calculating basic routing line, the fault traveling wave of each branches end arrives and the initial time that the fault traveling wave at substation bus bar place arrives, obtain array reference time; The mistiming of the initial time that during calculating fault, on basic routing line, the fault traveling wave of each branches end arrives and the initial time that the fault traveling wave at substation bus bar place arrives, set up array fault-time; By reference time array and fault-time array carry out least square fitting, realize the use processing of row ripple time of arrival of each collection point record, find faulty line.The present invention does not limit by fault type, has the advantage that computing is simple, route selection is reliable, practical.

Description

Based on the distribution network fault line selection method of multiterminal voltage traveling wave
Technical field
The invention belongs to Relay Protection Technology in Power System field, particularly a kind of distribution network fault line selection method based on multiterminal voltage traveling wave.
Background technology
Extensively adopt small grounding current system in China's low and medium voltage distribution network, its probability that singlephase earth fault occurs is the highest, because single-phase earth fault current is less, does not affect and powers continuously to load, and regulations stipulate can continue operation 1 ~ 2h by tape jam.But along with power distribution network development, bus feeder line increases and the use of cable in circuit year by year, short circuit capacitance electric current is increased, operate with failure for a long time and easily make failure propagation become or multipoint earthing short circuit at 2, arc grounding also can cause total system superpotential, and then damage equipment, destroys system safety operation, so must failure judgement circuit rapidly and accurately, accurately locate for further fault and provide foundation with failture evacuation.
In existing failure line selection, the route selection of many employing low current faults, but fault current is little, Earth Fault Detection difficulty.According to the difference of location design, be successively proposed the line selection apparatus remaining the principles such as method of addition based on active power method, injecting signal, wavelet analysis method, ground connection both at home and abroad.But existing various line selection apparatus is by the impact of the factors such as fault state complexity, faint, the on-the-spot electromagnetic interference (EMI) of fault current and out-of-balance current, and on-the-spot operational effect is unsatisfactory, and accuracy rate is not high.
Summary of the invention
In order to solve the above-mentioned technical matters that existing distribution network fault line selection exists, the invention provides a kind of distribution network fault line selection method based on multiterminal voltage traveling wave.The present invention is highly sensitive, speed is fast, strong robustness, do not limit by fault type and the method for operation, possesses comparatively strong fault tolerance ability, engineer applied is easy to realize, more accurately more reliable foundation can be provided for further localization of fault and failture evacuation, the service requirement with distributed power supply smart power distribution network can be met.
The present invention solves the problems of the technologies described above adopted technical scheme and comprises the following steps:
(1) transformer station in power distribution network and each basic routing line branches end installed rows ripple harvester;
(2) the bus connection switch divide-shut brake of transformer station in power distribution network is produced travelling wave signal, the initial time utilizing the capable ripple of row ripple harvester record trouble to arrive, the initial time t ' that the fault traveling wave calculating each branches end on basic routing line m arrives mnthe initial time t ' arrived with the fault traveling wave at substation bus bar place 0mistiming, obtain array H reference time of basic routing line m m=(t ' m1-t ' 0, t ' m2-t ' 0..., t ' mN-t ' 0), m=1 ..., k, k are the sum of basic routing line, and m is basic routing line numbering, and N is the sum of each branches end row ripple harvester on basic routing line m;
(3) when power distribution network breaks down, the initial time utilizing the capable ripple of row ripple harvester record trouble to arrive, the initial time t that the fault traveling wave calculating each branches end on basic routing line m arrives mnthe initial time t arrived with the fault traveling wave at substation bus bar place 0mistiming, obtain array G fault-time of basic routing line m m=(t m1-t 0, t m2-t 0..., t mN-t 0), m=1 ..., k, n are the numbering of each branches end row ripple harvester on basic routing line m, and N is the sum of each branches end row ripple harvester on basic routing line m;
(4) array H reference time is set up mwith array G fault-time mequation of linear regression G m=A m+ B mh m, calculate A according to principle of least square method mbest estimate, if A min [-0.3,0.3] scope, then circuit m is non-fault line, otherwise circuit m is faulty line.
In the above-mentioned distribution network fault line selection method based on multiterminal voltage traveling wave, described step sets up array H reference time in (4) mwith array G fault-time mequation of linear regression G m=A m+ B mh m, according to principle of least square method, calculate A mthe step of best estimate be: definition h nfor H min n-th (t ' mn-t ' 0), g nfor G mn-th (t mn-t 0), calculate A as follows m:
A m = ( Σh n 2 ) ( Σg n ) - ( Σh n ) ( Σh n g n ) N ( Σh n 2 ) - ( Σh n ) 2 → 0
If A min [-0.3,0.3] scope, then circuit m is non-fault line, otherwise circuit m is faulty line.
Technique effect of the present invention is: when the present invention utilizes the fault of power distribution network capable ripple harvester record, row ripple temporal information carries out route selection, rapid sensitive, is easy to realize, does not limit by fault type and the method for operation; The present invention utilizes equation of linear regression and principle of least square method to form route selection criterion, and computing is simple, and accuracy rate is high, is easy to realize, and effectively can reduce the recording error disturbing and cause.
Accompanying drawing explanation
The topology diagram of power distribution network in Fig. 1 the present invention.
Fig. 2 process flow diagram of the present invention.
The failure line selection fitted figure of circuit a in Fig. 3 the present invention.
The failure line selection fitted figure of circuit b in Fig. 4 the present invention.
The failure line selection fitted figure of circuit c in Fig. 5 the present invention.
Embodiment
Embodiment
See Fig. 1, Fig. 1 for implementing power distribution network topology diagram of the present invention, the distribution network fault line selection step that the present invention is based on multiterminal voltage traveling wave is:
(1) transformer station in power distribution network as shown in Figure 1 and 3 basic routing line branches end installed rows ripple harvesters, m (m=a is numbered to 3 basic routing lines, b, c), n is numbered to basic routing line each branches end row ripple harvester, wherein each branches end row ripple harvester of basic routing line a is numbered a1, a2, a3, a4, a5, be numbered b1, b2, b3 to basic routing line b each branches end row ripple harvester, basic routing line c each branches end row ripple harvester is numbered c1, c2, c3, c4.
(2) by the bus connection switch divide-shut brake of transformer station in power distribution network to produce travelling wave signal, utilize the initial time that the capable ripple of row ripple harvester record trouble arrives, the initial time t ' that the fault traveling wave calculating basic routing line m (m=a, b, c) branches end arrives mnthe initial time t ' arrived with the fault traveling wave at substation bus bar place 0mistiming, obtain array H reference time of basic routing line m (m=a, b, c) m:
H a=(t′ a1-t′ 0,t′ a2-t′ 0,t′ a3-t′ 0,t′ a4-t′ 0,t′ a5-t′ 0)=(150.00,133.33,126.67,73.33,30.00);
H b=(t′ b1-t′ 0,t′ b2-t′ 0,t′ b3-t′ 0)=(90.00,43.00,16.00);
H c=(t′ c1-t′ 0,t′ c2-t′ 0,t′ c3-t′ 0,t′ c4-t′ 0)=(135.80,155.70,65.70,13.90)。
(3) distribution network failure occurs on basic routing line c as shown in Figure 1, the initial time utilizing the capable ripple of row ripple harvester record trouble to arrive, the initial time t ' that the fault traveling wave calculating basic routing line m (m=a, b, c) branches end arrives mnthe initial time t ' arrived with the fault traveling wave at substation bus bar place 0mistiming, obtain array G fault-time of basic routing line m (m=a, b, c) m:
G a=(t a1-t 0,t a2-t 0,t a3-t 0,t a4-t 0,t a5-t 0)=(150.04,133.39,126.63,73.35,30.06);
G b=(t b1-t 0,t b2-t 0,t b3-t 0)=(89.96,42.99,15.98);
G c=(t c1-t 0,t c2-t 0,t c3-t 0,t c4-t 0)=(57.00,76.90,-46.44,-52.63)。
(4) array H reference time is set up mwith array G fault-time mequation of linear regression G m=A m+ B mh m, according to principle of least square method, calculate A mthe step of best estimate be: to power distribution network basic routing line m, definition h nfor H min n-th (t ' mn-t ' 0), g nfor G mn-th (t mn-t 0), N is the maximal value of each branches end row ripple harvester numbering n of basic routing line, calculates A m:
For circuit a: A a = ( Σ n = 1 5 h n 2 ) ( Σ n = 1 5 g n ) - ( Σ n = 1 5 h n ) ( Σ n = 1 5 h n g n ) 5 ( Σ n = 1 5 h n 2 ) - ( Σ n = 1 5 h n ) 2 = - 0.1908
For circuit b: A b = ( Σ n = 1 3 h n 2 ) ( Σ n = 1 3 g n ) - ( Σ n = 1 3 h n ) ( Σ n = 1 3 h n g n ) 3 ( Σ n = 1 3 h n 2 ) - ( Σ n = 1 3 h n ) 2 = - 0.0079
For circuit c: A c = ( Σ n = 1 4 h n 2 ) ( Σ n = 1 4 g n ) - ( Σ n = 1 4 h n ) ( Σ n = 1 4 h n g n ) 4 ( Σ n = 1 4 h n 2 ) - ( Σ n = 1 4 h n ) 2 = - 83.5953
The A of circuit c clearly can be found out by the above results cwell beyond the scope of [-0.3,0.3]; And the A of circuit a awith the A of circuit b bvalue levels off to 00, obviously belongs in the scope of [-0.3,0.3]; To sum up, easily judge that circuit c is as faulty line, and circuit a and b is non-fault line.Use MATLAB to array H reference time of power distribution network basic routing line m mwith array G fault-time mcarry out matching, fitting result is as shown in Fig. 3, Fig. 4, Fig. 5, and the point of a circuit and b circuit meets non-fault line that linear correlation is thought, the point of c circuit does not meet linear correlation, and institute thinks faulty line.It can thus be appreciated that the distribution network fault line selection method that the present invention is based on multiterminal voltage traveling wave correctly, reliably can select faulty line.

Claims (2)

1., based on a distribution network fault line selection method for multiterminal voltage traveling wave, comprise the following steps:
(1) transformer station in power distribution network and each basic routing line branches end installed rows ripple harvester;
(2) the bus connection switch divide-shut brake of transformer station in power distribution network is produced travelling wave signal, the initial time utilizing the capable ripple of row ripple harvester record to arrive, the initial time t ' that the fault traveling wave calculating each branches end on arbitrary basic routing line m arrives mnthe initial time t arrived with the fault traveling wave at substation bus bar place 0' mistiming, obtain array H reference time of basic routing line m m=(t ' m1-t ' 0, t ' m2-t ' 0... t ' mN-t ' 0), m=(a, b, c ...), n=(1,2 ..., N), n is the numbering of each branches end row ripple harvester on basic routing line m, and N is the sum of each branches end row ripple harvester on basic routing line m;
(3) when power distribution network breaks down, the initial time utilizing the capable ripple of row ripple harvester record trouble to arrive, the initial time t that the fault traveling wave calculating each branches end row ripple harvester n on arbitrary basic routing line m arrives mnthe initial time t arrived with the fault traveling wave at substation bus bar place 0mistiming, obtain array G fault-time of basic routing line m m=(t m1-t 0, t m2-t 0..., t mN-t 0);
(4) array H reference time is set up mwith array G fault-time mequation of linear regression G m=A m+ B mh m, calculate A according to principle of least square method mbest estimate, if A min [-0.3,0.3] scope, then circuit m is non-fault line, otherwise circuit m is faulty line.
2. the distribution network fault line selection method based on multiterminal voltage traveling wave according to claim 1, sets up array H reference time in described step (4) mwith array G fault-time mequation of linear regression G m=A m+ B mh m, according to principle of least square method, calculate A mthe step of best estimate be: definition h nfor H min n-th (t ' mn-t ' 0), g nfor G mn-th (t mn-t 0), calculate A as follows m:
A m = ( Σ h n 2 ) ( Σ g n ) - ( Σ h n ) ( Σ h n g n ) N ( Σ h n 2 ) - ( Σ h n ) 2
If A min [-0.3,0.3] scope, then circuit m is non-fault line, otherwise circuit m is faulty line.
CN201310031702.1A 2013-01-28 2013-01-28 Based on the distribution network fault line selection method of multiterminal voltage traveling wave Active CN103217622B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310031702.1A CN103217622B (en) 2013-01-28 2013-01-28 Based on the distribution network fault line selection method of multiterminal voltage traveling wave

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310031702.1A CN103217622B (en) 2013-01-28 2013-01-28 Based on the distribution network fault line selection method of multiterminal voltage traveling wave

Publications (2)

Publication Number Publication Date
CN103217622A CN103217622A (en) 2013-07-24
CN103217622B true CN103217622B (en) 2015-07-29

Family

ID=48815582

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310031702.1A Active CN103217622B (en) 2013-01-28 2013-01-28 Based on the distribution network fault line selection method of multiterminal voltage traveling wave

Country Status (1)

Country Link
CN (1) CN103217622B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108693446A (en) * 2018-05-25 2018-10-23 中国矿业大学 A kind of Fault Locating Method of non-synchronous sampling power grid transient state travelling wave modulus time difference

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104316833A (en) * 2014-10-14 2015-01-28 广东电网有限责任公司电力科学研究院 Line selection method for medium-voltage power distribution network fault traveling wave
CN104354608B (en) * 2014-11-04 2016-08-17 中铁工程设计咨询集团有限公司 The Intelligent Selection of contact net jumps device and electric power system
CN104833900B (en) * 2015-05-11 2017-10-20 国家电网公司 The faulty line selection method of low current singlephase earth fault
CN106771844B (en) * 2015-11-19 2019-10-15 中国石油化工股份有限公司 A kind of power network multipoint line Fault Locating Method and system
CN110501606B (en) * 2018-05-17 2021-11-02 云南电网有限责任公司曲靖供电局 Pure cable distribution line double-end traveling wave fault positioning method
CN109239529B (en) * 2018-09-30 2021-07-20 安阳霍远科技有限公司 System and method for preventing hidden danger of power line and warning information
CN109557421B (en) * 2018-12-29 2023-10-13 山东科技大学 Multi-branch distribution network fault location method based on initial traveling wave time difference relation
CN111381128B (en) * 2019-12-25 2022-10-21 长沙理工大学 Power distribution network fault positioning method and device and server
CN111007362B (en) * 2019-12-27 2022-05-03 广东电网有限责任公司电力科学研究院 Power distribution network fault line selection positioning system, method and equipment
CN111596173A (en) * 2020-06-06 2020-08-28 张朝 Information fusion line selection method based on ETL technology correction
CN113281609B (en) * 2021-04-23 2022-05-03 湖南工业职业技术学院 Active traveling wave positioning method and system for power distribution network fault and storage medium
CN113866553A (en) * 2021-08-24 2021-12-31 武汉华瑞伏安电力科技有限公司 Distributed fault double-end traveling wave positioning method independent of synchronous clock

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3586266B2 (en) * 2002-06-06 2004-11-10 東京電力株式会社 Fault location method for transmission line and fault location system using the same
CN1689859A (en) * 2004-04-27 2005-11-02 淄博科汇电气有限公司 Railway self-closing/cut-through line-to-ground fault range count method
CN101141062A (en) * 2007-07-31 2008-03-12 长沙理工大学 Electric network functional failure travelling wave positioning method
CN101267108A (en) * 2008-03-17 2008-09-17 长沙理工大学 Protection method for failure row wave network
CN101509949A (en) * 2009-03-20 2009-08-19 华南理工大学 Direct current transmission line double-end asynchronous and parameter self-adapting fault distance measuring time-domain method
CN101923137A (en) * 2010-06-30 2010-12-22 湖南湘能电气自动化有限公司 Single-phase ground fault line selecting method of small-electric current grounding system
CN201697994U (en) * 2010-06-30 2011-01-05 湖南湘能电气自动化有限公司 Small-current grounding system single-phase earth fault line selection device
CN102122814A (en) * 2010-12-30 2011-07-13 山东理工大学 Adaptive reclosing method based on travelling wave segmentation principle for mixed line
CN102353875A (en) * 2011-09-30 2012-02-15 山东理工大学 Fault distance measuring method for combined travelling wave of power transmission line

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE519943C2 (en) * 2000-12-14 2003-04-29 Abb Ab Method for fault location in a transmission line

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3586266B2 (en) * 2002-06-06 2004-11-10 東京電力株式会社 Fault location method for transmission line and fault location system using the same
CN1689859A (en) * 2004-04-27 2005-11-02 淄博科汇电气有限公司 Railway self-closing/cut-through line-to-ground fault range count method
CN101141062A (en) * 2007-07-31 2008-03-12 长沙理工大学 Electric network functional failure travelling wave positioning method
CN101267108A (en) * 2008-03-17 2008-09-17 长沙理工大学 Protection method for failure row wave network
CN101509949A (en) * 2009-03-20 2009-08-19 华南理工大学 Direct current transmission line double-end asynchronous and parameter self-adapting fault distance measuring time-domain method
CN101923137A (en) * 2010-06-30 2010-12-22 湖南湘能电气自动化有限公司 Single-phase ground fault line selecting method of small-electric current grounding system
CN201697994U (en) * 2010-06-30 2011-01-05 湖南湘能电气自动化有限公司 Small-current grounding system single-phase earth fault line selection device
CN102122814A (en) * 2010-12-30 2011-07-13 山东理工大学 Adaptive reclosing method based on travelling wave segmentation principle for mixed line
CN102353875A (en) * 2011-09-30 2012-02-15 山东理工大学 Fault distance measuring method for combined travelling wave of power transmission line

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
A Fault Line-Selection Method of Hybrid Cable-Overhead Line in Distribution Network Based on Morphology Filter and Hilbert-Huang Transform;Shu Hong-chun et al.;《Power and Energy Engineering Conference》;20090331;1-6 *
一种改进的配电网故障选线方法研究;田书等;《电气应用》;20120531;第31卷(第9期);58-61 *
小电流接地***故障选线方法综述;郭清滔等;《电力***保护与控制》;20100116;第38卷(第2期);146-152 *
电缆网故障选线方法的研究;苑舜等;《高压电器》;20110131;第47卷(第1期);43-48 *
配电网接地故障选线技术及其应用;张明春等;《山东电力技术》;20120630(第3期);33-36、52 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108693446A (en) * 2018-05-25 2018-10-23 中国矿业大学 A kind of Fault Locating Method of non-synchronous sampling power grid transient state travelling wave modulus time difference

Also Published As

Publication number Publication date
CN103217622A (en) 2013-07-24

Similar Documents

Publication Publication Date Title
CN103217622B (en) Based on the distribution network fault line selection method of multiterminal voltage traveling wave
CN101943737B (en) Single-phase earth fault diagnosis method and device
CN100470252C (en) Electric network functional failure travelling wave positioning method
CN108054736B (en) A kind of multiterminal flexible direct current power grid DC line protection method based on voltage pole wave
CN104316833A (en) Line selection method for medium-voltage power distribution network fault traveling wave
CN102495336B (en) Distributed single-phase earth fault ranging system and ranging method thereof
CN102963271B (en) Section power supply and status measurement and control method of parallel-connected traction networks at tail end of double track railway
CN102096021B (en) Traveling wave natural frequency-based power transmission network failure networking positioning and distance measurement method
CN102590654B (en) Element and method for discriminating fault electrode of DC transmission line
CN103267927B (en) A kind of low current neutral grounding system fault route selecting method utilizing power frequency component wavelet coefficient fitting a straight line to detect
CN102944814A (en) Power distribution network single-phase earth fault locating method based on transient state
CN108599114B (en) A kind of high voltage ac/dc combined hybrid system alternating current circuit transient state direction protection method
CN103163430A (en) Resonant grounding system fault line selection method by combining complex wavelets with ANN (artificial neural network)
CN104330708B (en) Fault location method for wide area traveling wave signal below power grid
CN103499772B (en) A kind of modified transmission line lightning stroke both-end travelling wave positioning method
CN103105563A (en) Electric power line fault traveling wave network locating method
CN103018630A (en) Single-phase earth fault transient line selection method of distribution network
CN103837799B (en) A kind of frequency domain method of voltage DC ground electrode circuit fault based on R-L model range finding
CN104297638A (en) Power distribution grid fault positioning method with high precision and low cost
CN105158637A (en) Fault traveling wave location method of multiple branch lines of power distribution network
CN102013671A (en) Transient travelling wave amplitude integral type superspeed bus protection system and method thereof
CN106970261A (en) Earth leakage detecting system for train
CN103018632A (en) Small current grounding system single-phase ground fault line selection method based on fisher information
CN102928731A (en) Power distribution network fault line selection method using zero-sequence current full quantity Hough transformation
CN104316836A (en) Online grid fault detection method based on relative protection entropy and nominal transition resistance

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160831

Address after: 410013 Hunan province Changsha City Lugu high tech Development Zone Industrial Park A2 building 201

Patentee after: Changsha Jingke Electric Technology Co. Ltd.

Address before: 410004 Hunan province Changsha Wanjiali road two No. 960

Patentee before: Changsha University of Sciences and Technology